Powering Sydney’s Future Workshop...Powering Sydney’s Future - Introduction • Sydney is the...

37
Monday 28 November, 2016 Powering Sydney’s Future Workshop 1

Transcript of Powering Sydney’s Future Workshop...Powering Sydney’s Future - Introduction • Sydney is the...

Monday 28 November, 2016

Powering Sydney’s Future Workshop

1

WelcomeGerard Reiter Executive General Manager, Asset ManagementTransGrid

2

Powering Sydney’s Future - Introduction

• Sydney is the most important load in the country and it is growing

• TransGrid and Ausgrid’selectricity networks are critical to support this growth

3

High load areas• CBD• Inner suburbs• Transport corridors

Key customers• Sydney CBD• Sydney Airport• Port Botany• Major rail and road links.

Powering Sydney’s Future - Introduction

Powering Sydney’s Future - Introduction

• Complex network built in the 60s and 70s

• Networks’ abilities to meet growing need is degrading

• Timing is critical. To have a solution in place to meet the need we have to act now

• TransGrid and Ausgrid are committed to an open and open-minded process to find a reliable and efficient solution

5

Powering Sydney’s Future – 2014 consultation

• 400 stakeholders representing the public, researchers, industry, government and regulators participated in a workshop.

• TransGrid and Ausgrid committed to:o Developing responsive network options – in the PSCRo Grow demand management using non-network options - in the PSCR and EOIo Playing active roles in the refinement of standards for a reliable supply at an

efficient cost - engaged with IPART o Continue to engage and collaborate – we have and continue to do so today

6

Powering Sydney’s FutureAusgrid driversMatthew WebbManager Network Risk and PlanningAusgrid

• Approx. 200MW load from new large customers

• Estimated 150 ~250MW from future large scale redevelopment

Powering Sydney’s Future – Ausgrid drivers Sydney – growth and additional loads

Powering Sydney’s Future – Ausgrid drivers Sydney – growth

Forecast demand growth peak

• Return to demand forecast growth seen in 2015 and 2016

• New large customer loads driving future growth

• Ausgrid base forecast is consistent with BIS Shrapnel forecast

Powering Sydney’s Future – Ausgrid driversDeteriorating fluid filled cables

• Ausgrid’s 132kV fluid filled cables mostly installed in 1960’s and 1970’s

• Ausgrid has approx. 350km• Repairs are complex and

time consuming• Ausgrid has an MOU with

the EPA for reducing fluid leaks over time

Failure history Leaks Test

Results

Predictive unavailability model

- History of cable failures with repair times getting longer- Consistent leaks and poor test results requiring repairs- All contributing to poor cable availability

Repair Times

Powering Sydney’s Future – Ausgrid drivers Deteriorating fluid filled cables

• Total cable unavailability over past 4 years of approximately 17%

• Cable fluid loss from leaks has been significant

• Maintenance requirements continue to increase

Powering Sydney’s Future – Ausgrid drivers Deteriorating fluid filled cables

Powering Sydney’s Future – Ausgrid drivers Planning based on community benefit

• Network energy delivery capacity is declining

• Customer demand for energy is increasing

• Shortfall is expected unserved energy (EUE)

• Trigger point - where accumulated value of EUE is greater than cost of project

Project Trigger Point

TransGrid driver, proposed reliability standard and this processAnthony EnglundGroup Manager, Investment Strategy and Solutions

TransGrid

14

Powering Sydney’s Future – TransGrid driver, proposed standard and process

• Not operating to its full capacityo Cable 42 CMS showed higher TR (2000s)o Backfill sampling (to 2009)o 1st derating - Anders & Orton review (2011)o Full backfill sampling program (to 2016)o 2nd derating – Anders (2016)o Cable and joint sampling (now)

Driver 3: Cable 41

• One of two 330kV cables, 20 km long, built in 1970s, 40 year nominal life

15

Powering Sydney’s Future – TransGrid driver, proposed standard and process

Proposed new reliability standard

• About fine-tuning price/service level balance

• IPART: ‘Modified n-2 + 0.6 minutes EUSE per year at average demand’

• EUSE equivalent of 20MW (UNSW or Kensington) one hour per year

• An important, evolutionary change but…

• Capacity reductions and load growth put us in deficit from 2017

• Challenge to supply energy, major challenge to supply appropriate capacity

• Key message: we need to know what non-network solutions can deliver

16

Powering Sydney’s Future – TransGrid driver, proposed standard and process

Project trigger point

Energy shortfall (MWh)

Powering Sydney’s Future – TransGrid driver, proposed standard and process

Capacity shortfall (MW)

Powering Sydney’s Future – TransGrid driver, proposed standard and process

Process

2016/17 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23

RIT-T process

Environmental planning process

Implementation phase

Design phase

• PSCR subs due 13 Jan 2017 • PADR Mar/April 2017 • PADR subs due May/June 2017 (6 weeks)• PACR July/Aug 2017

19

Considering all options Nalin PahalawaththaGroup Manager, Power System AnalysisTransGrid

20

Powering Sydney’s Future – Considering all options

The planning process considers:

Reliability

Cost

Environment

21

Powering Sydney’s Future – Considering all options

In situ replacement of cables

330 kV cable replacement: • Cable Outage – up to 2-5 years• High costs – similar to new cable

development• Access issues• 4 x the capacity of 132 kV cable

132 kV cable replacement:• Environmental risk – crossing harbour• High costs – similar to new cable

development• Limited improvement to network capability

22

Powering Sydney’s Future – Considering all options

New Cables – 330 kV Vs 132 kV

• Limited Capability enhancement from

132 kV option

load growth

Network Development flexibility

• 132 kV = higher costs ($/MW)

• 132 kV = higher community &

environmental impact

132 kV Option

330 kV Option

23

Powering Sydney’s Future – Considering all options

New cables – 330 kV vs 132 kV

• Limited Capability enhancement from

132 kV option:

o Load growth

o Network development flexibility

• High costs ($/MW)

• Community and environmental impact

24

Powering Sydney’s Future – Considering all options

Route selection: Sydney’s East• 3 out of 6 possible route options were

considered feasible (approx. 26km)

• Environmental impact on national parks and harbour crossing

• Significant high costs due to the geography of the area.

• Network limitations: overloading Sydney’s North to East via 330 kV lines

Sydney East

Sydney North

Rookwood Road

Sydney West

Sydney South

Beaconsfield

Haymarket

25

Powering Sydney’s Future – Considering all options

Route selection: Sydney’s North • 4 out of 7 possible route options

were considered feasible (tunnels, overhead lines, combinations)

• Environmental impact on national parks and harbour crossing

• Significant costs due to the geography of the area and the length of the route

Sydney East

Sydney North

Rookwood Road

Sydney West

Sydney South

Beaconsfield

Haymarket

26

Powering Sydney’s Future – Considering all options

Route selection: Sydney’s South• 3 out of 9 possible route options were

considered feasible (tunnels, overhead lines, combinations)

• Diversity issue:o Concentrate of 330 kV supply to

CBD from one locationo Part of route is along existing 330kV

cables

• Environmental and community impact on Georges River National Park and high density residential area

• Similar costs to Rookwood Road option

Sydney East

Sydney North

Rookwood Road

Sydney West

Sydney South

Beaconsfield

Haymarket

27

Powering Sydney’s Future – Considering all options

Route selection: Rookwood Road • 13 possible route options were considered

feasible (tunnels, overhead lines, combinations)

• Provided diversity to supply CBD area

• Utilised existing 330 kV supply capacity from Sydney’s West to Rookwood Road

• Low costs compared with the Sydney North and East options

• Relatively low community and environmental impact

Sydney East

Sydney North

Rookwood Road

Sydney West

Sydney South

Beaconsfield

Haymarket

28

Powering Sydney’s Future – Considering all options

Rookwood Road Options

Options2 x 330kV cables in stages

2 x 330kV cables at

once

Remediate Cable 41

Retire Cable 41

Operate Cable 41 at 132kV

Decommission Ausgrid cables

– 2 stages

Decommission Ausgrid cables

– 1 stage

1

2

3

4

5

6

29

Powering Sydney’s Future – Considering all options

Storage Curtailment of loadEmbedded generation

Alternatives to network augmentation which address a potential shortage in electricity supply

Network SolutionNon-Network Solutions

30

The possiblity of non-network

David BonesService Group Manager – Power Strategy and Economics

GHD

31

Powering Sydney’s Future – The possibility of non-network

Non-network comprises of: • Generation

• Storage

• Demand Management

Non-network components are 1. Unserved energy at risk

2. Project deferral

3. Part of the integrated project solution

32

Powering Sydney’s Future – The possibility of non-network

Inner Sydney’s daily demand profile

33

Powering Sydney’s Future – The possibility of non-network

Expected unserved energy in 2020-23 without Powering Sydney’s Future project

34

Powering Sydney’s Future – The possibility of non-network

Examples of non-network options

35

Powering Sydney’s Future – The possibility of non-network

Non-network case study – 60MW, 12 Hr, 8 week options

Existing Standby Generation Central Battery Central Power Station

36

Powering Sydney’s Future Workshop

37