AESO Export Capability Workshop February 16, 2006 Metropolitan Centre, Calgary. AB to BC Transfer BCTC perspective. Calgary, Alberta - Feb 16, 2006. The BC Transmission System. Snapshot: 18,000 km circuit transmission lines 287 switching, distribution and capacitor stations - PowerPoint PPT Presentation

Transcript of AESO Export Capability Workshop February 16, 2006 Metropolitan Centre, Calgary

AESO Export Capability Workshop

February 16, 2006

Metropolitan Centre, Calgary

AB to BC Transfer BCTC perspective

Calgary, Alberta - Feb 16, 2006

Feb. 16, 2006 Page 3

The BC Transmission System

Snapshot:• 18,000 km circuit transmission

lines• 287 switching, distribution and

capacitor stations• Control Centers

• 1 System Control Center• 4 Area Control Centers

• 244 microwave and repeater sites

• Transmission rights-of-way• Interconnected to Alberta and

the Pacific Northwest for over three decades

Feb. 16, 2006 Page 5

BCTC Bulk Transmission System Overview (export to US)

NICSEL

KLY

REV

WSN

MCA

CBK

ACK

VAS

GMS/PCN

LM & VI

SEL area gen

5L925L94

5L91

5L965L98

5L81 & 5L82

5L51 & 5L52

5L875L76 & 5L79

2L112

BPA

Feb. 16, 2006 Page 6

BCTC Bulk Transmission System Overview(import from US)

NICSEL

KLY

REV

WSN

MCA

CBK

ACK

VAS

GMS/PCN

LM & VI

SEL area gen

5L925L94

5L91

5L965L98

5L81 & 5L82

5L51 & 5L52

5L875L76 & 5L79

2L112

BPA

Feb. 16, 2006 Page 7

Transmission Line Forced Outage (3 pole) Approx Data

Notes:1. SPR provided

in late 2002

2. SPR provided in mid 2003

3. SPR to be provided in 2006

4. SPR provided in 2005

5. Include sequential ctgs in less than 5 minutes

6. * SPR provided

500kV LinesCircuit Length

(km)3 Phase forced

outages Data Years

Forced outage per

year

5L76 (note 1 ) 118 65 22 2.98

5L79 (note 2) 118 70 21 3.35

5L81 * 264 55 22 2.52

5L82 * 248 62 22 2.84

5L91 (note 3) 223 181 22 8.29

5L92 * 180 62 22 2.84

5L94 * 319 146 20 7.30

5L98 (note 4) 302 381 22 17.45

5L51 & 5L52 36 / 36 1 22 0.05

5L91 & 5L98   3 (note 5) 22 0.14

5L76 & 5L79   4 22 0.18

5L81 & 5L82   3 22 0.14

5L1/2/3/4/7 double contingencies approx 278 14 22 0.64

5L11/12/13 double contingencies approx 330 12 22 0.55

Feb. 16, 2006 Page 8

BCTC RAS

• RAS arms generation shedding, line tripping, reactive equipment switching, and calculates transfer limits

• RAS armed in real time dynamically

• RAS arming based on actual flows

• TSA runs every 4 minutes

• TSA arms RAS

• RAS armed automatically

Feb. 16, 2006 Page 9

Feb. 16, 2006 Page 10

Questions?