Project Planning Meeting
Project Lead SupportFull Service Transfer PDCs AEIT, Customer
AgenciesData Center Consolidation AEIT PDCs, AgenciesEnterprise Email AEIT SSRC, AgenciesSystem Architecture PDCs AEIT, AgenciesData Center Energy Efficiency
AEIT PDCsDefinition of Acronyms and Terms:AEIT = Agency for Enterprise Information TechnologyAgencies = State of Florida agenciesCustomer Agencies = Agencies that currently obtain co-location services from a Primary Data Center.PDCs = Primary Data Centers (currently Southwood Shared Resource Center and anticipating Northwood Shared Resource Center)SSRC = Southwood Shared Resource Center
The scope of full service transfer is all data center functions performed, managed, operated, or supported by state agencies with resources and equipment currently located in a primary data center—excluding application development functions.
Data center functions include, but are not limited to, all data center hardware, software, staff, contracted services, and facility resources performing data center management and operations, security, backup and recovery, disaster recovery, system administration, database administration, system programming, job control, production control, print, storage, technical support, help desk, and managed services.
(2009 SB 2574c1, Lines 1494 - 1501)
Deliverable Owner Date SourcePlan for transferring all resources to PDC
Customer Agencies
October 1, 2009
SB 2574c1, Lines 1504 - 1523
Provide standard format for data and facilitate efforts of customer agencies who are required to develop transition plans
PDCs AEIT recommends providing template by July 1, 2009
2009 Proviso SSRC/NSRC
Transition plan for absorbing transfer of customer agency data center resources into PDCs
PDCs November 15, 2009
2009 Proviso SSRC/NSRC
Complete transfer to full service
PDCs July 1, 2010 SB 2574c1, Line 1488
Getting Organized◦ Appoint / Hire Project Managers (AEIT recommendation)◦ Appoint / Hire a Service Architect (AEIT
recommendation)◦ Develop Project Management Plan◦ Develop Project Schedule◦ Develop Implementation Plan template◦ Obtain approvals from Board of Trustees
Responsible for transfer of resources in user agencies relating to provision of full services◦ Create template for customer agencies to complete
Submit LBRs to accommodate transferred equipment in FY 2010-2011
Prepare cost recovery plans Submit Transition Plan for absorbing
customer agencies’ resources to AEIT, EOG, Senate and House by November 15, 2009
Complete full service transfer by July 1, 2010
Identify costs and resources Provide PDC with plan for transferring
resources◦ Expenditures◦ Spending Authority (for equipment and software
for previous 5 years and projected upcoming 2 years)
Collaborate with agencies to identify FTEs to transfer to PDC and identify FTE reductions
Facilitate organizational change management (merging cultures)
Identify management structure Standardize job classes, titles, position
descriptions, and pay plans Make arrangements for office space Plan for and conduct cross-training of
existing and incoming staff
Consider physical and logical security issues◦ Gather and assess security requirements of
customer agencies◦ Assess the business impacts of potential security
changes
Create Disaster Recovery (DR) Plans with customer agencies
Create transition plan for existing DR sites Test DR Plan and Continuity of Operations
Plan (COOP) with customer agencies Develop COOP for PDC
Update PDCs’ Service Catalogs Map agency services to PDC service offerings Create transition plan for non-mapped services or
PDC accepts new service Review Service Support processes and
procedures with customer agencies (please share with AEIT):◦ Incident Management, Problem Management, Change
Management (including Requests for Change), and Configuration Management
Review service contracts and Service Level Agreements with the agencies
Prepare PDC inventory in cooperation with AEIT
Develop plan for communicating with customer agencies
Communicate with AEIT in accordance with plan from AEIT
Prepare and Submit FY 2010-2011 Legislative Budget Requests (LBRs)◦ PDCs shall request additional budget authority to
accommodate the transferred functions◦ Agencies shall make the budget adjustments
necessary to accomplish transfers Includes: Salary and Benefits, Operating Capital
Outlay (OCO), and other expenses Work with agencies to request federal
funding for PDC services
AEIT will convene a meeting with PDCs and their customer agencies to kick-off Full Service Transfer (tentatively May 7, 2009)
AEIT will seek formal acceptance of Full Service Transfer scope, objectives, and deliverables via AEIT’s formal Scope and Responsibilities document
PDCs will ….