Page 1: South East Elevation Section AA Section BB · 2020. 7. 14. · South East Elevation Section AA Party Wall - assess existing wall and insert lead flashing and if appropriate associated

South West ElevationPLEASE NOTE: Measured survey was carried out by client.Floor level and ground level relationship to be checkedon site with levels adjusted accordingly and all agreedwith client and LABC on site. A threshold drainagechannel will be required where the internal floor level isthe same as the external levels.

A

A

PLEASE NOTE: Check all dimensions on site.

2350

20001800

2200

3000

2350

B

B

North West Elevation

Approximate outline ofneighbouring property

Floor Level

Floor Level

Floor Level

Floor Level

Kitchen

South East ElevationSection AA

Party Wall - assess existing wall andinsert lead flashing and ifappropriate associated cavitytrays. Make good section of wallabove roof. Finish to clientsspecification.

Roof - min. fall of Firestone EDPMflat roof is 1:80. Roof drawn at 1:50falls to hidden gutter detail toperimeter of proposed roof.Installation and details all tomanufacturers latest specificationand installation instructions.

Roof light - Exact location to beagreed with client. Upstand detail,installation instructions and falls allto manufacturers latest details andinstallation instructions.

Internal Wall to Boundary - Build upstructural stud partition to supportroof timbers over. The exact designand details of the wall andassociated reinforced floor slab orfoundation all to be detailed by theStructural Engineer. This wallconstruction could be concreteblock or structural timber stud wallas drawn.

Party Wall - A small section of thiswall forms the garden boundarywith the neighbouring property.New cavity wall construction withsmall amount of insulationthroughout will improve comfortlevels in the garden store. Exactdesign and location of theboundary wall to be confirmed withneighbours and Structural Engineerconsulted regarding foundationdesign if necessary.

Lead flashing's and Cavity Trays tobe installed to all roof abutmentswith weep vents. All installed tomanufacturers latest detaileddrawings and installationinstructions.

Parapet Walls - Create parapetwalls to perimeter of garden storeand take Firestone EDPM roof finishand marine plywood substrate overthe head of the cavity wall finshhead of wall with a Marley Alutecpowder coated aluminium coping.All installed in accordance withmanufacturers latest detaileddrawings, instructions andspecification details.

Ground level of the neighbouringproperty to be confirmed on site.Min. 150mm below DPC.

Garden/BikeStorage

South East ElevationSection BB

Outline of previousextension

Floor Level Floor Level

ALL DRAWINGS SUBJECT TO BUILDING REGULATIONS APPROVALTO BE READ IN CONJUNCTION WITH STRUCTURAL ENGINEER'SDRAWINGS AND DETAILED CALCULATIONS.

- - -

- - -

- - -

- - -

- - -

All information remains the property of the designer and may not beused for any purpose whatsoever, or reproduced through any mediumwithout the written permission of the designer. No responsibility isaccepted for unauthorised use. Do not scale off drawings, work fromf i g u r e d d i m e n s i o n s o n l y a n d a l w a y s v e r i f y o n s i t e .

DRAWING NO. :

43 The Mount | Papcastle | Cockermouth | Cumbria | CA13 [email protected] | www.wkdesignarchitects.co.ukCarolyn Williamson 07773 329572 | Paul Kitchin 07968 094847

SCALE :DRAWN BY :DRAWING NO. :

Proposed Elevations and Section A-A and B-B

Alterations and Extensions to Longlands, Whinney HillCleator Moorfor Mr and Mrs Christie

19.39.06

PK1:100@A1

MAY 2020Pr

opos

ed 3

D M

odel

Ima

ges