Energy Production Systems Engineering - …thomasblairpe.com/PPE/lecture6_rev7.pdf67V = voltage...

Post on 20-May-2018

220 views 1 download

Transcript of Energy Production Systems Engineering - …thomasblairpe.com/PPE/lecture6_rev7.pdf67V = voltage...

Welcome to

EnergyProductionSystemsEngineeringThomas Blair, P.E.USF Polytechnic – Engineeringtom@thomasblairpe.com

Session 6:Electrical Systems Spring 2011

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Session 6: Electrical Systems

Electrical Systems

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical Systems

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsIEEE defined protection numbers21 = distance relay25 = synchronism / synch check relay27 = under voltage relay32 = directional power relay40 = loss of field relay46 = current unbalance / reverse phase relay47 = phase sequence – voltage relay49 = thermal relay50 = instantaneous overcurrent relay50N = Neutral instantaneous overcurrent relay50G = Ground instantaneous overcurrent relay

4

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsIEEE defined protection numbers51 = time delay overcurrent relay51N = Neutral time delay overcurrent relay51G = Ground time delay overcurrent relay52 = breaker59 = Overvoltage relay67 = directional overcurrent relay67V = voltage restrained directional overcurrent relay81U = under frequency relay81O = over frequency relay86 = lockout relay (mechanically latching)87 = differential current relay

5

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsGenerator protection – two functionsSecurity of power system (primary)Protection of generator from transients (secondary)(IPP may have different priority)

Types of protection relays –Differential current protection – sense internal faults andtrip quickly – slope = operate current / restraint current.

6

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsBrushlessExciter

7

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsBrushlessExciter

8

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsBrushlessExciter

9

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsBrushlessExciter

10

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsBrushlessExciter

11

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsBrushlessExciter

12

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsBrushlessExciter

13

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsBrushlessExciter

14

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsBrushlessExciter

15

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsBrushlessExciter

16

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsBrushlessExciter

17

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical Systemsrelaying

18

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsStator OC protection;Not typical, alternately, monitor stator temperature

Negative Sequence Current protection – protect rotor

Stator GF protection –Neutral impedance via distribution xfmr – OV relay onsecondary to detect GF – can not detect gnd near neutral–Third harmonic UV detect ground near neutral

19

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsField Ground Protection –Apply voltage to gnd on field to detect currentResistance across field to detect shiftBrushless – momentary connect gnd detection circuit viaslip rings

20

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical Systemsgnddetection

21

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsLoss of excitation –Loss of field, protect rotor heading during inductionoperationDetect MW & MVAR to detect absorbed MVAR

Motor protection – Detect reverse power to protectTurbine from overheat.

22

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsRotor –Cylindrical rotor (uniform air gap or round rotor)2 & 4 pole machinesSalient pole machines6 pole and moreDC excitation of field windingVentilation channels for gas flowConstruction discussion

23

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsRotor inBalance Pit

24

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsComponents

25

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsSize Factors –

Small machines: lower efficienciesBig machines: better efficiencies1000MW generator: almost 99%!!!Think again of magnetics and scale rulesTherefore rather one big machine than more smallermachines1% efficiency = thousands of $ per day in power plant!!!

26

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsModeling a synchronous generator

27

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsPower delivered function of power angle.

28

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsReal Power controlled by power angleReactive power controlled by voltage magnitude

29

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsTransient Reactance -

Sudden load changes give much lower synchronousreactanceSteady state has the usual reactanceLarge machines need up to 10 secs to reach normal Xsafter transients!Good for voltage regulation at transientsBad for circuit breakage: high current

30

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsTransformers

ConstructionK-FactorWinding configuration

31

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsTransformers & Transformer protection –Oil filled transformer – dry type transformers

High efficiency

K rating – steal quality – core area to operate farther awayfrom knee of saturation curve

Harmonics – positive / negative / zero sequenceTriplen harmonics

32

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical Systems

33

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsDry type transformer cooling systems.

34

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsVoltage designations

35

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsTransformer K factor

Defined in UL 1561Ih = rms current value (pu) at harmonic hHarmonic currents = additional heatingK-factor Xfmr > K-factor System

36

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsRecommended K factor for various applications

37

TYPICAL LOAD k-FACTORS K-4

Electric discharge lighting K-4UPS with input filtering K-4

Welders K-4Induction heating K-4PLCs / SS controls (other than VFDs) K-4

Telecommunications equipment K-13UPS without input filtering K-13Multiwire receptacle circuits in general care areasHealth care facilities and classrooms of schools, etc. K-13

Multiwire receptacle circuits supplying inspection or testing equipment on anassembly or production line

K-13

Mainframe computer loads K-20

Solid state motor drives (variable speed drives) K-20Multiwire receptacle circuits in critical care areasAnd operating/recovery rooms of hospitals K-20

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsMagnetization current / over excitation.

38

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsTransformer connections

39

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsTENV dry transformers in dirty, dusty environment – alsocast epoxy vs. VPI

Auto transformer – smaller adjust voltage – no isolation

Reactor – current limiting – reduced voltage start – withcapacitor for tuned filter

40

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsDry type –epoxy cast coil

41

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsInstrument transformer – PT & CT

Transformer polarity

PT vs. CT defined by application

PT circuits in parallel – CT circuits in series

Do not short PT circuit – Do not open CT circuitSpecial shorting switch

120V / 5A (1A)42

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsAccuracy – XXYZZZXX = max error at conditionsY = C or T (calculated or tested)ZZZ = volts secondary at 20X rated secondary current.

Example 7:What is the max error at what voltage secondary for a;

10C200 current transformer

43

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical Systems10C200 current transformer

Maximum error of 10% at 200 Volts on secondary side at20 times current (100A for 5A secondary)

44

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical Systems

45

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsPotentialTransformer

46

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsCurrentTransformer

47

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsThree parts of transformer –Winding conductors, core material, insulationGrain steel – M number (lower is lower loss)

Neutral terminal / conductor = twice size phase – maintainneutral to gnd voltage < 1 V. (solid grounded system)

Arrester 5 ft from transformer (vacuum switches and/orlighting exposure)

BIL ratings of transformers

48

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsInsulation Test

1 min, power-frequency high potTest1.2/50 full-wave voltage impulse test

49

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical Systems

50

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsFull Wave vs. Chopped Wave test

51

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

52

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

53

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsDry Type transformer BIL

54

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsStandard impedance < 500KVA = 3-5 %>500 KVA = 5.75 %

Fan cooling dry type = 133% rating w/ fan

Caution, temperature of conductor connection

VPI – vacuum to draw moisture out, inject epoxy, pressureapplied (inert gas) to push epoxy into winding – heat tocure epoxy

55

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsThermal insulation class (AMB 30C)

56

AVGTMPRISE C

HOT SPOTDIFF C

HIGHESTPERM RISE C CLASS

55 10 105 A105

65 15 120 A120

80 30 150 B150

115 30 185 F185

150 30 220 H220

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsNEMA 1NEMA 3RNEMA 4NEMA 12

Dry type reduced environmental requirements and fireprotection compared with oil

Dry type available to about 15MVA

57

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsCircuit Breaker – switch to open under current

Driven by spring action both close and tripDC power for charging motorExternal relay trip on protectionArc drawn –Air / Vacuum / SF6 / OilCoordination – discussed later in relaying section

58

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical Systems

59

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

60

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

61

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsSpecial considerations:Need DC to trip / close – battery fedSynchronizingDead bus transferMotor bus transfer – reclosing

62

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsGrounding –Ungrounded / low impedance / high impedance / solidgrounded

Advantages / disadvantages

Ungrounded – reliable – first GF no tripHigh transient voltageDifficult to locate groundGround detection via open delta transformer (DRAW)

63

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsGrounding –High impedance ground (10A) – low damage, can alarm onground increase reliability,Need sensitive relay to detect and locate groundTransient less than ungrounded but higher than lowimpedance ground.

64

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsGrounding –Low impedance ground (400A) – easily detected, higherdamage, easily located, transients less, trip on fault,reduced security

Solid grounded – most damage, easily detected, easilylocated, transients minimum, trip on fault, reducedsecurity

65

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical Systems

66

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical Systems

67

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical Systems

68

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsDifferential protection on delta wye may need wye deltaconnected CTs to compensate for 30 degree phase shift.

69

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical Systems

70

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsCan add grounding transformer to ground a delta fedsystem

71

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical Systems

72

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical Systems

73

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsSystem-grounding design considerations –Three levels of conductor insulation for MV cables: 100,133, and 173% levels.The solidly grounded system permits the use of 100%insulation level.If fault cleared within 1 hour, 133% insulation level shouldbe specifiedIf fault cleared more than 1 hour, 173% voltage levelinsulation should be used

74

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsGrounding –Adequate ground-return conductors to minimize theinherent step-and-touch potentials w/ solidly groundedsystems Instantaneous ground fault relaying to minimizethe fault duration.

See the NEC NESC and IEEE Std 80

75

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsAll non -current-carrying metallic structures areinterconnected and grounded.Purpose:Minimize potential difference between metallic membersMinimizing the risk of electric shocks to personnelImprove protective device performanced) To avoid fires in combustible atmospheres

76

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsInductance of ground path

L = 4 X 10-7 ln ( D / r’ ) H/m

Therefore, L increases as D increases

VD increases as D increases &Current tends to flow in closest cond.

77

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsTwo or more rods suggestedDistance between rods must be Lr1 + Lr2Example two 8 ft rods, should be 16ft distance(Numerous books and articles show the distance betweentwo standard length 8 or 10 ft rods to be 3 m (10 ft), whichis incorrect.)

78

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsImpedance depended on IEEE 80 Calc.Larger substations and generating stations < 1WSmaller substations and for industrial plants < 5WNEC, Article 250, approves the use of a single electrode, if< 25W

79

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsProtective relaying & coordination:

Two functions – Protection of equipment (secondary)Security of system (primary)

Trip when faulty condition present AND don’t trip whenfaulty condition not present

80

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsBalance of following concepts:Reliability – Relay system trip when fault exists inprotective zoneSecurity – Relay system trip only when fault exists inprotective zoneSelectivity – Relay system should trip minimum equipmentto remove faultSpeed – Relay system remove fault fast to minimizedamage and arc flash incident energy.Simplicity – minimum amount of equipment – maximizereliabilityEconomics – Reasonable cost

81

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsMost common – 50, 51, 27, 59, 81O, 81U, 87

PTs and CTs feed relays

82

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical Systems

83

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical Systems

84

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical Systems

85

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical Systems

86

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical Systems

87

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsGround fault –Unbalanced current – not easily detected by phase relay,use sensitive ground fault relayFor grounded system, use 50G or 51G as shown below.For ungrounded system use broken delta with 59 relay.

88

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical Systems

89

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsPhase Faults:Line to Line, Line to Ground (solid system), and 3 phasefault detection. 50 and/or 51 detect.

Overvoltage (59) – typically used on neutral or grounddetection systems

Frequency (81O & 81U) – indication of system transient.Protection during “Islanding”

90

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsDifferential relay (87) –Detect internal fault quickly – ignore external fault reliablyMay be more than just 2 winding device (i.e. 6 CT inputs)

Overcurrent (50/51) both phase and ground detection –51 device to allow for coordination between elements

91

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical Systems

92

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsDirectional overcurrent (67) –Control flow of power – prevent motoring of generatorNeed VT & CT to polarize relay

Distance relay (21), trip if fault in zone 1, backup for zone2, 3. Needs VT & CT input. Common application is lookingback into generator impedance (quick trip of breaker forgen fault).

93

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical Systems

94

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsSynchronizing relay (25) -

Both Synchronizing and Synch check

Magnitude, angle, rotation, frequency

95

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical Systems

96

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsTypical Relay& ProtectionOne-lineDiagram

97

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsShort Circuit Current Calculations

Purpose- Present considerations of short-circuit currentcalculations;- Illustrate common methods for calculations;- Furnish typical data used in calculations.

98

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsRotating Machine Equivalent Circuit

99

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsXd ’ ’ - subtransient reactance – (0 < t < 0.1s )Xd ’ - transient reactance – (0.1 < t < 0.5 to 2.0s )Xd - synchronous reactance – (0.5 to 2.0s < t ) SteadyState

When given Xdv ’ ’ – (at rated voltage, saturated, smaller)and Xdi ’ ’ – (at rated current unsaturated, larger), use Xdv’ ’

100

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsXd ’ ’ - subtransient reactance – (0 < t < 0.1s )No Value for Xd ’ and Xd as motor only contributes SCA forinitial cycles.

101

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsUtility normally shown with as infinite bus with fixedimpedance.For MV & HV systems, R usually ignoredFor LV system R includedArc Resistance not zero

102

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsSelect location for purpose of calculation- Establish simple modelRecognize restraints of modelAdjust model if assumptions too restraining

103

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsStep 1: Prepare system diagramsStep 2: Collect and convert impedance dataStep 3: Combine impedancesStep 4: Calculate short-circuit current

104

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsWye Delta Conversion

105

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsDelta Wye Conversion

106

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsPer Unit Calculations

107

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsPer Unit Calculations

108

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical Systemsexample

109

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsSoftware Model

110

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsSubtransientResult

111

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsSteady state result

112

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsFault at MCC1

113

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsCorrect Phase TCC

114

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsCorrect GroundTCC

115

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsIncorrect PhaseTCC

116

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsIn-Plant Electrical Distribution SystemEnsure reliability of systemEither higher spinning reserve – high failure rateLow spinning reserve – low failure rate

Without reliable distribution system, plant operation cannot be reliable.

117

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsDistribution system design standards:IEEE Color Books

EMERALD BOOK IEEE Std 1100-1999 IEEE RecommendedPractice for Powering and Grounding Electronic Equipment

RED BOOK IEEE Std 141-1993 IEEE Recommended Practicefor Electric Power Distribution for Industrial Plants

118

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsDistribution system design standards:IEEE Color Books

GREEN BOOK IEEE Std 142-1991 IEEE RecommendedPractice for Grounding of Industrial and CommercialPower Systems

BUFF BOOK IEEE Std 242-2001 IEEE RecommendedPractice for Protection and Coordination of Industrial andCommercial Power Systems

119

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsIEEE Color Books

BROWN BOOK IEEE Std 399-1997 IEEE RecommendedPractice for Industrial and Commercial Power SystemsAnalysis

ORANGE BOOK IEEE Std 446-1995 IEEE RecommendedPractice for Emergency and Standby Power Systems forIndustrial and Commercial Applications

120

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsIEEE Color Books

GOLD BOOK IEEE Std 493-1997 IEEE RecommendedPractice for the Design of Reliable Industrial andCommercial Power Systems

BRONZE BOOK IEEE Std 739-1995 IEEE RecommendedPractice for Energy Management in Industrial andCommercial Facilities

121

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsNFPA HFPE and Society of Fire Protection Engineers SFPEHandbook of Fire Protection EngineeringNFPA 101H, Life Safety Code HandbookNFPA 20, Centrifugal Fire PumpsNFPA 70, National Electrical CodeNFPA 70B, Electrical Equipment MaintenanceNFPA 70E, Electrical Safety Requirements for EmployeeWorkplacesNFPA 72, National Fire Alarm CodeNFPA 75, Protection of Electronic Computer/DataProcessing Equipment

122

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsDifference between

Code (Stand alone)Standard (Shall)Recommended Practice (Should)Guide (May)

123

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsSystem Planning.

a) Load development & schedule1) Peak load requirements2) Temporary power3) Timing

b) Load variations – load growth.

124

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical Systemsc) Nature of load in terms of its occurrence

1) Continuous2) Intermittent3) Cyclical4) Special or unusual loads5) Combination of above

d) Expected power factor

125

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsCost vs. Reliability- Radial system- Primary-selective systemSecondary selective system

- Simple spot network system- Secondary-network system

126

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical Systems

127

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsSimple Radial System

- Fault in device = power outage- Maintenance difficultOperation simple

Low capital costLarger installations where outage time not critical

128

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical Systems

129

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsExpanded Radial System –

Fault in main feed = power outageFault in xfmr = reduced outage- Maintenance difficultOperation simple

Low capital cost

130

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical Systems

131

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsPrimary Selective System –

-Protection against loss of primary feed-Still Xfmr Dependent-Primary source Maintenance easier-Slightly higher capital cost

132

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical Systems

133

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsProtection against loss of primary feedStill Xfmr DependentSlightly higher capital costOperation slightly more difficultOpen loop operationMore reliable with loop closed and directional protectionbut two devices to isolate fault

134

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical Systems

135

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsProtection against loss of primary feed and primary xfmrMaintenance of xfmrHigher capital costOperation more difficultSize xfmr & breaker for full load

136

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical Systems

137

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsSimilar to secondary selective systemXfmr sized for only one busN+1 transformer neededOperation difficult – interlock so xfmr only feed one bus ata timePossible retrofit

138

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical Systems

139

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsRequires Network ProjectorTrip on reverse powerHigh reliabilityHigh cost

140

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical Systems

141

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsTwo devices to isolate faultTrip on reverse powerHigh reliabilityHigher cost

142

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsExpected daily and annual load factor:

143

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsLarge motor-starting requirements

1) HP, FLA, LRA2) synchronous - induction3) Voltage4) Starting requirements

Special or unusual loads such as1) Welding2) Induction heating or melting3) Portable (Crane)

144

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical SystemsHarmonic-generating loads

1) VFDs2) Arc discharge lighting3) Arc furnaces4) SCR controlled loads

Special power quality requirements for sensitive or criticalloads

1) Data processing operations2) Special machines (Semiconductor process)3) Continuous process loads

145

Energy Production EngineeringThomas Blair, P.E.

(tom@thomasblairpe.com)

Electrical Systems

To be continued …

EnergyProductionSystemsEngineering

Thomas Blair, P.E.USF Polytechnic – Engineeringtom@thomasblairpe.com

End of Session 6:Electrical Systems

Spring 2011