Download - ST PAUL'S STREET - Ribble ValleyPROPOSED SIDE ELEVATION TO ST PAUL'S TERRACE PROPOSED SIDE ELEVATION TO CLUB PROPOSED FRONT ELEVATION Velux roof windows MAIN ROOF CONSTRUCTION Marley

Transcript
Page 1: ST PAUL'S STREET - Ribble ValleyPROPOSED SIDE ELEVATION TO ST PAUL'S TERRACE PROPOSED SIDE ELEVATION TO CLUB PROPOSED FRONT ELEVATION Velux roof windows MAIN ROOF CONSTRUCTION Marley

Ground F.L

Ground F.L

Eaves Level

Ridge Level

PROPOSED FRONT ELEVATIONPROPOSED SIDE ELEVATION TO CLUBPROPOSED SIDE ELEVATION TO ST PAUL'S TERRACE

Velux roof windows

MAIN ROOF CONSTRUCTIONMarley Modern concrete interlocking roof tiles (smooth face) laid at a pitch of 25 degrees on standard roof trusses at 600mm centres withsarking felt laid over rafters to BS 747. Trusses to be fixed to 100 x 75mm s/w wallplate and strapped to block work with Catnic type L 30x 5mm vertical m/s straps at least one meter in length at 2 meter centres. Roof trusses are to be provided with 100 x 25mm diagonal windbracing at 45 degrees to the 100 x 25mm longitudinal wind bracing. Roof space to be ventilated along eaves with Marley over fascia stripventilators ref. 22400. Manufacturer's specification should be complied with at all times.

EXTERNAL WALL CONSTRUCTIONNew external cavity wall to be constructed of 102mm face brickwork to match the adjacentproperties, 100mm cavity insulation bats within 100mm cavity (Drytherm), 125mm concreteblock with lightweight plaster finish and skim. Catnic BB2 stainless steel cavity wall ties to bespaced 900mm horizontally and 450mm vertically to comply with BS 1243 (1978). Cavity to beclosed along eaves and around all openings with Catnic CC50 insulated cavity closers positionedhorizontally and vertically to all openings. All openings are to be provided with Catnic lintelswith a minimum end bearing of 150mm at both ends. Brickwork used below DPC to beconstructed in Class B engineering or trench block may be used, the cavity is to be filled within200mm of the DPC with weak mix concrete. All new cavity walls are to be cut through toexisting cavities and be continuous.

WINDOWSPVC-U or hardwood window frame to be 1/10th of the floor are and have 1/20th opening lights and trickle ventsto achieve 8000m3 free air flow, windows are to be fitted with double glazed units having a minimum 16mm airgap with K glass in one skin and a 'soft' low-E coating. All frames are to have vertical and horizontal DPC's toall openings. Seal-a-mastic seals are to be provided around all window and door frames to provide a water tightseal. All glazing must be carried out in accordance with BS 6262. See notes on glazing in critical locations i.e.safety glazing.

Open roof structure to allow forventilation over the bin store.

PROPOSED REAR ELEVATION

INSULATIONInsulation of the roof space is to be 100mm thick Rockwool mineral wool roll bats laid betweenceiling joists over 12.5mm foil backed plasterboard, with a further 250mm fiberglass laid across-togive a total thickness of 350mm The insulation is to be extended over the timber wall plates off theinternal wall maintaining a minimum 50mm air gap between the insulation and the sarking felt toensure through ventilation of the roof space.

INTERNAL PARTITIONINGAll non-load bearing partitions are to be constructed of 100 x 50mm s/w studding at450mm centres on 100 x 75mm sole plate fixed to the floor. Partition to be insulatedwith Rockwool bats for sound insulation and covered with 12.5mm thickplasterboard with a density of 10kg/m2 and skim to both sides.

INTERNAL PARTITIONING - SOLID FLOORPartition walls constructed of concrete floor slab are to be 100mm thick lightweight blocks, anyinternal load bearing partition walls are to be constructed from 100mm solid concrete block andtaken down to strip foundation or constructed on reinforced concrete slabs.

GROUND FLOOR CONSTRUCTION (SOLID)New ground floor to be construction, clean stone well compacted to form levels with sand blinding,1200 gauge polythene DPM to be turned up at the edges and linked in to the DPC. kinkspanKooltherm K3 board 150mm thick with a top layer of 1000 gauage DPM membrane, slab 200mmconcrete C25 with one layer of A142 anti clacking steel reinforcement to be place 50mm from thetop of the slab.U value 0.22

TOP WATER DRAINAGEAll top water drainage are to be 100mm underground PVC-U or Supersleeve with flexible jointspiping to be laid at a minimum fall of 1:40. Drains passing under the building are to be protected bysurrounded with 100mm (min) granular material and where passing through a wall a suitably sizedlintel is to be provided over the opening ensuring that a 50mm space is maintained around the pipe.Openings must be masked to prevent fill. All underground drainage to comply with BS 8301 (1985).new gullies to be provided with rodding access, separate drainage systems are to be combined at thelast manhole depending on existing drainage systems.

WASTE PIPESAll waste pipes are to be a minimum of 38mm dia. to wash hand basins and sinks, pipes are to befitted with 75mm deep seal traps or anti-vac traps if connected directly to a soil and vent pipe.40mm waste pipes are to be provided to bath and showers. Soil and vent pipes are to be 100mmdia and terminated 1m above any opening windows adjacent to the stack, a suitable bird cage is tobe fitted to the top of the stack. Alternativly an air admittance valve may be used above the laststack connection. All installations are to comply with the Approved Document Part H and BS5572 (1978).

SMOKE ALARMSSmoke alarms are required to be fixed at ground and first floor levels andinterconnected. The alarm must be wired to the main supply and connected to itsown fused spur, alternatively the alarm may be connected to an intruder alarm if thesystem is specifically designed for this purpose. A smoke detector will cover anarea of 7.5m radius and a heat dector 5.3m radius, they should be fitted inaccordance with BS 5839 siting sensors within bedrooms, circulation area, head ofstairways, lounge/dining rooms and roof voids. Alarms within roof voids should befitted with a remote LED.

STAIRCASEThe new staircase shall comply with Part K of the Approved Document. The maximum rise andgoing for a private stair shall be any rise between 155mm and 220mm used with any goingbetween 245mm and 260mm or any rise between 165mm and 200mm used with any goingbetween 223mm and 300mm. The pitch of the staircase shall be no greater than 42 degrees, with aminimum headroom of 2m. The handrail is to be a minimum of 900mm high. Balustrades are tobe 1m high and capable of resisting a horizontal force of at least 0.36KN/m for each meter length.Maximum openings in the balustrades shall be no greater than 100mm and rails are to be verticalso as not to allow children to readily climb the guarding. Guarding to external balconies and roofedges to be a minimum of 1100mm high and resist a horizontal force of 0.74KN/m.

Part PAll electrical work required to meet the requirements of Part P(electrical safety) will be designed, installed, inspected and tested by aperson competent to do so. Prior to completion the L.A. must besatisfied that either:-An electrical installation certificate issued under a Competent PersonScheme has been issued; orAppropriate certificate and forms defined in BS 7671 (as ammended)have been submitted that confirms that the work has been inspectedand tested by a competent person. A competent person will have asound knowledge and experience relevent to the nature of the workundertaken and to the technical standards set down in BS 7671,be fullyversed in the inspection and testing procedures contained in theregulations and employ adequate testing equipment.

HEATINGHeating to be provided by low pressure radiators with a fan assisted combi boiler. Theinstallation is to be fitted in accordance with the Gas Regulations with a CORGIregistered fitter.

UNVENTED SYSTEMSAll unvented systems are to have an expansion pipe piped to the external elevation andextended down to floor level.

SUSPENDED TIMBER FLOOR CONSTRUCTIONFloor to be constructed of 25mm thick T&G floor boards with a density of15kg/m2 on 220 x 50mm gauged s/w floor joists (grade SC3) at 400mmcentres. Joists spanning onto party wall are to be fixed with Catnic joisthangers built into brickwork. Ceiling to be 12mm plasterboard nailed tounderside of joists with plaster skim finish. Lateral support to be provided at2m centres with galvanised m/s straps type L 30 x 5mm extended across 3joists. Catnic m/s herring bone strutting ref: HRB6, is to be provided alongmid-span of floor joist, last joist to be packed off the brick/blockwork.

NOTEAll windows on the rear elevation are to be glazed with white laminated obscureglass due to the separation distance from the existing properties.

NOTEAll windows on the rear elevation are to be glazed with white laminated obscureglass due to the separation distance from the existing properties.

NOTEWindows on this elevation are to beglazed with white laminated obscureglass due to the separation distance fromthe existing properties.

NOTER.W.P. Are to be fixed in the recessed brick pier as shown.

Bin Store

PLAN

ELEVATIONS

SS/Steel roof supports off the brick wallsforming a open top for ventilation.

1000mm

100m

m

4850

mm

2550

mm

5202mm

2500

mm

1000

mm

1800

mm3028

mm

2500mm

9444

mm

1300

mm

1800

mm

6344

mm

600m

m

HALL

LOUNGE

KITCHEN

W.C.

LOUNGELOUNGE

KITCHEN

BEDROOM BEDROOM

BEDROOM

LANDING

BATHROOM

PROPOSED FIRST FLOOR PLAN

PROPOSED GROUND FLOOR PLAN

4792

mm

W.C.

W.C.

LOUNGE

KITCHEN

W.C.

KITCHEN

LOUNGE

W.C.

KITCHEN

HALL

3295mm

3000mm

BEDROOM

LANDING

BATHROOM

3295mm

BEDROOM

LANDING

BATHROOM

3295mm

BEDROOM

LANDING

BATHROOM

3295mm

BEDROOM

LANDING

BATHROOM

3295mm

washer

Dryer

OvenFridge

Dishwasher

Hob

washer

Dryer

OvenFridge

Dishwasher

Hob

washer

Dryer

OvenFridge

Dishwasher

Hob

washer

Dryer

OvenFridge

Dishwasher

Hob

washer

Dryer

OvenFridge

Dishwasher

Hob

1000mm 500mm1100mm500mm 2520mm 500mm 1600mm 500mm

1100mm500mm 2520mm 500mm 1600mm 500mm

1100mm500mm 2520mm

500mm1600mm 500mm

1100mm500mm 2520mm

500mm1600mm 500mm

1100mm500mm 2520mm 500mm

900mm

6144

mm

2000

mm

1300

mm

4197

mm

3000mm

3616

mm

4094mm

3322

mm

BEDROOM BEDROOMBEDROOM BEDROOMBEDROOM BEDROOMBEDROOM BEDROOM

Wardrobe

Wardrobe

Wardrobe

Wardrobe

Wardrobe

Wardrobe

Wardrobe

Wardrobe

Wardrobe

Wardrobe

1000mm1946mm 2074mm1100mm

1574mm 1946mm 2074mm1100mm

1600mm 1946mm 2074mm1100mm

1526mm 1946mm 2174mm1100mm

1500mm 1946mm

6420mm

3857

mm

4862

mm

4095mm

2174mm 1100mm 900mm

9444

mm

1106

mm

740m

m22

07m

m

HALLHALL HALL

955mm 2000mm 2013mm 1020mm

594mm 575mm

820mm 2000mm 1710mm 1020mm

594mm 575mm

820mm 2000mm 1710mm 1020mm

594mm 575mm

820mm 2000mm 1691mm 1040mm

594mm 575mm

806mm 2000mm 1705mm 1040mm

1032mm

1184mm 2000mm 1337mm 1400mm

662mm 575mm

746mm 2000mm 1334mm 1402mm

662mm 575mm

746mm 2000mm 1337mm 1400mm

662mm 575mm

746mm 2000mm 1337mm 1400mm

662mm 575mm

806mm 2000mm 1525mm 1400mm 852mm

ST PAUL'S STREET

17

Plot 1

Plot 3

Plot 4

Turning Area

Plot 2

EXISTING MAIN SEWERThe existing main sewer 225mm dia salt glazedpipes run 900mm from the existing boundary wallat a depth of 2,2m.The building is required to be set back 3m from thesewer to comply with the requirements of UnitedUtilities.

NOTE

Plot 5

SCALE 1:200

Surface water attenuation tank

for drainage controled discharge

into sewer

Bin StoreNoteThe boundaries to each property are have a brickboundary walls 1m in height for viability. No hedgeplanting shall be permitted over 1m high.

NoteThe existing stone boundary wall to the front of theproperty is to be lowered to a height of 1.2m toprovide an open aspect over the field.

NoteA condition will be endorsed on these properties,that the owners will remove there bins from the binstore and placed outside at the rear of the turningspace for emptying on collection days by thecouncil.

3670mm

3650mm

3902mm

3905mm

13750mm

15172mm

13998mm

Care Home

ST PAUL'S STREET

Club

Residential

ST A

NN'S SQ

Beech Grove

ST P

AUL'S

TERR

Ordnance Survey (c) Crown Copyright 2017. All rights reserved. Licence number 100022432

51804mm

20575mm

This drawing is provided for planning & Building Regulations consent only.The contractor must check all dimensions on site before works are commenced. Thecontarctor must comply with all requirements of the Health & Safety Regulations.

DO NOT SCALE THIS DRAWINGÉ È

Scale Date

Drawing No. Revision

APBConsultant Building Surveyors

1 Maple GroveRamsbottom BL0 0ANTelephone 01706 826300Mobile 07976404449

Agent

Drawing

Project

Location

Client

1:100 & 1:500 1:200 21st September 2017

DWG/01 B 7th November 2017

Hambledon View Developments Ltd

Back St Paul's StreetClitheroe

Housing Development

Planning Consent