Download - Project management wtp pattuvam scheme feb 10 v2

Transcript
Page 1: Project management wtp pattuvam scheme feb 10 v2

Project Management of Project Management of Water Supply ProjectWater Supply ProjectCapacity: 93 MLD Cost: USD 80 MillionCapacity: 93 MLD Cost: USD 80 Million

Chandra DissanayakeChandra DissanayakeSenior Resident EngineerSenior Resident Engineer

Tokyo Engineering Consultants Co Ltd

Pattuvam Scheme, Kerala, IndiaPattuvam Scheme, Kerala, India

February 2010February 2010

Page 2: Project management wtp pattuvam scheme feb 10 v2

The state has been able to provide water to 79% of the urban and 59% of the rural population and efforts are being made to cover the rest of the population.

Accordingly a very ambitious project known as Kerala Water Supply Project (KWSP) was derived with support of International Corporation - Japan International Corporation Agency (JICA). Five Schemes under KWSP:

•Trivandrum

•Meenard

•Cherthala (Kollam)

•Kozhikode (Calicut)

•Pattuvam (in Kannur District)

KERALA WATER SUPPLY PROJECT (KWSP) & PATTUVAM SCHEME

Page 3: Project management wtp pattuvam scheme feb 10 v2

KERALA WATER SUPPLY PROJECT (KWSP)

• The Government of India is the borrower and the Kerala Water Authority is the executing Agency. This Project aims at rehabilitating and augmenting the water supply systems of two urban regions namely Kozhikode and Thiruvananthapuram and to construct new water supply systems for three rural regions namely, Pattuvam of Kannur district, Cherthala of Alappuzha district and Meenad of Kollam district. Pattuvam Scheme is the north most beneficial area from this massive project.

• The international consultants M/s TEC consortium (with Black & Veatch, GKW, STC, CED) led by M/s Tokyo Engineering Consultants Company Ltd (TEC). Japan has been selected by the KWA to manage the implementation of the project.

Page 4: Project management wtp pattuvam scheme feb 10 v2

Pattuvam Scheme

KERALA WATER SUPPLY PROJECT (KWSP) & PATTUVAM SCHEME

Kerala is a state located in southwestern India. Neighboring states include Karnataka to the north and Tamil Nadu to the south and east, and the Arabian Sea is to the west. Major cities include the state capital of Trivandrum (Thiruvanaputhram), Kollam, Cochin, Calicut (Kozhikode) and Kannur (Cannore).

Kozhikode Scheme

Cherthala Scheme

Meenard Scheme

Trivandrum Scheme

Page 5: Project management wtp pattuvam scheme feb 10 v2
Page 6: Project management wtp pattuvam scheme feb 10 v2

The Pattuvam Scheme is in Kannur District is the northern most area benefits with the KWSP. The objective of the scheme is to supply safe and potable water to 530,000 consumers in 10 villages, 7 semi-urban areas and 1 municipality in the Kannur District by constructing new facilities. Facilities include technical components for water abstraction, raw water transmission, water treatment, treated water transmission, storage reservoirs and distribution networks.

The project area covers 350 km2 and the water demand of the area is estimated as 93 MLD. The source is at Pazhassi Barrage at Valapattanam River at Kuiloor and the method of extraction is by intake well. The raw water is boosted through steel pipe of 1100 mm diameter for a length of 11 km, to the Treatment Plant. The capacity of the Treatment Plant located at Peruvalathuparamba is 93 millions liters per day.

PATTUVAM SCHEME

Page 7: Project management wtp pattuvam scheme feb 10 v2

Pattuvam Scheme PackagesPackage Description Contractor Cost

Ind Rs Million

Cost USD

Million

1 Intake, Raw Water Main, WTP

Kiriloskar Brothers, Pune

1,109 28

2 Transmission Main & Associated Work

SPML, Bangalore 1,219 27

3 Distribution Systems KRKCPL, Hydarbard

650 17

4 Service Reservoirs IVRCL, Hydrabard 395 8

Overall 3,349 80

Page 8: Project management wtp pattuvam scheme feb 10 v2

PROJECT MANAGEMENT

The Client, Kerala Water Authority has appointed Tokyo Engineering Consultants Co Ltd (TEC) as the leading consultant – The Engineer – to implement the project. The Pattuvam Scheme is led by highly experienced Senior Resident Engineer (SRE), Chandra Dissanayake who acts as Engineer’s Representative. He is supported by a project team of 36 personnel including four experienced Site Engineers. The SRE is responsible for managing the day-to-day work of the project: Construction supervision, project management, progress

monitoring and reporting, quality control, verification of contractor’s invoices etc.

Lead the construction supervision team set for the package. Liaison with the Consultant’s main office (Project Manager),

Contractors and Client for the performance of the assigned contract package.

Page 9: Project management wtp pattuvam scheme feb 10 v2

Site EngineerPackage 1

Site EngineerPackage 2

Site EngineerPackage 3

Site EngineerPackage 4

Junior Inspectors

4

Senior Inspector

Junior Inspectors

4

Senior Inspector

Junior Inspectors

4

Senior Inspector

Junior Inspectors

4

Senior Inspector

Admin & Support StaffOffice ManagerComputer Assistant – 2 NosOffice Assistant – 2 NosOffice Attendant– 2 NosDrivers – 5 Nos

Senior Resident EngineerChandra Dissanayake

Project Management Structure

Tokyo Engineering Consultants Co., Ltd. Japan

Page 10: Project management wtp pattuvam scheme feb 10 v2

Project Highlights• About 1,000,000 cubic meters of earthwork; 720 kilometres of

pipelines; 25,000 cubic meters of concrete and 2000 tonnes of steel. Total project value is USD80 Million.

• The project is unique in its nature and complexities, characterised by its spread across a large area. In view of the massiveness of the project and the complexities in the nature of the work components, it is a challenge and however essential and important for the Senior Resident Engineer to put in place a comprehensive project management, supervision, quality assurance and control during the implementation.

• The Project is being executed following a fast track approach.

Page 11: Project management wtp pattuvam scheme feb 10 v2

Pattuvam SchemeST1 ST2 SHT

FILTER

FHWW H

OHT

CB

KoonamTank I

KoonamTank II

CWT

CCT

P3

P2

P1

P4

CF

1200 dia MS pipe 22km

INTAKE

TRANSMISSION MAIN 80 km

DISTRIBUTION SYSTEM

SERVICE RESERVOIRS

SL

PB 1PB 2

1100 dia MS pipe 22km

630 Km pipelines

WTP 93 MLD

Pazhassi Dam

A

Serve for population of 530,000

Reservoir Capacity - 27 ML

Page 12: Project management wtp pattuvam scheme feb 10 v2

Package 1

Component Details

Intake Pump-well, Intake-well, Connecting pipeline & Buildings

Raw Water Main (supply & laying)

11 km 1118 mm dia MS Pipeline

WTP Various treatment structures & staff buildings

Page 13: Project management wtp pattuvam scheme feb 10 v2

Intake

Intake well & intake houseFoot bridgePump well & pump houseConduits for intakeRaw water pumps, surge vessel & pipingStaff housingSub station for intake

Page 14: Project management wtp pattuvam scheme feb 10 v2

Intake Model

Page 15: Project management wtp pattuvam scheme feb 10 v2

SRE’s Instruction on building coffer dam around Intake in late 2007

Page 16: Project management wtp pattuvam scheme feb 10 v2

Senior Resident Engineer discusses with Hon Minister for Water Resources on Construction Program of Intake in early 2008

Page 17: Project management wtp pattuvam scheme feb 10 v2

Intake site February 2008

Page 18: Project management wtp pattuvam scheme feb 10 v2

Intake site on January 2010

Page 19: Project management wtp pattuvam scheme feb 10 v2

Raw Water Pumping Main

11 km long mild steel pipeline from Intake to Water Treatment Plant

Page 20: Project management wtp pattuvam scheme feb 10 v2

Pipe-bridge on raw water pipeline

Page 21: Project management wtp pattuvam scheme feb 10 v2

Water Treatment Plant

Page 22: Project management wtp pattuvam scheme feb 10 v2

Water treatment Plant StructuresStructure NameRaw water Inlet/Cascade Aerator & Magnetic flow meter chamber

Lamella Clarifiers& Flocculators

Rapid Gravity Sand Filters

Filter control building

Used wash water holding tank

Chlorine contact tank & Treated Water Reservoir

Treated water pumping station

Balancing reservoir

Chemical Building

Chlorine building

Sludge balancing tank & pump house

MCC

Sludge Thickener

Sludge Lagoons

Roads, Compound, Landscaping

Staff housing

Page 23: Project management wtp pattuvam scheme feb 10 v2

Water treatment plant site on January 2007

Page 24: Project management wtp pattuvam scheme feb 10 v2

Water treatment plant on February 2010

Page 25: Project management wtp pattuvam scheme feb 10 v2

SRE with Team Leader, Site Engineer and Construction Manager

Page 26: Project management wtp pattuvam scheme feb 10 v2

Tiling on Aerator

Page 27: Project management wtp pattuvam scheme feb 10 v2

SRE with Senior Inspector on Balancing Reservoir

Page 28: Project management wtp pattuvam scheme feb 10 v2

Flocculaters, Clarifiers, Wash-water holding tank

Page 29: Project management wtp pattuvam scheme feb 10 v2

Clear water reservoir

Page 30: Project management wtp pattuvam scheme feb 10 v2

EOT Crane at pump-station

Page 31: Project management wtp pattuvam scheme feb 10 v2

Electrical panels in pump-station

Page 32: Project management wtp pattuvam scheme feb 10 v2

Balancing reservoir

Page 33: Project management wtp pattuvam scheme feb 10 v2

Vintage point – From the roof top of the balancing reservoir

Page 34: Project management wtp pattuvam scheme feb 10 v2

Access road to WTP

Page 35: Project management wtp pattuvam scheme feb 10 v2

Package 2

Transmission Main & Associated Work

From the Clear Water Reservoir at the WTP the water flows by gravity to the Master Balancing Reservoir at Koonam from where it flows to 7 zonal reservoirs and through 2 booster pumping stations to 5 zonal reservoirs. The total length of transmission main is 82 km.

Page 36: Project management wtp pattuvam scheme feb 10 v2

Package 2

Description Quantity

MS pipeline 25km

DI pipeline 50km

uPVC & PE pipeline 6km

Pipe bridges 4nos

Buildings & Associated Works

Page 37: Project management wtp pattuvam scheme feb 10 v2

KOONAM MBR

W.T.P. + BPT

Paddy field-below ground pipes

VALAKAI RIVER

POOMANGALAMRIVER

MS PIPESTWTM-

TALIPARAMBA-IRIKKURKSTP ROAD

MS 1219mm OD

MS 1118mm&1067mm OD

MALPPATTAMSREEKANDAPURAM

IRIKKUR

MALAPPATTAM ROAD

POKKUNDU

CHENGALAI RIVER

CHENGALAI BRIDGE

VALAKAI BRIDGE

10

2

7

54

3

9

8

6

10

1112

13141516

17

18

19

20

21

POOMANGALAM BRIDGE

MSPIPE LAID

FSL-158.80

MWL-138.90

LWL-150.90

LWL-135.00

PACKAGE II-

25.1

Length(KM) Laid(KM)

24.07

KANJIRANGADU JN. .

13m13m

18.20m 19.30m

24.00m24.00m24.00m

Gap 1WTP- KSTP Road

Gap 2Test gap

Gap 3KSTP-Kaniyar vayalroad crossing

Test gap Gap 4

Gap 5PKM CollegeRoad crossing +above ground

Gap 6Chengalai bridge

Gap 7Cherankunnu-Narikkalbreaking

Gap 8KSTP Road+ Valakkairoad crossing

Gap 9Above Ground + Belowground Valakkai

Gap 1074.4m on hold due to thedispute at Pokkundu

Gap 11Koonam MBR Inlet

Gap 12Above grounfd- Below groundPoomangalam Bridge

StreamOn pedestals

Below ground

119m

486m

Gap 9

Gap 5

96m

22m 21m

WTP to Koonam MBR

Koonam to Kanjirangad

Total

Balance(KM)

4.4

20.7

4.33

19.74 0.96

0.1

1.03

Page 38: Project management wtp pattuvam scheme feb 10 v2

KALLIASSERIMBR + OHSR

KARAKUNNU OHSR

KANNOM OHSR

KUZHICHAL OHSR

KARAKKUNDU OHSR

FROM KOONAM MBR

NADUKANIBPT + OHSR

MADAKKADU GLSR

ODUVALLITHATTU OHSR

MADAMTHATTU OHSR

ADIIKKAMPARA OHSR

KANJIRANGADOHSR

s

KARIKKAPPARA OHSR

KANJIRANGAD BPS

s

DI,uPVC &PE PIPESTWTM-PACKAGE II-

CHAPPARAPPADAV BRIDGE

DHARMASALA

MANNA JN.

INDEX

PIPE LAID

TALIPARAMBA-IRIKKURKSTP ROAD

TALIPARAMBA-COORGEROAD

KUPPAM RIVER UNDERWATER CROSSING

12

DI

uPVC

50.34

PE3

Sl No. Pipe Length (Km)

3.942.91

Laid (Km)

44.38

2.34

2.53

13m 21.433m 21.433m 21.433m

KUPPAM JN.

Balance (Km)

5.96

1.60

0.38

1 2

34

5

6

7

8

9

10

11

1213

14

15

16

17

18 19

20

21

22

23

24

2526

2728

29

Page 39: Project management wtp pattuvam scheme feb 10 v2

Valakkai Pipe Bridge

Page 40: Project management wtp pattuvam scheme feb 10 v2

MS Pipeline Laying along Highway

Page 41: Project management wtp pattuvam scheme feb 10 v2

Chengali pipe-bridge steel trusses

Page 42: Project management wtp pattuvam scheme feb 10 v2

Pipeline on pedestal at Valakkai

Page 43: Project management wtp pattuvam scheme feb 10 v2

Chapparapadawu pipe-bridge

Page 44: Project management wtp pattuvam scheme feb 10 v2

Package 3

Distribution System

Page 45: Project management wtp pattuvam scheme feb 10 v2

Package 3The project area has been divided in to 21 major distribution zones to be served by 1 Master Balancing Reservoir (MBR) and 12 zonal reservoirs. The total length of distribution network is 625 km.

– DI pipeline of 150-500mm dia 56 km– uPVC pipes of 75-280mm dia 428 km.– PE pipes 90 &110mm dia 139km

Page 46: Project management wtp pattuvam scheme feb 10 v2

Laying distribution pipeline (PE) on countryside

Page 47: Project management wtp pattuvam scheme feb 10 v2

Special Machinery for hard latraite excavation in trenches

Page 48: Project management wtp pattuvam scheme feb 10 v2

Special Machinery – smaller versions for narrow rural roads

Page 49: Project management wtp pattuvam scheme feb 10 v2

Package 4

Service Reservoirs

Page 50: Project management wtp pattuvam scheme feb 10 v2

Package 4

From Master Balancing Reservoir at Koonam water flows to 7 zonal reservoirs and through 2 booster pumping stations to 5 zonal reservoirs.

– Over Head Service Reservoirs 12 – Ground Level Service Reservoirs 1

Page 51: Project management wtp pattuvam scheme feb 10 v2

Package 4 ReservoirsKoonam (Tank I) – 3.18MLKoonam (Tank II) – 2.62MLKanjirangadu – 0.59MLKarikkapara – 0.92MLKalliasseri – 3.78MLKuzhichal – 2.75MLAdikampara – 4.18MLOduvallithattu – 0.26MLNadukani – 1.17MLMadamthatta – 1.18MLKarakundu – 1.95MLKarakunnu – 3.33MLKannom – 0.91MLMadakkadu – 0.26MLAdministrative BuildingsStaff Quarters

Page 52: Project management wtp pattuvam scheme feb 10 v2

Koonam Twin Reservoirs Capacity: 6 ML Height from the ground: More than 20m

Page 53: Project management wtp pattuvam scheme feb 10 v2

Karikapara Reservoir

Page 54: Project management wtp pattuvam scheme feb 10 v2

Adikampara Reservoir

Page 55: Project management wtp pattuvam scheme feb 10 v2

Oduwalaththatta Reservoir

Page 56: Project management wtp pattuvam scheme feb 10 v2

END