Exeon case study waste handling C125300 rev1...CASE STUDY Waste Handling PROJECT VALUE £150,000...

Post on 13-Sep-2020

2 views 0 download

Transcript of Exeon case study waste handling C125300 rev1...CASE STUDY Waste Handling PROJECT VALUE £150,000...

ISSUEA refuse processing plant in Kent was suffering from

poor air quality and high temperatures internally. The

EHO would not allow untreated extraction to outside

due to the high odour intensity within the building.

SOLUTIONExeon designed and installed an odour extraction

system with extract grills located as closely as

possible to the particulate source for maximum

removal. This enabled the air change rate to be

reduced to 3 (from the suggested 4) which has the

dual benet of lower energy consumption and less

heat loss.

Air quality was drastically improved following the

installation, both in regards to temperature and air

particulate.

The extracted air was ltered before discharge, to

remove both odour and particulate. The lter unit

succeeded in removing both 99% + of particulate

and also complying with the maximum odour limits

level as stipulated by the EHO.

Exeon Limited Unit 6 Fen End Stotfold Hitchin Herts SG5 4BA// // // // //

01462 410010 sales@exeon.co.uk t // e // w www.exeon.co.uk

ODOUR TREATMENT AND VENTILATION FOR WASTE TREATMENT PLANT

Ref: C125300

CASE STUDY

Waste Handling

PROJECT VALUE

£150,000