  • Electrical, Plumbing and Gas Permit Timeline

    Begin Process 1 2 3 4

    5

    Completed Application Submitted to the Town

    Review Based on Quality Managment Plan Requirements

    (If outstanding items exist return to step 1)

    1-2 weeks

    Issue Permit

    Applicant Requests Inspections

    (Plumbing ,Electrical ,Gas) at Strathmore.ca

    (quicklinks)

    2 weeks - 12 months depending on type of application

    V4.18.04.2019

    6Re-inspection

    Performed (if required)

    Internal Circulation and Review *At this stage each stakeholder must have adequate response time for a meaningful review. VOC = Verification of compliance to confirm completion of items noted on the inspection report.

    2-5 days

    Inspection Performed

    Final Inspection (if required)