NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING
SYLLABUS
Sl.No. Subject / Module - First Semester
No. ofWeeks
1 Power Plant Introduction & Industrial Safety 1
2 Power Plant Familiarisation 6
3 Power Plant Briefing & Scheme Tracing 2
4 Power Plant Operation 2
5 Rotation On-job(Operation) 5
6
Erection, Commissioning & Construction
Management 2
7Power Plant Performance & EfficiencyCalculation 1
8Power Plant Chemistry , Metallurgy ,NDT &Welding 2
9 Gas turbine & Combined Cycle Power Plant 1
10Advanced Steam Generation Technology-Supercritical and FBC 1
11
Business Communication & Personality
Development 1First Semester Examination 1
Subject / Module - Second Semester
12 Power Plant Protection 1
13 Energy Audit 1/2
14 Maintanence Planning & Cost Control 1
15 Nuclear Power Plant Familiarisation 1
16 Renewable and Hydro Power Plants 1
17 Maintanence Practice & Inspection 4
18 Design Analysis 119 Load Despatch 1
20 Power Reforms and regulations 1
21 Control & Instrumentation 2
22 IT Application in Power Sector & GIS 2
23 Environment Management 1
24 Rotational On Job(Maint.) 4
25 Training & visit to Mfrs. Works 2
26 Simulator 2
Project Presentation 1/2Margin For Holidays 1
Second Semester Examination 1
Total 52 1
8/6/2019 Syallabus of PGDC
2/61
NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING
Scheme of Examination
Distinction -75% and above
First Division -60% & Above
Second Division -50% to less than 60 %Pass Marks -Minimum 45% in internal & external examination separately and 50 % in overall Semester
A student failing in a particular semester in three or more subjects will have to repeat the Semester exam with
the next batch. A student failing in a particular subject will have to appear in the subject exam.
PaperNo. Title of the Paper - First Semester
No. ofWeeks
InternalTestMaxmarks
ExternalexamMax
Marks
TotalMaxmarks
Remarks
1
Power Plant Familiarisation-I(Power Plant Introduction & Safety, Generators &transformers) 3 50 100 150
2Power Plant Familiarisation-II(Boiler, Turbine & BOP) 4 50 100 150
3Power Plant Operation, Power Plant Performance &Efficiency Calculation 3 50 100 150
4Erection, Commissioning & Construction Management,Gas turbine & Combined Cycle Power Plant 3 50 100 150
5
Power Plant Chemistry, Metallurgy, NDT & Welding,Advanced Steam Generation Technology- Supercriticaland FBC 3 50 100 150
6 Rotation On-job(Operation) (Based on Viva Voce) 5 50 100 150
7Power Plant Briefing & Scheme Tracing(Based on Viva Voce) 2 50 50 100
8Business Communication & Personality Development(Based on Viva Voce) 1 50 50
Total 1050
First Semester Examination 1
Title of the Paper - Second Semester
1Power Plant Protection, Control & Instrumentation, EnergyAudit 3.5 50 100 150
2
Maintenance Planning & Cost Control, EnvironmentManagement, Nuclear Power Plant Familiarization,Renewable & Hydro Power Plants 4 50 100 150
3 Maintenance Practice & Inspection, Design Analysis 5 50100 150
4Load Dispatch, IT Application in Power Sector & GIS,Power Reforms & Regulation 4 50 100 150
5. Rotation On-job(Maintenance) (Based on Viva Voce) 4 50 100 150
6Training & visit to Mfrs. Works(Based on Viva Voce) 2 50 50
7 Simulator 2 100100
8Project(Based on Viva Voce) 0.5 50 100 150
Margin for holidays 1
Second Semester Examination 1
Total 521050
2
8/6/2019 Syallabus of PGDC
3/61
NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING
RULES AND REGULATIONA. ADMISSION AND ELIGIBILITY
1. The duration of the course leading to the Post Graduate Diploma In ThermalPower Plant Engineering shall be one academic year(52 weeks) divided intotwo semesters.
A candidate shall have to pass all the two semester examinations within amaximum period of three years of his/her admission to the first semester ofPost Graduate Diploma In Thermal Power Plant Engineering programmefailing which he/she will be deemed to be unfit for the programme. However,a candidate, who having passed the first semester examination discontinueshis studies, for legitimate and justified reasons may be permitted to joinsecond semester within one year of his passing the first semesterexamination.
2. The minimum qualifications for admissions to the first semester of PostGraduate Diploma In Thermal Power Plant Engineering programme shall be aBachelor degree in Engineering or AMIE or equivalent degree in Mechanical,Electrical, Electronics./Control & Instrumentation/ Power Engineering. Thoseappearing in their final year examination may also apply. However, they mustsubmit their result at the time of counseling. The Admission to this P.G.Diploma will be done on the basis of Merit based on a Common Entrance Test(CET) followed by counseling. CET will be conducted on rotation basis by theInstitutes in the sequence New Delhi, Nagpur, Neyveli and Durgapurrespectively.
3.(a) The first semester examination shall be open to a regular student who
I) has been on the rolls of the Institute during the first semester;II) has at least 75% attendance in the class during the semester;III) has obtained pass marks in the internal assessment/
workshop/practical exam. andIV) bears a good moral character
(b) The second semester examination shall be open to a regular student who:
i) has been on the rolls of the Institute for the concerned semesterii) has at least 75% attendance in the class during the semester;iii) has passed the first semester examination andiv) bears a good moral character.
B. EXAMINATION AND FEES
4. Every candidate shall be examined in the subject(s) as laid down in theScheme of Examinations/Syllabus prescribed . Course/Tuition fee should bedivided equally into two parts. Semester 1 fee should be deposited at the timeof counseling. Semester 2 fee should be deposited by 20th February of eachyear failing which a late fee of Rs.100/- per day may be charged. Each PGDCstudent will be charged a fee of Rs 200/- per subject as examination fee which
3
8/6/2019 Syallabus of PGDC
4/61
NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING
may be deposited one month before start of the semester examination ie. Rs.1600/- for first semester and Rs 1600/- for second semester.
5. The external examiner(s) will set the question papers as per the criteria laiddown in the Scheme of Examination for the program. Evaluation of semester
exam answer sheets will not be done in the same Institute. All the writtensemester exams will be of three hour duration.
6. The medium of instruction and examination shall be English.
7. Mobile phones, any extra piece of paper, notebook are banned in the examhall. A student indulging in exam malpractices may be expelled by theinvigilator/Chief Supdt. for one year from the exam and he will be able to takethe semester exams only after one year.
8. The amount of examination fee to be paid by a candidate for each semester
shall be as per the decision of NPTI from time to time.
9. The Examination for the first semesters shall ordinarily be held in the month ofJanuary and for the second semester in the month of July or on such dates asmay be fixed by the Director General, NPTI.
Supplementary examinations will be held for re-appear/failed candidatesas under:-
Semester When held
(a) First Semester Along with the Second Semester (b) Second Semester Along with the subsequent first Semester_________________________________________________________
10. The Course Coordinator of the concerned Institute shall forward the internal testmarks to the Principal Director/ Director at least one week before thecommencement of each semester examination alongwith list of the eligiblestudents who have satisfied the requirements of rules for appearing in theExamination.
11. (i) As soon as possible, after the competition of the examination the Principal
Director/ Director shall publish a list of candidates who have passed theSemester Examination.
(ii) Each successful candidate shall receive a copy of the detailed marks cardon having passed the Semester Examination.
12. The list of successful candidates after the Second semester examination shall bearranged as under in two divisions on the basis of the aggregate marksobtained in the first and second semester examinations taken together andthe division obtained by the candidate will be stated in his certificate.
a) Those who obtain 50% marks but less than 60% marksSECOND DIVISION;
b) Those who obtain 60% or more marks -
4
8/6/2019 Syallabus of PGDC
5/61
NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING
FIRST DIVISION;
c) Those who pass all the two semester examinations at the first attemptobtaining 75% or more marks in the aggregate shall be declared tohave passed with - DISTINCTION
C. EVALUATION
13. (i) The Principal Director/ Course Coordinator of the Institute will preservethe records on the basis of which the, Internal Assessment awardshave been prepared upto one month from the date of declaration of thesemester examination results. This record will be disposed off after onemonth. The first Semester results must be declared before 20 th ofFebruary of each year.
14. (i) The internal assessment/practical/workshop/training report/project
report award of a candidate who fails in any semester/paper(s) shall becarried forward to the next examination.
(ii) Candidate(s) who has not obtained pass marks in the InternalAssessment in any paper(s) will not be allowed to take examination inthe said paper(s) in the relevant semester. He/she will, however, beprovided opportunity to appear before the Committee of Examiners, tobe constituted by the Principal Director/ Director of the concernedInstitute to re-assess performance of the candidate and the internalassessment given by the Committee shall be final.
(iii) A candidate who fails to obtain pass marks in training report/projectreport shall be offered opportunity to undergo training again andconduct another project as the case may be and the same shall beassessed by a board of examinations appointed by the PrincipalDirector.
(iv) A candidate who fails to obtain pass marks in ROJT/practical/viva-voceshall have to re-appear before the board of examiners constituted bythe PD/Director.
15. (i) The candidate shall be required to submit three copies of his ProjectReport. The last date for receipt of Project Report in the office of theInstitute shall be one week before the commencement of the Secondsemester Examination.
In exceptional cases, the Director General may, on therecommendation of the Principal/Director of Institute, extend the lastdate of receipt of the project Report, till the commencement of theSecond semester examination, with late fee.
(ii) The Project Report shall be evaluated as per the guidelines specified in
the Scheme of Examination, jointly by the external and the internalexaminers. The appointment of the external examiner shall be made bythe Director General on the recommendation of the Principal Director ofthe respective institute.
5
8/6/2019 Syallabus of PGDC
6/61
NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING
(iii) The marks obtained by the candidate for the project report shall betaken into account when he appears in any future examination underreappear clause.
16. (a) The comprehensive viva-voce/workshop shall be conducted by a Boardof Examiners to be appointed by the Director General on therecommendation of the Principal Director/Director of the respectiveinstitute consisting of the following members:-
i) One Internal Faculty nominated by the Director of the concernedInstitute;
ii) One or Two External Examiners from the Industry/Academicfield
(b) The marks obtained by the candidate for the viva-voce/workshop shall
be taken into account when he appears in any future examinationunder re-appear clause.
17. The Project Report and Training Report, wherever specified will be submittedin the typed form as per the following requirements:
(i) The typing should be done on both sides of the paper (instead of singleside printing)
(ii) The font size should be 12 with Times Roman Format.(iii) The Project Report/Training Report may be typed in 1.5 (one and a
half) space. But the References/Bibliography should be typed insingle space.
(iv) The paper should be A-4 size.(v) Two copies meant for the purpose of evaluation may be bound in
paper-back form and one copy should be in hard binding.(vi) Students will select topic of the project by 30th October of each year.
Course Coordinator will submit the consolidated list of project withname of students to the Principal Director/Director on first working dayof November.
D PROMOTION AND REAPPEAR
18. The minimum percentage of marks to pass the examination in each semestershall be :-
a) 45% in each written paper and internal assessment separately;b) 45% in Training Report/Project Report and Viva-Voce separately.c) 50% in the total of each semester examination.d) A candidate who has secured minimum marks to pass in each paper but
has not secured the minimum marks required to pass in aggregate for thesemester concerned may take re-examination (in not more than twopapers) to obtain the aggregate percentage required to pass the
semester.
19. A candidate whose result is declared late without any fault on his/her part,may attend classes for the next higher semester provisionally at his own risk
6
8/6/2019 Syallabus of PGDC
7/61
NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING
and responsibility, subject to his/her passing the concerned semesterexamination. In case a candidate fails to pass the concerned semesterexamination, his/her attendance/internal assessment in the next highersemester in which he was allowed to attend classes provisionally will standcancelled.
20. A candidate shall be promoted to the next higher semester if he/she passes atleast 50% of the theoretical papers (i.e. excluding subjects in which marking isdone on the basis of Viva Voce) having prescribed in the semester, failingwhich he/she shall be declared as FAIL in that semester and he/she shall berequired to appear in the failed semester in all the papers currently in force as,a private candidate (as ex-student).
EXPLANATION : 50% of five papers will be taken as three and that ofseven papers as four and that of nine papers as five under this Clause.
E. OTHER PROVISIONS
21. Question paper for the External exams will be common for all the institute andwill be set by a faculty who will be paid honorarium of Rs. 2500/- per subjectplus postage charges on actual basis. Question paper setting will beresponsibility of one of the institute on rotation basis ie. New Delhi, Nagpur,Neyveli and Durgapur respectively. Question papers will be broadly subjectivein nature.
22. Answer sheets of the Semester exams will not be evaluated in the parentinstitute and sent for outside evaluation. The evaluator will be paid anhonorarium @ Rs. 40 per copy plus postage on actual basis. For evaluatingthe project report or conducting viva voce the external and the internalexaminer will be paid honorarium of Rs. 40/- and Rs. 20/- respectively perstudent plus TA. Similarly faculty evaluating for simulator will be paidhonorarium @ Rs. 20/- per student.
23. The invigilators in the semester exams will be paid a honorarium of Rs. 200/-per sitting of 3 hour. For 30 students one invigilator, for 30-60 students twoinvigilator and for more than 60 students 3 invigilators may be employed.Principal Director/ Director in-charge will act as Chief Superintendant of the
examination and will be responsible for smooth conduct of examination andshall be paid a lump sum honorarium of Rs 2000/- for the semester finalexams. A centre clerk and two peons (for sealing, water serving etc.) may beappointed by the Chief Supdt. for conduct of semester examination and maybe paid an honorarium of Rs.120/- and Rs.50/- per sitting respectively. Thecentre clerk will assist the Chief Supdt. in making seat plan, maintenance offiles (attendance, billing, dispatch of answer sheets etc.) for the exams.
24. Tabulation of the internal and external marks will be done by a faculty andshall be paid honorarium @ Rs. 20 per student. He will be responsible forcollecting all the marks and tabulation and publication of the final result. The
Principal Director /Director Incharge will nominate the tabulator of theirrespective institute. The tabulation records of the passed out students will bekept with Training Officer/Course Coordinator of the respective institutes.
7
8/6/2019 Syallabus of PGDC
8/61
NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING
25. A sumptuary allowance of Rs.1000/- per month may be granted to the coursecoordinator of PGDC in TPPE at the respective institutes and this expenditurewill be met from the examination fee collection. The Course Coordinator willmaintain the records of registration, feedback (to be taken once in eachsemester) and will prepare the day wise module of the course and intimate
the faculty for their lectures.
26. Instruction For The Question Paper Setter: The question setter will set twosets of question paper for each subject and mark on the envelop Set A andSet B and seal them separately. The sealed Envelops For Set A and Set Bshould be sealed in a bigger envelop and sent to the respective principaldirector. The Paper setter should maintain the confidentiality of the questionpaper and all rough worksheets should be destroyed. The question should bebroadly subjective in nature and should cover all parts of the syllabus. Themaximum marks for each subject is 100 and pass marks is 45. The timeallowed for each paper will be 3 hours. The subject syllabus can be identified
by the following help:
Power Plant Familiarisation I: This includes the General Introduction module,Industrial Safety module and 5th and 6th week module of Power PlantFamiliarisation.
Power Plant Familiarisation II: This includes 1st to 4th week module of PowerPlant Familiarisation
All other subjects have nomenclature pertaining to the modules which havebeen included.
27. The corporate quality committee will meet every year in the last week of Julyto review the status of the course.
28.Any other provision not contained in the above shall be governed by the rulesand regulations framed by NPTI from time to time.
8
8/6/2019 Syallabus of PGDC
9/61
NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING
FIRST
SEMESTER
PGDC IN TPPE
9
8/6/2019 Syallabus of PGDC
10/61
NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING
Module : General Introduction(Duration): week
FORENOON AFTERNOON
DAY-1 Registration and Inauguration , CourseDescription, Institute facilities
Growth of power Industry afterIndependence
DAY-2 Site Selection (Site availability, Rawmaterial, Fuel, load evacuation, Water,
Transport, Pit Head Station ,Air Pollution,Topography, Skilled manpower ).
Coal to Electricity (Coal /Air / Flue/ Gas/ Water /Steam Path ,Brief description of main equipments
involved in a Thermal Power plant Station )
DAY-3 General layout of a Thermal PowerStation (Block Diagram of mainequipments, Generator and theirAuxiliaries)
Visit to Thermal Power Station
10
8/6/2019 Syallabus of PGDC
11/61
NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING
Module : Industrial Safety(Duration): week
FORENOON AFTERNOON
DAY-1 Accidents (Causes & Factors, Cost ofAccidents , Accidents Prevention,Investigation of Accidents, Reporting andRecording Systems of Accidents)
First Aid (Basics of First Aid, How injuries arecaused in lifting, falls etc.)
DAY-2 Fire fighting (Fundamentals of Fire, FireFighting Equipments and systems, FireExtinguishing Methods, Demonstration ofvarious fire.)
Industrial Safety & hazards(Industrial Hazards,Protective Clothing and Equipment, Safe workpractices in power Plants, permit to work system,safety in moving and storage of materials,Housekeeping Safety rules)
11
8/6/2019 Syallabus of PGDC
12/61
NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING
Module : Power Plant Familiarization
(Duration): 6 week
FORENOON AFTERNOON
DAY-1 Steam Cycle Theory (Carnot cycle ,Rankine cycle, with reference to aspecific unit 500/210 MW , steamproperties)
Coal (Types of coal and their characteristics, Theirsuitability for different kinds of Boiler, Alterations infiring methods due to change of coal composition)
DAY-2 Coal Handling system (Location andlayout, Main Equipments and theirfunctions , Coal transportation ,preparation, storage and reclamation ,MGR system, safety aspects , Fireprevention and fire fighting in coalhanding plant )
Combustion Theory(Definition , Combustionrequirements, factor influencing combustion,combustion of fuels , gross and net calorific value)
DAY-3 Fuel Oil Systems (Location and siteselection, Type of fuel used , Mainequipment and their functionsTransportation, handling , storage Fueloil preparation before firing)
Plant visit (visit to coal handling plant, visit to fueloil station)
DAY-4 Description of Main Boiler(Classification and Types, Arrangementsof main boiler , Fundamentals of Boilerdesign , Location of various pressureparts)
Boiler Circulation Theory (water walls boilingphenomena , Nucleate / Film boiling , Natural /Controlled / Forced circulation )
DAY-5 Constructional detail of Super heaters,Re heaters, Economizers, De superheaters.
Steam Separation theory ( Boiler Drum & itsinternals)
12
8/6/2019 Syallabus of PGDC
13/61
8/6/2019 Syallabus of PGDC
14/61
NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING
Module : Power Plant Familiarization(Duration): 6 week
3RDWEEK
FORENOON AFTERNOON
DAY-1 Furnace, Safeguard, supervisorySystem
(Description of field equipments (no C&I )
Audio Visual Session (FSSS)
DAY-2 Water Supply System (soft water,clarified water, cooling water, D. Mwater)
Steam Turbines (Classification of TurbinesMetallurgical considerations, WorkingPrinciples
DAY-3 Description of main components i.e.
Turbine casing, rotor steam admissionvalves, couplings , bearings etc.
Turbine lubrication Oil System Construction and
working Principles of main Oil pumps , Oil coolers)
DAY-4 Steam condensation andCondensers(film wise/drop wisecondensation, Direct/ indirectcondensation and vacuum creation)
Audio-visual (vacuum System, Turbinelubrication Systems
DAY-5 Power Station Pumps (Classification ofpumps, Centrifugal pumps, positivedisplacement pumps)
Boiler Feed Pump (Function of BFPConstructional details)
14
8/6/2019 Syallabus of PGDC
15/61
NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING
Module : Power Plant Familiarization(Duration): 6 Weeks
4TH WEEK
FORENOON AFTERNOON
DAY - 1 . Circulating Water System (Open/
Closed system, CW Pumps, Cooling
Towers, CT Pumps, CT Fans)
Plan Visit (CW System including
Cooling Towers, CT Pumps, CT
Fans, Condenser Vacuum Ejectors,
BFP)
DAY - 2 Regenerative Feed Heating System
(Working Principle and constructionaldetails of L.P. Heaters, Deaerators,
H.P. Heaters GSC, Ejector)
Visit to (Regenerating Feed
Heating System, TurbineLubricating Oil system, Water
Treatment Plant)
DAY - 3 Turbine Governing System ( Types of
Governing systems. Various
components, systems and their
functions, Oil circuit for Governing
System. Overall working of governing
system with reference to load throw
off. Load raising).
Turbine Governing System
(Contd.)
DAY - 4 Audio/Visual Session on Governing
System.
HP/LP Bypass system and PRDS
and its utility, Various interlocks
and protections
DAY 5 Audio/Visual Session on HP/LP By
pass System.
Plant visit (Governing System andHP/LP By pass System).
15
8/6/2019 Syallabus of PGDC
16/61
NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING
Module : Power Plant Familiarization
(Duration) : 6 Weeks
5TH WEEKFORENOON AFTERNOON
DAY - 1 Generator Constructional Details
(Basic principle of electricity,
generation
Development of generator design,
Construction details of rotor, stator etc.
Tutorial/General discussion.
DAY - 2 Hydrogen Cooling System and Stator
Water Cooling System (Different types
of cooling arrangements for rotor andstator, Selection and properties of
coolant, Air cooling, Hydrogen
cooling, Stator water cooling, H2
Charging/ PurgingCycle).
Audio visual on Hydrogen cooling
system
DAY - 3 Hydrogen Seal Oil System (Details of
the system, Function and purpose of
differential pressure regulator and
pressure oil regulators, Types of
Hydrogen seals and their constructiondetails).
Generator Excitation System and
AVR (Principles, Simple arrangem-
nts of excitor and its field winding,
Classification of excitation system -
High Frequency / static excitationsystem - their merits and demerits,
Automatic Voltage Regulator).
DAY - 4 Audio/Visual Session on Excitation
System.
Plant Visit (Generator and
Auxiliaries, Hydrogen cooling &
Stator Water Cooling System,
Hydrogen Seal oil system).
DAY 5 Transformers (Working Principles,
Various types of transformers used in apower station, Constructional features
of main transformer and accessories,
Bucholtz relay and main protections,
Types of cooling, Mulsifire and other
fire protection systems.
Audio/Visual/Discussion session.
16
8/6/2019 Syallabus of PGDC
17/61
NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING
Module : Power Plant Familiarization
(Duration) : 6 Weeks
6TH WEEK
FORENOON AFTERNOON
DAY - 1 Motors(Fundamentals, Constructional
details of HT/LT Motors, Various
motors used .in Power Stations.
Plant visit (Transformers
Excitation System)
DAY - 2 HT-LT Supply system/DC Supply
System (A typical layout of 6.6 KV,
3.3 KV and 415 V supply system in a
TPS, DC Supply system in a TPS .
Audio visual on electrical System.
DAY - 3 Switchyard (A typical layout of
Switchyard of a Thermal PowerStation, Bus system, Isolators, CTs,
PTs, Earthing, Oil Circuit Breakers,
Air Blast Circuit Breakers. SF6 Circuit
Breakers).
Plant Visit (Switchyard, HT/LT
System, DC Supply System).
DAY - 4 Audio/Visual Session Discussion
DAY 5 Written Appraisal.
17
8/6/2019 Syallabus of PGDC
18/61
NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING
Module : Scheme Briefing & Tracing
(Duration) : 2 Weeks1ST
WEEK
FORENOON AFTERNOON
DAY - 1 Scheme briefing in class room on
Boiler Drum connections, Feed
regenerating Heating System, Air and
Flue Gas Path.
Class Room briefing on Fuel oil
system and milling system.
DAY - 2 Class Room briefing on Main steam.
Cold reheat, Hot reheat lines,
condensate & feed water lines, BFP,
CW schemes.
Class Room briefing on Hydrogen
cooling, stator water cooling, seal
oil system, switchyard, AC/DC
auxiliary power supply system,
DAY - 3 Scheme Tracing: Coal Handling,
Receiving points. stocking lines,weighing, sampling. Screening,
crushing, bunker filling, conveyors,
tension arrangement for conveyors.
Oil Handling (Unloading
arrangements, oil tank mountings,oil pump house connections, tank
heating. pipe line layout with
provisions for expansion.).
DAY - 4 Boiler - Feed Water Schemes (Feed
control station arrangement,economiser connections, economiser
recirculation lines, boiler drum, water
wall connections; drain header, blow
down lines, CBD, IBD, SH/RH,attemperator station).
Steam Schemes (MS, CR & HRH
lines up to turbine control valvesincluding HP/LPby pass, locationof safety valves, vents and drains,
auxiliary PRDS schemes, auxiliary
steam distribution, soot blowing
steam lines).
DAY 5 Air and Flue Gas Schemes (ID,FD, PA
fans and their control system including
Seal air/ Scanner air/ Igniter air
Fans/Systems/ Damper control forsecondary air.
Fuel Schemes (Scheme of RC
bunkers and RC feeders, Coal mill
connections. Light oil and.
atomising air system, location oftrip valves, air control valves,
nozzles valves and igniters. Heavy
oil and atomising steam system).
18
8/6/2019 Syallabus of PGDC
19/61
NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING
Module : Scheme Briefing & Tracing
(Duration) : 2 Weeks2ND WEEK
FORENOON AFTERNOON
DAY - 1 Water Treatment Plant (Raw water
tanks to DM Water storage tanks,
arrangement of Pressure
sand/Activated carbon filters, cation,
anion, mixed beds, degassifier, back
washing system, regeneration,
Phosphate and Hydrazine dozing
scheme.
Ash Handling System - Bottom
Ash and Fly ash disposal system
hoppers/Clink grinder, HP/LP
water injection, Ash slurry pumps
etc.
DAY - 2 Steam Extractions and Drains(Schemes of turbine extractions,
FCNRVS, Heater drain connections,
HP/LP drips. Schemes for heating
flanges and studs. Steam
connections/condenser air line
connections to ejectors, Unit drain
tank/flash tank connections).
Condensate and Feed WaterSchemes (CEP connections,
scheme of condensate flow,
ejectors, gland steam coolers, LP
heater, deaerator connections.
Scheme of Feed Water flow, BFP
connections, Feed water
connections to HP heaters,
Location of valves,interconnections, by pass
arrangement for heaters)
DAY - 3 Turbine Oil System (Turbine lube oil
schemes, lube oil purification schemes,
location of MOT & lube oil pumps, Oil
coolers, cooling water connections.
CW System and Cooling Towers
(locating moving screens, CW
Pumps, Venting arrangements,
Valve locations, Chlorination
schemes).
DAY - 4 Generator (Seal oil scheme, Hydrogen
scheme, Stator water cooling schemes,
Excitation arrangements).
Switchyard (GT to feeder line
arrangements, locating various
transformers (GT, UA SAT, CTO,PTO), switchgears, isolator
earthing arrangement, buses etc
DAY 5 Auxiliary Power Supply (6.6 KV
schemes/ 420 V Schemes, arrangement
of breakers, buses. DC system, battery
bank arrangement).
Viva-voce.
19
8/6/2019 Syallabus of PGDC
20/61
8/6/2019 Syallabus of PGDC
21/61
8/6/2019 Syallabus of PGDC
22/61
NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING
Module : ROJ (OPERATION)
(Duration): 5 Weeks
1STWEEK
FORENOON AFTERNOON
DAY - 1 Working with Boiler Firing floor Operator :(Cleaning of oil guns/Filters and their trial run,
Checking feed control valves, blow down valves,
air vents, coal feeders, secondary air dampers,
ash level in economisers hoppers, Operation of
Blow downs, chemical dosing valves operation,
Charging of drum gauge glass aux. steam for
soot blowing).
Continue.....
DAY - 2 Working with Coal Mill Operator (Shift taking
over/handing over checks, Pre start checks,Routine checks, Mechanical Isolation of mills,
Cold and hot air damper operation, Activities
during emergency in mill area, Changing over of
seal air filter, Oil filling into mill gear box)..
Continue .....
DAY - 3 Working with. Ash. Disposal operator
(Checking for Shift taking over/handing over,
Routine check (Note atleast one reading), Ash
flow rate in full load and partial load unit
operation (from Bottom ash and ESP Hoppersetc., ESP field electrical system, Isolation and
charging of ESP fields, Ash disposal urn Color
of Ash
Continue .....
DAY - 4 Working with Boiler Fans Operator (Checking
-for shift taking over and handing over, Routine
checks (Note: atleast one reading), Isolation of
ID,FD,PA fans, Charging of lube Oil system,
Change over of lube oil pump)
Continue .....
DAY 5 Working with Compressor Operator (Shift
handing over/taking over checks, Routine checks
(Note: atleast one reading), Charging of Drier,
Regeneration of Drier, Starting and stopping
procedure. Emergency operation.
Continue .....
Note:- The students shall Undertake the 'Rotational On-job Training (Oprn),in the Power Station
identifiedby the concerned NPTI. The course Co-ordinator shall make the appropriate shiftroaster suiting to local conditions/shift roaster of the power plant.
22
8/6/2019 Syallabus of PGDC
23/61
NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING
Module : ROJ (OPERATION)
(Duration) : 5 Weeks
2ND WEEK
FORENOON AFTERNOON
DAY 6 Working with Boiler side supervisor(Shift taking over/handing over checks,
Coordination with local operators,
Reporting to Control Room,. Routine
checks (Note: atleast one reading).
Continue .....
DAY 7 Working with Boiler Control Desk
Operator (Shift handing/taking over
checks, Receiving site report from
operators and supervisor concern,
Logging of parameter (Note: atleast onereading), Operation procedure of
different equipment
Continue .....
DAY 8 Working with Boiler Control Desk
Operator
(Shift handing/taking over checks,
Receiving, site report from operators
and supervisor concern Logging of
Parameter (note: atleast one reading),
Operation procedure of differentequipment.
Continue .....
DAY 9 Working with CEP Operator (Shift
handing over and taking over, Routine
checks, Chemical dosing pump, starting
procedure and making of chemical
solution, Checking of make up and other
controller, Priming of water box, Start of
ejectors, Charging of LP Heat
Continue .....
DAY 10 Working with BFP Operator (Shift
handing over and taking over, Routine
checks (Note: atleast one reading),
Precheck for starting BFP, Charging of
lub oil system, Change over of filters,
checking of control v/vs., Operation of
Recirculation valves, Charging Isolation
of HP Heaters, Deaerator water heating,
Aux.. steam charging/isolation) Valve
Continue .....
23
8/6/2019 Syallabus of PGDC
24/61
NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING
Module : ROJ (OPERATION)
(Duration) : 5 Weeks
3RD WEEK
FORENOON AFTERNOON
DAY 11 Working with Turbine Operator(Shift handing over & taking over, Routine checks
(Note: one reading), rechecks for starting lub oil
system, Filling of oil in Main Oil Tank, AC, DC,Jacking oil pump checks, Instrumentation fitted with
main oil tank, Parameters of Governing system,
Charging and isolation of governing system, ESV, IVs
and control V/Vs, local operation, HP/LP By pass
Continue .....
DAY - 12 Working with Generator Operator ( Shift handing
and taking over, Routine checks, Pre start checking ofseal oil, Hydrogen cooling, Stator water cooling system,
Purging of H2 and C02 of Hydrogen cylinder charging,
Cooler/Filter charging.
Working with Turbine Supervisor (Shift
handing/taking over, Routine checks by supervisor,
Coordination with Operator, Reporting to Control
Room)
Continue .....
DAY - 13 Working with Turbine Desk Operator (Shift handing
over & taking over, Receiving report from supervisorsand operators, .Logging of parameters, Operation
Procedure of main equipment, ATT & ATRS operation,
Emergency operation).
Continue .....
DAY - 14 Working with Electrician/Supervisor (Shift handing
over and taking over, Routine check of Diesel set and
other parameter, HT & LT Breaker Isolation and
normalisation procedure, Charging of DC Batteries,
Checking ofGT, U AT and service transfolll1ers, Safety
devices, Operation of switchgear compressor).
Continue .....
DAY 15 Working withElectrical Desk Engineer(Shift handing over/taking over checks,
Routine check (Note one reading), Operation procedure
of various equipment at generator desk like excitation s
stem. AVR etc).
Continue .....
24
8/6/2019 Syallabus of PGDC
25/61
NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING
Module : ROJ (OPERATION)
(Duration) : 5 Weeks
4TH WEEK
FORENOON AFTERNOON
DAY 16 Working with Hydrogen Plant Operator(Shift handing / taking over, Operation of H2
Plant, Filling operation of H2 cylinder,
Analysis of H2and O2 concentration. Routine
checks).
Continue .....
DAY - 17 Working Coal handling control room
(Shift handing/taking over, Pre-checks of
CRP equipment operation, Operation of
Crusher, belt conveyor, tripper, flap gate,
Unloading procedure of wagons, Magneticseparator and weighing arrangement, Routine
checks, Bunker filling and level monitoring,
Coordination with mines, unit incharge and
shift incharge, Coal amt. recording,
Reclaimer).
Continue .....
DAY 18 Working with Switchyard Control Room
Engineer (Shift handover/takeover, Routine
check, Load schedule for the month, week
and day, Load sharing by Units,Charging/isolation of HT Bus, Reporting to
in house and external agencies about load
schedule. operation of Isolators and brokers).
Continue .....
DAY 19 Working with Cooling tower and cooling
water pump operator (Shift handing
over/taking over, Routine checks, Pre-start
checks of CT and CW Systems,
Starting/Isolation of cooling towers, CT .'
Pumps, CW Pumps, Emergency operation,Lub oil system of C\V and CT Pumps.
Continue .....
DAY 20 Working with Performance Monitoring
Cell (Collection of information from each
section, Programme for calculation (show at
least one day calculation of all parameter),
Analysis of result and comments preparation,
Daily plant meeting (input and output),
Reporting to concern about plant
performance).
Continue .....
25
8/6/2019 Syallabus of PGDC
26/61
NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING
Module : ROJ (OPERATION)
(Duration) : 5 Weeks
5THWEEK
FORENOON AFTERNOON
DAY - 21 Working with Shift chemist(Shift
handing over / taking over, Routine
activities, Collection of samples of
(Coal:-oil, H2, Drum Water, Steam
Condensate etc.) (note down pt. of
sampling), Analysis of sample (Note
down the value), Action suggested to
bring the concentration normal.
Continue .....
DAY 22 Working with DM Plant chemist (Shift
handing over and taking over, Routinechecks, Storage tank. for clarified and
DM water, Starting and Isolation of DM
Water pump Regeneration of Ion
Exchange
Continue .....
DAY - 23 Working with Unit Incharge (Shift
hand over/take over, Investigation and
reporting of plant defects and
abnormalities. Issue and canceling of
PTW, Hot and Cold startup of unit,Decision during emergency,
coordination and reporting of problem to
higher Management, Main parameters,
monitored (take one reading).
Continue .....
DAY - 24 Working with Shift Incharge (Shift
handing over / take over, Receiving
report from unit Incharge, Instruction to
SCE regarding load sharing, Reporting
to higher management, Main parametersmonitored (take one
reading).
Continue .....
DAY 25 Working with Air-conditioning
Operator
(Shift hand over/take over. Routine
checks (take one reading). Temperature
Control, Humidity Control, Operation of
AC Plant, Dust Control).
Apprasial/Disussions
26
8/6/2019 Syallabus of PGDC
27/61
NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING
Module : Erection, Commissioning & Construction Management
(Duration) : 2 Weeks
Erection, Commissioning1st Week
FORENOON AFTERNOON
DAY - 1 Preparation of commissioning, trial run
of various equipments, commissioning
of valves, air and gas tightness test of
boiler.
Chemical cleaning of Boiler
preparation for boiler light up,
thermal flow test of water walls and
economisers, steam blowing.
DAY - 2 Safety Valve setting, reliable run of
boiler, Hydraulic test of boiler.
Alkaline flushing and commission-
ing regenerative system, acid
cleaning of oil pipe lines, oilflushing procedure of lubricating
oil and governing, system.
DAY - 3 Turbine Lubricating oil flow testing,
steam blowing, reheater safety Valve
setting, vacuum tightness test ejector
testing.
Commissioning of governing
system ATRS & ATT, and TSE.
DAY - 4 Commissioning of generator and
auxiliaries (Generator testing, rotorand stator cooling system, excitation
system
Commissioning of electrical system
(Circuit breakers, isolators, CT andPT, rectifiers, switchgear DC
system).
DAY 5 C&I Commissioning activities
(Minimum instrumentation s required
for major C&I commissioning,
commissioning of control of valve,
tuning of control valves).
Discussion/Appraisal
27
8/6/2019 Syallabus of PGDC
28/61
NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING
Module : Erection, Commissioning & Construction Management
(Duration) : 2 WeekConstruction Management
2
nd
WeekFORENOON AFTERNOONDAY - 1 Construction, Site Organisation and
Administration Estimating, Costing
and Bidding
Construction Contracts &
Contracting Construction Materials
and Construction Project
Management Techniques
DAY - 2 Tendering, Bidding, Contract Laws &
Claims Management Risk
Management Project Risk
Management
Construction site Personnel
Management Manpower Planning
Techniques Labour Laws for
Construction
DAY - 3 Site Management, Construction
Finance Management, and Cost
Accounting
Materials and Logistics
Management, Project Management
DAY - 4 Introduction to Construction Safety,
Common Safety Hazards, Laws on
Construction Safety, Health andWelfare, Safety Practices and
Standards
Introduction to Equipment and
Machines used in power plant
construction, Planning andSelection, Case Studies on
Construction Equipment
Planning and Selection
DAY 5 Construction Equipment Maintenance,
Case Studies on Construction
Equipment Maintenance
Management Information Systems
in construction management,
Construction Quality Management,
Productivity, Safety and Quality
28
8/6/2019 Syallabus of PGDC
29/61
NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING
Module : Power Plant Performance and Efficiency Calculation
(Duration) : 1 Week
FORENOON AFTERNOON
DAY - 1 Introduction, Need for performance
monitoring, objective, controllable and
un-controllable factors, basic
requirements.
Factors influencing performance of
Boilers and Optimisation (Fuel
properties, excess air, fineness of
PF etc.)
DAY - 2 Performance Monitoring of Boiler
Auxiliaries (Pulverisers, Factors,
sampling of pulverised coal, classifier
adjustments, mill rejects, causes and
remedies) Air Heaters (effect of AHoutlet temperature, Performance tests)
Fans (Performance, curves, optimum
operation point.)
Boiler efficiency calculation
(Direct method calculation,
limitations in adopting direct
method, (Losses method, Other
standard method.)
DAY - 3 Factors influencing performance of
turbine( Steam pressure, temperature
and
Back pressure, cylinder efficiency,
deposits on turbine blades, blade
roughness, effect of tubes) TurbineLosses..
Factors affecting performance of
condenser and feed heater ( TTD,
CW inlet, temperature, CW flow,
heat transfer across tubes) Heaters
(air accumulation, steam side/
water side fouling, drainage, Effectof attemperation in reheaters). Heat
balancing.
DAY - 4 Turbine heat rate calculations (Method
parameters required).
Optimisation of auxiliary power
consumption (Scope, variable
speed drives, operation of un-
necessary running auxiliaries).
DAY 5 Logging and recording (Scope of
logging and recording, use ofDAS/DDC in performancemonitoring).
Discussion and appraisal.
29
8/6/2019 Syallabus of PGDC
30/61
NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING
Module : Power Plant Chemistry ,Metallurgy, NDT and Welding
Duration : 2 Week
Chemistry
1/2 Week
FORENOON AFTERNOON
DAY - 1 Basic chemistry (Atomic structure,
elements, compounds, mixtures,
solutions, ionization, salts acids alkali
pH values).
Pre and post treatment of water.
DAY - 2 Chemical control and treatment of
Boiler feed water and steam. Coolingwater treatment
Classification of coal & oil, their
sampling and analysis
DAY - 3 Corrosion theory and deposition
30
8/6/2019 Syallabus of PGDC
31/61
NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING
Module : Power Plant Chemistry ,Metallurgy, NDT and Welding
Duration : 2 WeekMetallurgy
1 Week
FORENOON AFTERNOONDAY - 1 Introduction to Metallurgy and its
relevance in power industry crystal
structure - space lattices - crystal lattice
imperfections - crystal structure under
stress.
Elastic and Plastic deformations,
strain hardening and fracture
Mechanical properties of materials -
Testing of materials.
DAY - 2 Steel making - MicrostructureComposition/property relationship of steel
- effects of - alloying - power plant steels.
Heat treatment and surface hardeningof steel failure mechanism - typical
such situations in a power plant.
DAY - 3 Non-ferrous metals and alloy's:
Application of Non ferrous metals and
alloys in PP condenser components -
conductors slot wedges in generator rotor -
pipe to pipe couplings - bearings. Copper,
Aluminum, Nickel, Magnesium. Titanium
and their alloys in properties of theses
alloys failure mechanism.
Non metallic materials : Use of
plastics and rubber in PP
Thermoplastics thermo sets rubbers
their properties. Application, coatings,
adhesive, linings, insulation seals,
sealants, gaskets etc. Application of
ceramics in Power Plant Insulation
Refractory properties.
DAY - 4 Material selection for Design Material
requirement, specification and relevant
standards fro boiler, turbine, generator
components Piping and Valves :
Appreciation of component, fabrication
metal forming, casting forging, pipe
bending, tube manufacture.
Protective surface treatment. (Metal
cleaning protective Metal coating,
Fabrication of precoated metals).
DAY 5 Defect analysis and life assessment. Lowtemperature behavior. high temperature
behavior - defect assessment of
solidification crack austenite stainless steel
welds, cracking in CrMoV weldment etc.
Thermal fatigue - various tests - Defects
assessment route and calculation of
damage. Remaining life assessment
beyond design life of boilers, turbine
rotors, generator rotors etc.
Group discussion and appraisal
31
8/6/2019 Syallabus of PGDC
32/61
NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING
Module : Power Plant Chemistry ,Metallurgy, NDT and Welding
Duration : 2 Week
NDT & WELDING1/2 Week
FORENOON AFTERNOON
DAY - 1 Introduction to welding and types of
welding.
Description of welding methods
generally used in thermal power
station.
DAY - 2 Welding machines, types of electrodes,
precautions during welding process,
welding defects.
Purpose of NDT and types of
defects cover by NDT.
DAY - 3 NDT Methods used in power station
(Principle, equipments, utilization,merits and de-merits).
32
8/6/2019 Syallabus of PGDC
33/61
NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING
Module : Gas turbine & combined cycle power plant
(Duration) : 1 Week
1st
week
FORENOON AFTERNOON
DAY - 1 Gas Turbine and Combined cyclepower plant-introduction, basic cyclesand types of CCGT
Fuels for gas turbine plants,physical and chemical propertiesof fuels and their analyses
DAY - 2 Description and construction details ofCompressorsDescription and construction details of
Combustors
Gas turbine construction details-blade materials and its selection,cooling arrangement
DAY - 3 Gas turbine support system, inlet /exhaust systems, lube oil system, fireprotection system, governing system
Waste heat recovery steamgenerator - Description andconstruction details.Cogeneration plants.
DAY - 4 Emission control main emissionproducts, its effects and control.
Operation of Gas Turbine andCCGT plant- Pre checks, Startupand shutting down procedureincluding normal operation.
DAY 5 Efficiency and performancemonitoring, optimization of CCGT,performance testing.
Combined cycle power plantmaintenance- planning forschedule maintenance, variouschecks, case study.
33
8/6/2019 Syallabus of PGDC
34/61
NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING
Module : Advanced Steam Generation Technology- Supercritical and FBC
(Duration) : 1 Week
FORENOON AFTERNOON
DAY - 1 Introduction to supercritical
technology, advantages-World
scenario in supercritical technology.
Arrangement of super critical
boilers and their types. Comparison
between spiral water wall
circulating and vertical tubing.
DAY - 2 Special alloys for super critical boilers
and welding techniques.
Differences between Supercritical
and subcritical Technology
DAY - 3 Introduction to FBC TechnologyAdvantages, Scope, Fuel flexibility etc
Classification of FBC technology
boilers.
DAY - 4 Description of various components ofCFBC Boiler
Environmental benefits
DAY 5 Limitations, major concerns in the O&M ofFBC Boilers Visit to Supercritical/FBC Boilers
.
.
.
34
8/6/2019 Syallabus of PGDC
35/61
8/6/2019 Syallabus of PGDC
36/61
NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING
SECOND
SEMESTER
PGDC IN TPPE
36
8/6/2019 Syallabus of PGDC
37/61
NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING
Module : Power Plant Protection
(Duration) : 1 Week
FORENOON AFTERNOON
DAY - 1 Introduction (Terminology,
Requirements of protective system,
Historical developments) Protective
Relays (Types and their applications,
Construction, Maintenance
requirements, Setting and testing).
Methods of system earthing and the
fault conditions, Lighting / Surge
Instrument transformers.
DAY - 2 General Protection (Neutral earthing.Stator and rotor earth faults, Sustained
external faults, Instability, Protective
systems used above).
Transformer Protection (Variousprotections, Protective systems for
Transformers, UATs & STs).
DAY - 3 Motors (Faults and protection
systems).
Automatic Voltage (Requirements,
types and function mechanical,
electronic amplifier magnetic
amplifier regulators, construction,
maintenance and testing).
DAY - 4 Bus bar Protection (Continuity of
supply, Discrimination, Circulating
current systems, Special features
relating to different voltage - Pilot
wire, carrier current, systems).
protection, PLCC Tele
Communication).
Feeder Protection (Continuity of
discrimination, Outline of Pilot
wire, carrier current, protection,
PLCC Tele communication).
DAY 5 Visit to Power Station and Lab.
demonstration.
Group discussion and appraisal.
37
8/6/2019 Syallabus of PGDC
38/61
NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING
Module : Energy Audit(Duration): week
FORENOON AFTERNOON
DAY-1 Need for Energy Audit and AuditProcedures. Energy Audit Macro Level & Micro Level.
Energy Management System, EnergyAuditing and their implementationtechniques for power industries.
DAY-2 Energy Saving methods withtypical examples and exercisesfor power stations
Ways to minimize losses in powertransmission & distribution system
DAY-3 Energy Losses An Integratedoptimal strategy for reduction ofT&D Losses.
38
8/6/2019 Syallabus of PGDC
39/61
NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING
Module : Maintenance Planning & Cost Control
(Duration) : 1 Week
FORENOON AFTERNOON
DAY - 1 Aims and objective of maintenance
efficient service, high plant
availability, maintenance learningengineer's duties.
Integration of maintenance with
requirements, plant reliability,
plant and daily work programs.
DAY - 2 Preventive maintenance of running
units.
Planning of major plant overhauls
shutdowns.
DAY - 3 Planning techniques critical path
analysis, charting system etc.
Purchasing and stores control-
standards, cost codes. Control of
stores and store records.
DAY - 4 Cost control. Direct costs, indirect
costs, outage costs, budgeting and
costing work, budgetary control.
Contract procedures (Conditions of
contract, capital applications and
procedure, project evaluation,
interest and depreciation charges).
DAY 5 Role and application of Information
Technology in maintenance planning.
Group discussion and Appraisal
39
8/6/2019 Syallabus of PGDC
40/61
NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING
Module : Nuclear Power Plant Familiarization
(Duration) : 1 Weeks1ST WEEK
FORENOON AFTERNOONDAY - 1 Introduction of nuclear energy, energy
from nuclear fusion, plasma, energyfrom nuclear fission
The fission process and fissionproducts, radioactivity, radioactivematerials
DAY - 2 Regulation for governing theproduction of power from nuclear fuel& safety aspect. National policyregarding Nuclear power generation.
Nuclear reactor and power plant-Reactor, general components ofnuclear reactor.
DAY - 3 Pressurized water reactor (PWR),boiling water reactors (BWR) &Canadian deuterium uranium reactor(CANDU)-mass and heat balance,working principle and constructiondetails
Gas-cooled reactor, liquid metalcooled reactor - mass and heatbalance, working principle andconstruction details, material forGas-cooled reactor, liquid metalcooled reactor, advantages and
limitation. Sodiumgraphite reactorSGR, fast reactors.
DAY - 4 Organic cooled and moderatorsreactor, Breeder reactors workingprinciple and construction details,material for reactor
Nuclear materials-nuclear fuel,coolant, moderating and reflectingmaterials, shielding materials.
DAY 5 Nuclear waste & its disposal-types ofnuclear waste ,effect of nuclearradiation
Appraisal
40
8/6/2019 Syallabus of PGDC
41/61
NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING
Module : Renewable Energy and Hydro Power Plants
(Duration) : 1 Week
FORENOON AFTERNOON
DAY - 1 Energy Sector Reforms, RegulationsEnvironment and RE
Wind Energy Systems
DAY - 2 Solar thermal power systems Direct energy Conversation - SolarPhotovoltaic, Fuel Cells.
DAY - 3 Biomass Energy Systems. Introduction of small, mini andhydro power generations
DAY - 4 Basic features of hydro Turbines Hydrology and estimation of waterpotential
DAY 5 Site selection and Layout of Hydropower plants
Description of Hydro TurbineInterlocks and protection
41
8/6/2019 Syallabus of PGDC
42/61
NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING
Module : Maintenance Practice & Inspection
(Duration) : 4Weeks1ST WEEK
FORENOON AFTERNOON
DAY - 1 Checking of Boiler tubes for external
damage due to erosion or cutting.
Method to overcome, e.g.
strengthening of tubes in the flow
channels.
Hydraulic test, allowable rate of
pressure drop. Checking of welds
pin holes.
DAY - 2 External cleaning of boiler surface and
water washing. Use of sky climber,
Different types of tube failures creep
overheating
Measurement of tube wall
thickness, Checking of flue gas
path for direct corrosion or erosion
and leakage.
DAY - 3 Checking of isolating and regulating
dampers for leakage, proper alignment,
adjustment for both under cold and hotoperation conditions.
PA, ID & FD fan check for inlet
dampers bearing alignment, vibrat-
ion both radial and axial shift ofmagnetic centre of motor and rotor,
fan blade conditions mode of
repairs, hard facing
DAY - 4 Checking of boiler mountings and their
adjustments (a) Gauges glasses, (b)
Safety valves, their checking and
settings of safety valves for blow
down and dropping
Checking the burner nozzle for
burnout and reasons for the same
and its metallurgy
DAY 5 Check the flow distribution in burners
adjustment of orifices or valves check
the burner flow direction and its
adjustment, checking of burner
chamber, dampers breakage of linksand proper gauge operation
Check the rollers or ball wear of
coal mill also Ball ring segment
wear. Keeping of capacity and hour
of operation. Check roller thrust
bearings and ring, seals
42
8/6/2019 Syallabus of PGDC
43/61
NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING
Module : Maintenance Practice & Inspection
(Duration): 4Weeks2ND WEEK
FORENOON AFTERNOON
DAY - 1 Check the adjustment of roller of ball
pressure check for leakage of coal and
air around journal assembly main shaft
and possible contamination of
lubricating oil method for reservation
Check the gear-box worm and
worm wheel driver for wear and
backlash allowable limits. Check
classifier vane angular position
proper operation and coal fineness
DAY - 2 Air heater maintenance/trouble
shooting causes and remedies
Soot Blowers Maintenance/Trouble
shooting causes and remedies
DAY - 3 Safety valve maintenance and its float
procedures, trouble shooting/causes
remedies
Procedure for alkali boil out and
acid cleaning preservation and
flushing, Procedure for flushing
and preservation both wet and dry
DAY - 4 Internal checking of drum and druminternals, Checking of at temperature
including spray nozzle and shock linen
Boiler bottom air seal, proper andfree movement and expansion of
boiler setting when hot. Normal
water level and flow in bottom seal.
Adjustment and prevention of dust
accumulation in the seal chamber
DAY 5 Maintenance of clinker grinder, bottom
ash hoppers maintenance of De-
watering pump slurry pumps and slurry
line
Furnace tightness checking, Bench
mark for draught loss for different
gas flow
43
8/6/2019 Syallabus of PGDC
44/61
NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING
Module : Maintenance Practice & Inspection
(Duration) : 4Weeks
3RD WEEK
FORENOON AFTERNOON
DAY - 1 Checking of tubes for any obstruction
land test or temperature rise and drop
test.
Procedure of welding of tubes in
membrane walls and tubes of
different composition
DAY - 2 Mechanical portion of governing
system and its maintenance
Checking of over speed ring and
eccentricity pick up for correct
operation.
DAY - 3 Checking of turbovisory instrument
particularly total expansion and
differential expansion
Turbine rotor and blade
maintenance and inspection checks,
Checking of turbine cylinders for
cracks deformation.
DAY - 4 Checking the rotor position with
respect to clearance in HP IP and LP
wheel clearance and also thrust bearing
and its wear. Checking the condition of babbit metal for scoring pitting,
chipping of or lack of bondage
between the babbit and the shell.
Main oil pump cleaning/flushing of
main oil tank, pipes, cleaning of
filters oil coolers, mtce. , of jacking
oil pumps.
DAY 5 Overhauling of control valves, ESVs
and IVs, Maintenance and inspection
of oil system turbine oil coolers,
Maintenance of condensate side and
steam side tubes
Condenser tube maintenance, off
lead and off load cleaning
procedure
44
8/6/2019 Syallabus of PGDC
45/61
NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING
Module : Maintenance Practice & Inspection
(Duration): 4Weeks
4TH WEEK
FORENOON AFTERNOON
DAY - 1 Maintenance of main ejectors and
starting ejectors Trouble shooting
causes remedies, Checking of axial
shift indicating system for Clean oil
nozzle and strainers.
Checking of bearing clearances and
allowable limits. Checking of
cylinders parting surface, for
proper matching, its grinding for
the purpose.
DAY - 2 Checking of gland and seal strips, their
clearances with allowing limits.
Checking the coupling alignment
of HP IP and LP rotors andgenerator and their. Setting.
Checking and setting of bearings
on foundation. Checking of shaft
sinking due to I vacuum pulling.
DAY - 3 Generator Maintenance : A Stator -
Checking overhang winding, clamp
and shields, loss wedges and
overheating.
Rotor checking of shaft earthing
arrangement. hydrogen seal and
leakages (purge test) loss wedges,
end ring for cracks, overheating.
Insulation resistance and windingresistance.
DAY - 4 Transformer maintenance - insulation
testing drying out routine maintenance.
HT Switchgear testing - routine
and type tests.
DAY 5 Motor Insulation checking, terminal
checking, phasing out. motor drying.
Cable jointing, material and
techniques
45
8/6/2019 Syallabus of PGDC
46/61
NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING
Module : Design Analysis(Duration): 1 week
1st WEEK
FORENOON
AFTERNOON
DAY-1 Process designing, Equipment and
System Design criteria
Pressure Vessel design
DAY-2 Heat Exchanger Design, Rotating
equipment design
Steam Generator Design
DAY-3 Steam turbine design consideration Piping layout& Piping Design, Design of
Ash handling systems and equipment
DAY-4 Electrical System Design Design of HT/LT motors
DAY-5 Design of transformers Instrumentation System Design
46
8/6/2019 Syallabus of PGDC
47/61
NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING
Module : Load Dispatch
(Duration) : 1 Week
FORENOON AFTERNOON
DAY - 1 Objective, functions and structure of
Load dispatching stations An
overview.
Location of load dispatch stations
area, state and regional and their
functions Voltage and frequency
control. Trends in design and
engineering of load dispatch /
systems.
DAY - 2 MW and AVAR sharing between
stations and systems voltage control-Concept of base load and peak load
operations - Economic dispatch
aspects.
Load forecasting - Short tern and
long term.
DAY - 3 Application of computers - DAS,
RTUs and SCADA.
HVDC systems and SVC
operation.
DAY - 4 Networking and protocol for data
exchange latest developments.
PC based power system study
package.
DAY 5 Visit to load dispatch centre. Group discussion and appraisal.
47
8/6/2019 Syallabus of PGDC
48/61
NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING
Module : Power Reforms and Regulations(Duration): 1 week
1st WEEK
FORENOON
AFTERNOON
DAY-1 Power sector reforms-the Indianperspective, Indian Electricity Act2003
National electricity policy, energyconservation act
DAY-2 Power sector reforms inGeneration, Transmission
Distribution Reforms
DAY-3 CERC-Functions andresponsibilities Case studies on Open Access system-long term and short term
DAY-4 National Tariff policy/ Multi yeartariff/ABT
APDRP/RGGVY Scheme
DAY-5 Power Trading and Sharing Case studies on tariff discovery throughcompetitive bidding, quality of power
48
8/6/2019 Syallabus of PGDC
49/61
NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING
Module : Control & Instrumentation
(Duration) : 2 Weeks
1st WEEK
FORENOON AFTERNOON
DAY - 1 Concept and .layout of Control and
Instrumentation in Thermal Power
Plant.
Pressure Measurement and
measuring instruments.
DAY - 2 Temperature measurement andmeasuring Instruments.
Flow measurement and measuringInstruments.
DAY - 3 Level Measurement and measuring
Instruments.
Practical demonstration on pressure
and flow measurements.
DAY - 4 Practical demonstration on level and
temperature measurements.
Protection and interlocks of Boiler,
turbine and their auxiliaries.
DAY 5 Introduction to auto control. Auto control loops used in thermal
stations.
49
8/6/2019 Syallabus of PGDC
50/61
NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING
Module : Control & Instrumentation
(Duration) : 2 Weeks2nd WEEK
FORENOON AFTERNOON
DAY - 1 Turbovisory instrumentation (Parameters
limits, Basic concepts of measuring
devices).
Commissioning of control loops
demonstration.
DAY - 2 ATRS. Visit to control and instrument at
control/control stations in the
stations.
DAY - 3 Analytical Instrumentation for (Boiler
Water, Steam, Flue Gas, H2/02/C02).
Practical demonstration and
analytical instruments. (Correct :
sampling and testing).
DAY - 4 Introduction to DOC and DAS in
Thermal
Power Station.
Continued ...
DAY 5 Introduction to new/latest technology in
Control and Instrumentation in modernthermal power station.
Group discussion (Performance)
50
8/6/2019 Syallabus of PGDC
51/61
NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING
Module : IT Application in Power Sector & GIS
(Duration) : 2 Weeks
1st week
FORENOON AFTERNOON
DAY - 1 Core of Information Technology (IT)Information Technology OverviewData Structures
Development of ComputerTechnologyCommunication & NetworkingData Processing Techniques
DAY - 2 Hands-on practice on Windows, MS-Office and Typical Application Packages.
4 Exercises of Hour duration to be done
in this session.
Computer Networks Resource
Sharing Network Topologies
Network Hardware Wired vs.
Wireless Networks Wi-fi &
Bluetooth Communications
Limitations - Client/Server
Architecture - LAN, WAN, TCP/IP -
Network Security.
DAY - 3 Hands-on practice on troubleshooting andgeneral maintenance of Computers and
Peripherals. Disk Cleanup
Defragmentation Detecting and Clearing
Software Virus & Spyware Preventive
Maintenance Procedures
Network and Internet based
Communications Domains DNS,
SLIP, PPP, FDDI - Browsers, Servers,
Search Engines Email - File
Transfer Protocol (FTP) - Telnet -
Internet Relay Chat - Instant
Messaging Cyber Laws
DAY - 4 Hands-on practice on Windows 2000 or
higher network O/S ConfiguringWorkgroups Configuring TCP/IP -
File/Folder Sharing, Printer Sharing and
Internet Sharing.
Internet Management - Security
Concepts, Information Privacy andCopyright issues Web Hosting -
Commerce on Internet - Governance
on Internet Management
Information Systems.
DAY 5 Hand-on practice on implementing aNetwork based Management Information
System using MS-Access
Project Management Software MS-
Project / Primavera.
.
51
8/6/2019 Syallabus of PGDC
52/61
NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING
Module : IT Application in Power Sector & GIS
(Duration) : 2 Weeks
2nd week
FORENOON AFTERNOON
DAY - 1 Concept of Geographical InformationSystem (GIS)Basics of GeographyHardware & Software Requirement
Fundamentals of GIS and MappingData VisualisationThematic Map Preparation
DAY - 2 Concepts of Remote Sensing Technology(RS)Basics of Remote SensingElectromagnetic Energy
Elements of Remote SensingFundamentals of Photogrammetry
DAY - 3 Concepts of Global Positioning System(GPS)Basics of GPS
Concepts of Global PositioningSystem (GPS)Working with GPS/DGPS
DAY - 4 Applications of GIS/RS in Power Generation
Applications of GIS/RS in Power Transmission and Distribution
DAY 5 Working with ARC-FM & CYMDIST
software
Working on various softwares for
distribution network planning and
analysis
.
52
8/6/2019 Syallabus of PGDC
53/61
8/6/2019 Syallabus of PGDC
54/61
NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING
Duration:4 Weeks1ST WEEK
FORENOON AFTERNOON
DAY - 1 Boiler Maintenance (Acquaintancewith various tools and tackles, Lifting
and material handling equipments,
consumables and spares).
Turbine stop valves and controlvalve mtc., Turbine governing
system setting, Gland sealing
system inspection, Deaerator
maintenance.
Overhauling of oil system, oil
coolers, testing for leakage,
flushing of main oil tanks etc
DAY - 2 Boiler Drum (Drum internal and
mounting inspection) Firing Floor(Oil guns, igniter, air, fans, scanner air
fans, Air heater, soot blowers, wind
box, burner, tilt and coal feeder).
Turbine Basement/ 0 meter
(condenser tube cleaning, CWPump Maintenance)
DAY - 3 Furnace (Boiler tube leakage
attending during shut down), edge
preparation and welding, post heating
etc. , Weld defects testing by NDTmethod, stress relieving, Coal Mills
(Preventive maintenance andoverhauling activities, Inspection of
classifier blades. Inspection of bull ring
segment replacement. Thrust bearing
and gear box replacement).
Turbine Basement/ 0 meter
(BFP maintenance, inspection of
bearing, inspection of balancing
system, inspection of mechanicalsystem, Hydraulic coupling scoop
mechanisms, Adjustments of lubeoil pressure and filter cleaning ,
BFP alignment). HP-LP Hearers
Detection of tube leakage and
plugging, Alternating water box
leakage).
DAY - 4 ID, FD & PA Fans (Preventive
maintenance and overhauling
activities, Vibration points).
ESP and Ash Handling System (ESPmaintenance fly ash maintenance,
clinker grinder, bottom ash, slurry
pumps etc.)
HP-LP Heaters (Oil Pumps
maintenance Centrifuge bowl
cleaning), CT Fans
(Preventive maintenance of CTFans and Gear box, Trays and
Nozzle cleaning, Fan blades angle
adjustment
DAY 5 Turbine Maintenance Stores
(Acquaintance with various tools and
tackles, Lifting and equipments,
consumables and spares).
Water treatment plant and
Hydrogen plant (Maintenance of
raw water pump and DM pump.
Maintenance of H2 for
compressors).
Module : ROJ (Maintenance)
54
8/6/2019 Syallabus of PGDC
55/61
NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING
Duration: 4 Weeks2nd WEEK
FORENOON AFTERNOON
DAY - 1 Coal Handling Plant (Crushermaintenance Conveyor maintenance.
Feeder maintenance).
Coal Handling Plant (Tripper
maintenance, Stacker cum Reclaimer
maintenance
Exposure to maintenance andtesting requirements for Drives
DAY - 2 Oil Handling Plant (Oill heaters
maintenance, Oil pumps rotary and
reciprocating pump etc.,
Filters/strainers maintenance).
Exposure to maintenance and
testing requirements for TSE
DAY - 3 Familiarisation of organisation
procedures for routine and preventive
maintenance, breakdown and
emergency repairs and Instrument lab.
set up for calibration and repairs.
Exposure to maintenance and
testing requirements for
Temperature Instrument
DAY - 4 Exposure to maintenance and testing
requirements of pressure, flow and
level instruments at site and in lab.
. Exposure to maintenance and
testing requirements for DDC,
DAS etc.
DAY 5 Transformers Electric Generator
55
8/6/2019 Syallabus of PGDC
56/61
NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING
Module : ROJ (Maintenance)
Duration: 4 Weeks3rd
WEEK
FORENOON AFTERNOON
DAY - 1 Circuit Breakers . Continue
DAY - 2 Electric Motors . Continue
DAY - 3 Electro Static Precipitator . Continue
DAY - 4 Cables
DAY 5 Relays and Soleenoid . Continue
56
8/6/2019 Syallabus of PGDC
57/61
NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING
Module : ROJ (Maintenance)
Duration: 4 Weeks4th WEEK
FORENOON AFTERNOON
DAY - 1 Cranes Lift
DAY - 2 Air Conditioning System Diesel Set
DAY - 3 HT/LT Supply Circuits HT/LT Supply Circuits
DAY - 4 AC/DC Lighting Circuits Batteries
DAY 5 Viva Voce Viva Voce
57
8/6/2019 Syallabus of PGDC
58/61
NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING
Module : Visit to Manufacturing Units/TPS
Duration: 2 Weeks
1ST WEEK
DAY - 1 Monday - Travelling
DAY - 2 Tuesday Visit to BHEL, Hardwar/ Visit to Chandrapur TPS,
MSEB
DAY - 3 Wednesday Travelling
DAY - 4 Thursday Visit to BHEL, Hyderabdad
DAY 5 Friday - Visit to BHEL, Bangalore
DAY - 6 Saturday - Travelling
Note:- The tour programme can be adjusted by the Institute depending their convenience.
58
8/6/2019 Syallabus of PGDC
59/61
NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING
Module : Visit to Manufacturing Units/TPS
(Duration) : 2 Weeks2ND WEEK
DAY - 1 Monday Visit to Neyveli/Vijaywada TPS
DAY - 2 Tuesday Travelling
DAY - 3 Wednesday Visit to BHEL, Trichy/ Visit to Trombay, TPS
DAY - 4 Thursday Visit to BHEL, Bhopal / Visit to Uran Gas Based
PS, MSEB
DAY 5 Friday - Travelling
DAY - 6 Saturday Visit to BHEL, Ranipet/ Visit to DESU Gas Turbine
Project
59
8/6/2019 Syallabus of PGDC
60/61
8/6/2019 Syallabus of PGDC
61/61
NATIONAL POWER TRAINING INSTITUTEPOST GRADUATE DIPLOMA COURSE IN THERMAL POWER PLANT ENGINEERING
2ND WEEK
FORENOON AFTERNOON
DAY - 1 Milling Plant Operation and raising
pressure as per Boiler loadrequirements
(Operation of second set of auxiliaries
and load sharing, Change over of
controls from manuals to auto).
Discussion on: (Milling Plant,
Burner, Optimum Sec. Air andDrum Level control, Burner
Mechanism and attemperators).
DAY - 2 Raising load in TG (Operation of
second set of auxiliaries and load
sharing, Checking of protections,
Changeover of controls from manual
to auto).
Unit shutting down procedures.
DAY - 3 Shutting down unit from full load to 30
MW and again raising load to full load
condition.
Unit start up from hot and warm
conditions.
DAY - 4 Tripping unit from full load on some
protection and start up again from hot
condition.,
Emergency problems in unit
(Boiler. Turbine and Generator).
DAY 5 Operation unit under emergencysituation.
Summing up programme/Appraisal.