RELATIONSHIP-OBJECTIVE ANALYSIS
Getting Full Value From Earned Value With a Value-Added Way of Looking at
Performance Measurement
Presented at the 14th Annual International Integrated Program Management Conference
Tysons Corner Sheraton Premiere Hotel
November 19, 2002
Presented By Will Gran
Windmill International, Inc.
Nashua, New Hampshire 03060-5830
(603) 888-5502
2
Value-Added From Earned Value • Review some basics• Traditional analyses
– Line graph presentation– EAC formula
• Relationship-Objective Analysis– Variances
– Efficiencies
– Resource use rates
– Estimates at completion
• Some closing thoughts . . .
3
When I Say . . . I Mean . . . Planned Value BCWSCompleted Value BCWPResources Used ACWPRemaining Planned Value BCWRBaseline Total Value BACResource Value Variance CVTime Value Variance SVResource Use Efficiency Index CPITime Value Efficiency Index SPIContract At Cost TCContract At Price TPContract Liability CP
4
EVMS 32 Criteria
• Industry Standard EIA 748, paragraph 2.4.f“Develop revised estimates of cost at completion based
on performance to date, commitment values for material, and estimates of future conditions. Compare this information with the performance measurement baseline to identify variances at completion important to company management and any applicable customer reporting requirements including statements of funding requirements.”
5
Performance Analysis Process• Objective analysis from the data:
– Status performance to time now– Look for performance trends– Compare tends with a baseline plan– Project performance trends into the future– Relate projected trends to some meaningful objective
• Subjective analysis from information:– Investigate root causes of variances– Identify future influencing factors and risk– Adjust projected trends– Assess resource requirements– Compare with contract parameters
6
Traditional Performance Analysis
The Line GraphX-Axis: Passage of time
Years, quarters, months, weeks, days, etc.
Y-Axis: Measure of ResourcesDollars, items, lengths, volumes, etc.
7
The Line Graph
8
Line Graph Charts
The presentation is limiting . . .
– Depicts absolute values versus a time scale
– That focus on performance history
– Difficult to identify trends
– Difficult to compare trends to a baseline plan
– Difficult to develop credible cost projections to completion
9
Estimate At Completion FormulaEAC = Actuals + PF X Remaining Planned Value
– Assumes Performance Factor will be a constant
– And 1 unit of Planned Value will convert to 1+/- unit of Actual
The Estimate At Completion Formula
– Provides a point estimate
– Is a limited predictive metric
– That inherently underestimates overruns
– And inherently underestimates underruns
10
The Traditional Analyses
Line Graph Charts
and the
Estimate At Completion Formula
Provide partial value from Earned Value
11
Why The Difference In EACs?
12
A Different Look At Performance
Relationship-Objective Analysis
X-Axis: Value of work completed
Y-Axis: Progress toward an (Objective)
Percent Complete = Work Completed Baseline Total Value X 100
Percent Of (Objective) = Resources Value Value Of (Objective) X 100
13
Relationship-Objective GraphAn X - Y Scatter Diagram
14
An (Objective) May Be• Baseline Total Value • Estimate At Completion• Contract At Cost• Contract At Price• Contract Liability
• Or any general (Objective) that is a specific resource value
15
Variance As Percent Line Graph
16
Variances As % Of Baseline Plan
• Deviation from baseline time plan
• Deviation from baseline resource plan
Reduces volatility of variance trends in early periods of the project.
Time Variance = Completed Value - Planned Value Baseline Total Value X 100
Resource Variance = Completed Value - Resources Used Baseline Total Value X 100
17
Variances As % Of Baseline PlanAn X - Y Scatter Diagram
18
Performance Efficiency Since Start
• Value of work completed with resources used
• History of past performance efficiency
• Efficient > 100%• Inefficient < 100%
Resource Use Efficiency Index Since Start = Completed ValueResources Used X 100
Time Value Efficiency Index Since Start = Completed ValuePlanned Value X 100
19
Resource Use Efficiency Since StartAn X - Y Scatter Diagram
20
Performance Efficiency To Finish
• Ability to accomplish work within (Objective)
• Future performance required
Efficiency Index To Meet (Objective) = Remaining Planned Value(Objective) Resources Remaining X 100
Efficiency Index To Meet (Objective) = Baseline Total Value - Completed Value(Objective) - Resources Used X 100
21
Resource Use Efficiency To Finish
22
Rate Of Using Resources
• History of a “resource burn rate”
Resource Use as % Of (Objective) = Resources Used (Objective) X 100
Planned Value as % Of (Objective) = Planned Value (Objective) X 100
Completed Value as % Of (Objective) = Completed Value (Objective) X 100
23
Rate Of Using Resources
24
EAC = Actuals + PF X Remaining Planned Value
– Assumes Performance Factor will be a constant
– And 1 unit of Planned Value will convert to 1+/- unit of Actual
The Estimate At Completion Formula
– Provides a point estimate
– Is a limited predictive metric
– That inherently underestimates overruns
– And inherently underestimates underruns
Estimate At Completion (EAC)
25
Performance FactorsShould be related to performance
Running Average ~ Resource Use Efficiency Index (Period of Time)
Product ~ Resource Use Efficiency Index X Time Value Efficiency Index
Weighted ~ 0.8 Resource Use Efficiency Index + 0.2 Time Value Efficiency Index
Time Value Kicker ~ Resource Use Efficiency Index + 0.2 Time Value Efficiency Index
Cumulative ~ Resource Use Efficiency Index
26
Estimate At Completion
27
Trend Line Projection Analysis
• Identify performance trend
• Select set of data to project trend
• Determine “best fit” line– Y-Axis intercept– Slope of “best fit” line
• Extrapolate to 100% complete
Projects performance trend to end of effort
28
Resource Use Trend Projection
29
EAC Trend Projection
30
Best Case - Worse Case - Most Likely
31
Thoughts While Showering . . .
• Focus on the BIG picture first, then dig deeper
• Volatility indicates poor baseline plan, poor discipline, or both
• Watch for front loading due to optimistic planning
• Significant change in scope creates a new baseline
• Don’t be fooled by the early “resource variance hump”
• Time variances are associated with Work-In-Progress
• Time variances disappear when work is completed
• Resource variances accumulate when work is completed
• Time variances lead resource variances
• Look for long term trends and assess impacts
32
Thoughts While Shaving . . .
• An Index produces a ratio• EAC formula produces a point estimate• EAC as percent of an (Objective) produces a rate of
change• Trends usually appear before 20% Complete
• Relationship-Objective Analysis extrapolates rate of change trend to completion . . .
. . . And gives you Full Value from Earned Value
33
Thoughts While Sitting . . .
• The Performance Factor is not constant as the Estimate At Completion formula assumes
• The trend of the Performance factor is the key determining parameter for the most realistic Estimate At Completion
• Understand which Performance factor should be the best predictor and why
34
Agathe Christie Says . . .
“Getting Full Value from Earned Value with Relationship-Objective Analysis is like a good
detective story.
The main characters are introduced, the plot is established, and the clues to Who Dunit
emerge in the first 20% of the story.”