Advanced BIM and Lean Jaime Johnston, Bryden Wood Associates Brian Swain, Brian Swain Ltd.

Post on 19-Jan-2016

230 views 0 download

Tags:

Transcript of Advanced BIM and Lean Jaime Johnston, Bryden Wood Associates Brian Swain, Brian Swain Ltd.

Advanced BIM and Lean

Jaime Johnston, Bryden Wood Associates Brian Swain, Brian Swain Ltd

Lean Improvement Programme

Birmingham Gateway Project

Lean Programme Objectives• Focus on the delivery of Client requirements

• Stabilise & improve the programme

• Improve quality, delivery, cost and H&S performance

• Work collaboratively with all teams across the Critical Paths to promote teamwork, sustainable & practical solutions

• Start Early

The Five Lean Principles

• Specify what creates ‘value’ from the client’s perspective

• Identify all steps across the whole value stream for every product family

• Make those actions that create value flow

• Only make what is pulled by the customer

• Strive for perfection by continually removing successive layers of waste.

Client Agreed Value Definitions

A lean principle that drives the definition of:

Customer valuesWithin the

Project ConstraintsAnd therefore drives the

clarity of

Goal Deployment

• Delivery Early• High Quality• Whole Life Cost

Drive Value

YET

AchieveCost

Collaborative Programme Compression

Objective: Stabilise and Improve the Programme Delivery to Client’s Needs

Lean Tools and Techniques

• Stability & Improve

• Whole programme focus

• Improvements at all levels

• Client and Contractor involvement

Maximising the Benefits• Early engagement & start up = maximum benefits = Stability and Improve

• Whole programme analysis and improvements - Design - Handover

Critical Path Focus

Gateway Atrium DemolitionObjective - secure & achieve 6 month programme reduced from 12 months

Achieved • 5 months for bulk of demolition - with slow start,

overlap of areas • Associate trades interfaced - floating decks, Rail • Additional works integrated - tension, edge works

Lean Activities

Visual Management DeploymentDesign Hub – Collaborative clusters Project Completion Hub - focus

Gold Command Room - Hotspots/escalation

Project Completion - detailed planning

Supporting schedule of meetings, actions reviews, escalation and performance

7 Wastes - Improved Performance

• Overproduction

• Inventory

• Transportation

• Process

• Idle Time

• Operator Motion

• Bad Quality

Dispersal Tunnel Scope

Where does it fit? Is it Critical?

Potential Options

• Build a new Tunnel• Expensive, safe, impacts other Construction activities

• Move it in sections • Slow, disruptive, repetitive risk, costly

• Move swiftly• Cost effective, riskier, less disruptive

• CLIENT MOST SATISFIED

Steps to identify improvement

Preparatory Works

• Cabling replaced

• Plug and play connections

• Back up distribution boards installed

• Unit movement jacks and wheels

• Trial runs and test

Lean Deployment Benefits

Specific Highlights:-• Demolition Process Improvement 12months to 6 months

• Dispersal Tunnel 3 weeks to 52 hours

• Asbestos process improvement turnaround 8.3 days down to 3 days

• Vertical Access Programmes saved 2 weeks / area

• John Lewis Partnership and Facades XCSC handover and Façade productivity

• Duty Managers Process 50% reduction in leadtime

• Quantifiable benefits = £28m • Mitigated Losses • Numerous associated benefits – Facades, Rail platforms, Vertical Access• Collaborative Planning deployed, Logistics planning and work studies

Associated Benefits

General Overview• Embedded Collaborative Planning as the norm

• Data and visual process level driven

• Embedded Visual Management in various formats

• Focus on Programme Compression, not just acceleration

• Senior Team Facilitation

• Impartial Process Driven

• Completion process support