Post on 05-Feb-2021
Electrical, Plumbing and Gas Permit Timeline
Begin Process 1 2 3 4
5
Completed Application Submitted to the Town
Review Based on Quality Managment Plan Requirements
(If outstanding items exist return to step 1)
1-2 weeks
Issue Permit
Applicant Requests Inspections
(Plumbing ,Electrical ,Gas) at Strathmore.ca
(quicklinks)
2 weeks - 12 months depending on type of application
V4.18.04.2019
6Re-inspection
Performed (if required)
Internal Circulation and Review *At this stage each stakeholder must have adequate response time for a meaningful review. VOC = Verification of compliance to confirm completion of items noted on the inspection report.
2-5 days
Inspection Performed
Final Inspection (if required)