Download - WEEKLY PROGRESS REPORT

Transcript
Page 1: WEEKLY PROGRESS REPORT
Page 2: WEEKLY PROGRESS REPORT

AMISA CLUBHOUSE AND GUARDHOUSE

Page 3: WEEKLY PROGRESS REPORT

As of July 21,2009

SCHEDULED ACCOMPLISHMENT 17.281%

ACTUAL ACCOMPLISHMENT 14.7445%

VARIANCE -2.5365%

SUMMARY OF ACCOMPLISHMENTS

PROJECT DURATION 213 Calendar Days

NUMBER OF DAYS LAPSED 53Calendar Days

NUMBER OF DAYS REMAINING 160Calendar Days

PROJECTED ACCOMPLISHMENT 17.281%

ACTUAL ACCOMPLISHMENT 14.7445%

VARIANCE -2.5365%

Page 4: WEEKLY PROGRESS REPORT

AMISA CLUBHOUSE

Page 5: WEEKLY PROGRESS REPORT

CHB WALL PILING AND ON GOING FORMWORK ON EXTERIOR COLUMNS

Page 6: WEEKLY PROGRESS REPORT

AMISA GUARDHOUSE

Page 7: WEEKLY PROGRESS REPORT

ON GOING PILING OF CHB FOR GUARDHOUSE

Page 8: WEEKLY PROGRESS REPORT

EXCAVATION FOR CHB FENCE NEAR GUARDHOUSE

SEPTIC TANK FOR GUARDHOUSE