Capital Market Day - Brickworks - ANH Updates clean 100418 · Microsoft PowerPoint - Capital Market...

Post on 07-Jul-2020

12 views 0 download

Transcript of Capital Market Day - Brickworks - ANH Updates clean 100418 · Microsoft PowerPoint - Capital Market...

Capital Market Day - 3 November 2016

PERSIMMON PLC

BRICKWORKS

1Capital Market Day - 3 November 2016

Brickworks - Opportunity

• Increase in industry volume in 2013

• Sourcing clay bricks problematic

• Action required to secure supply

• Build programme management

• Build cost control

2

Brickworks - Site

Capital Market Day - 3 November 2016

• Harworth, South Yorkshire

• Brownfield site

• Former glassworks

• Site remediated by Persimmon

• Local to raw materials

• Excellent links to M1 and A1

3Capital Market Day - 3 November 2016

Brickworks - Factory

• Construction underway

• New build factory

• Aggregate storage area

• Storage yard for product

• Weighbridges for material

control

• 1,900m2 / 20,000sqft

• Commissioning Q1 2017

4Capital Market Day - 3 November 2016

Brickworks - Equipment

• Manufactured in Spelle, Germany

• World leading supplier

• Innovative design

• Robust construction

• High durability

• Low maintenance

• High degree of automation

5Capital Market Day - 3 November 2016

Brickworks - Process

Key Components:

• Batching and Mixing Plant

• Cement Silos

• Brick Machine

• Curing Chamber

• Packaging Line

Process:

• Pigment coloured concrete

• Bricks pressed in moulds

• Controlled environment curing (high energy kilns not required)

• Void packed - No timber pallets

• Stretch hooded for despatch

6Capital Market Day - 3 November 2016

Brickworks - Product

• Consistent high quality

• Vibrant colours

• Excellent kerb appeal

• Durable finish

• Dimensionally precise

• Superior strength

• 100% recyclable

• Concrete is a CO2 absorber

7Capital Market Day - 3 November 2016

• c. 80 million bricks per annum

• Shift operation to optimise efficiencies

• 25 employees

• Limited product range increases efficiency

• Other products possible with simple 10 minute mould change e.g. block paving

• Products adaptable to meet local planning requirements

Brickworks - Operation and Capacity

8Capital Market Day - 3 November 2016

Brickworks - Economics

• Investment < £10 million

• Payback period under 3 years

• Assist build programming and site efficiencies to aid productivity

improvement