Week  10  Tutorial  Activity    Oval  Pavillion  During  the  week  10  tutorial,  we  went  on  a  final  site  visit  to  the  oval  pavilion.  Notes  on  the  feature  of  pavilion:  

• Retaining  wall  stopping  overflow  –  800mm  deep  o Any  moisture  finds  its  way  to  drainage  cell,  then  removed  through  

storm  water  drainage  pipes  • Cables  

o Orange:  electrical  o White:  columns  o Grey:  water  

• Welding  used  to  join  steel  members  • Bolting  and  screws  used  to  fasten  to  timber  and  steel  members  • Horizontal  purlins  

o Levels  of  roof  § Noise  insulation  followed  by  moisture  barrier,  heat  

insulation  and  upper  roof  • Roof  supported  by  four  main  columns  –  window  self  supporting  • Tongue  and  groove  timber  –  can  only  be  used  for  wall  cladding  due  to  

larger  groove  • Hidden  fixing  –  don’t  see  nails/screws  • Window  –  cover  plate    (sliding)  • ‘Z’  purlin  

o Can  cross  over  member  • ‘C’  purlin  

o Sits  on  top  of  member  • Timber  sound  proof  flooring  • CFC  sheets  –  compressive  • Brick  veneer  • Timber  wall  • Over-­‐flashing  • Internal  floor  higher  than  external  floor  to  eliminate  the  risk  of  flooding  

o 300mm  floor  thickness  • Thicker  concrete  due  to  the  weight  of  the  brick  wall  • Yellow  termite  proofing  on  floor  

 Images  

   

Retaining  Wall   Wall  cladding  –  tongue  and  groove  

Page 2: Yasmeen - W10 Constructing Journal

                               

Termite  proofing   Timber