PPD CMS Away Day, Cosenors House, 29/9/05 D.J.A. Cockerill 1
DJAC: PPD CMS ECAL Hardware Tasks
(i) The next 2.5 years
(ii) The following 2.5 years
To March 2008
April 2008 – Oct 2010
PPD CMS Away Day, Cosenors House, 29/9/05 D.J.A. Cockerill 2
VPTs
Continued mass production testing to ~Sep 2006
Main contract
Replacements contract
Database RAL – CERN to ~Dec 2006
VPT sorting to ~ Dec 2006?
Shipping to CERN – all by Dec 2006?
People
Bruce, Joolz, Martin, Laurie (only to 31 March – X, 2006!)
VPT Production
PPD CMS Away Day, Cosenors House, 29/9/05 D.J.A. Cockerill 3
HV cards/Umbilical/Motherboards/VFE cards
Components fully specified by Jan 2006Preproduction for Dee4, 20 SC sets by Spring 2006:
- 105 HV cards- 20 umbilicals- 20 Motherboards- 105 VFE cards
PeopleClaire, Ken, Bob, (Matt, Mark, Werner)
SC Front End
Thermister calibration
20 calibrated thermisters needed for Dee4 SCs by Spring 2006Total of 560 calibrated thermisters, evenly to end 2007
People Paul, Joolz
RAL PPD/RAL ID
ETH-Z
PPD CMS Away Day, Cosenors House, 29/9/05 D.J.A. Cockerill 4
VPT HV
HV distributionPreparation for Dee4CAEN HV supply + prototype distribution box by April 2006HV software drivers tested with SC01 at RAL
HV distribution method defined WITHIN a Dee, by April 2006
PeopleClaire, Ken, Bob, Philip, Barbara, (Tony)
PPD CMS Away Day, Cosenors House, 29/9/05 D.J.A. Cockerill 5
VPT HV
HV test boxTest pre-production HV card/umbilical assemblies for Dee4
Measure/check continuity, iL at 1500VConstruction by RAL PPD, by March 2006Test of first 20 assemblies by April 2006, ship to CERN
PeopleClaire, Ken, Laurie, Joolz, Barbara, (Tony)
PPD CMS Away Day, Cosenors House, 29/9/05 D.J.A. Cockerill 6
Mass production of HV cards/umbilicals, summer 2006 – spring 2007
Procurement RAL PPDTests of HV cards/Umbilical assemblies with HV test box
(Motherboards/VFE cards ETH-Z)
Tests for correct trigger mapping to the motherboards,before mounting on DeesRAL PPD/Virginia ??
PeopleClaire, Ken, Laurie, Joolz, Barbara, Dave, (Tony)
VPT HV mass production
PPD CMS Away Day, Cosenors House, 29/9/05 D.J.A. Cockerill 7
VPT LED Stability pulser
Prototype LED firing box for Dee4 by April 2006Up to 5 fibre outlets needed for Dee4
PeoplePaul, Bob, (John Hill/Tony, fixing to patch panel, fibre routings)
Collaboration with Virginia – decide who does what, by Jan 2006- Newer/better LEDs/improved coupling- LED driver- Complete drive boxes- Interface to ECAL DAQ
As an alternative monitoring system, by summer 2006- can we get to 50, 100 GeV equivalent??
PeoplePaul, Bob, Ken, Dave, (Tony)
PPD CMS Away Day, Cosenors House, 29/9/05 D.J.A. Cockerill 8
Dee4 at CERN
Dee4 assembly/tests Spring/Summer/Autumn 2006
SC soak test stand by March 2006
Oversight of Dee assembly: SC assembly/mounting on Dee4
Dee4 test stand - collaboration with Virgina for front light injection tests- use prototype HV distribution system
- tests of motherboard trigger configuration- learn to operate ‘mobile’ ECAL electronics test stand
- analysis of data- VPT LED stability pulser
People.
Dave, Claire, Barbara, Joolz, Paul, (Matt, Tony) at CERN
PPD CMS Away Day, Cosenors House, 29/9/05 D.J.A. Cockerill 9
Dee4 in beam at CERN
Dee4 in test beam October 2006 and/or April 2007
Installation at H4
Debugging
Shifts
AnalysisProof of VPT stability
People
Dave, Ken, Claire, Bruce, Barbara, Joolz, Paul, Bob
PPD CMS Away Day, Cosenors House, 29/9/05 D.J.A. Cockerill 10
Dee1 – Dee4
Dee1 – Dee4 from Summer 2006 – March 2008
Bare SC assembly from Q1 2006 onwards
SC mass production from summer 2006 – Feb 2008
RAL PPD - responsibility for SC soak tests
- analysis of test stand data
- continuity/HV/trigger tests on Dee, in collaboration with Virginia
- analysis of Dee4 test data
- VPT LED pulser systems/checks, in collaboration with Virginia
People
Dave, Claire, Bruce, Barbara, Joolz, Paul, Bob, (Tony, John)
Mounting of Dees on HE± , 2007/2008
PeopleKen, (John, Tony)
PPD CMS Away Day, Cosenors House, 29/9/05 D.J.A. Cockerill 11
Dee1 – Dee4
Complete HV distribution systems
- needed for bldg 867 integration tests
- Full Dee4 system by Feb 2007 (keep in 867)- Dee1-3 systems by Dec 2007
People
Claire, Ken, Joolz, Barbara, (Tony)
Mounting of Dees on HE± , 2007/2008
PeopleKen, (John, Tony)
PPD CMS Away Day, Cosenors House, 29/9/05 D.J.A. Cockerill 12
The Transition
March 2008
4 Dees installed in CMS
Need to Shepherd our resources
as the group’s Brownian motion diminishes
What do we do?
My personal opinion, particularly for the first (EE) LHC run :
PPD – duty to show EE working as expected
duty to show VPTs are stable
(does not necessarily imply continuous calibration
responsibility)
People
Dave, Ken, Claire, Bruce, RA1, RA2
PPD CMS Away Day, Cosenors House, 29/9/05 D.J.A. Cockerill 13
2.5 years of LHC running
Hardware
PPD – responsibility for all things ‘VPT’
keep it all running during LHC on periods
interventions/repairs/upgrades during short/long shutdowns
- Special care/analysis at each substantial luminosity increase
VPT leakage currents, stability, noise…….
- Analysis of data – to check EE performance
People
Dave, Ken, Claire, Bruce, RA1, RA2
CMS run control
Ken
PPD CMS Away Day, Cosenors House, 29/9/05 D.J.A. Cockerill 14