The Great DebateShould Schedule Revisions Require
Owner Approval?
Should Schedule Revisions Require Owner Approval?
• The Debaters:
• Pro position debated by the team of Chris Carson and Mark Boe– affectionately called “The Naysayers”
• Con debated by the other team of Mark Sanders and Carmelita Thorndike – just call them “The Manipulators”
• Now, for those that are unenlightened enough that they don’t know these famous orators, a few biographical facts:
2
Carmelita Thorndike
• The SCL COO, Contractor Rep (you want what? when?)
• Represents the Contractor viewpoint
3
Mark Boe, P.E., PSP, all around good guy
• Master of the “it depends” response (Partner in charge of RFIs)
• Represents the Owner viewpoint
4
Mark Sanders, P.E., PSP, CCE
• Contractor – friendly consultant (ohhh, the poor contractor!)
• Represents the Contractor viewpoint
5
Chris Carson, PSP, CCM, PMP
• Pure and Subjective Owner CM (never met a change order he liked)
• Represents the Owner viewpoint
6
Should Schedule Revisions Require Owner Approval?
• NOTE:
• The Pro position is that revisions should require Owner approval
• The Con position is that revisions should be allowed without approval and should not require Owner approval
• The terms come from shortening of the Latin phrase, “pro et contra” which means “for and against”
• Now for some background to frame the debate…
• These slides look like they were designed by the cost engineers.
7
Should Schedule Revisions Require Owner Approval?
• Definitions– Schedule Revisions
• Any change to the schedule except for progress updates
• Serious changes to network logic and/or durations
– Schedule Updates
• Progress only
• No changes to any logic, durations, calendars, lags, constraints, or other
software settingssoftware settings
• And we choose:– Schedule Revisions
• Serious changes to network logic and/or durations
• Minor changes to accommodate project management minor changes to
plan are included in schedule updates
8
Should Schedule Revisions Require Owner Approval?
• Available Owner Actions– Silence (as Donald calls it) of the owner – receipt only, no response to schedule
submission
• Owner anticipates that the schedule will meet the schedule specifications
• Owner does not provide any response to the schedule
– Review and acceptance
• Owner acknowledges schedule contains no conflicts with their needs
(milestones, Owner responsible work, access)(milestones, Owner responsible work, access)
• Owner checks to see that schedule meets schedule specs
• Owner review comments on issues with the statement above
– Review and Approval or Rejection
• Owner reviews for technical accuracy, and agrees that the project is
constructible as represented in the schedule
• Owner review comments clarify approval of constructability
• Owner review comments on any technical issues, generally providing
deficiencies and best practice violations (hopefully separately)
9
Should Schedule Revisions Require Owner Approval?
• Available Contractor Actions for Submissions– Contractor language indicating silence is approval (Donald)
– Failure to submit schedule
– Failure to respond to Owner’s comments
– Rebuttal of Owner’s comments
– Build claim
10
Should Schedule Revisions Require Owner Approval?
• Legal positions concerning approval (see end):– oDoes it matter where a schedule is approved or not?
– oHow does it affect time extension requests?
– oHow does it affect forensic claims?
11
Should Schedule Revisions Require Owner Approval?
• When a schedule is approved there is a rebuttable presumption of correctness or reasonableness of the schedule. Santa Fe, Inc., VABCA No. 2168, 87-3 BCA ¶ 20,104 (1987). – Because of this rebuttable presumption of the reasonableness of the
schedule where an approval is in place, many Owners are afraid of approving any schedule much less an early completion schedule. approving any schedule much less an early completion schedule.
– However, the approval process is the only chance for the Owner to weigh in on overly aggressive or erroneous schedules (with all float removed, defective logic, unauthorized inclusion of constraints, unrealistically short approval cycles, etc.).
12
Should Schedule Revisions Require Owner Approval?
• Case law holds that even where a schedule has been approved it will be thrown out if it contains unrealistic logic and/or durations. – See e.g. Neal & Co. v. United States, 36 Fed. Cl. 600 (1996); Hensel
Phelps Construction Co., ASBCA No. 49270, 99-2 BCA par 30,531 (1999).
13
Should Schedule Revisions Require Owner Approval?
• Owners and/or their Construction Managers will occasionally refrain from approving or acting upon a Contractor’s proposed schedule because they fear that their response can later be used by the Contractor as acceptance of the schedule and the Owner’s responsibility under the schedule. – In many cases, this type of forbearance is unsuccessful. Courts have – In many cases, this type of forbearance is unsuccessful. Courts have
imposed implied obligations upon Owners with regard to the schedule despite the Owner’s silence.
– In one case, when an Owner even orally disclaimed parts of the schedule but failed to actually reject the Contractor’s initial proposed schedule, the Owner was held to be bound to time durations contained in the submitted schedule. Fullerton Constr. Co., ASBCA No. 12275, 69-2 BCA ¶ 7876 (1969). See also G. Blindzius Contractors, Inc., ASBCA No. 37707, 90-2 BCA ¶ 22,835 (1990).
14
Should Schedule Revisions Require Owner Approval?
NOW, ON TO THE DEBATE!
15
Should Schedule Revisions Require Owner Approval?
• Doesn’t the Contractor own the schedule?– Pro – Project is for the use of the Owner
16
Should Schedule Revisions Require Owner Approval?
• Doesn’t the Contractor own the schedule?– Con – Contractor has risk of performance
17
Should Schedule Revisions Require Owner Approval?
• Shouldn’t the Schedule model the project plan?– Pro – Updated schedules will be the basis for future Time Impact Analyses
18
Should Schedule Revisions Require Owner Approval?
• Shouldn’t the Schedule model the project plan?– Con – Nimble project management requires that the Contractor make changes
constantly to keep up with field decisions and deviations
19
Should Schedule Revisions Require Owner Approval?
• Didn’t the Owner already review and approve the original baseline schedule?
– Pro – Why should new revised schedules escape this scrutiny?
20
Should Schedule Revisions Require Owner Approval?
• Didn’t the Owner already review and approve the original baseline schedule?
– Con – Update is a different condition; owner already knows means and methods
21
Should Schedule Revisions Require Owner Approval?
• Isn’t the approval process difficult?– Pro – Analysis must be done anyway, just another step
22
Should Schedule Revisions Require Owner Approval?
• Isn’t the approval process difficult?– Con – Adds another cycle or requires dual schedule submission, and what
happens when Owner wants to reject revisions?
23
Should Schedule Revisions Require Owner Approval?
• How to handle time frame for review/comment/approve?– Pro – Can be done easily during update review
24
Should Schedule Revisions Require Owner Approval?
• How to handle time frame for review/comment/approve?– Con – Takes too much time away from management
25
Should Schedule Revisions Require Owner Approval?
• Doesn’t the Owner provides a double check that all scope is included?
– Pro – Raises quality of schedule & ensures that predictions of completion are more accurate
26
Should Schedule Revisions Require Owner Approval?
• Doesn’t the Owner provides a double check that all scope is included?
– Con – Scope and performance risk is up to Contractor
27
Should Schedule Revisions Require Owner Approval?
• Doesn’t the Contractor own the schedule?– Pro – Project is for the use of the Owner
28
Should Schedule Revisions Require Owner Approval?
• Doesn’t the Contractor own the schedule?– Con – Contractor has risk of performance
29
Should Schedule Revisions Require Owner Approval?
• Shouldn’t the Schedule model the project plan?– Pro – Updated schedules will be the basis for future Time Impact Analyses
30
Should Schedule Revisions Require Owner Approval?
• Shouldn’t the Schedule model the project plan?– Con – Nimble project management requires that the Contractor make changes
constantly to keep up with field decisions and deviations
31
Should Schedule Revisions Require Owner Approval?
• Didn’t the Owner already review and approve the original baseline schedule?
– Pro – Why should new revised schedules escape this scrutiny?
32
Should Schedule Revisions Require Owner Approval?
• Didn’t the Owner already review and approve the original baseline schedule?
– Con – Update is a different condition; owner already knows means and methods
33
Should Schedule Revisions Require Owner Approval?
• Isn’t the approval process difficult?– Pro – Analysis must be done anyway, just another step
34
Should Schedule Revisions Require Owner Approval?
• Isn’t the approval process difficult?– Con – Adds another cycle or requires dual schedule submission, and what
happens when Owner wants to reject revisions?
35
Should Schedule Revisions Require Owner Approval?
• How to handle time frame for review/comment/approve?– Pro – Can be done easily during update review
36
Should Schedule Revisions Require Owner Approval?
• How to handle time frame for review/comment/approve?– Con – Takes too much time away from management
37
Should Schedule Revisions Require Owner Approval?
• Isn’t there a risk of claims positioning in revisions?– Pro – Owner must have ability to enter into discussion about claims positioning
38
Should Schedule Revisions Require Owner Approval?
• Isn’t there a risk of claims positioning in revisions?– Con – Claims only happen when there is an impact event or productivity drag
39
Should Schedule Revisions Require Owner Approval?
• Shouldn’t the Owner must have input into how its work interfaces with schedule changes ?
– Pro – Contractor often does not include Owner responsible work, such as review time, or Owner-furnished equipment delivery
40
Should Schedule Revisions Require Owner Approval?
• Shouldn’t the Owner must have input into how its work interfaces with schedule changes ?
– Con – Schedule has milestones and information for Owner to use
41
Should Schedule Revisions Require Owner Approval?
• Don’t changes in the schedule make it harder to monitor and compare?
– Pro – Analysis must be done anyway, just another step
42
Should Schedule Revisions Require Owner Approval?
• Don’t changes in the schedule make it harder to monitor and compare?
– Con – Adds another cycle or requires dual schedule submission, and what happens when Owner wants to reject revisions?
43
Should Schedule Revisions Require Owner Approval?
• Shouldn’t the Owner have an expectation that the Contractor will build according to submitted baseline?
– Pro – Owner’s plans are based on baseline schedule, any deviations must be reviewed
44
Should Schedule Revisions Require Owner Approval?
• Shouldn’t the Owner have an expectation that the Contractor will build according to submitted baseline?
– Con – Owner can watch the schedule and must be flexible enough to allow progress, including changes in plan
45
Should Schedule Revisions Require Owner Approval?
• Shouldn’t the Owner have an opportunity to run risk management on the revised schedule?
– Pro – Risk management is a serious need and requires constant review
46
Should Schedule Revisions Require Owner Approval?
• Shouldn’t the Owner have an opportunity to run risk management on the revised schedule?
– Con – Risk of performance is Contractor’s
47
Should Schedule Revisions Require Owner Approval?
• Aren’t there Liquidated Damages for late completion?– Pro – Goal is for the project to finish on time, not to earn LDs
48
Should Schedule Revisions Require Owner Approval?
• Aren’t there Liquidated Damages for late completion?– Con – Risk of LDs should be enough control for Owner
49
Should Schedule Revisions Require Owner Approval?
• Shouldn’t the Owner be allowed to protect against early completion schedules produced during updates?
– Pro – Float is generally available to first need, early completion schedules can be a Contractor’s attempt to take possession of float
50
Should Schedule Revisions Require Owner Approval?
• Shouldn’t the Owner be allowed to protect against early completion schedules produced during updates?
– Con – Good progress will cause this situation anyway
51
Should Schedule Revisions Require Owner Approval?
• Doesn’t the Owner have a right to ensure schedule includes resource planning and availability?
– Pro – Failure to continue to plan for resource availability will ensure failure of project
52
Should Schedule Revisions Require Owner Approval?
• Doesn’t the Owner have a right to ensure schedule includes resource planning and availability?
– Con – Risk and resource availability is up to Contractor
53
Should Schedule Revisions Require Owner Approval?
• Can’t the Owner reject the submitted revised update schedule anyway?
– Pro – Better to know it immediately than later when it causes a problem
54
Should Schedule Revisions Require Owner Approval?
• Can’t the Owner reject the submitted revised update schedule anyway?
– Con – Exactly, if Owner disapproves, schedule is worthless to Contractor for management
55
Should Schedule Revisions Require Owner Approval?
• Doesn’t the process of review and approval result in better negotiated schedule changes?
– Pro – This is a good thing, better to negotiate than to wind up in a claim situation
56
Should Schedule Revisions Require Owner Approval?
• Doesn’t the process of review and approval result in better negotiated schedule changes?
– Con – Just increases the burden on an already overworked project manager and field staff
57
Should Schedule Revisions Require Owner Approval?
• This Debate is Terminated for Convenience!!
58
You have just the skills we need in a consultant
Should Schedule Revisions Require Owner Approval?
• In the 2005 AACE International Transactions, Pat Galloway states in her paper on “CPM Scheduling and How the Industry Views Its Use”,
– “Owners have a variety of reasons that they specify revisions in their specifications. The largest response as to why a schedule revision was required was equally shared, 72 percent between:
• Project behind Schedule
• Change Orders. • Change Orders.
– The next major reason cited was critical path changes, 56 percent.
– Other reasons noted by Owners for requiring schedule revisions included:
• Resource changes for either manpower or equipment.
• Logic changes/duration changes/or Contractor sequence changes.
• When requested by the Owner.
• When time extensions are approved.”
• All these reasons might result in a revision, no matter whether the Owner requested them or not
59
Should Schedule Revisions Require Owner Approval?
• In the 2005 AACE International Transactions, Jim O’Brien and Earl Glenwright state in their paper, “Contemporary Controversies – Circa 2005”– “A schedule cannot be continuously changed if the project is to be
completed 'as scheduled'.”
– “Deviations from the 'planned' schedule will always occur for no other reason than the planned durations and resource performance are estimates. The deviation must be watched as a sequence of activities is estimates. The deviation must be watched as a sequence of activities is accomplished.
– When the deviation[s] become a problem then corrective action must be taken but the planned schedule is not changed. The corrective actions are taken to put the project back on the planned course.”
• This position supports not keeping the schedule model current with the plan, following this philosophy, revisions would not be an issue.
• Reactions?
60
Should Schedule Revisions Require Owner Approval?
• How do today’s schedules with resource and/or cost loading deal with full or partial acceptance by Owner? (suggestion by Donald McDonald)
• Assuming cost and resource loaded schedules, does that change the argument?
– Pro – No, it gets even more important that Owner has ability to review and – Pro – No, it gets even more important that Owner has ability to review and approve
– Con – No, it just increased the complexity and time involved in allowing the Owner to review and comment
61
Should Schedule Revisions Require Owner Approval?
• So, what’s the answer? Approve or not?
• VOTING TIME!
• Should Schedule Revisions Require Owner Approval?
– Yea -
– Nay -
• And the winners are:
62
The Great DebateShould Schedule Revisions Require
Owner Approval?