System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
1
Contents 1. WATER INTAKE SYSTEM ...................................................................................................................... 3
1.1 Intake Pumps Breakers Check List ................................................................................................. 3
1.2 Intake Pumps Soft Starter Check List ............................................................................................ 6
1.3 Functional Test for Raw Water Pumps .......................................................................................... 9
1.4 Start-Up Test for Raw Water Pumps ........................................................................................... 13
1.5 Automatic Trash Rake System Start-up and Training Record Form ............................................ 17
2. ALUM SYSTEM ................................................................................................................................... 19
2.1 FM 200 Fire Fighting System ....................................................................................................... 19
2.2 Electric Room AIR CONDITIONER ................................................................................................ 23
2.3 ALUM TURBINE MIXERS .............................................................................................................. 24
2.4 LIGHTING FIXTURES ..................................................................................................................... 25
2.5 HVAC - Exhaust Fans, Intake Hoods and Duct ............................................................................ 26
2.6 Alum Building Drainage Submersible Pumps .............................................................................. 27
2.7 Alum Building Electrical Heater ................................................................................................... 28
2.8 Alum Building 2 Ton Electrical Crane Site Test Certificate .......................................................... 29
2.8.1 KoneCranes Training Record Form ....................................................................................... 31
3 FLOCCULATOR SYSTEM ...................................................................................................................... 32
3.1 RAPID MIX.................................................................................................................................... 32
3.1.1 RAPID MIX TURBINE MIXERS ................................................................................................ 32
3.2 CLARIFIERS ................................................................................................................................... 34
3.2.1 Clarifiers 7 & 8 ...................................................................................................................... 35
3.2.2 Clarifiers 9&10 ...................................................................................................................... 36
4 FILTRATION SYSTEM ........................................................................................................................... 37
4.1 HVAC – Exhaust Fans and Ducts .................................................................................................. 37
4.2 - 30” Filter Influent Channel and Backwash Channel Actuated Valves ...................................... 38
4.3 Auma Actuated Valves Training Record Form ............................................................................. 39
4.4 Filter Building Auma Actuated Valves Control Panels Training Record Form ............................ 40
4.5 Filter Gallery Actuated Valves Check List ................................................................................... 41
5 PUMPING AND RESERVOIR SYSTEM ................................................................................................... 42
5.1 HIGH LIFT PUMP STATION ........................................................................................................... 42
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
2
5.1.1 HSPS. Breakers (Switchgear) Check List ............................................................................... 42
5.1.2 HSPS Soft Starters Check List ................................................................................................ 46
6 BALANCE OF SYSTEM .......................................................................................................................... 50
6.1 TRANSFORMERS & Training Record Form ................................................................................... 50
6.1.1 İfraz 3 – 750kVA Transformer - WNO2-41TL-A .................................................................... 51
6.1.2 İfraz 3 - 750 kVA Transformer - WNO2-41TL-B ................................................................... 63
6.1.3 Ifraz 3 – 500kVA Transformer - WNO2-60TL-A .................................................................... 75
6.1.4 Ifraz 3 – 300kVA Transformer - WNO2-75TL-A.................................................................... 87
6.1.5 Ifraz 3 – 150 kVA Transformer - WNO2-65TL-A ................................................................... 99
6.1.6 Maroda Intermediate Pump Station 225 kVA Transforer - WNO2-81TL-A ........................ 111
6.1.7 Ifraz 3 – 10 MVA Transformer - WNO2-02TL-A .................................................................. 123
6.1.8 Ifraz 3 – 10MVA Transformer WNO2-02TL-B ..................................................................... 135
6.1.9 Maroda Intermediate Pump Station – 10 MVA Transformer - WNO2-02TL-C .................. 147
6.1.10 Maroda Intermediate Pump Station – 10MVA Transformer - WNO2-02TL-D ................. 159
6.2 IFRAZ 2 PUMP STATION ............................................................................................................. 171
6.2.1 - 8 Ton Electrical Crane Site Test Certificate ................................................................... 171
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
3
1. WATER INTAKE SYSTEM
1.1 Intake Pumps Breakers Check List
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
4
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
5
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
6
1.2 Intake Pumps Soft Starter Check List
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
7
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
8
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
9
1.3 Functional Test for Raw Water Pumps
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
10
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
11
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
12
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
13
1.4 Start-Up Test for Raw Water Pumps
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
14
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
15
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
16
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
17
1.5 Automatic Trash Rake System Start-up and Training Record Form
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
18
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
19
2. ALUM SYSTEM
2.1 FM 200 Fire Fighting System
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
20
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
21
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
22
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
23
2.2 Electric Room AIR CONDITIONER
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
24
2.3 ALUM TURBINE MIXERS
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
25
2.4 LIGHTING FIXTURES
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
26
2.5 HVAC - Exhaust Fans, Intake Hoods and Duct
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
27
2.6 Alum Building Drainage Submersible Pumps
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
28
2.7 Alum Building Electrical Heater
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
29
2.8 Alum Building 2 Ton Electrical Crane Site Test Certificate
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
30
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
31
2.8.1 KoneCranes Training Record Form
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
32
3 FLOCCULATOR SYSTEM
3.1 RAPID MIX
3.1.1 RAPID MIX TURBINE MIXERS
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
33
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
34
3.2 CLARIFIERS
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
35
3.2.1 Clarifiers 7 & 8
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
36
3.2.2 Clarifiers 9&10
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
37
4 FILTRATION SYSTEM
4.1 HVAC – Exhaust Fans and Ducts
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
38
4.2 - 30” Filter Influent Channel and Backwash Channel Actuated Valves
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
39
4.3 Auma Actuated Valves Training Record Form
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
40
4.4 Filter Building Auma Actuated Valves Control Panels Training Record Form
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
41
4.5 Filter Gallery Actuated Valves Check List
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
42
5 PUMPING AND RESERVOIR SYSTEM
5.1 HIGH LIFT PUMP STATION
5.1.1 HSPS. Breakers (Switchgear) Check List
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
43
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
44
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
45
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
46
5.1.2 HSPS Soft Starters Check List
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
47
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
48
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
49
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
50
6 BALANCE OF SYSTEM
6.1 TRANSFORMERS & Training Record Form
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
51
6.1.1 İfraz 3 – 750kVA Transformer - WNO2-41TL-A
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
52
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
53
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
54
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
55
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
56
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
57
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
58
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
59
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
60
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
61
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
62
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
63
6.1.2 İfraz 3 - 750 kVA Transformer - WNO2-41TL-B
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
64
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
65
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
66
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
67
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
68
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
69
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
70
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
71
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
72
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
73
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
74
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
75
6.1.3 Ifraz 3 – 500kVA Transformer - WNO2-60TL-A
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
76
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
77
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
78
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
79
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
80
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
81
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
82
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
83
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
84
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
85
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
86
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
87
6.1.4 Ifraz 3 – 300kVA Transformer - WNO2-75TL-A
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
88
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
89
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
90
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
91
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
92
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
93
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
94
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
95
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
96
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
97
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
98
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
99
6.1.5 Ifraz 3 – 150 kVA Transformer - WNO2-65TL-A
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
100
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
101
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
102
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
103
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
104
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
105
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
106
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
107
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
108
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
109
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
110
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
111
6.1.6 Maroda Intermediate Pump Station 225 kVA Transforer - WNO2-81TL-A
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
112
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
113
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
114
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
115
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
116
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
117
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
118
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
119
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
120
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
121
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
122
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
123
6.1.7 Ifraz 3 – 10 MVA Transformer - WNO2-02TL-A
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
124
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
125
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
126
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
127
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
128
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
129
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
130
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
131
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
132
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
133
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
134
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
135
6.1.8 Ifraz 3 – 10MVA Transformer WNO2-02TL-B
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
136
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
137
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
138
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
139
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
140
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
141
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
142
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
143
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
144
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
145
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
146
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
147
6.1.9 Maroda Intermediate Pump Station – 10 MVA Transformer - WNO2-02TL-C
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
148
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
149
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
150
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
151
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
152
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
153
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
154
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
155
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
156
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
157
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
158
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
159
6.1.10 Maroda Intermediate Pump Station – 10MVA Transformer - WNO2-02TL-D
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
160
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
161
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
162
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
163
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
164
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
165
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
166
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
167
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
168
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
169
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
170
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
171
6.2 IFRAZ 2 PUMP STATION
6.2.1 - 8 Ton Electrical Crane Site Test Certificate
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
172
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
173
System Functional and Start-Up Check Lists
Erbil – Ifraz Water Project
174