Durchführer
Provision of Potable
Water and Effluents
Treatment in Paraguay -
Investment Projects and
Legal Framework
Durchführer
ESSAP S.A.: Company of Sanitation Service of
Paraguay S.A.Mission: provide potable water and sewerage continuously and
efficiently, offering quality service, transparency and honesty, committed
to improving the quality of life of the population and the preservation of
the environment
Antecedent: Born on October 26, 1954 under the name CORPOSANA
originally, with the aim to develop projects, construction, operation and
management of the works and the potable water and sewerage services
from the city of Asunción, and since 1966 for all republic.
On April 1, 2002 within the process of transformation of state enterprises,
the legal concept is changed, and renamed ESSAP SA, with a
shareholding of 99.9% of the Paraguayan State and 0.1% of FEPASA.
Durchführer
• Law Nº 1614/00 "General of the Regulatory Framework ...", by
which is set all the requirements to be met by providers and users
of potable water and sewerage systems.
• Law Nº 2051/03 “of Public Procurement”, whereby is established
the regime procurement of goods, services and works with state
agencies.
• Additionally, should enforce labor law, civil, environmental, tax
laws and other regulations in force in the Republic of Paraguay
applicable to state agencies and corporations.
Legal Framework
Durchführer
Law Nº 5396/15
• Process with Sovereign Guaranteed of the Paraguayan State.
• For the approval process is used procedures of the National Public
Investment System.
• For the bidding process is used the Law No. 2051/03 "Public
Procurements".
• The offeror proposes its own source long-term financing as part of the
technical and financial proposal.
• The allocation is performed based on the net present value (NPV or
VPN), whereby the bids are evaluated and compare beetwen offeres,
competing in terms of amount and terms of financing.
• is required a minimum 25% of local stake in the performance of the
contract, which may be by direct participation in the consortium and /
or outsourcing of domestic firms.
Durchführer
Government target for 2018
-10%
0%
10%
20%
30%
40%
50%
60%
1989 1993 1998 2003 2008 2013 2018
5% 4% 4%8%
15%11%
8%
Proyeccion de Cobertura en Saneamiento
1989
1993
1998
2003
2008
2013
2018
Projection of Coverage in sanitation
Durchführer
Priority Works and Financing Sources
• 3 (three) invesment with
started process.
• 6 (six) in Managing Projects
and/or Financing sources
Durchführer
1. Construction and Extension of Sanitary Sewer System and
Construction of Wastewater Treatment Plants in the Lambare, Luque,
M.R. Alonso Basin
Summary of
works:Collecting Network Building (Primary,
Secondary and Tertiary); Pumping Stations and
Lines Drive; two Wastewater Treatment plants;
Support to Operations Management.
Beneficiary
Population:
1.600.000 residents (projecting until the year
2045).
Invesment
Amount:US$ 425.000.000.-
Project
Design:It contains an Advanced Draft, Project
Executive is responsible for the company to be
awarded.
Status: In process of evaluation of Prequalification
delivered on 01/04/2015.
Licitacion
Modality:International public process with financing
(Law Nº 2051+Law Nº5074)
Durchführer
2. Execution of Filling the Site and Construction of Housings Affected by
the Relocation of the Construction of Wastewater Treatment Plant in the
Bella Vista and Itay Basin. Includes: Filling the site, housings
construction and subfluvial emmisary.
Beneficiary
Population:
425.000 residents
Invesment
Amount:
US$ 20.000.000.-
Project Design: Executive Project (since Año 2014)
Funding
source:
Loan BIRF 7710-PA
Licitation
Process:
International Public Process
Estatus: In evaluation process of the offers
delivered on March 25.
Durchführer
3. Total Sanitation Program of the Asuncion Bay and the Expansion and Improvement
Program of Sanitary Sewerage System of Asuncion. It includes the Construction of 3
(three) TPWW (Varadero, Bella Vista and San Lorenzo.).
Summary of
works
1) Collecting Rehabilitation and Improvement
Networks in Basin Varadero and Bella Vista
(downtown of Asunción and vicinity); 2)
Expansion and Improvement of collector
networks in the San Lorenzo (area of influence
of Lake Ypacarai); 3) Construction of three
Wastewater Treatment Plant.
Beneficiary
Population:
805.000 residents (projecting until the year
2045).
Invesment
Amount:
US$ 110.000.000.-
Project Design: Executive Project in final stage of design
(Donation of the IADB).
Funding source: Loan of the Interamerican Development Bank
(IADB).
Estatus: in the process of parliamentary approval
Durchführer
4. Construction of the Integrated Potable Water System and Sanitary Sewer
Systems of Ciudad del Este, Hernandarias, Pte. Franco and Minga Guazú –Alto
Paraná Region.
Summary of
Works:
Potable Water: Water Treatment Plant, main
wáter pipes, impulsion, Distribution Centers and
distribution network.
Sanitation Sewerage: Collector Network Primary,
Secondary and Tertiary; Pumping Station y
Impulsion lines; Treatment Plant of Waste Water.
Beneficiary
Population:
1.500.000 residents.
Invesment Amount: US$ 500.000.000.
Status Advanced Draft projecto in running by ESSAP with
funds provide by Itaipú Binacional.
Funding source: International public process with financing
(Law Nº 2051+Law Nº5074)
Durchführer
Map of the Project of Water System of Alto Paraná.
Durchführer
Map of the Project of Sewerage System for Alto Parana.
PTAR 1
PTAR 3
PTAR 4
PTAR 7
PTAR 6PTAR 5
PTAR 2
• 7 (seven) Treatment Plants of Waste Water
•Pumping Station
•Impulsion lines
•Collector networks
Durchführer
5. Construction of the Sanitary Sewer System and Treatment Plant
of Waste Water of the Yukyry Stream Zone.
Beneficiary
Population:
230.000 residents
Invesment
Amount:
US$ 110.000.000.-
Project
Design:
Without project.
Funding
source:
International public process
with financing
(Law Nº 2051+Law Nº5074)
Estatus: Itaipu has started the bidding
process for procurement of
Consulting Services for the
Preparation of the Design
Project (Draft Advanced)
Aº Yukyry
Proyecto:
1°stage: TPWW for treatment of the water of Yukyry stream
2°stage: receive and treat the wastewater of Stream Yukyry basins and sub basins
Durchführer
6. Construcción de Planta de Tratamiento de Agua Potable de
Piquete Cué. (cobertura de zona Limpio y M.R. Alonso y
Emboscada).
Beneficiary
Population:
230.000 residents
Invesment
Amount:
US$ 130.000.000.-
Project Design: Without project.
Funding source: International publica process
with financing
(Law Nº 2051+Law Nº5074)
Estatus: Stage of Project definition and
funding source.
Durchführer
Components to be Built:
Treatment Plant Water on Piquete Cue,
Distribution Center (D.C.) and water mains
pipes.
Durchführer
7. Construction of two Potable Water Treatment Plant over
Tebicuary River. (Caazapá, Maciel, Bertoni, Iturbe, Yuty, Yegros,
Leandro Oviedo and San Pedro del Paraná).
Beneficiary
Population:
65.000 residents
Invesment
Amount:
US$ 180.000.000.-
Project
Design:
Without project.
Funding
source:
International publica process with
financing
(Law Nº 2051+Law Nº5074)
Estatus: Stage of Project definition and
funding source.
Durchführer
Beneficiary
Population:
45.000 residents
Invesment
Amount:
US$ 50.000.000.-
Project Design: Without project.
Funding source: International publica process
with financing
(Law Nº 2051+Law Nº5074)
Estatus: Stage of Project definition and
funding source.
8. Construction of Potable Water
Treatment Plant on Puerto Triunfo
(Victory Harbor). (Natalio, Yatytay and
Ma.Auxiliadora).
Durchführer
9. Construction of Treatment Plant of Potable Water on Puerto Antequera
(Antequera Harbor). ( Puerto Antequera and San Pedro de Ycuamandiyu).
Beneficiary
Population:
30.000 residents
Invesment
Amount:
US$ 50.000.000.-
Project Design: Without project.
Funding source: International publica process with
financing
(Law Nº 2051+Law Nº5074)
Estatus: Stage of Project definition and
funding source.
Durchführer
Summary of Priority Works on Water and Sanitation.
Item DenominationBeneficiary
Population:
Invesment AmountUS$
1Construction and Extension of Sanitary Sewer System and Construction of
Wastewater Treatment Plants in the Lambare, Luque, M.R. Alonso Basin1.600.000 425.000.000
2
Execution of Filling the Site and Construction of Housings Affected by the
Relocation of the Construction of Wastewater Treatment Plant in the Bella
Vista and Itay Basin. Includes: Filling the site, housings construction and
subfluvial emmisary.
425.000 20.000.000
3
Total Sanitation Program of the Asuncion Bay and the Expansion and
Improvement Program of Sanitary Sewerage System of Asuncion. It includes
the Construction of 3 (three) TPWW (Varadero, Bella Vista and San
Lorenzo.).
805.000 110.000.000
4
Construction of the Integrated Potable Water System and Sanitary Sewer
Systems of Ciudad del Este, Hernandarias, Pte. Franco and Minga Guazú –
Alto Paraná Region.1.500.000 500.000.000
5Construction of the Sanitary Sewer System and Treatment Plant of
Waste Water of the Yukyry Stream Zone. 230000 110.000.000
6Construcción de Planta de Tratamiento de Agua Potable de Piquete
Cué. (cobertura de zona Limpio y M.R. Alonso y Emboscada). 230.000 130.000.000
7
Construction of two Potable Water Treatment Plant over Tebicuary
River. (Caazapá, Maciel, Bertoni, Iturbe, Yuty, Yegros, Leandro
Oviedo and San Pedro del Paraná). 65.000 180.000.000
8Construction of Potable Water Treatment Plant on Puerto Triunfo
(Victory Harbor). (Natalio, Yatytay and Ma.Auxiliadora). 45.000 50.000.000
9Construction of Treatment Plant of Potable Water on Puerto Antequera
(Antequera Harbor). ( Puerto Antequera and San Pedro de Ycuamandiyu).30.000 50.000.000
Totales 4.930.000 1.575.000.000
Durchführer
The price of Potable Water Service on Paraguay