ADB Loan 8271-CAM (SCF) / 3007-CAM (SF) ADB Grant 0350-CAM (SCF)
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM
QUARTERLY PROGRESS REPORT Q1 2016
MEF/PMO 7/19/2016
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Q1 2016 QPR
i
TABLE OF CONTENTS
A. INTRODUCTION ............................................................................................................................... 1
B. BASIC DATA ..................................................................................................................................... 2
C. PROGRAM PURPOSE AND IMPACT ................................................................................................. 4
D. SUMMARY OF PROJECT STATUS ..................................................................................................... 6
E. UTILIZATION OF FUNDS .................................................................................................................. 7
F. SUMMARY OF PHYSICAL IMPLEMENTATION PROGRESS ................................................................ 8
G. PROGRESS AND ACHIEVEMENTS DURING Q1 2016 ........................................................................ 8
G.1 Output 1: Conducive Legal and Regulatory Environment....................................................... 8
G.2 Output 2: Agricultural Land-Use Zoning Improved ................................................................. 9
G.3 Output 3: Climate Resilient Rice Value Chain Infrastructure developed ................................ 9
G.4 Output 4: Enhanced rice value chain support services ......................................................... 10
G.5 Output 5: Feasibility Study, Design and Pilot Testing of WICI .............................................. 11
G.6 Output 6: Efficient Program management and Implementation ......................................... 11
H. GENDER ACTION PLAN .................................................................................................................. 12
I. ENVIRONMENT AND CLIMATE CHANGE ....................................................................................... 12
J. RESETTLEMENT ............................................................................................................................. 12
K. ASSESSMENTS OF RISKS, ASSUMPTIONS AND COMPLAINCE WITH CONVENANTS ...................... 12
K.1 Assessment of Risks and Assumptions.................................................................................. 12
K.2 Compliance with Covenants ................................................................................................. 13
K.3 Compliance conditions for ADB Program Loan - 3006 (CAM) .............................................. 13
L. PROGRAM ISSUES AND REMEDIAL ACTION .................................................................................. 14
Annex 1 Monitoring Frameworks
Annex 2 Financial Summaries
Annex 3 Summary of Priority Sub-Projects
Annex 4 Gender Action Plan
Annex 5 PIC Activities
Annex 6 Policy Compliance Matrix
Annex 7 Agreed Action Plan
Annex 8 Risk Management Matrix
Annex 9 Compliance with Loan and Grant Covenants
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Q1 2016 QPR
ii
ACRONYMS AND ABBREVIATIONS
ADB Asian Development Bank
AEA Agro-ecosystems Analysis
AFD Agence Française de Développement
AFD-SCCRP AFD Support to the Commercialization of Cambodian Rice Program
CARDI Cambodian Agricultural Research and Development Institute
CARM ADB Cambodian Resident Mission
CCCA Cambodia Climate Change Alliance
CEFP Committee for Economic and Financial Policies
CISIS Cambodia Information System on Irrigation Schemes
CLUP Commune Land-use Planning
CS Construction Supervision
DAE Department of Agricultural Extension
DAEng Department of Agricultural Engineering
DD Detailed Design
DMF Design and Monitoring Framework
EARF Environmental Assessment Review Framework
EIA Environmental Impact Assessment
EMP Environment Management Plan
EoI Expression of Interest
FAO Food and Agriculture Organization (of the United Nations)
FS Feasibility Study
FWUCs Farmer Water User Community
GAFSP Global Agriculture and Food Security Program
GAP Gender Action Plan
GDA General Directorate of Agriculture (of MAFF)
GIS Geographic Information System
IEE Impact Environment Examination
ISS Implementation Support Specialist
LUP Land Use Planning
M&E Monitoring and Evaluation
MAFF Ministry of Agriculture, Forestry and Fisheries
MEF Ministry of Economy and Finance
MIH Ministry of Industry and Handicrafts (formerly under MIME)
MLMUPC Ministry of Land Management, Urban Planning and Construction
MOWRAM Ministry of Water Resources and Meteorology
NIO National Implementation Office
O&M Operation and Maintenance
PDA Provincial Department of Agriculture
PDWRAM Provincial Department of Water and Resources and Meteorology
PIC Project Implementation Consultants
PIO Provincial Implementation Offices
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Q1 2016 QPR
iii
PMO Project Management Office
PPCR Pilot Program for Climate Resilience
PPMS Program Performance Monitoring System
PPP Public-Private Partnership
PPTA Preparatory Project Technical Assistance
QPR Quarterly Progress Report
RGC Royal Government of Cambodia
RSPG Rice Seed Producer Group
SCF Strategic Climate Fund
SDP Sector Development Program
SIP Sub-project Identification Proposal
SNEC Supreme National Economic Council
SPCR Strategic Program for Climate Resilience
TA Technical Assistance
TOR Terms of Reference
UNFCC United Nations Framework Convention on Climate Change
WICI Weather-indexed Crop Insurance
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Q1 2016 QPR
1
A. INTRODUCTION
1. The Climate Resilient Rice Commercialisation Sector Development Program (Rice-
SDP), which commenced in November 2013, supports the implementation of the ‘Policy on
the Promotion of Paddy production and Rice Export’ of the Royal Government of Cambodia
(RGC). It is designed to help transform the predominantly subsistence rice sector into a
commercially oriented one by improving household and national food security and expand rice
export through (i) removing the legal and regulatory constraints inhibiting rice
commercialization; (ii) improving productivity of paddy crops and consistency in quality of
milled rice; (iii) enhancing rice value chain support services; and (iv) addressing risks of
climate change through mitigation and adaptation.
2. The Quarterly Progress Report (QPR) for Quarter 1 of 2016 provides a description of
the progress that has been achieved during that period. The PPMS that has been developed
by the PIC team will be used as the basis for the QPRs commencing in Q2, in order to allow
more time for training of the PIO and NIO teams in the collection of the data for each indicator
and the establishment of the database for each office. The QPR also includes as summary of
the financial progress although the rates of disbursement are still very low due to the long
delays in the commencement of many activities. It is anticipated that commencing in Q2 the
rates of disbursement will improve.
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Q1 2016 QPR
2
B. BASIC DATA
ADB Loan/Grant Numbers
ADF Loan 3006 - CAM; ADF Loan 3007 - CAM; SCF Loan 8271 - CAM; Grant SCF 0350 - CAM; GAFSP Grant 0349 - CAM.
Program Title Climate Resilient Rice Commercialization Sector Development Program (Rice SDP)
Borrower Royal Government of Cambodia
Executing Agency Ministry of Economics and Finance (MEF)
Implementing Agencies
Ministry of Agriculture, Forestry and Fisheries (MAFF) Ministry of Water Resources and Meteorology (MOWRAM) Ministry of Land Management, Urban Planning and Construction (MLMUPC) Provincial Governments (Battambang, Kampong Thom and Prey Veng)
Program Steering Committee
Committee for Economic and Financial Policies (CEFP)
Total Project Cost (USD million)
87.41 (excluding taxes and duties of USD 5 million)
Program Financing (USD million)
ADB Loans
ADF 3006 - CAM: 24.00 ADF 3007 - CAM: 31.00 SCF 8271 - CAM: 5.00 ADB Grants
SCF 0350 - CAM: 4.50 GAFSP 0349 - CAM: 14.60
Date of Loan/Grant Approval by ADB
27th June 2013 for all Loans and Grants
Date of Signing of Loan/Grant Agreements
26th August 2013 for all Loans and Grants
Date of Effectiveness of ADB Loan/Grant
13th November 2013 for all Loans and Grants
Closing Date of ADB Loan/Grant
30th June 2017 for ADB Loan 3006 - CAM 31st March 2020 for other ADB Loan and Grants and GAFSP Grant
Dates of Last ADB Review Mission
10 - 15 February 2016
Program Impact Increased net incomes of stakeholders along the rice value chain.
Program Outcome Enhanced production of quality rice in Cambodia while preserving the natural resource base.
Components
1. Conducive legal framework and regulatory environment established to facilitate climate-resilient commercialization:
- Promoting production and distribution of improved quality seed. - Strengthening agricultural land management. - Strengthening farmer’s organisations and promoting contract farming; - Facilitating the domestic trading and export of milled rice.
2. Agricultural land-use zoning improved:
- Establishing land-use zones. - Updating rice ecosystems and soil classification maps for identification of higher
yielding rice growing areas. - Incorporating agro-ecosystems analysis into commune land-use planning; - Developing the capacity of MLMUPC at national and sub-national levels to
undertake joint work in relation to agricultural land-use planning. 3. Climate resilient rice value chain infrastructure developed
- Rehabilitation and climate proofing of irrigation systems. - Construction of paddy drying and storage facilities.
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Q1 2016 QPR
3
- Construction of seed cleaning, drying, grading and storage facilities. 4. Rice value chain support services enhanced to improve quality of Cambodian rice
- Improving the availability and quality of commercial rice seed; - Upgrading technical extension materials to guide production in the four main
rice crops. - Capacity building (technical and financial) of mill managers and operators; - Facilitating access to credit by farmers, traders and millers.
5. Weather Indexed Crop Insurance (WICI) piloted
- Undertaking a detailed Feasibility Study (FS) to determine the appropriateness of a WICI scheme.
- Designing the operational parameters, product penetration plan and institutional arrangement.
- Piloting the scheme in selected areas in three target provinces. 6. Efficient program management and implementation
- Effective project management; - Capacity building of the Project Management Officer (PMO) and each national
Implementation Offices (NIOs) and the Provincial Implementation Offices (PIOs).
- Coordination between policy development and investment activities.
Program Area
The Project covers three provinces: Battambang (BTB), Kampong Thom (KPT) and Prey Veng (PRV). A number of sub-projects will be carried out in each target province for (i) rehabilitation of existing irrigation, drainage and flood control systems; (ii) paddy drying and storage facilities to be operated by private sector under Public Private Partnerships (PPPs); and (iii) rice seed drying and storage facilities to be operated by private sector under PPP arrangements.
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Q1 2016 QPR
4
C. PROGRAM PURPOSE AND IMPACT
4. The Climate Resilient Rice Commercialization Sector Development Program (Rice-
SDP) comprises a policy-based program loan together with other loans and grants from ADB
sources. The Rice=SDP impact will be increased net incomes of stakeholders along the rice
value chain. The outcome is enhanced production of quality rice in Cambodia while preserving
the natural resource base.
5. The Rice-SDP will address key high priority and strategic measures stated in the Rice
Policy to improve national food security and expand rice export through (i) removing legal and
regulatory constraints inhibiting rice commercialization; (ii) improving productivity of paddy
crops and consistency in quality of milled rice; (iii) enhancing rice value chain support services;
and (iv) addressing risks of climate change through mitigation and adaptation. The Rice-SDP
has the following six outputs:
Output 1 - A Conducive Legal and Regulatory Environment established to facilitate
Climate-Resilient Rice Commercialization
This output focuses on legal and regulatory reforms that (i) promote production and
distribution of improved quality seed; (ii) strengthen agricultural land management; (iii)
strengthen farmers’ organizations and promote contract farming; and (iv) facilitate the
domestic trading and export of milled rice.
Output 2 - Agricultural Land-use Zoning improved
This output comprises: (i) establishing land-use zones; (ii) updating rice ecosystems
and soil classification maps for identification of higher yielding rice growing areas; (iii)
incorporating agro-ecosystem analyses into commune land-use planning, and (iv)
developing the capacity of Ministry of Agriculture, Forestry and Fisheries (MAFF) and
Ministry of Land Management, Urban Planning and Construction (MLMUPC) at the
national and sub-national levels to undertake joint work in relation to agricultural land-
use planning.
Output 3 - Climate Resilient Rice Value Chain Infrastructure developed
This output comprises high priority investments in three major rice-producing provinces
– Battambang(BTB), Kampong Thom (KPT), and Prey Veng (PVG). The investments
include: (i) rehabilitation and climate proofing of irrigation systems; (ii) construction of
paddy drying and storage facilities; and (iii) construction of seed cleaning, drying,
grading and storage facilities. The investments have been identified and prioritized
based on provincial development priorities.
Output 4 - Rice Value Chain Support Services Enhanced to Improve Quality of
Cambodian Rice
This output comprises: (i) improving the availability and quality of commercial rice
seed; (ii) upgrading technical extension material to guide production in the four main
rice crops; (iii) capacity building (technical and financial) of mill managers and
operators; and (iv) facilitating access to credit by farmers, traders, and millers.
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Q1 2016 QPR
5
Output 5 - Weather-indexed Crop Insurance Piloted
This output comprises: (i) undertaking a detailed feasibility study to determine the
appropriateness of a weather-indexed crop insurance scheme; (ii) designing the
operational parameters, product penetration plan, and institutional arrangements; and
(iii) piloting the scheme in selected areas in three program provinces.
Output 6 - Efficient Program Management and Implementation
This output comprises: (i) effective program management; (ii) capacity building of the
Program Management Office (PMO) and each National Implementation Office (NIO)
and Provincial Implementation Office (PIO); and (iii) coordination between policy
development and investment activities.
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Q1 2016 QPR
6
D. SUMMARY OF PROJECT STATUS
Status of project scope/implementation arrangements compared with those in the report and RRP, and whether major changes have occurred or will need to be made:
The Program has made slow progress so far due to a number of factors concerning the Project Implementation Consultant (PIC) team and also the limited capacity of the IAs and
their relative unfamiliarity with ADB project procedures. The scope and implementation arrangements remain in line with those of the RRP to date.
Assessment of the likelihood that the Project purpose will be met in part or in full, and whether remedial measures are required based on the current project scope and
implementation arrangements:
It is too early to make any definitive judgement on this. The Program has made very limited progress during the first year but the achievement of the compliance conditions for the
Program loan fund release are reasonably well on track. With the restructuring of the PIC team and the mobilisation of key team members there can now be much more consistent
and skilled technical support provided to the IAs. The production of the PPMS and the AWPB for 2016 these will provide a guide for the implementation during 2016 and a better
means of tracking performance.
An assessment of changes to the key assumptions and risks that affect attainment of the development objectives:
Of the risks identified in the RRP the most challenging issue concerns “the inherently complex nature of sector development program modality and limited technical skills and resources
to implement legal and regulatory reforms”. PIC Agricultural Policy Specialists are assisting the government in implementing legal and regulatory reforms for compliance with the
release of the Second Tranche in Q2 2016. The current situation is summarised in Annex 5.
Other program developments, including monitoring and reporting on environmental and social requirements that might adversely affect the pro's viability or
accomplishment of immediate objectives:
At this early stage, no significant factors have emerged which might adversely affect the project’s long-term viability. The accomplishment of immediate objectives is partly
constrained by the issues that are described in Section J.
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Q1 QPR 2016
7
E. UTILIZATION OF FUNDS
6. The Climate Resilient Rice Commercialization Sector Development Program (Rice-
SDP) is funded through loans/grants from ADB with a total amount of USD 63.3 million,
together with a Program loan amounting to USD 24 million. The breakdown is as follows:
ADB Program Loan No. 3006 - CAM USD 24.0 million
ADB Loan No. 3007 - CAM USD 31.0 million
Global Agriculture & Food Security program (GAFSP) Grant No. - 0349 USD 14.6 million
Strategic Climate Fund (SCF) Loan No. 8271 - CAM USD 5.0 million
SCF Grant No. 0350 - CAM USD 4.5 million
Royal Government of Cambodia USD 8.3 million
7. The cumulative disbursement (for investment and recurrent costs) for each funding
source is as follows:
Table 1
Summary of Cumulative Disbursement by EA/IAs and Funding Source
(USD)
8. The overall cumulative disbursement, for investment and recurrent (implementation
and supervision costs), at the end of Q1 2016 was USD 1,256,091 (69 percent) and 564,038
(31 percent) respectively and the overall disbursement rate was eight percent.1 The total
disbursement during Q1 2016 amounted to USD 380,144 which represented a disbursement
rate of six percent against the AWPB for 2016.
1 Annex 2 contains Summary Tables of Expenditure and Disbursement Progress.
Overall
Budget
Cumulative
Disbursement
to date
Budget
Balance
%
Disbursement
rate
EA/IA
MEF/PMO 11,424,300 1,161,875 10,262,425 10%
MAFF/NIO 23,751,900 178,437 23,573,463 1%
MOWRAM/NIO 17,957,200 166,528 17,790,672 1%
MLMUPC/NIO 2,917,500 93,107 2,824,393 3%
BTB/PIO 2,144,800 76,793 2,068,007 4%
KPT/NIO 2,144,800 83,025 2,061,775 4%
PVG/NIO 2,144,800 60,366 2,084,434 3%
Total Budget 62,485,300 1,820,129 60,665,171 3%
Source of Funds
ADB Loan No. 3007 - CAM 30,073,600 940,388 29,133,212 3%
GAFSP Grant No. 0349 14,601,400 178,514 14,422,886 1%
SCF Grant No. 0350 -CAM 4,997,600 0 4,997,600 0%
SCF Loan No. 8271 - CAM 4,501,200 208,570 4,292,630 5%
RGC 8,311,500 492,657 7,818,843 6%
Total Budget 62,485,300 1,820,129 60,665,171 3%
Agency/
Category
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Q1 2016 QPR
8
F. SUMMARY OF PHYSICAL IMPLEMENTATION PROGRESS
9. During the quarter the Annual Work Plan and Budget (AWPB) for 2016 was finalised
and a draft was submitted to ADB/CARM for approval. The AWPB had been drafted during
Q4 2015 but the submission was delayed due to the unexpected departure of the Project
Implementation Consultant (PIC) Team Leader due to ill health. The replacement PIC Team
Leader was mobilised in mid-February was able to complete the compilation of the AWPB
document in consultation with the PMO, NIO and PIO teams.
10. There were a total of seven international consultants and nine national consultants
working during the quarter. The new team members mobilised during the quarter were the
Team Leader, PPP Specialist and the national Implementation Support Specialist (ISS) for
BTB.
11. ADB conducted a short Review Mission from 10th to 15th February which was led by
the Project Officer from ADB Manila. The Aide Memoire included an agreed action plan and
the current status of the action plan in shown in Annex 6. At the conclusion of the Mission it
was announced that the supervision of the RiceSDP would be transferred to ADB/Cambodian
Resident Mission (CARM) with effect from March 1st.
G. PROGRESS AND ACHIEVEMENTS DURING Q1 2016
12. The main accomplishments during Q1 can be summarised as follows:
G.1 Output 1: Conducive Legal and Regulatory Environment
13. The current status of the progress of the compliance with the covenants is summarised
as follows:
Promoting local seed production and distribution: The Cambodian National Seed
Policy, which had been drafted and was under review by MAFF/GDA, has been revised
and will be further reviewed in May when the PIC international Seed Specialist returns.
The 1st draft of the National Seed Standards has been completed and work has
commenced on the production of a revised 2nd draft. The 1st draft of the Prakas on
Procedures for Providing Quality Seed Certification has been completed and work has
commenced on the 2nd draft. The 1st draft of the General Introduction to the
Examination of Distinctiveness, Uniformity and Stability of New Varieties of Plants has
been completed and work has commenced on the 2nd draft. Similarly, the Guidelines
for the Conduct of Tests for Distinctiveness, Uniformity and Stability of Rice has been
completed.
Strengthening agricultural land management: In the case of the Law on
Management and Use of Agricultural Land the 1st draft was prepared and a regional
consultation was conducted although the draft remains lacking expert advice on
gender issues for the inclusion of the role of women in the draft law. The 1st draft of
the National Action Program to combat land degradation in Cambodia has been
prepared and this was submitted to the Council of Ministers for review but was returned
for more information to be included. An outline of the guideline for establishment of
agricultural land use zones has been prepared but there is not yet an approval of the
outline.
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Q1 2016 QPR
9
Improvement phytosanitary restrictions: The Law on Plant Protection and
Phytosanitary Measures has been drafted but there is a need for further working group
meetings to review the content.
G.2 Output 2: Agricultural Land-Use Zoning Improved
G.2.1 Output 2.1: Undertake Commune Agro-Ecological Analysis (CAEA)
14. The MAFF/NIO team have prepared a Concept Paper for the conduct of the CAEA in
the 90 pilot communes. Because of the introduction of a number of new tools in the guideline
for CAEA there will be Training of Trainers (ToT) courses conducted in each province for the
district agriculture staff to ensure that they fully understand these procedures. The Concept
Paper was reviewed by the PIC team and was endorsed to the PMO for them to submit to
ADB/CARM for approval. It is planned to commence the first ToT in BTB province early in Q2.
G.2.2 Output 2.2: Incorporation of the CAEAs into the Commune Land Use Plans (CLUPs)
15. Following the Review Mission in February the Ministry of Land Management, Urban
Planning and Construction (MLMUPC) NIO team, with the support of the PIC team, have
drafted the ToR for the hire of consultants to conduct the CLUPs in the 90 target communes.
During March the ToR was extensively reviewed several times and by the end of the quarter
was ready to be finalised for submission to ADB/CARM for their no objection. The completion
of the CLUPs is to be conducted over a three-year period and should commence in Q4 2016.
G.2.3 Output 2.3: Rice ecosystem Mapping
16. The MAFF/NIO team have prepared a concept paper outline the procedure for the
preparation of the rice eco-system maps. The objective will be to (i) update the agricultural soil
classification and database using existing data/information and conduct additional soil
sampling and analysis in order to produce updated soil classification maps; (ii) update existing
rice ecosystem map focusing on the three target provinces; and (iii) establish a database on
soil type, land use and site specific suitability for the agricultural development plan.
G.3 Output 3: Climate Resilient Rice Value Chain Infrastructure developed
G.3.1 Output 3.1: Recruitment of national consultants for irrigation sub-project
feasibility studies
17. There are a total of 19 irrigation sub-projects that were re-prioritised by the Ministry of
Water Resources and Meteorology (MOWRAM)/NIO with support from the PIC team. Based
upon the ToR for the Feasibility Studies, Detailed Design and Construction Supervision
(FSDDCS) the consultant team was selected and mobilised in February 2016. They have
commenced work on the two irrigation sub-projects which were studied during the Project
Preparatory Technical Assistance (PPTA) namely Chhuck Khsak in KPT province and Prey
Sanhga in BTB province. The consultants will update the original FSs and revise all documents
as needed prior to submission by MOWRAM for no objection.
G.3.2 Output 3.2: Recruitment of national consultants for seed/paddy drying and
storage facilities
18. In the case of the FSDDCS for rice seed/paddy drying and storage there are 11 sub-
projects identified by the MAFF/NIO. The ToR for the FSDDCS consultants was prepared by
the MAFF/NIO with support from the PIC team and the announcement for Expressions of
Interest was made in March with a closing date in April.
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Q1 2016 QPR
10
G.3.3 Output 3.3: Works contract procurement for rehabilitation of identified irrigation
schemes
19. There has been no progress yet. When the revision of the two FSs for Chhuck Khsak
and Prey Sangha sub-projects has been completed and ADB no objection provided the
MWORAM/NIO will proceed with the budding advertisement for the civil works contract award.
G.3.4 Output 3.4: Works contract procurement for paddy drying and storage facilities
20. There has been no progress yet. It is envisaged that the works contract procurement
for the first facilities will not commence until Q2 2017.
G.3.5 Output 3.5: Works contract procurement for rice seed drying and storage
facilities
21. There has been no progress yet. It is envisaged that the works contract procurement
for the first facilities will not commence until Q2 2017.
G.3.6 Output 3.6: Contract services for implementation of sub-project associated
initiatives
22. In the case of the land levelling there was a consultative workshop organised in KPT
in March 2016 to discuss with local contractors, as well as PIO representatives from the PDAs
in each province, the strategy for proceeding with the land levelling. The workshop included
the conduct of demonstrations on land levelling organised by the MAFF Department of
Agricultural Engineering. The workshop concluded with the conduct of a meeting attended by
the RiceSDP PMO Director and Manager during which there were discussions of the bidding
procedure that could be applied for the award of works contracts for the land levelling to the
local contractors. The main issues that surfaced were (i) the lack of experience of the
contractors with formal bidding procedures; (ii) the lack of legal registration by local contractors
with the provincial authorities; (iii) the lack of equipment for performing the precision land
levelling; and (iv) the lack of knowledge on the techniques for performing the precision land
levelling. The PIC Team Leader was charged with the responsibility for the preparation of a
Concept Paper analysing the costs of doing land levelling based upon commercial practice
and also the financial benefits of land levelling.
G.3.7 Output 3.7: Procuring Public-Private Partnerships (PPPs) to operate paddy
drying and storage facilities
23. Following the mobilisation of the PIC PPP specialist an assessment has commenced
of the opportunity for the application of the PPP modality for paddy drying and storage
facilities. The assessment entails field visits to each target province to meet with stakeholders
in the rice post-harvest sector to determine their interest in this mode of support in relation to
the paddy/seed drying and storage sub-projects that were identified during the PPTA. The
results of this assessment will be available by the end of Q2 2016.
G.4 Output 4: Enhanced rice value chain support services
G.4.1 Output 4.1: Increased availability of quality rice seed
24. A preliminary rice seed action plan has been prepared by the MAFF/NIO team with the
support of the PIC team. This plan provides preliminary estimates of the volumes of foundation
and registered rice seed that will be required each year to satisfy the estimated demand for
certified seed within the irrigation sub-project sites areas. It also proposes an assessment of
the existing agriculture stations in each target province that can take responsibility for the
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Q1 2016 QPR
11
production of registered seed, and an assessment of the capacity of the Rice Seed Producer
Groups(RSPGs)/Agricultural Cooperatives (ACs) to produce the certified rice seed, using the
registered seed purchased from the agriculture stations, which will be sold to farmers. The
plan also includes an assessment of each RSPGs/ACs to identify the support that will be
required to increase their production capacity and the training support that will be delivered.
In order to prepare the staff of the District Office of Agriculture (DoA) there will be a Training
of Trainers (ToT) on Rice Seed Production Farmer Field Schools (FFSs) conducted
commencing in Q2 2016. It is estimated that an area of at least eight hectares will be required
for registered rice seed production on the agriculture station for the 2016 wet season crop.
G.4.2 Output 4.2: Expand and develop technical extension services
25. No progress has yet been made. This is an activity which is under the responsibility of
the PIOs. There is a need for further discussion between the MAFF/NIO and the PDAs to
identify the scope of these extension activities that will be implemented.
G.4.3 Output 4.3: Enhance business management capacities
26. No progress has been made yet. This activity will commence in 2017.
G.4.4 Output 4.4: Improved Access to and Reduced Cost of Financing
27. No progress has been made yet. This activity will commence in 2017.
G.5 Output 5: Feasibility Study, Design and Pilot Testing of Weather Indexed Crop
Insurance (WICI)
28. The ToR for the conduct of the Feasibility Study and the Pilot Testing of the WICI was
approved by ADB and the request for EoIs was advertised in February 2016. At the closing
date in March there has been only two submissions which was insufficient and there was no
request for extension of the deadline.
G.6 Output 6: Efficient Program management and Implementation
29. There were some minor changes to the composition of the NIO and PIO staffing and
there is not yet fully gender disaggregated data available for the project counterpart teams.
The PIC team provided continuing support during the quarter with the mobilisation of the
replacement Team Leader and PPP Specialist. The international M&E Specialist and Seed
Specialist also completed short term inputs during the quarter. The replacement national
Implementation Support Specialist for BTB province was mobilised.
30. During the quarter a decision was made to deploy the PIC team to their respective
NIOs so that they can work in daily contact with their counterparts. This was made by possible
by the establishment of dedicated office space and facilities by each of the NIOs. The PMO
completed the procurement of the office furniture for each NIO and the procurement of the
office furniture and equipment for the PIOs also commenced during the quarter.
31. The PIC team provided support for the development of PPMS guidelines and prepared
the ToR for the Baseline Survey both of which were submitted to the PMO for review and
endorsement to ADB.
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Q1 2016 QPR
12
H. GENDER ACTION PLAN
32. Gender considerations are cross-cutting throughout the Rice-SDP and the Program
will enhance access by women at all levels to decision making, resources and services.
Gender issues have also been incorporated into appropriate covenants of the Program Loans
and Grants. A comprehensive Gender Action Plan has been prepared and will be regularly
updated on a quarterly basis. 2
33. The PIC team includes two gender experts, one international and one national, who
will be mobilised in Q2 2016 to support the gender mainstreaming training program and the
assist in the incorporation of guidelines for gender consideration into al manuals that are
developed.
I. ENVIRONMENT AND CLIMATE CHANGE
34. Through the preliminary capacity needs assessment conducted in 2015, it was
identified that the staff of the PMO, NOIs and POIs have a limited knowledge of climate
change. This is in terms of technical, economic, social, political and policy issues and actions
needed on climate change vulnerability and adaptation. It includes the prediction of climate
change impacts and incorporating climate resilience engineering designs for the rehabilitation
of irrigation systems as well as Climate Smart Agriculture (CSA) technologies into rice seed
production programs and agricultural extension programs.
35. During Q1 plans were prepared for the conduct of initial awareness raising on
environmental issues for delivery to all NIO and PIO teams. The climate vulnerability
assessments for irrigation system and crop insurance produce that are weather-indexed will
be conducted though collecting historical data on climate information over the last ten years
and consultations with key stakeholders in the area of each sub-project in the three provinces.
Climate risk assessments will be conducted to identify the climate change adaptation options
applicable for the sub-project civil works to ensure that they incorporate proofing for climate
change
J. RESETTLEMENT
36. No progress has been made yet. There will be a need for a reassessment of the
resettlement needs of the two irrigation sub-projects that are being studied by the FSDDCS
consultants recruited by MOWRAM/NIO.
K. ASSESSMENTS OF RISKS, ASSUMPTIONS AND COMPLAINCE WITH
CONVENANTS
K.1 Assessment of Risks and Assumptions
37. A comprehensive assessment of risks and assumptions was undertaken from the
onset on project implementation. This has then been updated, during Q4 to ensure and assess
whether risk and assumptions are in line with the current status of implementation. A copy of
the updated risk matrix for the Rice-SDP project can be found in Annex 7.
2 Annex 3 provides the current Gender Action Plan.
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Q1 2016 QPR
13
K.2 Compliance with Covenants
38. The relevant loan agreements covering the Rice-SDP are as follows:
Loan Type Date
Loan Agreement (Special Operations) for Climate Resilient Rice Commercialization Sector Development Program (Loan 3006)
Agreements, Loan Agreement (Special Operations)
August 2013
Loan Agreement (Special Operations) for Climate Resilient Rice Commercialization Sector Development project (Loan 3007)
Agreements, Loan Agreement (Special Operations)
August 2013
Grant Agreement (GAFSP) for Climate Resilient Rice Commercialization Sector Development Project
Agreements, Grant Agreement August 2013
Loan Agreement (ADB Strategic Climate Fund) for Climate Resilient Rice Commercialization Sector Development Project
Agreements, Loan Agreement (Special Operations)
August 2013
Grant Agreement (ADB Strategic Climate Fund) for Climate Resilient Rice Commercialization Sector Development Project
Agreements, Grant Agreement August 2013
K.3 Compliance conditions for ADB Program Loan - 3006 (CAM)
39. As The Program Loan Covenants are established in the loan and grant agreements
with further reference to the Development Policy Letter (April 2013) and Appendix 4 Policy
Matrix of the RRP (June 2013).
40. The Loan Agreement for the Commercial Sector Development Program, ADF 3006
(August 2013) includes a specific agreement under Schedule 3 on the withdrawal of funds:
“4. No withdrawal shall be made from the Loan Account for the First Tranche unless
ADB is satisfied that the Borrower has met the policy actions for the release of the
tranche specified in Attachment 2 to this Schedule.
5. Notwithstanding any other provisions of this Loan Agreement and except as ADB
may otherwise agree, no withdrawals shall be made from the Loan Account for the
Second Tranche unless ADB is satisfied, after consultation with the Borrower, that (a)
sufficient progress has been achieved by the Borrower in the carrying out of the
Program; (b) the policy actions that were met for the release of the First Tranche
continue to be complied with by the Borrower; and (c) the Borrower has met the policy
actions for the release of the Second Tranche specified in Attachment 3 to this
Schedule.”
41. The PIC team have continued to provide support to the MAFF/NIO and the Technical
Working Groups to enable the achievement of the compliance conditions for the release of the
2nd tranche, which also require continued compliance by the Borrower for the actions under
this first tranche (Schedule 3, see paragraph 52 above). To date the work by the PIC has
established the status of each of the agreed policy actions. Most are currently not yet
compliant, although for most of these items the Government (MAFF) is in the process of
drafting the necessary legislation or establishing Technical Working Groups to consider these
issues. An update on the progress towards achieving compliance is shown in Appendix 5.
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Q1 QPR 2016
14
L. PROGRAM ISSUES AND REMEDIAL ACTION
42. A series of issues were identified during Q1 2016 which are summarised below, together with where appropriate remedial action which is
being applied or is required.
Issue/Problem Proposed Remedial Action(s)
Output 1: Conducive Legal and Regulatory Environment established
Issues and Constraints in Policy Development
Some further progress has been made with the policy conditions and documents by MAFF/NIO and PIC working through each of the Technical Working Groups. In the case of those relating to
seed there has been better progress achieved/. However, in the case of those relating to land management and plant protection there remains much work to be done and there is cause for concern
that the deadline may not be met. A concerted effort is required by all concerned wo ensure that these deadlines can be met in order to avoid having to request an extension of the date until later
in the year.
Output 2: Agricultural Land Use Zoning Improved
Selection of target communes. There is a need for a consensus from the sub-national
level on the selection of the target communes.
The selection process for the identification of the 90 target communes was led by the PIC team in
collaboration mainly with the MLMUPC and MAFF NIO teams. The criteria which had been used
focussed on the selection of districts related to the location of the identified sub-project sites and
included all other communes in those identified districts. There is a need for further validation of the
commune selection with the sub-national teams to ensure there is a consensus amongst all project
stakeholders.
Output 3: Climate Resilient Rice Value Chain Infrastructure developed
Conduct of land levelling within sub-project sites areas. There is a lack of experience
and expertise on land levelling.
Initial consultations that have been conducted with local contractors in each province have revealed
that there are very few of them that have any part experience of land levelling. Past projects have
established land levelling demonstrations in conjunction with MAFF/Dept. of Agricultural Engineering
but the land levelling activities have not been continued after these projects were completed. There
has previously been no engagement with local contractors to identify an approach to enable them to
become involved in land levelling and they do not have the equipment that is needed, specifically the
laser equipment, which has to be imported. There are also differences of opinion on the actual cost
of the land levelling with the figures adopted by MAFF being somewhat higher than those quoted by
local contractors who have acquired the necessary equipment and have done land levelling. Local
contractors lack formal registration and are ineligible to bid for contract awards under the RiceSDP.
Further consultations are needed with farmers to introduce the concept of land levelling and the need
for them to contribute to the cost, and for local contractors to be trained in the use of the equipment
required.
Development of PPP approaches that can be applied for paddy drying and storage.
The proposed PPP modality in the PAM may not result in interest from the private sector.
The establishment of paddy drying and storage facilities as standalone facilities may need further
consideration to verify that they wold be viable and would attract private sector investment. The
proposed management arrangements whereby they remain the property of the provincial
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Q1 2016 QPR
15
Issue/Problem Proposed Remedial Action(s)
governments also need to be re-evaluated. In the case of the seed drying and storage facilities these
would be best targeted at existing Rice Seed Producer Groups (RSPGs) that have sufficient capacity.
Output 4: Enhanced Rice Value Chain Support Services
Bidding for the FSDDCS contracts. There have been few Expressions of Interest (EoIs)
submitted for the opportunity to bid for the contracts.
The FSDDCS contract has been advertised as one package, this is despite proposals from the PIC
team that the package should be split into up to three packages for each stage of the work. Because
of difficulties that have emerged with the availability of land at some sites it may not be possible to
pursue all of the proposed facilities. It will be necessary to re-bid for the FSDDCS contract and this
can provide an opportunity to reconsider the packaging of the contract(s).
Output 5: Feasibility Study, Design and Pilot Testing of WICI
Bidding for the WICI Feasibility study and Pilot Testing. There have been few
Expressions of Interest submitted for the opportunity to bid for the contract.
This is a very technical area that requires specific expertise in crop insurance work in other countries,
given that it is almost completely new to Cambodia. Nevertheless, crop insurance provides a huge
opportunity to make investment by smallholders a much more attractive proposition since the money
that they invest will be protected in the event of abnormal climatic events. Since there were few EoIs
submitted
Output 6: Efficient Project Management and Implementation
Lack of financial within the PIO teams. Long delays have been experienced in the
submission of the financial reports by the PIOs.
The PIO teams do not include adequate financial skills and the counterpart that are working are not
full time. Although the PIOs have one Administrative Assistant they are unable to compile the
necessary financial reports and also have limited English language capability. There is an urgent need
for each PIO to recruit a Financial Assistant who can ensure that there is improved financial
management for the PIO and that financial reports are submitted in a timely manner.
Working locations of the PIC team. The PIC team are working at the SNEC office and
have infrequent contact with the NIO teams.
The PIC team have been working within the offices available to them at the SNEC office. This has
been partly because the NIOs had not established office facilities for their staff and consultants and
there was no office furniture or equipment available. Since these constraints have been overcome
and there are now well equipped office facilities available in each NIO it is essential that the PIC
team members are deployed to work in their respective NIOs so that they can have daily interaction
with the NIO teams.
Annex 1
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q1 2016
16
DESIGN AND MONITORING FRAMEWORK FOR OVERALL PROGRAM
Design Summary
Performance Targets and Indicators with Baselines
Data Sources and
Reporting
Mechanisms
Assumptions and Risks
IMPACT:
Increased net
incomes of
stakeholders along
the rice value chain
Average farming household incomes increased from
$400 in 2010 to $700 by 2020
Revenue of rice exporters increased from
$100 million in 2012 to $600 million in 2020
Net profit of rice exporters increased from
$30 million in 2012 to $180 million by 2020
National Institute of Statistics’ Yearbook
Ministry of Commerce annual trade statistics
Assumption Medium-term macro-economic
Stability.
Risks
Lack of political commitment in Rice-SDP
implementation.
Climate change impacts may undo the intended gains and reduce anticipated benefits.
OUTCOME:
Enhanced production
of quality rice in
Cambodia while
preserving the natural
resource base
Paddy production increased from 8.0 million tons in
2012 to 9.5 million tons by 2018
Milled rice exports increased from 200,000 tons in
2011 to 1.2 million tons in 2017
Wet paddy exports to Viet Nam and Thailand reduced to 0.2 million tons by 2018 (2011 baseline: 2.2 million tons per annum) a.
MAFF annual crop
production
statistics
Ministry of Commerce annual trade statistics
Risks
Institutional and implementation risks from lack of
technical skills and resources.
Improper natural resources management may exacerbate the impacts of climate change.
OUTPUTS:
1. Conducive legal
and regulatory
environment
established to facilitate climate- resilient rice commercialization
By 2015, (i) policy and regulatory framework for local seed production are in place, (ii) guidelines for establishing agricultural land use zones are completed, (iii) legislation on sustainable management and use of agricultural land are operational, (iv) regulatory systems for farmers’ organizations and contract farming are functional, and (v) milled rice standards and trade facilitation measures in place
Tranche compliance reports prepared by the executing agency
Assumption Political parties and beneficiaries are
cooperative in the reform process.
Risk
Policy coordination and enforcement
are not strong.
Annex 1
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q1 2016
17
DESIGN AND MONITORING FRAMEWORK FOR OVERALL PROGRAM
Design Summary
Performance Targets and Indicators with Baselines
Data Sources and
Reporting
Mechanisms
Assumptions and Risks
2. Agricultural land-use zoning improved
90 rice growing communes in target provinces
complete AEAs and incorporate into CLUPs by
2017.
90 groups of farmers consulted (with at least
40% female representation) during the
preparation of CLUPs by 2015.
Progress reports produced quarterly by the executing agency
Assumption MLMUPC can accommodate AEAs
as an input to CLUPs.
3. Climate- resilient
rice value chain
infrastructure
developed
23,000 hectares (ha) of command area served
by climate-resilient rehabilitated irrigation
structures by 2017 (40% unskilled laborers
employed in the rehabilitation are women; 50%
of construction subcommittee members are
women; two FWUCs established in each
irrigation scheme, with women occupying 30%
of the management positions).
Four seed drying and storage facilities constructed by 2017 with a combined storage capacity of 8,000 tons (30% unskilled laborers and 50% administrative staff are women).
Capacity for drying paddy in target provinces extended
by 2,000 tons per day and capacity for paddy storage in
target provinces extended by 40,000 tons by 2018.
Progress reports
produced quarterly
by the executing agency
Assumptions
Climate-resilient infrastructure is economically viable
and politically acceptable.
Efficient operation of control structures to deliver water to canals.
Private entities are interested and capable of managing facilities.
Risk
River basin studies do not take climate change impact into
Account.
Annex 1
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q1 2016
18
DESIGN AND MONITORING FRAMEWORK FOR OVERALL PROGRAM
Design Summary
Performance Targets and Indicators with Baselines
Data Sources and
Reporting
Mechanisms
Assumptions and Risks
4. Rice value
chain support services enhanced to improve quality of Cambodian rice
2,400 tons of fragrant rice seed produced per
annum in target provinces by 2018
70% of farmers (disaggregated by sex) in target provinces using commercial seed every 2 years by 2018 (2012 baseline: 10%)
30% of farmers (disaggregated by sex) have leveled their paddy fields by 2018 (2012 baseline: 5%); 50% of farmers in target provinces (disaggregated by sex) obtain technical advice through trained input suppliers by 2016 (2012 baseline: 10%)
10 rice millers in target provinces use independent financial management advisory services by 2016 (2012 baseline: 0)
Progress reports produced quarterly by the executing agency
Progress reports produced quarterly by the executing agency
Assumptions
Growers accept the higher price needed
to purchase quality
seed
Farmers have resources to part finance the land leveling
Risk
Drying and storage facilities are not
operated at full
capacity
5. WICI piloted
100,000 ha of rice producing areas covered by
WICI by 2017 (50% of the policy holders
are women, of which 10% are from
households headed by women)
(2012 baseline: 0)
15 local input suppliers, 3 local financial institutions, and 3 local marketing agencies participating in the pilot tests in three provinces by 2015 (2012 baseline: 0)
Feasibility study
report
Design of WICI and evaluation report
Quarterly reports by the insurance firm
Assumption
Feasibility study recommends design and piloting
Risk
Piloting WICI shows no feasibility in
Cambodia
Annex 1
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q1 2016
19
DESIGN AND MONITORING FRAMEWORK FOR OVERALL PROGRAM
Design Summary
Performance Targets and Indicators with Baselines
Data Sources and
Reporting
Mechanisms
Assumptions and Risks
6. Efficient program management and implementation
Rice-SDP performance monitoring system,
disaggregated by sex, designed and operational within 6 months of effectiveness. Baseline surveys completed within 12 months of loans and grants effectiveness and end-line impact evaluation undertaken 6 months
before Rice-SDP completion date
For PMO and PIOs, 30% of administrative
and technical positions are filled by women by
Q3 2013; progress of gender actions included as part of Rice-SDP progress reports. For PMO and PIOs, 30% of administrative
and technical positions are filled by women by
Q3 2013; progress of gender actions included as part of Rice-SDP progress reports
Progress reports produced quarterly by the executing agency. Base-line and end-line impact evaluation by the executing agency
Progress reports produced quarterly by the executing agency
Assumption
Qualified staff are appointed for
Implementation
Risks
Provincial capacity is insufficient
The availability of qualified staff is limited
ADB - Asian Development Bank; ADF -Asian Development Fund; AEA - Agro-Ecosystems Analysis; CLUP - Commune Land-use Plan; FWUC - Farmer Water User Community; GAFSP - Global Agriculture and Food Security Program; MAFF - Ministry of Agriculture Forestry and Fisheries; MLMUPC - Ministry of Land Management Urban Planning and Construction; NIO - National Implementation Office; PIC - Program Implementation Consultant; PIO - Provincial Implementation Office; PMO - Program Management Office; Rice-SDP - Climate Resilient Rice Commercialization Sector Development Program; SCF - Strategic Climate Fund; WICI - weather-indexed crop insurance.
a A separate survey on baseline and target indicator will be conducted during the second year of the program to validate information of informal paddy
trade across the border with Thailand and Viet Nam.
Annex 1
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q1 2016
20
DESIGN AND MONITORING FRAMEWORK FOR OVERALL PROGRAM
Activities with Milestones Inputs
1. Improvement of legal and regulatory environment
1.1. Establish policy working groups by Q4 2013
1.2. Produce compliance report for second tranche by Q2 2016 2. Improvement of agricultural land-use zoning
2.1. Undertake commune AEAs by Q4 2017
2.2. Incorporate the AEAs into CLUPs by Q4 2017
2.3. Develop three provincial rice ecosystem maps by Q4 2017 3. Development of rice value chain infrastructure
3.1. Recruit national consultants for subproject feasibility studies by Q3 2014
3.2. Rehabilitate identified irrigation schemes by Q4 2018
3.3. Establish paddy drying and storage facilities by Q4 2018
3.4. Establish seed drying and storage facilities by Q4 2018 3.5. Implement subproject-associated initiatives by Q4 2018 4. Enhancement of rice value chain support services
4.1. Increase availability of quality rice seed
4.1.1. Develop a national seed certification scheme by Q4 2015
4.1.2. Produce foundation and certified seed by Q4 2017
4.2. Expand and develop technical extension services
4.2.1. Revise six “technology information procedures” on rice production by Q4 2015
4.2.2. Develop extension services material by Q4 2015
4.3. Enhance business management capacities
4.3.1. Study the adoption of bulk handling by Q2 2015
4.3.2. Provide technical assistance to rice mill by Q4 2018 4.3.3. Organize study tours and training for millers by Q4 2016
4.4. Improve access to and reduce cost of finance
4.4.1. Develop capacities of financial institutions by Q4 2016 5. Feasibility study, design and pilot testing of WICI
5.1. Engage consultants for feasibility study by Q1 2014
5.2. Determine feasibility of WICI in Cambodia by Q2 2014
5.3. Upgrade automatic weather stations by Q4 2014
5.4. Pilot WICI in selected areas by Q2 2015 6. Project management and implementation
6.1. Appoint and mobilize PICs by Q1 2014
6.2. Design and operate Rice-SDP’s gender disaggregated program performance monitoring system by Q2 2014
1. ADF Policy Loan: $24.00 million
2. ADF Loan: $31.00 million
Item Amount
Civil Works 17.60 Associated Initiatives 0.53
Vehicles & Equipment 0.65
Consulting Services 3.75
Implementation Support 7.54
Interest Charges 0.93 3. GAFSP Grant: $14.60 million
Item Amount Civil Works 0.62 Equipment 7.17
Contract Services 3.28
Office Equipment 0.10 Consulting Services 1.11
Training and Studies 1.81
Implementation Support 0.51 4. ADB SCF Loan: $5.00 million
Item Amount
Civil Works 3.31
Associated Initiatives 1.10
Contract Services 0.59 5. ADB SCF Grant: $4.50 million
Item Amount
Civil Works 0.42
Crop Insurance 2.00
Consulting Services 2.08
6. Government: $8.33 million Item Amount
Staff Costs 1.46
Resettlement Costs 0.43
Land Purchase 0.88
Taxes and Duties 5.54
SCF Loan Service Charge 0.02
Annex 1
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q1 2016
21
MONITORING FRAMEWORK FOR GAFSP
GAFSP Results Area
Indicators in Cambodia’s GAFSP Rice-SDP Indicators
(with reference to the GAFSP M&E Plan)
1. Raising Agricultural Productivity
An increasingly productive and diversified agricultural system that is capable of assuring food security.
40,000 beneficiary farmers (20,000 are women farmers) and 400
farmer organizations are benefited by extension, technology transfer,
improved production trainings and sets of low-input and improved
technical packages.
- Six technical information procedures for lowland rice production
upgraded by 2017.
- 20,000 days of training to raise agricultural productivity provided to
extension agents, agro-dealers, farmers, community members etc.
(disaggregated by gender).
- 30 subproject contracts providing extension services executed between
Rice-SDP and participating provincial department of agriculture (PDAs)
by 2018, covering an estimated 30,000 households.
- An increment of 30,000 hectares of paddy land on which modern
production technology has been adopted by 2018.
- At least 30,000 households will adopt water saving technology by land
levelling promoted by Rice-SDP by 2018.
Pro-poor and pro-women
community groups, particularly of food-insecure households, who are empowered to actively develop their potentials, opportunities and minimize risks and represent their own interests in political and administrative environment.
Community projects are implemented using participatory
planning techniques.
- Paddy area with improved/rehabilitated irrigation and drainage services
will be 23,000 ha by 2018
- Number of water users provided with new/improved/rehabilitated
irrigation and drainage services (disaggregated by gender) estimated to
be 23,000 by 2018
- Number of operational water user associations estimated to be 23 by
2018 within the subproject areas.
Annex 1
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q1 2016
22
MONITORING FRAMEWORK FOR GAFSP
GAFSP Results Area
Indicators in Cambodia’s GAFSP Rice-SDP Indicators
(with reference to the GAFSP M&E Plan)
Farmers have secure tenure to their land.
Land titles for rural land use are provided to project beneficiaries, including indigenous communities.
- 90 communes will have completed commune land use plans (CLUPs)
based on the agro- ecosystem analyses performed in these communes
by 2017.b/
2. Linking Farmers to Markets
Reduce transfer and transaction costs.
Traditional value chain partnerships strengthened for four commodities in 10 provinces over 3 years.
- 30,000 farming households become members of production association
and water user community members (30% are women) by 2017
Other value addition. Distribution of post-harvest storage systems to project villages by end
of year 4.
- Volume of paddy under improved post-harvest management increased
by 30,000 tons (in terms of storage capacity) by 2018
- Paddy drying capacity increased by 2,000 tons per day by 2018 in
participating provinces
- Six public-private seed processing facilities (grading, dying and storage)
installed by 2018
- 50,000 client days of training on better post-harvest procedures
provided (50% of participants being women)
3. Reducing Risk and Vulnerability
Community self-reliance for food security and nutrition and health.
40,000 households (20,000 women-headed households) are trained in home gardening techniques by year 4.
- A weather-indexed crop insurance scheme introduced to improve
weather-related risks by 2017 (co-financed by PPCR)
- 100,000 ha of rice producing areas covered by a WICI scheme
directed towards vulnerable groups (co-financed by PPCR)
4. Improved Non-farm rural livelihoods
Annex 1
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q1 2016
23
MONITORING FRAMEWORK FOR GAFSP
GAFSP Results Area
Indicators in Cambodia’s GAFSP Rice-SDP Indicators
(with reference to the GAFSP M&E Plan)
Promoting non-farm rural
entrepreneurship. 4,000 self-help groups organized and functioning by end year 4. Basic administration training conducted within 6-months of self- help group formation. 1,000 micro-businesses (women headed) & 1,000 small-scale agro-processing developed and functioning at basic level by year 3 Community micro-projects are implemented by year 4. Set of vocational training packages are developed by end year 2. 4,000 (2,000 are women) are trained in new and/or additional vocational skills by year 4.
- Number of people trained:
- 10 rice millers trained through advisory services by 2016;
- 100,000 FWUC members trained in group management and irrigation
scheme operations and maintenance by 2018; 100 staff of financial
institutions in participating provinces receive training on the needs of
farmers wishing to diversify their livelihood sources by
- 2018: 1,000 farmers trained in requirements of financial institutions to
assist in gaining access to credit by 2018 (with 30% women participants)
Component 5: Technical assistance, institution building, capacity development
Policies, Plans and regulatory
framework of MAFF are fully established, maintained and coordinated.
MAFF have implemented and enforced
policies, plans, regulations for which they are responsible under this program.
- Five legal and regulatory frameworks will be in place by 2016 to promote
rice commercialization
- 300 participants in M&E workshops, training events, seminars,
conferences etc. (disaggregated by gender and affiliation)
Gender is mainstreamed in MAFF.
The gender unit in MAFF is functioning and fully funded to continue implementation of gender mainstreaming policies.
- Gender targets are mainstreamed into each of the component
outputs under Rice-SDP
Policies and information on aspects of food security related to agriculture and water management.
Food security concepts are integrated
into development programs and policy.
- Food security aspects of the Rice Policy are fully accommodated
under Rice-SDP by 2018
b/
Rice-SDP is not involved in land titling due to its political complexity. However, CLUPs established with assistance from Rice-SDP will facilitate the Government’s work in land titling.
Annex 1
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q1 2016
24
MONITORING FRAMEWORK FOR SCF PPCR
Results Indicators (consistent with PPCR Core Indicators)
Increased resilience of households, communities, businesses, sectors and society to climate change and climate variability through investments in irrigation subprojects being rehabilitated and climate proofed.
Numbers of people supported by the PPCR-supported Project to cope with effects of climate change as demonstrated by:
- 50,000 farmers will benefit from climate resilient irrigation structures by 2018
(2012 baseline: 0)
- Enhanced gender mainstreaming - 30% unskilled laborers employed in the rehabilitation are women by
o 2018; 30% of construction sub-committee members are women; 2 farmer water user committees
o established in each irrigation scheme, with women occupying 30% of the management positions.
(2012 baseline: 0)
- At least five local engineering firms will practice commercial design and construction of irrigation system that incorporated climate resilience options by 2019 (2012 baseline: 0).
- 100,000 ha of rice producing areas covered by WICI within the three participating provinces by 2017 (50% of the policy-holders is women, of which 10% is from female headed household) (2012 baseline: 0)
- 15 local input suppliers, 3 local financial institutions, and 3 local marketing agencies participating into the pilot
tests in three provinces (2012 baseline: 0).
- Four seed drying and storage facilities constructed by 2017 with a combined storage capacity of 8,000 tons
(30% unskilled laborers and 50% administrative staff are women)
- Capacity for drying paddy in target provinces extended by 2,000 tons per day by 2018
- Capacity for paddy storage in target provinces extended by 40,000 tons by 2018.
Annex 1
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q1 2016
25
MONITORING FRAMEWORK FOR SCF PPCR
Results Indicators (consistent with PPCR Core Indicators)
Climate responsive investment approaches implemented through land leveling as adaptation demonstrations being conducted in each irrigation subproject.
- Quality of and extent to which climate responsive instruments/investment models are developed and tested, as
reflected by
- 30% of farmers (disaggregated by sex) have leveled their paddy fields in target provinces by 2018 (2012
baseline: 0)
- At least nine private contractors in three project provinces engaged and trained to offer land leveling services by
2016 (2012 baseline: 0).
- Twenty private contractors, including 5 led by female entrepreneurs, replicated offering land leveling services at
their own initiatives in three participating provinces by 2018 (2012 baseline: 0).
- Strengthened capacity of provincial departments in Project provinces in improving efficiency of irrigation water
use through land leveling - baseline: 0% paddy land area leveled, target: 15% paddy land area leveled by 2018
Strengthened climate responsive
development planning
Degree of integration of climate change in national, including sector planning, as reflected by:
- Strengthened capacity of provincial departments in Project provinces in improving efficiency of irrigation
water use through land leveling - baseline: 0% paddy land area leveled, target: 15% paddy land area
leveled by 2018.
- A joint working group including female representatives established by the government to develop
agricultural land-use zoning as a climate adaptation strategy; developed and issued a framework providing
procedures for establishing agricultural land-use zones, incorporating measures and targets for involving
women in planning and decision making.
Annex 1
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q1 2016
26
MONITORING FRAMEWORK FOR SCF PPCR
Results Indicators (consistent with PPCR Core Indicators)
Strengthened adaptive capacity through
mill management training initiatives that
integrate climate change concerns.
- Extent to which vulnerable households, communities’ businesses and public sector services use improved
PPCR supported tools, instruments, strategies, activities to respond to CV&CC, as reflected by:
- 30% of rice mills in three project provinces equipped with knowledge to address change in paddy supply
patterns induced by climate change by 2018 (2012 baseline: 0).
- Post-harvest losses reduced from 15% of crop yield in 2012 to 10% of crop yield by 2017.
- Enhanced quality and participation of the private sector in providing advisory services to rice millers to address
climate change impacts, as reflected by: 10 local firms participating in providing advisory services to rice millers
by 2018. (2012 baseline: 0)
- Increased leverage factor of PPCR funding, reflected by an estimated $5 million from private sector mills by
2018 to address change in paddy supply patterns induced by climate change (2012 baseline: 0).
Strengthened adaptive capacity through developing and piloting weather-indexed crop insurance scheme.
Quality of and extent to which climate responsive instruments/ investment models are developed and tested, reflected by:
- 100,000 ha of paddy areas in three Project provinces covered by WICI by 2017 (2012 baseline: 0).
- 50% of insured rice farmers (i.e., policy-holders) is women.
- Enhanced capacities and participation of the private sector in paddy crop risk mitigation, reflected by: 15 local
input suppliers, three local financial institutions, and three local marketing agencies participating in crop
insurance services by 2017 (2012 baseline: 0).
Annex 1
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q1 2016
27
MONITORING FRAMEWORK FOR SCF PPCR
Results Indicators (consistent with PPCR Core Indicators)
Improved institutional framework in place through the adoption of sector development program approach encompassing policy and institutional reform and appropriately coordinated climate resilient investments.
Evidence of strengthened government capacity and coordination mechanisms that demonstrate integration of climate vulnerability in national, including sector planning to mainstream climate resilience, reflected by
- Three important legal documents (a law, a policy and an action program) will be in place by 2016 to address
climate change risks and/or adjusted to incorporate climate change risks, including (i) Law on Management and
Use of Agricultural Land (ii) Framework providing procedures for establishing agricultural land-use zones; and
(iii) National action program to combat land degradation in Cambodia.
- Under the guidance of the Committee for Economic and Financial Policies (CEFP), a cross-sectoral mechanism
taking into account of climate variability and climate change will be established by 2016 as part of the review
and adjustment of the Policy on the Promotion of Paddy Production and Rice Export.
Annex 2
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q1 2016
28
Rice SDP - Climate Resilient Rice Commecialisation Sector Development Program
ADB Loans 3006 & 3007 - CAM; GAFSP Grant 0349; SCF Loan 8271 & Grant 0350
Statement of Expenditure
Cumulative since Effectiveness Date
Reporting for the Quarter Ending: 31 March 2016
PMR 1: Project Monitoring Report: Uses of Funds By Category for the Quarter Ending 31st March 2016
(Note: Q = Quarter, YTD = Year to date, CTD = Cummulative to date) (Quaterly Report. In USD)
(1) (2) (3) (4) (5) (6) (7)=(2)-(3)-(5) (8)=(5)/(2) (9)=(6)/(1)
I- INVESTMENT COSTS
MEF/PMO 8,821,200 2,680,410 98,593.00 98,593.00 917,070.83 1,763,339.17 4% 10%
MAFF/NIO 22,521,100 1,528,904 - - 92,772.50 1,436,131.50 0% 0%
MOWRAM/NIO 16,701,400 885,000 - - 91,112.82 793,887.18 0% 1%
MLMUPC/NIO 1,808,600 252,484 43,000.00 43,000.00 43,000.00 209,483.74 17% 2%
BTB/PIO 690,100 45,930 - - 41,900.00 4,030.00 0% 6%
KPT/NIO 690,100 45,930 43,000.00 43,000.00 43,000.00 2,930.00 94% 6%
PVG/NIO 690,100 45,930 27,235.00 27,235.00 27,235.00 18,695.00 59% 4%
Sub Total (I): Investment Costs 51,922,600 5,484,588 0.0 211,828.00 211,828.00 1,256,091.15 4,228,496.59 4% 2%
II. IMPLEMENTATION AND SUPERVISION COSTS
MEF/PMO 2,603,100 268,220 97,951.56 97,951.56 244,803.87 23,416.13 37% 9%
MAFF/NIO 1,230,800 189,990 19,690.72 19,690.72 85,664.12 104,325.88 10% 7%
MOWRAM/NIO 1,255,800 98,040 16,654.95 16,654.95 75,415.25 22,624.75 17% 6%
MLMUPC/NIO 1,108,900 177,840 11,547.00 11,547.00 50,106.88 127,733.12 6% 5%
BTB/PIO 1,454,700 145,940 32,647.87 32,647.87 34,892.63 111,047.37 22% 2%
KPT/NIO 1,454,700 149,360 11,008.50 11,008.50 40,024.61 109,335.39 7% 3%
PVG/NIO 1,454,700 147,080 7,719.97 7,719.97 33,130.91 113,949.09 5% 2%
Sub Total (ii): Implementation and Supervision Costs 10,562,700 1,176,470 0.0 197,220.57 197,220.57 564,038.27 612,431.73 17% 5%
GRAND TOTAL (I)+(II) 62,485,300 6,661,058 0.0 409,048.57 409,048.57 1,820,129.42 4,840,928.32 6% 8%
Category
Disbursement
Rate % Overall
Actual Expenditure
Disbursement
Rate % 2016Overall Budget 2016 Budget
Unliquidated
ObligationsQ1 2016 YTD Q1 2016 CTD Q1 2016
2016 Budget
Balance
Annex 2
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q1 2016
29
Rice SDP - Climate Resilient Rice Commecialisation Sector Development Program
ADB Loans 3006 & 3007 - CAM; GAFSP Grant 0349; SCF Loan 8271 & Grant 0350
Disbursement Accounts by Financiers (USD)
Cumulative since Effectiveness Date
Reporting for the Quarter Ending: 31 March 2016
EAs/IAs Total Allocation (1)Unliquidated
Obligations (2)
Cumulative
Expenditure (3)
Budget Balance
(4) = (1)-(2)-(3)
I. LOAN 3006 - CAM (SF)
MEF/PMO 24,000,000
MAFF/NIO
Sub-Total 24,000,000 0 - 0
II. LOAN 3007 - CAM (SF)
MEF/PMO 6,183,000 678,915.03 5,504,085
MAFF/NIO 7,850,400 55,402.91 7,794,997
MOWRAM/NIO 11,476,300 79,211.51 11,397,088
MLMUPC/NIO 840,600 29,090.30 811,510
BTB/PIO 1,241,100 30,585.36 1,210,515
KPT/PIO 1,241,100 33,277.65 1,207,822
PVG/PIO 1,241,100 33,904.81 1,207,195
Sub-Total 30,073,600 0 940,387.57 25,507,680.25
III. GAFSP GRANT
MEF/PMO 1,230,700 130,720.87 1,099,979
MAFF/NIO 10,929,400 32,586.75 10,896,813
MOWRAM/NIO 782,800 15,206.76 767,593
MLMUPC/NIO 1,609,900 1,609,900
BTB/PIO 16,200 16,200
KPT/PIO 16,200 16,200
PVG/PIO 16,200 16,200
Sub-Total 14,601,400 0 178,514.38 14,374,285.62
IV. SCF LOAN
MEF/PMO -
MAFF/NIO 588,500 588,500
MOWRAM/NIO 3,306,600 3,306,600
BTB/PIO 367,500 367,500
KPT/PIO 367,500 367,500
PVG/PIO 367,500 367,500
Sub-Total 4,997,600 0 - 4,997,600.00
V. SCF GRANT
MEF/PMO 2,080,000 208,570.40 1,871,430
MAFF/NIO 2,000,000 2,000,000
MOWRAM/NIO 421,200 421,200
Sub-Total 4,501,200 - 208,570.40 4,292,630
VI. RGC
MEF/PMO 1,928,800 143,668.40 1,785,132
MAFF/NIO 2,385,500 90,446.96 2,295,053
MOWRAM/NIO 1,970,200 72,109.80 1,898,090
MLMUPC/NIO 467,000 64,016.58 402,983
BTB/PIO 520,000 46,207.27 473,793
KPT/PIO 520,000 49,746.96 470,253
PVG/PIO 520,000 26,461.10 493,539
Sub-Total 8,311,500 - 492,657.07 7,818,843
GRAND TOTAL 86,485,300 - 1,820,129.42 56,991,038
Annex 3
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DEFVELOPMENT PROGRAM Quarterly Progress Report Q1 2016
30
GENDER ACTION PLAN
The program is categorized as effective gender mainstreaming. It will enhance access of women farmers to decision making, resources, and services. Gender issues were incorporated into appropriate tranche conditions as stated in the policy matrix and gender indicators were included in all program outputs.
Gender Action Plan (GAP Activities, Indicators and Targets,
Timeframe and Responsibility)
Progress
Issues and Challenges
Output 1. A Conducive Legal and Regulatory Environment established to facilitate Climate Resilient Rice Commercialization
Gender issues will be subsequently main-streamed into the Agricultural Land Law and the Law on Management and Use of Agricultural Land Responsibility: MAF, PDS, GSS Time: dependent on progress in Output 1: Policy
Gender issues are reflected in Agricultural Land Policy and the Law on Management and Use of Agricultural Land; however, qualitative and quantitative sex-disaggregation of the beneficiaries are not yet reflected in reports.
The Agricultural Land Policy and the Law on Management and Use of Agricultural Land are of particular importance because they are conditional to the release of the second tranche of funds by ADB.
Considering MAFF is a pioneer in gender mainstreaming, it was a surprise that the issue has completely left out gender issues in Land Policy White Paper, Agricultural Land Policy and Law on Management and Use of Agricultural Land.
Ensure gender analyses included in development of all policies Responsibility: PMO, NIOs MAFF, and PDS, GSS Time: by Q1 2016
The ADB has very clear guidelines and policies on consultations and in general expects as full and as meaningful consultation as is practically possible with all PIOs but with more intensive consultations with primary stakeholders, which include groups of people that are targeted to benefit from projects it finances.
Review draft policy documents stated in the second tranche of the policy matrix before the Government’s submission to ADB to ensure inclusion of gender mainstreaming issues. (Relevant policy documents reviewed and include gender issues by Yr 3)
Ensure inclusion of gender expertise in working groups for policy development
Responsibility: PMO, NIOs, LUP/GIS Time: by Q3 2015
The terms of reference for the Gender Specialists have been carefully reviewed with a few queries that need to be clarified by ADB.
Women staff comprise 17.7 % of total 96 NOI, PMO, PICs staffs which is below the 30% target as per project GAP.
The ambitious percentages as indicated in the GAP for women participation vary from 30 % to 50% e. Within PIC team and PMO, NIOs and PIOs, it was interpreted with caution because from experience, conditional clauses especially in construction/civil works may hamper progress.
All laws and legal documents will be adequately disseminated among male and female groups. Responsibility: PMO, NIOs, MAFF, MLMUPC, MOWRAM, LUP/GIS Time: dependent on progress in Policy issues
Not yet accomplished
Content of documented material for dissemination to be determined
Annex 3
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DEFVELOPMENT PROGRAM Quarterly Progress Report Q1 2016
31
Gender Action Plan (GAP Activities, Indicators and Targets,
Timeframe and Responsibility)
Progress
Issues and Challenges
Output 2. Agricultural Land Use Zoning Improved
The guidelines for Establishing Agricultural land-use Zones will incorporate measures for involving women in planning and decision making.
Responsibility: NIO, MAFF and LUP/GIS Time: by Q1 2016
Landownership as indicator of wealth is acceptable but should include female-headed households as a sub-indicator.
A balance will have to be accepted so that technical activities will not override gender issues and vice versa. This matter has been brought up with the Gender Consultant at ADB Cambodia Resident Mission.
Ensure participation of women and women heads of households in collection of data and information relating to land-use zoning through use of women focal group discussion meetings. 90 groups of farmers consulted (with at least 40% female representation) during the
preparation of commune land use plans by 2018 Responsibility: PDA, PDLMUPC, LUP/GIS Time: by 2018
Not yet accomplished
Time frame has to be fine-tuned and fitted in with the other activities
The Rice-SDP monitoring system will incorporate sex disaggregated data. The GAP will be implemented within each and every program activity where relevant.
The GAP is prepared in order to highlight and remind the implementing agencies of their responsibilities.
Output 3. Climate Resilient Rice Value Chain Infrastructure Developed
Women will comprise 50% of the community
membership of construction sub-committees Responsibility: PDWRAM, RIE-H, CMS Time: concurrent with rehabilitation activities
Not yet accomplished
In the planned updating of the project GAP next year at Q3, 2016, the targets will be re-validated through series of participatory data gatherings with project beneficiaries and other stakeholders.
Separate women farmers’ meetings to discuss their needs related to location, alignment and access to irrigation infrastructure Responsibility: PDWRAM, PIOs and CMS Time: concurrent with rehabilitation activities
Not yet accomplished
Pending on timeframe of implementation of irrigation-related sub-projects
Final designs on infrastructure investments will be signed by construction sub-committees and commune councils. Further changes to the design must again be approved by the construction sub-committee
Not yet accomplished
The process of approval is to be determined. Sub-projects implementation to commence after feasibility studies (for some) and detailed design (for all)
Annex 3
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DEFVELOPMENT PROGRAM Quarterly Progress Report Q1 2016
32
Gender Action Plan (GAP Activities, Indicators and Targets,
Timeframe and Responsibility)
Progress
Issues and Challenges
Responsibility: PDWRAM RIE-H, CMS Time: concurrent with rehabilitation activities
In labor-based civil works, 40% of unskilled laborers will be women. Women will receive
equal pay for equal work. Child labor will not be employed. These conditions are to be included in all construction contracts Responsibility: PIOs, PDWRAM, PDA and
Procurement Specialists Time: during sub-project implementation
Not yet accomplished
Construction contracts of each sub-project have differing conditions, including targets and will be addressed as sub-projects become implemented
Employment opportunities targeted at men and women will be communicated to communities Responsibility: PIOs, PDA, PDWRAM, RIE-H, CMS Time: during sub-project implementation
Not yet accomplished
Targeted for implementation as project implementation progresses.
Target of at least 30% employment of women as unskilled laborers in rice drying and
warehousing facilities Responsibility: PIOs, PDA and Procurement Specialists Time: at pre-construction phase
Construction and other civil works will be started after recruitment of consulting engineers; some preliminary design activities are currently implemented
Evidenced from employment list of facility after it is in operation
The nature of construction works involving women will be determined during pre-construction orientation with contractors
Target 50% women’s employment as administrative staff in rice drying and storage
facilities Responsibility: PIOs, PDA, RIE-H, Procurement Specialists Time: post facility establishment
A balance will have to be accepted so that technical activities will not override gender issues and vice versa.
Contract stipulates special conditions. Employment list of facility after it is in operation
Target 50% women employed in seed production facilities as unskilled and semi-
skilled laborers, e.g. seed and seed bed preparation, weeding and seed grading and sorting, packaging etc.
Discussions have been held with Some Seed Growers’ Groups in Farmers’ Cooperatives in target areas. This process will be expanded.
Target in business contracts. List of employment in each and every production facility, after they are in operation
Annex 3
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DEFVELOPMENT PROGRAM Quarterly Progress Report Q1 2016
33
Gender Action Plan (GAP Activities, Indicators and Targets,
Timeframe and Responsibility)
Progress
Issues and Challenges
Responsibility: PIOs, PDA, Facility Operators, Business Dev. & Comm. Specialists, PPP Specialist Time: post facility establishment
Occupational safety measures and training provided to all workers. Responsibility: PDA, Facility Operators and Business Dev. & Comm. Specialists, PPP Specialist Time: pre-construction
To be implemented during pre-construction phase Targeted for implementation as project
implementation progresses.
Farmer Water User Communities (FWUCs) will accept membership registrations from husband and wife – 50% target for each. Responsibility: PDWRAM, PIO and CMS Time: throughout sub-project development
Community Mobilization Specialist (CMS) has been increasing awareness and encouraging commune authority preparation for FWUC to increase the participation of women.
Formal documentation, public announcements and membership lists of each FWUC are to be developed
Target at least 30% women in management positions in FWUCs. Women will be provided
training on leadership and management and will be remunerated for their roles. Responsibility: PDWRAM, PIO and CMS Time: throughout sub-project development
Community mobilization specialist (CMS) has been providing awareness and encouraging commune authority preparation for FWUC to increase the participation of women.
FWUC in Battambang (Prey Sangha) were established by ECOSORN project and recognized by PDWRAM, but they require strengthening
Some FWUCs require strengthening
List of attendees in training to be assessed during implementation of each sub-project
FWUC advisory committees established to monitor FWUC activities will comprise 50% women. Responsibility: PDWRAM, PIO and CMS Time: throughout sub-project implementation
Not yet accomplished
Facilitate gender mainstreaming training at community level with all project financed activities.
PIOs undertake training in all sub-project activities
Affected members dissatisfied with FWUC resolutions of disputes have the right to appeal to the FWUC advisory committee. Responsibility: PDWRAM, PIO and CMS Time: during facility operation
Not yet accomplished
FWUC advisory committee has a procedure for disputes and appeals after FWUC formation, pending on each sub-project
Affected women/households in FWUC will be identified and the information will be transferred to MAFF and PDA in the 3 provinces to be
Annex 3
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DEFVELOPMENT PROGRAM Quarterly Progress Report Q1 2016
34
Gender Action Plan (GAP Activities, Indicators and Targets,
Timeframe and Responsibility)
Progress
Issues and Challenges
included and prioritized in work-plans and training activities.
Water provision where feasible, will include both irrigation and non-irrigation water needs of households.
Responsibility: FWUC, PDWRAM and CMS Time: during sub-project implementation
Not yet accomplished
Villagers consulted in each and every sub-project on irrigation; pending on timeframe of sub-project implementation
Output 4. Rice Value Chain Support Services Enhanced to improve Quality of Cambodian Rice
Target at least 30% women in management positions in farmer cooperatives Responsibility: PDA, PIO, CMS Time: during sub-project implementation
Not yet accomplished. Preliminary discussions held with farmer cooperatives in Battambang.
Women in farmer cooperatives are the primary recipients of the project’s livelihood skills training to be conducted tentatively by 2016
Women will be provided training on leadership and management of cooperatives Responsibility: PDA, PIO and CMS Time: during sub-project operation
The GSS’s TOR and PAM’s GAP guide gender mainstreaming targets in the 30 sub-projects.
The GAP has been discussed with the other PICs ensuring that it is understood and that they include the stipulated targets in their activities. Review of policies and development of M&E have resulted in full gender inclusion.
In the planned updating of the project GAP in early 2016, the targets will be re-validated through a series of participatory data gathering missions with project beneficiaries and other stakeholders.
Farmer cooperatives will target membership of 50% men and 50% women. Responsibility: PDA, PIO and CMS Time: during sub-project implementation
Not yet accomplished. Preliminary discussions held at target sites in Battambang.
In the planned updating of the project GAP in early 2016. The formation and structure of cooperatives depends on the specifications of each sub-project.
Women will comprise 50% of participants in all project supported training in extension and
water management. Responsibility: PDA, PIO and Extension
Specialist Time: 2015-2017
Not yet accomplished
Undertake gender training at central and provincial levels Training to be completed by Yr 3 (Many government staff have been trained from different projects in the past 10 years. Training if required will be repetitive.)
Annex 3
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DEFVELOPMENT PROGRAM Quarterly Progress Report Q1 2016
35
Gender Action Plan (GAP Activities, Indicators and Targets,
Timeframe and Responsibility)
Progress
Issues and Challenges
Agricultural extension training materials and revision of technology implementation procedures will include specific training needs identified by women farmers on enhancing productivity, diversification of produce, animal husbandry and safety procedures and new income generating activities. Responsibility: PDA, PIO and Extension Specialist Time: throughout
Not yet accomplished
PIOs, the main provincial and district staff and contracted service providers will undertake training on relevant sub-project activities involving diversification to establish community-based sub-committees’ roles and responsibilities.
50% of farmers in pilot on farm trials and
demonstrations will be women. Responsibility: PDA, PIO and Extension
Specialist Time: during sub-project execution
Not yet accomplished. Discussions at sites in Battambang show awareness and practice of this to varying extents.
Selection procedure stipulates women participation at commune targets.
Extension training activities will ensure location and timing convenient for women. Responsibility: PDA, PIO and Extension Specialist Time: throughout
Not yet accomplished
Extension training schedule will be implemented at every sub-project from Year 2016
Training material will be designed to meet the needs of female and male farmers including illiterate farmers Responsibility: PIO, PDA and Extension Specialist Time: throughout
Not yet accomplished. Build upon work done by JICA and IRRI
Select material by considering women’s needs in the community.
Some 25% of agricultural extension workers
trained shall be women. Not yet accomplished
Facilitate the mainstreaming of safety issues into MAFF/PDA animal husbandry training
Annex 3
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DEFVELOPMENT PROGRAM Quarterly Progress Report Q1 2016
36
Gender Action Plan (GAP Activities, Indicators and Targets,
Timeframe and Responsibility)
Progress
Issues and Challenges
Responsibility: PDA, PDWRAM and Extension Specialist Time: 2016 through sub-project operation
List of extension workers in each province provided for action in 2016
Mass media extension material to be gender sensitive. Responsibility: PIOs, PDAs and Extension Specialist Time: throughout
Not yet accomplished
PIO will monitor the mass media extension material.
Facilitate linkages with Ministry of Health/Communicable Disease Project Phase 2, the Zoonotic Disease Unit and MAFF/GDA to provide occupational health and safety training to especially women poultry raisers
Address lack of access to credit by women and poor households (similar to TOR item xii). Responsibility: PDA, PIO, BAFS and CMS Time: during sub-project implementation
Not yet accomplished
Train provincial and district staff and contracted service providers in establishing and strengthening women’s savings and loan groups
Training depends on the formation of co-operative in each sub-project (use cross- provincial expertise among the 3 provinces. Some PDAs have experience in facilitating savings and loan groups)
Output 5. Weather-Indexed Crop Insurance (WICI) piloted
Some 50% of farmers under the pilot insurance scheme will be women and 10% of these to be female headed households. Responsibility: PMO, NIOs, PIOs, PIC, WICI
Consultants Time: Q4 2018 if feasible
Not yet accomplished Activity depends on the results of the WICI scheme pilot program
Output 6. Efficient Program Management and Implementation
Support PMO and PIOs. Responsibility: PMO, ISS-PIOs, PIC-GSSs Time: throughout
An orientation on GAP has been undertaken for the PMO and NIO MAFF and 3 PIOs.
Continuing discussions with PMO regularly
Gender balance may be achieved after the series of gender sensitization workshops with NIO, PMO and PICs.
The PIO has members who were not at all involved in the PPTA so the awareness and knowledge of Rice-SDP is weak. Wonder,
Annex 3
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DEFVELOPMENT PROGRAM Quarterly Progress Report Q1 2016
37
Gender Action Plan (GAP Activities, Indicators and Targets,
Timeframe and Responsibility)
Progress
Issues and Challenges
however, why the Program set such high percentages especially in women participation as unskilled workers in construction / rehabilitation activities knowing that out-migration from villages has almost depleted the able-bodied population, both men and women. PPTA did not mention this phenomenon.
Ensure sex-disaggregated performance monitoring system is established and operational. Responsibility: PMO-M&E, GSSs, MIS/Database Specialist Time: pre-construction phase as sub-project
implementation progresses
The GSSs have contributed to the drafting of the TOR for FS of sub-projects. The GAP in English and Khmer versions has been widely distributed.
There are hurdles to be overcome including over-saturation of gender training, ambitious targets, imbedded preference for separate gender activities and perception that gender inclusion interferes in technical activities.
All PMO and PIO staff shall be provided with gender training and roles and responsibilities involved in implementing the GAP. Responsibility: PMO, PIOs and GSSs Time: Q4 2014 and continuous
Training materials were produced in Khmer language by national gender consultant and distributed to participants during the training.
Total participants attending the training was 85 of which 15 (18%) were women.
Some challenges were raised during the training:
- Lack of budget for gender activities: training, meeting for villagers ,etc
- Number of women participating in the project is high but less women at decision making level
Note: - Fewer women attended gender training in
line NIO, PMO and PICs.
About 30% of technical and administrative positions to be filled by women (originally by Q2, 2013). Responsibility: PMO and GSSs Time: Q4 2015 – Q4 2017
To be implemented
Facilitate gender mainstreaming training at community level within all project-financed activities by preparation of material by Yr 1 and Training during Yrs 1, 2 and 3 (use material from other relevant projects)
Ensure participatory evaluations are conducted with male and female farmer groups at mid-term and end of the project reviews. Responsibility: PMO and ADB Time: periodically throughout
To be implemented
Review/monitor program progress and monitoring reports including baseline surveys and end-line impact evaluation reports to ensure data is gender disaggregated (Review progress reports quarterly).
Appendix 4
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DSEVELOPMENT PROGRAM Quarterly Progress Report Q1 2016
38
Progress Report for Program Implementation Consultants (Q1 2016)
1. David Moles (TL and Business Development and Commercialization Specialist)
Duration: 15/2 mobilized: intermittent
Tasks: arrange orientation/familiarization activities with project-related agencies; develop
and coordinate work plans with international/national specialists (inputs and deliverables);
with PMO, field visits to project
Introduced monthly work planning and reporting for all PIC team members.
Attended consultation on land levelling in KPT and assisted in preparation of concept paper
for MAFF/NIO.
Commenced consolidation of AWPB 2016 documents and budgets.
Outputs: Concept paper on land levelling and preliminary drafts of the budget for AWPB for
2016.
2. Leng Sothat (Deputy Team leader- and Seed Certification Specialist)
Duration: 1/1 - 31/3 full time
Tasks: Assisted in the facilitation of the ADB Review Mission in February.
Provided guidance and orientation to the incoming TL.
Liaised with project-related agencies; develop and coordinate work plans with international/
national specialists (inputs and deliverables); with PMO, field visits to target provinces.
Outputs: Network of related agencies initiated, field visit reports, workshop Program,
drafting work plan AWPB 2016
3. Men Sarom (Policy Development Specialist)
Duration: 1/1 - 31/3 full time
Tasks: review/familiarization with current ADB policies and relate to compliance with
components of Rice-SDP and RGC; liaise with CEFP
Outputs: Status report on policy compliance developed; arrangements.
4. Francesco Goletti (Policy Development Specialist)
Duration: intermittent
Tasks: review/familiarization with current ADB policies and relate to compliance with
components of Rice-SDP and RGC; liaise with CEFP
Outputs: Status report on policy compliance developed; arrangements.
5. Chhun Bunlong (Land Use Planning/GIS Specialist)
Duration: Intermittent
Tasks: Worked with MLMUPC to develop the ToR for the CLUP process.
Assisted MAFF with AEA mapping in key rice agro-ecosystems/edaphic zones.
Outputs: First draft CLUP ToR and AEA mapping with strategy to rationalize systems with
MAFF.
6. Mr. Long Sona, Environment/Climate Change Specialist
Duration: Intermittent
Tasks/Outputs: Prepare training materials and design awareness raising trainings for NIOs
and PIOs on environmental assessments and climate change impact.
7. Dr. Michael Turner, Seed Certification Specialists
Duration: Intermittent
Tasks/Outputs: Completed review of Seed Policy documents.
Assisted with identification of the seed laboratory equipment.
Appendix 4
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DSEVELOPMENT PROGRAM Quarterly Progress Report Q1 2016
39
Advised on the content of the rice seed action plan.
8. Mrs. Pong Limsan, MIS/Database Specialist
Duration: 1/1 - 31/31 full time
Tasks/Outputs: Continued with the development of the RiceSDP website and development
of the FSMIS database.
9. Mr. Sok Chea, Implementation Support Specialist, Prey Veng
Duration: 1/1 - 31/31 full time
Task/outputs Assisted the PIO to develop their SOPs and the establishment of the office
facilities and recruitment of staff.
10. Mr. Khiev Sam Oeun, Implémentation Support Specialist, Kampong Thon
11. Task/outputs Assisted the PIO to develop their SOPs and the establishment of the office
facilities and recruitment of staff.
12. Mr. Yingyod Yingyuenyong, Post-Harvest Specialist
Duration: intermittent
Tasks/outputs: Revised the Terms of Reference for FS, DD and CS consultants and conducted
field visits to selected sub-project sites.
Reviewing sub-project.
13. Mr. Oeurn Sophat, Post-Harvest Specialist
Duration: 1/1 - 31/31 full time
Tasks/Outputs: Revised the Terms of Reference for FS, DD and CS consultants and conducted
field visits to selected sub-project sites.
Reviewing sub-project.
14. Ms. Irene Villapando, M&E Specialist
Duration: intermittent
Tasks/Output: Drafting of the PPMS and QPR format.
15. Mr. Ruben Salgado, Procurement Specialist
Duration: intermittent
Tasks/Output: Advised MAFF/NIO on the finalization of the ToRs for FSDDCS for paddy
drying and storage and WICI and the procedures for advertising for EoIs.
16. Mr Gerard Blondet
Duration: intermittent
Tasks/Outputs: Preliminary orientation of the Rice SDP and the use of the PPP approach.
Appendix 5
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q1 2016
40
AGRICULTURAL POLICY COMPLIANCE MATRIX
POLICY ACTION No. COMPLIANCE INDICATOR
Compliance
Status
Status of Preparation and Plan to Completion
( = Done NR = not required)
First Draft Second Draft Final Draft MAFF
Approval
Submit to
COM
A. Promote Local Seed Production and Distribution
A1. Develop Rice
Seed Sector 1
MAFF shall have issued the Cambodian
Seed Policy.
Not yet
complied Jan 2016 Feb 2016 Mar 2016 NR
A2. Implement the
Law on Seed
Management and
Plant Breeders’
Rights (2008)
2 (a) MAFF shall have issued the National
Seed Standards.
Not yet
complied
Dec
2016 Jan 2016 Feb NR
3
(b) MAFF shall have issued the Prakas on
Procedures for Providing Seed Quality
Certification.
Not yet
complied Jan 2016 Feb 2016 Mar 2016 NR
4
(c) MAFF shall have issued the General
Introduction to the Examination of
Distinctiveness, Uniformity and Stability of
New Varieties of Plants.
Not yet
complied Jan 2016 Feb 2016 Mar 2016 NR
5
(d) MAFF shall have issued the Guidelines
for the Conduct of Tests for
Distinctiveness, Uniformity and Stability of
Rice.
Not yet
complied Jan 2016 Feb 2016 Mar 2016 NR
B. Strengthen Agricultural Land Management
B1. Strengthen the
Legal Framework
for
6
(a) The Borrower shall have issued the
Land Policy “White Paper”, including a
chapter on Land and Gender Policy.
Complied
Appendix 5
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q1 2016
41
POLICY ACTION No. COMPLIANCE INDICATOR
Compliance
Status
Status of Preparation and Plan to Completion
( = Done NR = not required)
First Draft Second Draft Final Draft MAFF
Approval
Submit to
COM
Agricultural Land
Management 7
(b) MAFF shall have drafted the Law on
Management and Use of Agricultural Land,
focusing inter alia, on (i) women’s access to
information on land administration,
management and distribution; (ii) women’s
equal participation and representation in
all commissions and committees; and (iii)
equal benefits for women in land related
initiatives.
Not yet
complied Feb 2016 Apr 2016 May 2016 Jun 2016
B2. Promote
Sustainable Land
Management
8
MAFF shall have prepared and the
Borrower shall have adopted the national
action program to combat land
degradation in Cambodia.
Not yet
complied Jan 2016 Feb 2016 Mar 2016 Apr 2016
B3. Develop Land-
use Zoning 9
MAFF shall have issued guidelines for
establishing agricultural land use zones,
incorporating measures and targets for
involving women in planning and decision
making.
Not yet
complied Jan 2016 Feb 2016 Mar 2016 NR
C. Strengthen Farmers’ Organizations and Promote Contract Farming
C1. Regulate
Farmers’
Organizations
10
MAFF shall have submitted the draft Law
on Agricultural Cooperatives to the
National Assembly.
Complied
Appendix 5
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q1 2016
42
POLICY ACTION No. COMPLIANCE INDICATOR
Compliance
Status
Status of Preparation and Plan to Completion
( = Done NR = not required)
First Draft Second Draft Final Draft MAFF
Approval
Submit to
COM
C2. Promote
Contract Farming
in Rice Production
11 The Borrower shall have issued the Sub-
decree on Contract Farming. Complied
D. Facilitate Domestic Trading and Export of Milled Rice
D1. Establish
Standard
Specifications for
Cambodian Milled
Rice
12 MIME shall have issued standards for
various varieties of Cambodian milled rice. Complied
D2. Establish
Phyto-sanitary
Regulations
13
MAFF shall have submitted the draft Law
on Plant Protection and Phytosanitary
Measures to the National Assembly.
Not yet
complied
Feb 2016 Apr 2016 May 2016 Jun 2016
Appendix 5
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q1 2016
43
No Policy Conditions
2015 2016
December January February March April May June
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
1 Seed Policy Second draft Final Draft MAFF
Approval
2 Seed Standards Second
Draft Final Draft
MAFF
Approval
3 Seed Certification Second draft Final Draft MAFF
Approval
4 DUS Introduction Second draft Final Draft MAFF
Approval
5 DUS Testing Second draft Final Draft MAFF
Approval
6 Land Management Second draft Final Draft MAFF
Approval
Submit to
COM
7 Land Degradation Second draft Final Draft MAFF
Approval
Submit to
COM
8 Land Zones Second draft Final Draft MAFF
Approval
9 Law on Plant Protection and
SPS Second draft Final Draft
MAFF
Approval
Submit to
COM
Annex 6
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q1 2016
42
Status of Agreed Actions dated 15 February 2016
CAM-Climate Resilient Rice Commercialization Sector Development Program (Rice-SDP) Time Bound Action Plan for 2016
No. Agreed Actions Due Date Responsibility Progress
1
Contract signed with the FSDDCS (Feasibility Study, Detailed
Design and Construction Supervision) consultants for
irrigation subprojects
15 Feb
2016 NIO-MOWRAM
Completed
Contract has signed with the FSDDCS consultants
on 15 February 2016.
2
Contract signed with Feasibility Study, Detailed Design and
Construction Supervision consultants (FSDDCSC-MAFF) for
paddy drying and seed storage facilities
Revised TOR and budget estimate replacing Procurement Specialist (18pm) with M&E Specialist (32pm) submitted to ADB by 22 February 2016
Submission 1 submitted to ADB by 21 Mar 2016
RFP issued by 01 Apr 2016
Submission 2 submitted to ADB by 20 May 2016
Submission 3 submitted to ADB by 6 Jun 2016
Submission 4 submitted to ADB by 20 Jun 2016
30 June
2016
NIO-MAFF with
support from
PMO/PIC
Procurement
Specialists
Partly Completed
ToR drafted together with budget estimate and
including the M&E Specialist for MAFF/NIO was
submitted to ADB for no objection.
3
Contract signed with feasibility study, design and pilot testing
of weather indexed crop insurance (FSDPT-WICI)
consultants
Submission 1 submitted to ADB by 21 Mar 2016
RFP issued by 01 Apr 2016
Submission 2 submitted to ADB by 6 Jun 2016
Submission 3 submitted to ADB by 21 Jun 2016
Submission 4 submitted to ADB by 5 Jul 2016
15 July
2016
NIO-MAFF with
support from
PMO/PIC
Procurement
Specialists
Partly Completed
ToR drafted and submitted to ADB for no objection.
Annex 6
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q1 2016
43
No. Agreed Actions Due Date Responsibility Progress
4
TOR and budget estimate for the service contract package
for Commune Land Use Planning (CLUP) prepared and
submitted to ADB
28
February
2016
NIO-MLMUPC
with support
from PMO/PIC
Procurement
Specialists
Completed
The ToR and Budget estimate for CLUP was
submitted to ADB in March 2016.
Comments received were incorporated into revised
ToR which was resubmitted to ADB on 20 April
2016.
5
Finalized the Detailed Engineering Design, Bidding
Documents and completed the bid invitation works for the
Chhuk Ksach and Prey Sangha subprojects
Submit the final design and bid invitation documents for Chhuk Ksach subproject to PRC through NIO-MOWRAM approval by 1 April 2016
Submit the final design and bid invitation documents for Prey Sangha subproject to PRC through NIO-MOWRAM approval by 30 April 2016
15 May
2016
NIO-MOWRAM
in coordination
with FSDDCSC-
MOWRAM
Partly Completed
- Detailed engineering design and bidding
documents of Prey Sangha will submit on 12
May 2016. Expect to advertise the bid
invitation by 26 May 2016, and bid opening by
27 June 2016.
- Detailed engineering design and bidding
documents of Chhuk Ksach will submit on 31
May 2016 and expect to advertise the bid
invitation by 10 June 2016 and bid opening on
11 July 2016.
6
Bid Evaluation Reports (BERs) submission to ADB for Chhuk
Ksach and Prey Sangha subprojects
30 June
2016
NIO-MOWRAM
in coordination
with FSDDCSC-
MOWRAM
Partly Completed
- Expect to complete the bid evaluation report
for Prey Sangha canal on 12 July 2016 and
expect to award the contract by 29 July 2016.
- Expect to complete the bid evaluation report
for Chhuk Ksach canal on 26 July 2016 and
expect to award the contract by 12 August
2016.
Annex 6
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q1 2016
44
No. Agreed Actions Due Date Responsibility Progress
7 Award the contracts for Chhuk Ksach canal and Prey Sangha
canal subprojects.
31 July
2016
NIO-MOWRAM
with support
from PMO/PIC
Procurement
Specialists
On Going
The contract award is mostly depend raining
season. However, both subproject could start by
early of the dry season around November 2016 and
project implementation works will be finalized by
May 2017.
8
Finalized the detailed engineering design and bidding
documents and bid invitation for the following 4 canals:
Trach, Ta Mao, Kampong Thnal and Chamkar Kuoy.
31 Detc
2016
NIO-MOWRAM
in coordination
with FSDDCSC-
MOWRAM
On Going
Detailed engineering design, bidding documents
and bids invitation works for the four subprojects
four sub-projects will be completed by 31 Dec 2016.
9 Contract award for 2 contract works out of the 4 subprojects
(listed under S. No. 8) awarded.
31 Dec
2016
NIO-MOWRAM
with support
from PMO/PIC
Procurement
Specialists
On Going
The Contract award will be completed on time as
according the project implantation plan.
10
Up on receive of the detail design approval by NIO-
MOWRAM for the Chhuk Khsach canal and Prey Sangha
subprojects, the implementation works for the Resettlement
Plans including the PRs preparation, update works for the
rest of subprojects will be implemented in 3 months’ time
31 July
2016
MOWRAM and
IRC with support
of PIC
Completed
The Project effected peoples has observed by the
FSDDCS consultants during the projects
preliminary project visit stages. The resettlement
plan will be updated and the resettlement works will
be implemented as defined in the project
implementation plan.
11 BER for the procurement of equipment for Agriculture
Laboratory submitted to ADB
18 March
2016
NIO-MAFF with
support from
PMO/ PIC
Procurement
Specialists
Completed
BER was submitted to ADB for no objection.
Annex 6
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q1 2016
45
No. Agreed Actions Due Date Responsibility Progress
12 Contract for the equipment for Agriculture Laboratory
awarded
15 April
2016 NIO-MAFF
Not Completed
13 Implementation plan for certified seed production prepared,
finalized and submitted to ADB
31 March
2016
NIO-MAFF with
support from
PMO/IC
Partly Completed
Implementation plan has been prepared and
discussed with ADB on March 7th. Clarification on
the payment of fees for MAFF Trainers is awaited.
14 Execution plan for the Laser Land Levelling activity prepared
and submitted to ADB
30 April
2016
NIO-MAFF with
support from
PIC
Partly Completed
PIC have prepared a Concept Paper on land
levelling which is being reviewed by NIO - MAFF.
15 Implementation plan and budget for CAEA submitted to ADB
28
February
2016
NIO-MAFF with
Agriculture
Extension
Department
Partly Completed
Implementation Plan and Budget for the conduct of
the CAEA has been prepared by NIO-MAFF and
submitted to PMO for review in March 2016.
16
Implementation plan and budget for Soil survey, classification
and mapping; and Rice ecosystem mapping submitted to
ADB
28
February
2016
NIO-MAFF with
Agricultural Land
Resources
Management
Department
Partly Completed
Implementation plan and budget has been prepared
and submitted to the PMO for review in March
17 2016 Work Plan and Budget consolidated, finalized and
submitted to ADB for approval
28 Feb
2016 PMO
Completed
PIC Team have finalized the 2016 Work Plan and
Budget and PMO submitted to ADB on 28 Marc
2016. Comments were received and the AWPB has
now been revised to reflect these changes.
18 Consolidated Training Program with Cost Estimate for 2016
submitted to ADB
28 Feb
2016 PMO
Completed
Consolidated Training Plan was prepared by the
PIC Team and incorporated into the 2016 AWPB.
19 PIC PPP Specialist mobilized 8 Mar 2016
PIC Completed
PPP Specialist was mobilized on 8 March 2016
Annex 6
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q1 2016
46
No. Agreed Actions Due Date Responsibility Progress
20 PIC Environment and Climate Change Specialist mobilized 15 Mar
2016 PIC
Partly completed
NIRAS submitted two cvs to the PMO for
consideration on 5 April 2016.
21 CV of proposed candidate for National Gender Specialist
position submitted to PMO and ADB for no-objection
28 Feb
2016 PIC
Partly completed
NIRAS have submitted the cv of replacement
candidate to PMO on 5 April 2016
22 PPMS Draft finalized
28 Feb
2016
PMO with
support from
PIC M&E
Specialist
Completed
Draft PPMS prepared by the PIC Team was
submitted to the PMO and was discussed during
meeting at ADB/CARM on 24 March 2016.
23
First updated PPMS for performance as of 30 June 2016
submitted (and updated and submitted subsequently every 6
months
Baseline surveys completed and included in the PPMs by 30 June 2016
31 Jul 2016
PMO with
support from
PIC M&E
Specialist
Partly Completed
First round of training on the PPMS has been
completed in each target province.
First test of the PPMS will be done during April for
the Q1 Progress Report.
ToR for the Baseline Survey is now under
preparation.
Annex 7
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q1 2016
47
Rice-SDP RISK MANAGEMENT MATRIX
(L = Likelihood: (5 = Almost Certain; 4 = Likely; 3 = Possible; 2 = Unlikely; 1 = Rare; C = Consequence: (5 = Severe; 4 = Major; 3 = Moderate; 2 = Minor; 1 = Negligible) R = Risk Level: (4 = Extreme; 3 = High; 2 = Medium; 1 = Low)
Identified Risk Damage to Project L C R Risk Response Responsibility for
Managing
Project Outcome
Farmers fail to make the
transition from export of paddy
to Viet Nam / Thailand, to sell
to local millers and rice
exporters
Failure in transition would negate the
longer-term objectives of increase in
revenue from rice exports and increase
in net profit of rice exporters.
5 5 4
Ensure that a separate survey on baseline and target indicator is
conducted during the second year of the program to validate
information of informal paddy trade across the border with Thailand
and Viet Nam, as provided for in the PAM.
PMO & MAFF with
support from PIC
Project Outputs
Output 1: A Conducive Legal and Regulatory Environment Established to Facilitate Climate-Resilient Rice Commercialization
Delays in finalizing and
approving the Seed Policy
Delayed release of 2nd Tranche might
affect implementation of investment
components of the Project.
2 4 2 Ensure that the latest version of the Seed Policy is reviewed as
quickly as possible and passed to MAFF for approval MAFF
Delays in finalizing the Prakas
required to implement Chapter
3 of the Seed Law (2008)
Delayed release of 2nd Tranche might
affect implementation of investment
components of the Project; lack of good
Prakas will impede the implementation
of the seed certification scheme, which
is a key ‘value chain service’
3 4 2
The latest versions of the Prakas must be critically reviewed to
ensure that they provide a sound basis for the operation of the seed
certification scheme and of the seed testing laboratory.
MAFF
Delays in meeting the deadline
for submission of Law on
Agricultural Land Use and
Management by the Tranche 2
due date (June 2016).
Delayed release of 2nd Tranche might
affect implementation of investment
components of the Project.
4 3 2
Ensure that sufficient resources are available to GDA/MAFF on time
to carry out the required preparation of documents and
consultations. Agree on a timeline for preparation of intermediate
drafts of regulations. Recruit experts (e.g. for land and women
issues) to assist in the formulation of drafts for discussion. Use PIC
experts to facilitate review of documents and meetings.
MAFF
Appendix 6
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q3 & Q4 2015
48
Identified Risk Damage to Project L C R Risk Response Responsibility for
Managing
Output 2: Agricultural Land-use Zoning Improved
Implementation of CAEA and
CLUP is delayed and the
annual target cannot be met.
CEAE lays the foundation and provides
essential information to guide the
implementation of Rice SDP sub-
projects and other activities. Any delay
in CAEA implementation will have
serious impacts on all other project
components.
2 4 3
Despite good preparation (the CAEA manual has been upgraded,
training materials have been produced and communes prioritised
for CAEA implementation) there remains a risk of delay. Close
technical backstopping will be important to avoid this, especially in
the early rounds of CAEA until experience is gained. Un-coupling
CAEA from CLUP has significantly reduced the likelihood of delays
and the plan to involve the Rice SDP Extension Specialist in the 3
CAEA pilots will greatly reduce this risk.
MAF, DAE
backstopping, POIs,
Output 3: Climate Resilient Rice Value Chain Infrastructure Developed
Delay of the implementation of
the planned and scheduled
sub-projects
If the certain infrastructure/building
implementation projects are delayed,
that can cause in worst case almost one
year delay for implementation because
of the seasonal and weather conditions.
In addition this can have affect for the
other planned & scheduled activities.
3 4 2 Strong and on-going project management and following the critical
and scheduled milestones agreed. EAs/IAs/PIC
Output 4: Rice Value Chain Support Services Enhanced to Improve Quality of Cambodian Rice
Insufficient certified/improved
seed is available due to slow
implementation of the seed
certification scheme
Increase in paddy production and
improvements in quality of milling paddy
will not be achieved
4 3 2
Ensure that seed certification is implemented in line with the
Prakas and that all necessary resources are available to launch
certified seed production; this includes the availability of sufficient
basic (foundation) seed from CARDI, which may need to be
addressed by the project.
MAFF/CARDI
Use of certified seed is
unpopular among farmers due
to prohibitive price or other
reasons
This would adversely affect the targeted
increase in paddy production to 9.5
million tons in 2018.
3 4 2
What type or variety to plant is the decision of the farmer. If non-
certified seeds have a lower price and there is a ready market for
paddy from such seeds, a farmer will decide to use non-certified
seeds. Rice-SDP needs to strongly support dissemination of new
technologies to farmers such as the use of commercial seeds.
MAFF
Appendix 6
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q3 & Q4 2015
49
Identified Risk Damage to Project L C R Risk Response Responsibility for
Managing
Mixture of different rice
varieties without clearly
identified will affect to the
rice market and export.
This mixture can be done in each
of rice value supply chain from
farming, trading, milling, exporting
for sake of the business, especially
the imitated fragrant rice variety
“Sen Kro Obb” mix with the original
fragrant rice “Pka Rumduol”.which
hard to identify by normal physical
analysis.
4 4 3
GDA/MAFF must use Cambodia Rice Standard for all rice products
and set up Central Lab with adequate equipment to measure and
certify the rice samples in time.
Ministry of Commerce shall enforce all millers and rice exporters to
respect code of conduct and true to label.
MAFF/MoC
Output 5: Weather-indexed Crop Insurance Piloted
Farmers fail or have no interest
to buy insurance for their
crops.
Smallholder farmers still depending on
donation provided by relief agencies
when their crop damaged by disasters.
4 3 2
Crop insurance concept is new to Cambodia. Thus, it will require a
considerable effort to develop legal infrastructure, promote private
sector participation and raise awareness among stakeholders.
Government subsidies on the premium payout is one of the best
way to get farmer participating in the initial stage/piloting phase.
MAFF, MEF, PIC
Output 6: Efficient Program Management and Implementation
Coordination between all
involved agencies
As the project structure is complex and
there are many different stakeholders,
the coordination of the implementation
and other activities is crucial
3 3 2 PPMS and other management tools in place and effective use.
Strengthen the coordination role and mechanisms of the EA. EAs, IAs, PIC
Annex 8
CLIMATE RESILIENT RICE COMMERCIALIZATION SECTOE DEVELOPMENT PROGRAM Quarterly Progress Report Q1 2016
50
Summary of priority sub-projects
No. UnitRiels
(Billion)
USD
(Million)
B-7 Rehabilitation of Anglong Ruon system Thmor Korl Irrigation Rehabilitation of 6.3 km of link canal, 21 km of secondary canals and associated structures 1,200 ha 6 2 4 1,065 3 2
B-8 Rehabilitation of Ta Maov Irrigation System Thmor Korl Irrigation Rehabilitation of 4.0 km of link canal, 5.8 km (5) secondary canals and associated structures 200 ha 5 1 1 195 2 4
B-9 Rehabilitation of Mok Rea Secondary Canal Rokha Kiri Irrigation Rehabilitation of 5 km of secondary canal 800 ha 5 1 1 510 6 9
B-6 Rehabilitation of O’ Voir Irrigation System Moung Roussei Irrigation Construction of 1.9 km dike and rehabilitation of 7.3 km of canal and associated structures 1,800 ha 5 1 4 720 9 6
B-3Support for Seed Production in Chong Samnay
with Irrigation RehabilitationMoung Roussei Seed Production
Rehabilitation of 4 km of secondary canal and associated water management structures with support for
seed producing cooperative4,500 ha 2 1 19 5,343 4 5
B-2 Prey Sangha Rice Seed Production Bavel Seed ProductionRehabilitation of 4.4 km of main canal and associated water management structures with support for
seed producing cooperative1,145 ha 2 1 9 522 1 (RS) 1 (RS)
B-4 Seed Drying and Storage Facility Bavel Seed Production Construction of seed drying and storage facility for PPP operation (to be defined) 600 ton 7 2 9 522 5 3
B-5 Seed Drying and Storage Facility Moung Roussei Seed Production Construction of seed drying and storage facility for PPP operation (to be defined) 600 ton 7 2 19 5,343 7 7
B-1 Paddy Drying and Storage Facility Thmor Korl Paddy Storage Construction of 10,000 ton paddy drying and storage facility for PPP operation 10,000 ton 16 4 335 102,978 8 8
K-7 Rehabilitation of Chhuk Khsak Canal Barray Irrigation Rehabilitation of 9 km of secondary canal and associated structures 1,430 ha 4 1 9 1,253 1 (RS) 1 (RS)
K-10 Rehabilitation of Bat Trang Irrigation System Stoung Irrigation Construction of new 120 m weir and rehabilitation of 6 km of irrigation canals 2,000 ha 8 2 16 2,951 7 2
K-9 Rehabilitation of Ta Soong Canals Barray Irrigation Rehabilitation of 1 secondary canal and associated structures 1,330 ha 5 1 12 2,715 5 6
K-8Rehabilitation of Kampaeuy Secondary Canal of
Stung Chinit Irrigation SystemBarray Irrigation Rehabilitation of 7 km of secondary canal and associated structures 650 ha 6 1 4 1,234 4 4
K-3Support for Rice Seed Production with
Rehabilitation of Trach Canal
Stoung & Kg
SvaySeed Production
Support for seed production in San Kor Mean Chey, Kg Svay District, and Trach Canal Stoung District;
and rehabilitation of 4 existing canals and associated structures 947 ha 7 2 18 2,304 3 3
K-4Support for Rice Seed Production with
Rehabilitation of Pnov Irrigation SystemSantuk & Barray Seed Production
Support for rice seed production in Chhuk Ksach, Barray District, in Kvek Baray Dst, and Pnov, Santuk
Dst, and rehabilitation of 8.2 km of Pnov irrigation canal and associated structures1,056 ha 6 1 12 2,834 8 8
K-5 Seed Drying and Storage Facility Barray/ Stoung Seed Production Construction of seed drying and storage facility for PPP operation 600 ton 7 2 12 2,834 6 7
K-6 Seed Drying and Storage Facility Kg Svay/ Stoung Seed Production Construction of seed drying and storage facility for PPP operation 600 ton 7 2 18 2,304 10 10
K-1 Paddy Drying and Storage Facility Stung Sen Paddy Storage Construction of 10,000 ton paddy drying and storage facility for PPP operation 10,000 ton 16 4 59,000 2 5
K-2 Paddy Drying and Storage Facility Stoung Paddy Storage Construction of 10,000 ton paddy drying and storage facility for PPP operation 10,000 ton 16 4 331 60,000 9 9
P-10 Rehabilitation of Ansong Irrigation System Kg Trabek Irrigation Rehabilitation of 6 km of main and 24 km of secondary canals (6), and associated structures 1,192 ha 8 2 5 1,073 4 3
P-9 Rehabilitation of Anlong Char Canal Preah Sdach Irrigation Rehabilitation of 15km of main canal and structures 2,659 ha 7 2 10 2,135 6 7
P-11 Rehabilitation of Rumlech Irrigation system Sithor Kandal IrrigationRehabilitation of reservoir, rehabilitation of 130 m of existing dam, construction of new spillway, and
rehabilitation of 3 km of main and 9 km of secondary canals and associated structures2,117 ha 7 2 10 1,011 5 4
P-7Rehabilitation of Chhue Teal, Boeung Khanhey
Irrigation SystemSvay Antor Irrigation Rehabilitation of 4.8 km of existing dike and 8 km of main canal and associated structures 3,032 ha 6 2 26 2,602 9 8
P-8Rehabilitation of Chamcar Kuoy Canal
RehabilitationSvay Antor Irrigation Rehabilitation of 8.5 km of existing main canal and structures 1,900 ha 6 1 9 1,428 3 9
P-4Support for Seed Production Program at Russey
Sanh VillageSithor Kandal Seed Production
Capacity building in rice seed production, and rehabilitation of associated irrigation system, including
7.5km of main and 20km of secondary canals1,200 ha 7 2 9 3,447 8 2
P-3Support to Seed Production Program at Kg.
Thnal VillagePreah Sdach Seed Production Capacity building in rice seed production, and rehabilitation of 4 km of irrigation canals 550 ha 2 1 6 84 2 6
P-6 Seed Drying and Storage Facility Sithor Kandal Seed Production Construction of 600 Ton seed drying and storage facility for PPP operation 600 ton 7 2 9 3,447 7 5
P-5 Seed Drying and Storage Facility Preah Sdach Seed Production Construction of 600 Ton seed drying and storage facility for PPP operation 600 ton 7 2 6 n.a. 10 10
P-1 Paddy Drying and Storage Facility Svay Antor Paddy Storage Construction of 10,000 ton grain drying and storage facility for PPP operation 10,000 ton 16 4 9 1,623 1 (RS) 1 (RS)
P-2 Paddy Drying and Storage, Facility Preah Sdach Paddy Storage Construction of 10,000 ton grain drying and storage facility for PPP operation, at Kg Thnal Village 10,000 ton 16 4 375 72,732 11 11
Overall Totals 223 56 1,307 344,209
Priority
(2012)
Prov. Re-Priority
(Jan 2015)
BATTAMBANG PROVINCE
KOMPONG THOM PROVINCE
PREY VENG PROINCE
No Name of Subproject District Type Summary Description
Details Estimated CostNo. of
Villages
No of Direct
Beneficiaries
(HH)
Annex 9
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q1 2016
51
Compliance with Loan and Grant Covenants (Q1 2016)
SN Covenant Reference in Loan / Grant
Agreement Status as of Q1 2016
Financial
1 (a) The Recipient shall (i) maintain separate accounts and records for the Project; (ii) prepare annual financial statements for the Project in accordance with accounting principles acceptable to ADB; (iii) have such financial statements audited annually by independent auditors whose qualifications, experience and terms of reference are acceptable to ADB, in accordance with international standards for auditing or the national equivalent acceptable to ADB; (iv) as part of each such audit, have the auditors prepare a report (which includes the auditors' opinion on the use of the Grant proceeds and compliance with the financial covenants of this Grant Agreement as well as on the use of the procedures for the imprest fund and statement of expenditures) and a management letter (which sets out the deficiencies in the internal control of the Project that were identified in the course of the audit, if any); and (v) furnish to ADB, no later than 6 months after the end of each related fiscal year, copies of such audited financial statements, audit report and management letter, all in the English language, and such other information concerning these documents and the audit thereof as ADB shall from time to time reasonably request. (b) ADB shall disclose the annual audited financial statements for the Project and the opinion of the auditors on the financial statements within 30 days of the date of their receipt by posting them on ADB's website. (c) The Recipient shall enable ADB, upon ADB's request, to discuss the financial statements for the Project and the Recipient's financial affairs where they relate to the Project with the auditors appointed pursuant to subsection (a) (iii) hereinabove, and shall authorize and require any representative of such auditors to participate in any such discussions requested by ADB. This is provided that such discussions shall be conducted only in the presence of an authorized officer of the Recipient, unless the Recipient shall otherwise agree.
Grant 0349, Section 4, para 2
The PMO and also NIOs and PIOs have all established separate Imprest Accounts for receipt of project loan and grant funds. Annual financial statements for end of financial year 2015 were prepared and external audits will be conducted in Q2 2016. PMO have provided training to the NIO and PIO accounting staff on the SOPs.
2 (a) The Borrower shall (i) maintain separate accounts and records for the Project; (ii) prepare annual financial statements for the Project in accordance with accounting principles acceptable to ADB; (iii) have such financial statements audited annually by independent auditors whose qualifications, experience and terms of reference are acceptable to ADB, in accordance with international standards for auditing or the national equivalent acceptable to ADB; (iv) as part of each such audit, have the auditors prepare a report (which includes the auditors' opinion on the use of the Loan proceeds and compliance with the financial covenants of this Loan Agreement as well as on the use of the procedures for the imprest fund and statement of expenditures) and a management letter (which sets out the deficiencies in the internal control of the Project that were identified in the course of the audit, if any); and (v) furnish to ADB, no later than 6 months after the end of each related fiscal year, copies of such audited financial statements, audit report and management letter, all in the English language, and such other information concerning these documents and the audit thereof as ADB shall from time to time reasonably request.
Loan 3007, Article 4, para 2
The PMO and also NIOs and PIOs have all established separate Imprest Accounts for receipt of project loan and grant funds. Annual financial statements for end of financial year 2015 were prepared and external audits will be conducted in Q2 2016. PMO have provided training to the NIO and PIO accounting staff on the SOPs.
Annex 9
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q1 2016
52
SN Covenant Reference in Loan / Grant
Agreement Status as of Q1 2016
(b) ADB shall disclose the annual audited financial statements for the Project and the opinion of the auditors on the financial statements within 30 days of the date of their receipt by posting them on ADB's website. (c) The Borrower shall enable ADB, upon ADB's request, to discuss the financial statements for the Project and the Borrower's financial affairs where they relate to the Project with the auditors appointed pursuant to subsection (a)(iii) hereinabove, and shall authorize and require any representative of such auditors to participate in any such discussions requested by ADB. This is provided that such discussions shall be conducted only in the presence of an authorized officer of the Borrower, unless the Borrower shall otherwise agree.
3 (a) The Recipient shall (i) maintain separate accounts and records for the Project; (ii) prepare annual financial statements for the Project in accordance with accounting principles acceptable to ADB; (iii) have such financial statements audited annually by independent auditors whose qualifications, experience and terms of reference are acceptable to ADB, in accordance with international standards for auditing or the national equivalent acceptable to ADB; (iv) as part of each such audit, have the auditors prepare a report (which includes the auditors' opinion on the use of the Grant proceeds and compliance with the financial covenants of this Grant Agreement as well as on the use of the procedures for the imprest fund and statement of expenditures) and a management letter (which sets out the deficiencies in the internal control of the Project that were identified in the course of the audit, if any); and (v) furnish to ADB, no later than 6 months after the end of each related fiscal year, copies of such audited financial statements, audit report and management letter, all in the English language, and such other information concerning these documents and the audit thereof as ADB shall from time to time reasonably request. (b) ADB shall disclose the annual audited financial statements for the Project and the opinion of the auditors on the financial statements within 30 days of the date of their receipt by posting them on ADB's website. (c) The Recipient shall enable ADB, upon ADB’s request, to discuss the financial statements for the Project and the Recipient's financial affairs where they relate to the Project with the auditors appointed pursuant to subsection (a)(iii) hereinabove, and shall authorize and require any representative of such auditors to participate in any such discussions requested by ADB. This is provided that such discussions shall be conducted only in the presence of an authorized officer of the Recipient, unless the Recipient shall otherwise agree.
Grant 0350, Section 4, para 2
The PMO and also NIOs and PIOs have all established separate Imprest Accounts for receipt of project loan and grant funds. Annual financial statements for end of financial year 2015 were prepared and external audits will be conducted in Q2 2016. PMO have provided training to the NIO and PIO accounting staff on the SOPs.
Safeguards
4 The Borrower shall ensure that the preparation, design, construction, implementation and operation of the Project, each Subproject and all Project facilities comply with (a) all applicable laws and regulations of the Borrower relating to environment, health and safety; (b) the Environmental Safeguards; and (c) all measures and requirements set forth in the lEE, the EMP, and any corrective or preventative actions set forth in a Safeguards Monitoring Report.
Loan 3007, Schedule 5, para 2
Work has not yet commenced on the feasibility studies for the sub-projects.
5 The Borrower shall ensure that climate change considerations are incorporated in Loan 3007, Schedule 5, Work has not yet commenced on the feasibility studies for
Annex 9
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q1 2016
53
SN Covenant Reference in Loan / Grant
Agreement Status as of Q1 2016
the design and implementation of the Subprojects. para 3 the sub-projects.
6 The Borrower shall ensure that no subproject which meets ADB's category A environmental criteria set out in the Safeguard Policy Statement is included in the List of Candidate Subprojects, and that no subproject with category A environmental criteria is financed under the Project.
Loan 3007, Schedule 5, para 4
Work has not yet commenced on the feasibility studies for the sub-projects.
7 The Borrower shall ensure that all land and all rights-of-way required for the Project, each Subproject and all Project facilities are made available to the Works contractor in accordance with the schedule agreed under the related Works contract and all land acquisition and resettlement activities are implemented in compliance with (a) all applicable laws and regulations of the Borrower relating to land acquisition and involuntary resettlement; (b) the Involuntary Resettlement Safeguards; (c) the RF; and (d) all measures and requirements set forth in the respective RP, and any corrective or preventative actions set forth in a Safeguards Monitoring Report.
Loan 3007, Schedule 5, para 5
Work has not yet commenced on the feasibility studies for the sub-projects.
8 Without limiting the application of the Involuntary Resettlement Safeguards or the RP, the Borrower shall ensure that no physical or economic displacement takes place in connection with the Project until: (a) compensation and other entitlements have been provided to affected people in accordance with the RP; (b) a comprehensive income and livelihood restoration program has been established in accordance with the RP; and (c) all land and all rights-of-way required for a Subproject is free of all encumbrances.
Loan 3007, Schedule 5, para 6
Work has not yet commenced on the feasibility studies for the sub-projects.
9 The Borrower shall ensure that no subproject which meets ADB's category A resettlement criteria set out in the Safeguard Policy Statement is included in the List of Candidate Subprojects, and that no subproject with category A Resettlement Criteria is financed under the Project.
Loan 3007, Schedule 5, para 6
Work has not yet commenced on the feasibility studies for the sub-projects.
10 The Borrower shall ensure that the Project does not have any indigenous peoples impact, all within the meaning of the Safeguard Policy Statement. In the event that the Project does have any such impact, the Borrower shall take all steps required to ensure that the Project complies with the applicable laws and regulations of the Borrower and with the Safeguard Policy Statement.
Loan 3007, Schedule 5, para 8
Work has not yet commenced on the feasibility studies for the sub-projects.
Social
11 The Borrower shall ensure that the GAP is fully implemented and that all Project related activities are designed and implemented in accordance with ADB's Policy on Gender and Development (1998). In particular, the Borrower shall ensure: (a) 50% female membership in community construction sub-committees; (b) 40% female employment as unskilled laborers in Works; (c) 30% female in management positions in farmer cooperatives and farmer water user's committees; (d) 50% female farmers in pilot on farm trials and demonstrations and pilot crop insurance schemes; and (e) 50% female trainees in all Project training.
Loan 3007, Schedule 5, para 13
GAP is being updated as a part of the QPRs
12 The Borrower shall ensure that Project Provinces promote active community awareness and stakeholder participation in the design, implementation and
Loan 3007, Schedule 5, para 17
Work has not yet commenced on the feasibility studies for the sub-projects.
Annex 9
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q1 2016
54
SN Covenant Reference in Loan / Grant
Agreement Status as of Q1 2016
performance monitoring of the Subprojects, though (a) disseminating information regarding the nature of the Subprojects in open public forums, and (b) establishing a mechanism for public consultation.
Sector
13 The Borrower shall: (a) ensure that all policy actions adopted under the Program as set forth in the Policy Letter and the policy matrix continue to be in effect for the duration of the Program and subsequently; and (b) adopt all policy actions under the Program, as set forth in the Policy Letter and the policy matrix, in accordance with the planned schedule and shall ensure that such policy actions continue to be in effect for the duration of the Program and subsequently.
Loan 3006, Schedule 4, para 2
Work on completion of the policy documents for compliance with June 30 deadline is not yet completed.
14 The Borrower shall keep ADB informed of policy discussions with other multilateral and bilateral aid agencies that may have implications for the implementation of the Program and shall provide ADB with an opportunity to comment on any resulting policy proposals. The Borrower shall take into account ADB's views before finalizing and implementing any such proposal.
Loan 3006, Schedule 4, para 3
Work on completion of the policy documents for compliance with June 30 deadline is not yet completed.
15 The Borrower shall ensure that the Counterpart Funds are used to finance the structural adjustment costs relating to the implementation of the reforms under the Program and other activities consistent with the objectives of the Program. The Borrower shall further ensure that the Counterpart Funds are used in accordance with its Standard Operating Procedures.
Loan 3006, Schedule 4, para 4
Work on completion of the policy documents for compliance with June 30 deadline is not yet completed.
16 The Borrower shall ensure that each contract for Eligible Items is awarded on the basis of the purchaser's normal commercial procurement practices in the case of procurement by the private sector, or the Borrower's prescribed procurement procedures in the case of procurement by the public sector, having due regard for principles of economy and efficiency.
Loan 3006, Schedule 4, para 5
Work on completion of the policy documents for compliance with June 30 deadline is not yet completed.
17 The Borrower shall, and shall cause MEF, MAFF, MLMUPC and MIME to, (a) comply with ADB's Anticorruption Policy (1998, as amended to date) and acknowledge that ADB reserves the right to investigate directly, or through its agents, any alleged corrupt, fraudulent, collusive or coercive practice relating to the Program; and (b) cooperate with any such investigation and extend all necessary assistance, including access to all relevant books and records, for satisfactory completion of such investigation.
Loan 3006, Schedule 4, para 6
Work on completion of the policy documents for compliance with June 30 deadline is not yet completed.
Others
18 The Borrower and MEF shall ensure that the Project is implemented in accordance with the detailed arrangements set forth in the PAM. Any subsequent change to the PAM shall become effective only after approval of such change by the Borrower and ADB. In the event of any discrepancy between the PAM and this Loan Agreement, the provisions of this Loan Agreement shall prevail.
Loan 3007, Schedule 5, para 1
Work on revision of the PAM will commence in Q2 led by the PIC team.
19 a) The Borrower shall maintain, or cause to be maintained, records and documents adequate to identify the Eligible Items financed out of the proceeds of the Loan and to record the progress of the Program. (b) The Borrower shall enable ADB's representatives to inspect any relevant records
Loan 3006, Article 4, para 2
PMO will introduce recording systems for all IAs to ensure that all relevant information is recorded.
Annex 9
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q1 2016
55
SN Covenant Reference in Loan / Grant
Agreement Status as of Q1 2016
and documents referred to in paragraph (a) of this Section
20 (a) As part of the reports and information referred to in Section 6.05 of the Loan Regulations, the Borrower shall furnish, or cause to be furnished, to ADB all such reports and information as ADB shall reasonably request concerning (i) the Counterpart Funds and the use thereof; and (ii) the implementation of the Program, including the accomplishment of the targets and carrying out of the actions set out in the Policy Letter, (b) Without limiting the generality of the foregoing or Section 6,05 of the Loan Regulations, the Borrower shall furnish, or cause to be furnished, to ADB quarterly reports on the carrying out of the Program and on the accomplishment of the targets and carrying out of the actions set out in the Policy Letter.
Loan 3006, Article 4, para 3
PMO will introduce recording systems for all IAs to ensure that all relevant information is recorded.
21 The Borrower shall enable ADB's representatives to inspect the Project, the Goods and Works, and any relevant records and documents.
Loan 3007, Article 4, para 3
PMO will introduce recording systems for all IAs to ensure that all relevant information is recorded.
22 The Recipient shall enable ADB's representatives to inspect the Project, the Goods and Works, and any relevant records and documents.
Grant 0349, Article 4, para 3
PMO will introduce recording systems for all IAs to ensure that all relevant information is recorded.
23 The Recipient shall enable ADB's representatives to inspect the Project, the Goods and Works, and any relevant records and documents.
Grant 0350, Article 4, para 3
PMO will introduce recording systems for all IAs to ensure that all relevant information is recorded.
24 The Recipient shall (a) ensure that the proceeds of the Grant are used for the purposes of the Project and not diverted for any other purpose; (b) promptly inform ADB if it becomes aware that the proceeds of the Grant are being or have been used for the purpose of any payment to a person or entity, or for import of goods, if such payment or import is prohibited by a decision of the United Nations Security Council taken under Chapter VII of the Charter of the United Nations; and (c) take necessary measures to ensure that entities to which the Recipient makes the proceeds of the Grant available comply with the provisions of this paragraph.
Grant 0349, Article 4, para 4
PMO will introduce recording systems for all IAs to ensure that all relevant information is recorded.
25 The Borrower shall make available necessary budgetary and human resources to fully implement each EMP and RP.
Loan 3007, Schedule 5, para 9
PMO will introduce recording systems for all IAs to ensure that all relevant information is recorded.
26 The Borrower shall ensure that all bidding documents and contracts for Works contain provisions that require contractors to: (a) comply with the measures relevant to the contractor set forth in each lEE, EMP and RP, and any corrective or preventative actions set forth in a Safeguards Monitoring Report; (b) make available a budget for all such environmental and social measures; (c) provide the Borrower with a written notice of any unanticipated environmental or resettlement risks or impacts that arise during construction, implementation or operation of the Project that were not considered in each lEE, EMP and RP; (d) adequately record the condition of roads, agricultural land and other infrastructure prior to starting to transport materials and construction; and (e) fully reinstate pathways, other local infrastructure, and agricultural land to at least their pre-project condition upon the completion of construction.
Loan 3007, Schedule 5, para 10
PMO will introduce recording systems for all IAs to ensure that all relevant information is recorded.
Annex 9
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q1 2016
56
SN Covenant Reference in Loan / Grant
Agreement Status as of Q1 2016
27 The Borrower shall do the following: (a) submit semi-annual Safeguards Monitoring Reports to ADB and disclose relevant information from such reports to affected persons promptly upon submission; (b) if any unanticipated environmental and/or social risks and impacts arise during construction, implementation or operation of the Project that were not considered in each lEE, EMP and RP, promptly inform ADB of the occurrence of such risks or impacts, with detailed description of the event and proposed corrective action plan; and (c) report any actual or potential breach of compliance with the measures and requirements set forth in an EMP or RP promptly after becoming aware of the breach.
Loan 3007, Schedule 5, para 11
Work has not yet commenced on the feasibility studies for the sub-projects.
28 The Borrower shall ensure that no proceeds of the Loan are used to finance any activity included in the list of prohibited investment activities provided in Appendix 5 of the Safeguard Policy Statement.
Loan 3007, Schedule 5, para 12
Work has not yet commenced on the feasibility studies for the sub-projects.
29 The Borrower shall ensure that candidate subprojects in each Project Province are considered and feasibility studies and detailed design of such candidate subprojects are carried out in the order of priority indicated in the List of Candidate Subprojects.
Loan 3007, Schedule 5, para 14
Work has not yet commenced on the feasibility studies for the sub-projects.
30 After completion of the requisite feasibility studies, the Borrower shall cause the PMO to ascertain whether the candidate subprojects meet the following criteria to be eligible for financing under the Project: (a) a subproject should be technically feasible and economically viable. If the estimated economic rate of return is below 12%, other significant benefits shall be quantified to demonstrate economic viability of such subproject; (b) procurement package(s), method(s) of procurement and cost estimates shall have been prepared; (c) a detailed financing plan for operation and maintenance of the subproject shall have been prepared: (i) identifying the entity which shall be responsible for the operation and maintenance of the subproject; and (ii) confirming the Project Province's commitment though budgetary allocation to provide requisite funds needed for the operation and maintenance of the subproject; (d) public hearings on a subproject proposal shall have been held in concerned communes and villages, and beneficiary representatives shall have been included in the subproject implementation subcommittee to ensure continued public consultation and supervision; (e) the subproject must be shown to have no significant negative environmental or social impacts, and mitigation measures shall have been identified for minor impacts; (f) the subproject must be shown to have no significant resettlement impacts, and if such subproject Is categorized as Category B, a RP has been prepared in accordance with the RF, the Borrower's laws and regulations and the Safeguard Policy Statement; and (g) the subproject must be shown to have no outstanding social safeguards issues resulting from existing facilities. In case there are any such outstanding issues, the
Loan 3007, Schedule 5, para 15
Work has not yet commenced on the feasibility studies for the sub-projects.
Annex 9
CLIMATE RESILIENT RICE COMMERCIALISATION SECTOR DEVELOPMENT PROGRAM Quarterly Progress Report Q1 2016
57
SN Covenant Reference in Loan / Grant
Agreement Status as of Q1 2016
Borrower shall ensure that the PIO concerned shall have prepared a corrective action plan in accordance with the Safeguard Policy Statement to address the same.
31 In case that a candidate subproject does not meet the criteria provided in paragraph 15 above, it shall be replaced by the next priority candidate subproject for the respective Project Province under the List of Candidate Subprojects. If a candidate subproject not listed in the List of Candidate Subprojects is to be considered, such subproject shall be examined and screened by MEF with the support from an independent consultant acceptable to ADB and the Borrower and submitted to ADB for approval.
Loan 3007, Schedule 5, para 16
Work has not yet commenced on the feasibility studies for the sub-projects.
32 Within 12 months of the Effective Date, the Borrower shall cause MEF to engage a suitably qualified and experienced social science institute, university, consulting firm or a non-governmental organization, acceptable to ADB, to monitor Project benefits and submit annual benefit monitoring reports to the Borrower and ADB.
Loan 3007, Schedule 5, para 18
Not due yet.
33 The Borrower shall and shall cause MEF, MAFF, MOWRAM, MLMUPC and the Project Provinces to (a) comply with ADB's Anticorruption Policy (1998, as amended to date) and acknowledge that ADB reserves the right to investigate directly, or through its agents, any alleged corrupt, fraudulent, collusive or coercive practice relating to the Project; and (b) cooperate with any such investigation and extend all necessary assistance, including access to all relevant books and records, as may be necessary for the satisfactory completion of any such investigation.
Loan 3007, Schedule 5, para 19
Not due yet.
34 The Borrower shall and shall cause MEF, MAFF, MOWRAM, MLMUPC and the Project Provinces to ensure that the anticorruption provisions acceptable to ADB are included in all bidding documents and contracts, including provisions specifying the right of ADB to audit and examine the records and accounts of MEF, MAFF, MOWRAM, MLMUPC, Project Provinces and all contractors, suppliers, consultants, and other service providers as they relate to the Project.
Loan 3007, Schedule 5, para 20
Not due yet.