| 1Infrassure Ltd. Roman Beerli – Testing following construction - 24th September 2013
Testing of Engineering Projects / Plants following Construction
Testing of Engineering Projects / Plants following ConstructionIMIA WGP 82
24th September 2013 Delhi Conference
Roman Beerli
| 2Infrassure Ltd. Roman Beerli – Testing following construction - 24th September 2013
Work group members
Chairman:Roman Beerli, Infrassure Ltd
IMIA EC Sponsor:Michael Robertson, Liberty
Team Members:Andy Hottinger, AXIS ReThomas Gebert, ZurichDario Popovic, Infrassure Ltd Wolfgang Voelcker, Munich Re
| 3Infrassure Ltd. Roman Beerli – Testing following construction - 24th September 2013
Table of content
• Risk Assessment
• Management, operator experience, contractor/subcontractor
• Risk share, handover and insurance requirements in construction
contracts
• Specific Perils and Vulnerabilities of Project Components
• The soft factor issue: human errors
• Policy cover
• Conclusion
| 4Infrassure Ltd. Roman Beerli – Testing following construction - 24th September 2013
Risk Assessment
• Management, operator experience, contractor/subcontractor
Complex facility construction projects
Testing and commissioning, design errors
Experience of Commissioning Engineers
Tight project time schedule
| 5Infrassure Ltd. Roman Beerli – Testing following construction - 24th September 2013
Risk Assessment
• Management, operator experience, contractor/subcontractor
Complex facility construction projects
Testing and commissioning, design errors
Experience of Commissioning Engineers
Tight project time schedule
| 6Infrassure Ltd. Roman Beerli – Testing following construction - 24th September 2013
Risk Assessment
• Management, operator experience, contractor/subcontractor
Complex facility construction projects
Testing and commissioning, design ….errors
Experience of Commissioning Engineers
Tight project time schedule
| 7Infrassure Ltd. Roman Beerli – Testing following construction - 24th September 2013
Risk Assessment
• Management, operator experience, contractor/subcontractor
Complex facility construction projects
Testing and commissioning, design errors
Experience of Commissioning…Engineers
Tight project time schedule
| 8Infrassure Ltd. Roman Beerli – Testing following construction - 24th September 2013
Risk Assessment
• Management, operator experience, contractor/subcontractor
Complex facility construction projects
Testing and commissioning, design errors
Experience of Commissioning Engineers
Tight project time schedule
| 9Infrassure Ltd. Roman Beerli – Testing following construction - 24th September 2013
Risk Assessment
• Risk sharing, handover and insurance requirements in construction contracts
Contractors and subcontractors
Loss of profit
Construction period vs. Maintenance period
Handover
| 10Infrassure Ltd. Roman Beerli – Testing following construction - 24th September 2013
Risk Assessment
• Specific Perils and Vulnerabilities of Project Components
Location and layout of a construction site
Cold testing & Hot testing and commissioning
FLEXA
NATCAT
Special Scenario
| 11Infrassure Ltd. Roman Beerli – Testing following construction - 24th September 2013
Risk Assessment
• Specific Perils and Vulnerabilities of Project Components
Location and layout of a construction site
Cold testing & Hot testing and commissioning
FLEXA
NATCAT
Special Scenario
| 12Infrassure Ltd. Roman Beerli – Testing following construction - 24th September 2013
Risk Assessment
• Specific Perils and Vulnerabilities of Project Components
Location and layout of a construction site
Cold testing & Hot testing and commissioning
FLEXA
NATCAT
Special Scenario
| 13Infrassure Ltd. Roman Beerli – Testing following construction - 24th September 2013
Risk Assessment
• Specific Perils and Vulnerabilities of Project Components
Location and layout of a construction site
Cold testing & Hot testing and commissioning
FLEXA
NATCAT
Special Scenario
| 14Infrassure Ltd. Roman Beerli – Testing following construction - 24th September 2013
Risk Assessment
• Specific Perils and Vulnerabilities of Project Components
Location and layout of a construction site
Cold testing & Hot testing and commissioning
FLEXA
NATCAT
Special Scenario
| 15Infrassure Ltd. Roman Beerli – Testing following construction - 24th September 2013
Risk Assessment
• Specific Perils and Vulnerabilities of Project Components
Location and layout of a construction site
Cold testing & Hot testing and commissioning
FLEXA
NATCAT
Special Scenario
| 16Infrassure Ltd. Roman Beerli – Testing following construction - 24th September 2013
Risk Assessment
• The soft factor Issue: human errors
Why does it still fail?
Feedback processes in other industries
Safety culture
Interaction between involved parties
| 17Infrassure Ltd. Roman Beerli – Testing following construction - 24th September 2013
Risk Assessment
• The soft factor Issue: human errors
Why does it still fail?
Feedback processes in other industries
Safety culture
Interaction between involved parties
| 18Infrassure Ltd. Roman Beerli – Testing following construction - 24th September 2013
Risk Assessment
• The soft factor Issue: human errors
Why does it still fail?
Comparison with other industries
Safety culture
Interaction between involved parties
| 19Infrassure Ltd. Roman Beerli – Testing following construction - 24th September 2013
Risk Assessment
• The soft factor Issue: human errors
Why does it still fail?
Comparison with other industries
Safety culture
Interaction between involved parties
| 20Infrassure Ltd. Roman Beerli – Testing following construction - 24th September 2013
Risk Assessment
• The soft factor Issue: human errors
Why does it still fail?
Comparison with other industries
Safety culture
Interaction between involved parties
| 21Infrassure Ltd. Roman Beerli – Testing following construction - 24th September 2013
Policy cover
• There are 3 main criteria to be considered:
Definition for the testing and commissioning period
Duration
Fulfillment of criteria
Different conditions
Extensions
| 22Infrassure Ltd. Roman Beerli – Testing following construction - 24th September 2013
Conclusion
• The testing and start up phase is the most critical time during an erection project
• Time schedules are an important tool to evaluate critical path and potential buffer zones
• Test and commissioning period is to be defined clearly in the insurance contract
• Due to higher exposure and live feed to the equipment the conditions have to pay credit to this changing environment
• Experienced contractor with good procedures in place combined with a policy wording based on risk sharing can mitigate the overall exposure
| 23Infrassure Ltd. Roman Beerli – Testing following construction - 24th September 2013
“ It is not the beauty of a building you should look at; its the construction of the foundation that will stand the test of time.
Dave Allan Coe
“ If a building looks better under construction than it does when finished, then it’s a failure.
Doug Coupland
Any questions?
Infrassure Ltd., Uetlibergstrasse 134A, P. O. Box 5089, CH-8045 Zürich, Switzerland www.infrassure.com