30.11.05suite4121 Inspection & Test Overview. 30.11.05suite4122 Why does an electrical installation...

Post on 16-Dec-2015

221 views 0 download

Tags:

Transcript of 30.11.05suite4121 Inspection & Test Overview. 30.11.05suite4122 Why does an electrical installation...

30.11.05 suite412 1

InspectionInspection & Test& TestOverviewOverview

30.11.05 suite412 2

Why does an electrical installation require Inspection and Testing?

BS 7671:2001

711-01-01 Every installation shall, during711-01-01 Every installation shall, during

erection and on completion erection and on completion before beingbefore being

put into serviceput into service be inspected and tested to be inspected and tested to

verify, so far as is reasonably practicable,verify, so far as is reasonably practicable,

that the requirements of the Regulations that the requirements of the Regulations

have been methave been met

30.11.05 suite412 3

Before being put into service

““It’s ok misses we've finished the electric's,It’s ok misses we've finished the electric's,

we've put the supply on”. “be back nextwe've put the supply on”. “be back next

week to test it”week to test it”

Simple: If it has not been inspected and tested,

it should not be energised.

No discussion - No connection!No discussion - No connection!

30.11.05 suite412 4

712-01-01 Inspection

The inspection shall be made to verify that the installed electrical equipment is:

(i) in compliance with Section 511 compliance with standards - British Standards or, Harmonized Standard

(ii) correctly selected and erected in accordance with the Regulations

(iii) not visibly damaged or defective so as to impair safety

30.11.05 suite412 5

Certification

30.11.05 suite412 6

Every Inspection and Test mustbe recorded on the appropriatecertificate

30.11.05 suite412 7

The Installation Certificate

“Where do I use it?”

30.11.05 suite412 8

• For new installations

• For alterations or additions that include a new circuit

30.11.05 suite412 9

The Installation Certificate

“what does it consist of?”

30.11.05 suite412 10

• Details of client

• Installation address - Must include post code

• Description and extent of the installation

• Signatories those with a responsibility for (i) The design (ii) The construction (iii) The inspection and testing

• Recommend date for next inspection

30.11.05 suite412 11

Who recommends the date for the next inspection (Periodic) ?

THE DESIGNER

30.11.05 suite412 12

Who recommends the date for subsequentinspections and tests (Periodic) ?

THE INSPECTOR

30.11.05 suite412 13

SUPPLY CHARACTERISTICS AND EARTHING ARRANGEMENTS

• TN-C (of specialist nature)

• TN-S• TN-C-S • TT

• IT (of specialist nature)

30.11.05 suite412 14

Number and type of live conductors

• whether the supply is a.c. or d.c.• number of phases• number of poles

30.11.05 suite412 15

Nature of Supply Parameters

• nominal voltage U/Uo (V) Fixed

• nominal frequency, f (Hz) Fixed

• external loop impedance Ze ()

• prospective fault current, Ipf (kA)

30.11.05 suite412 16

Prospective Fault Current (Ipf) kA

May be obtained by

• Measurement

• Calculation

• Enquiry Public Electricity Supply (PES)

30.11.05 suite412 17

External loop impedance Ze

May be obtained by

• Measurement

• Calculation

• Enquiry

30.11.05 suite412 18

Supply Protective Device Characteristics (PES)

• Type i.e. BS 1361 Type 2, BS 88

• Nominal current rating (A)

30.11.05 suite412 19

Particulars of installation referred to in the certificate

• Means of earthing

• Maximum demandMaximum demand (Not rating of (Not rating of

serviceservice head fuse)head fuse)

• Details of earth electrode resistance Details of earth electrode resistance if applicableif applicable

30.11.05 suite412 20

Review - Characteristics of Supply

313-01-01 The following characteristicsof the supply or supplies, from whateversource shall be determined by calculation, measurement, enquiry or inspection

30.11.05 suite412 21

• The nominal voltage/s

• The nature of the current and frequency

• The prospective short circuit current

• Earth fault loop impedance Ze

• Maximum demand after diversity

• Type and rating of overcurrent device at the origin of the installation

30.11.05 suite412 22

Main Protective Conductors

Earthing Conductor

• Material Cu - copper etc

• c.s.a

• Connection verified (low resistance ohmmeter)

30.11.05 suite412 23

Main Equipotential Bonding Conductors

• Material Cu - copper etc

• c.s.a

• Connection verified (low resistance ohmmeter recommended maximum value 0.05)

30.11.05 suite412 24

BS /BS EN NumberNumber of PolesCurrent RatingVoltage Rating

30.11.05 suite412 25

Main Switch or Circuit Breaker

• BS Type and Number of Poles

• Current rating (A)

• Voltage rating

• Fuse rating or setting

• Location

• RCD In (mA) and operating time (mS) at In

30.11.05 suite412 26

Comments on Existing Installation

To be used for alterations or additions

30.11.05 suite412 27

Schedule of items inspected

Refer to ScheduleCommon to both Installation

&Periodic Inspection Report

30.11.05 suite412 28

The Visual Inspection

Chapter 71 Initial Verification

Footnote to Regulation 711-01-01Precautions shall be taken to avoid danger to persons and to avoid damageto property and installed equipmentduring inspection and testing

30.11.05 suite412 29

The Visual Inspection

712 Inspection

Inspection shall precede testing andshall normally done with that part of theinstallation under inspection disconnected from the supply

30.11.05 suite412 30

Test equipment to GS 38

Probes 4mm max pref 2mm max

Fused Leads

Finger Guards

Safe Isolation

30.11.05 suite412 31

Schedule of Test Results

Refer to Schedule

Common to both Installation&

Periodic Inspection Report

30.11.05 suite412 32

Periodic Inspection Report (PIR)

• Change of use or ownership

• As a result of damage. Fire - Flood etc

• Electrical overloading

• To ensure compliance/continued compliance with the Regulations

• Mortgage/Insurance request

• Local bylaws - Places of public entertainment - Theatres/Cinemas etc

30.11.05 suite412 33

Periodic Inspection Report (PIR)

• Some areas common to Installation Certificate, i.e.

• Details of client and installation

• Recommended next inspection date

• Signature of competent person

• Supply characteristics

• Particulars of installation

30.11.05 suite412 34

(PIR) continued

• Schedule of inspection

• Schedule of test results

30.11.05 suite412 35

Major Differences

• Estimated age of installation?

• Evidence of alterations or additions?

• Are there records available?

• Extent and limitations

• Observations and recommendations

30.11.05 suite412 36

Extent and Limitations

• Extent - Details indicating what part/sExtent - Details indicating what part/s of the installation will be inspected andof the installation will be inspected and testedtested

• Limitations - State exactly what items are excluded, i.e. portable appliances, fire alarm systems, emergency lighting, cctv, door entry systems, smoke detectors etc.

30.11.05 suite412 37

Numerical codeNumerical code

Departures from BS 7671 must be allocateda numerical code

• 1. requires urgent attention

• 2. Requires improvement

• 3. Requires further investigation

• 4. Does not comply with BS 7671 - imply that installation is unsafe

30.11.05 suite412 38

Minor Works

An alteration or addition to an existing installation that does not include the addition of a new circuit, i.e. spur to radial or ring circuit etc.