Professional Development Learning Event – 27 March 2007
1
Using Earned Value Analysis
Professional Development Learning Event – 27 March 2007
2
Why Do I Need It ?
What Is It ?
How Do I Do It?
Earned Value
Professional Development Learning Event – 27 March 2007
3
Today’s Situation
Need for accurate and consistent status information
Numerous complex (and interrelated) projects Projects with many WBS activities
Virtual offices
Diverse technology platforms
Professional Development Learning Event – 27 March 2007
4
There’s Room For Improvement
70% of projects are:• Over budget• Behind schedule
52% of all projects finish at 189% of their initial budget
And some, after huge investments of time and money, are simply never complete
Source:The Standish Group
Professional Development Learning Event – 27 March 2007
5
Earned Value Analysis (EVA)
• “Earned Value Analysis” is:• an industry standard way to:
•measure a project’s progress where direct measures cannot be used
•Predict future performance, and•provide schedule and budget variances
along the way
• By integrating three measurements, it provides consistent, numerical indicators with which you can evaluate and compare projects.
Professional Development Learning Event – 27 March 2007
6
EVA – the three elements
It compares the PLANNED amount of work with what has actually been COMPLETED, to determine if Cost , Schedule, and Work accomplished are progressing as planned.
Work is “Earned” or credited as it is completed.
Professional Development Learning Event – 27 March 2007
7
Earned Value is needed because...
Provides an “Early Warning” signal for prompt corrective action.
Bad news does not age well.
Still time to recover
Timely request for additional funds
Professional Development Learning Event – 27 March 2007
8
Earned Value Management EVolution
1959 US DoD began looking at Milestone Charts and Rate of Expenditure Curves. 1963-64 Earned Value concept begins with the ‘Minuteman’ & ‘Titan III’ rocket programmes. 1966 USAF - Cost/Schedule Planning & Control Specification (C/SPCS). 1967 US DoD - Cost/Schedule Control Systems Criteria (CSCS2). 1972 US DoD - Issued the Joint Implementation Guide (JIG). (revisions were to follow 1976, 1980, 1987 and 1996). 1972 NASA 1975 US Dept of Environment (DoE) 1982 US National Security Agency 1989 Australian DoD 1990 Canadian DoD 1992 National Oceanic & Atmospheric Administration (NOAA) 1994 Federal Bureau of Investigation (FBI), Inland Revenue Service (IRS) 1996 JIG replaced by Earned Value Management Implementation Guide (EVMIG) (revised 1997) Present World wide implementations…….USA, Europe, Canada, Australia, Japan
Professional Development Learning Event – 27 March 2007
9
Traditional Plan vs. Actual view
• Is there a performance problem? Is it a good or bad position?
0
20
40
60
80
100
J F M A M J J A S O N D
£k
Budget
Actual
Professional Development Learning Event – 27 March 2007
10
Terminology
• BCWS - Budgeted Cost of Work Scheduled
• ACWP - Actual Cost of Work Performed
• BCWP - Budgeted Cost of Work Performed
Professional Development Learning Event – 27 March 2007
11
Earned Value Definitions
• BCWS: “Budgeted Cost of Work Scheduled”
• The planned earned value to be performed by the milestone date.
Professional Development Learning Event – 27 March 2007
12
Earned Value Definitions (cont.)
• ACWP: “Actual Cost of Work Performed”
• Actual Cost to date.
Professional Development Learning Event – 27 March 2007
13
Earned Value Definitions (cont.)
BCWP: Budgeted Cost of Work Performed
The actual earned value i.e. the value of the work performed based on its planned value
Professional Development Learning Event – 27 March 2007
14
• Establish the activities (milestones)
• Calculate a budget for each activity (milestone). What is the cost of completing the activity?
• Ideally one activity (milestone) per reporting period
• In a table, record the cumulative budget for each milestone and draw the graph
How to construct the baseline (BCWS) (planned earned value)
Professional Development Learning Event – 27 March 2007
15
How to construct the baseline (BCWS)
1 2 3 4 5 6 7 8 9 10Produce a book
Chapter 1 BCWS 10Chapter 2 BCWS 10Chapter 3 BCWS 10Chapter 4 BCWS 10Chapter 5 BCWS 10Chapter 6 BCWS 10Chapter 7 BCWS 10Chapter 8 BCWS 10Chapter 9 BCWS 10Chapter 10 BCWS 10
TOTAL BCWS 10 20 30 40 50 60 70 80 90 100
BCWS
0
20
40
60
80
100
120
1 2 3 4 5 6 7 8 9 10
BCWS
Professional Development Learning Event – 27 March 2007
16
How to score the Earned Value (BCWP) (actual earned value)
• When an activity (milestone) is achieved, the Earned Value (EV) is scored equal to its planned value
• It has nothing to do with how much you get paid
• The EV is scored in the period in which it was completed
Professional Development Learning Event – 27 March 2007
17
How to score the EV (BCWP)
1 2 3 4 5 6 7 8 9 10Produce a book
Chapter 1 BCWS 10BCWP 10
Chapter 2 BCWS 10BCWP 10
Chapter 3 BCWS 10BCWP 10
Chapter 4 BCWS 10BCWP 10
Chapter 5 BCWS 10BCWP 10
Chapter 6 BCWS 10BCWP 10
Chapter 7 BCWS 10BCWP 10
Chapter 8 BCWS 10BCWP
Chapter 9 BCWS 10BCWP
Chapter 10 BCWS 10BCWP
TOTAL BCWS 10 20 30 40 50 60 70 80 90 100TOTAL BCWP 10 10 20 20 30 70
0
20
40
60
80
100
120
1 2 3 4 5 6 7 8 9 10
BCWS
BCWP
Professional Development Learning Event – 27 March 2007
18
How to record Actual Cost (ACWP)
• Actual cost of doing the work
• This may be recorded for each activity (milestone). This is the ideal situation, but you may only have information relating to actual cost for the entire project. This is also acceptable
• You may be accumulating an actual cost in a period prior to the activity is delivered.
Professional Development Learning Event – 27 March 2007
19
How to record Actual Cost (ACWP)1 2 3 4 5 6 7 8 9 10
Produce a bookChapter 1 BCWS 10
ACWP 8BCWP 10
Chapter 2 BCWS 10ACWP 2 5BCWP 10
Chapter 3 BCWS 10ACWP 1 5 4BCWP 10
Chapter 4 BCWS 10ACWP 2 3 2BCWP 10
Chapter 5 BCWS 10ACWP 5 5BCWP 10
Chapter 6 BCWS 10ACWP 8BCWP 10
Chapter 7 BCWS 10ACWP 9BCWP 10
Chapter 8 BCWS 10ACWPBCWP
Chapter 9 BCWS 10ACWPBCWP
Chapter 10 BCWS 10ACWPBCWP
TOTAL BCWS 10 20 30 40 50 60 70 80 90 100TOTAL ACWP 8 10 16 23 35 59TOTAL BCWP 10 10 20 20 30 70
0
10
20
30
40
50
60
70
80
90
100
1 2 3 4 5 6 7 8 9 10
BCWS
ACWP
BCWP
Professional Development Learning Event – 27 March 2007
20
Earned Value (BCWP)
Actual Costs (ACWP)
PlannedCosts(BCWS)
Budget At Completion (BAC)
Time
£
Today
Graphical representation of project progress
Professional Development Learning Event – 27 March 2007
21
Exercise
Describe the status of each project using EV terminology
10 minutes
Professional Development Learning Event – 27 March 2007
22
6 examples
Today
£
Time
BCWS
BCWP
ACWP
1.
As at today, the value of the work that has been completed is greater than plan, therefore we are ahead of schedule. The actual cost of work is less than plan and also less than the BCWP. Therefore we have been doing the work very much cheaper than plan.
Today
£
Time
BCWS
ACWP
BCWP
2.
As at today, the value of the work is less than planned, therefore we are behind schedule. The actual cost of work is greater than plan and also greater than the BCWP. Therefore we have been doing the work considerably more costly than planned.
Professional Development Learning Event – 27 March 2007
23
6 examples
Today
£
Time
BCWS
BCWP
ACWP
3. 4.
Today
£
Time
BCWS
ACWP
BCWP
As at today, the value of the work is greater than planned value, therefore we are ahead of schedule. The actual cost of work is greater than plan but less than the BCWP. Therefore despite having spent more money than plan, on the work we have completed, we are doing it cheaper than the plan.
As at today, the value of the work is greater than planned value, therefore we are ahead of schedule. The actual cost of work is greater than plan and also greater than the the BCWP. Therefore as well as spending more money than planned, we are overspent on the work that we have completed.
Professional Development Learning Event – 27 March 2007
24
6 examples
Today
£
Time
BCWS
BCWP
ACWP
5. 6.
Today
£
Time
BCWS
ACWP
BCWP
As at today, the value of the work is less than planned value, therefore we are behind schedule. The actual cost of work is less than plan and also less than the BCWP. Therefore as well as being under the planned expenditure, we are also doing the work cheaper than the plan
As at today, the value of the work is less than planned value, therefore we are behind schedule. The actual cost of work is less than plan but is greater than the BCWP. Therefore despite having spent less than the plan, on the work that we have done we are overspending
Professional Development Learning Event – 27 March 2007
25
Some Derived Metrics
SV: Schedule Variance (BCWP - BCWS) A comparison of the amount of work
performed to what was planned to be performed.
A negative variance means the project is behind schedule
CV: Cost Variance (BCWP - ACWP) A comparison of the budgeted cost of work
performed with actual cost. A negative variance means the project is over
budget.
Professional Development Learning Event – 27 March 2007
26
SPI: Schedule Performance IndexSPI = BCWP / BCWS
SPI < 1 means project is behind schedule
CPI: Cost Performance IndexCPI = BCWP/ACWP
CPI < 1 means project is over budget
Some More Derived Metrics
Professional Development Learning Event – 27 March 2007
27
Cost indices and variances
• Cost Performance Index (CPI) = BCWP ACWP
• Cost Variance (CV) = BCWP - ACWP
• Cost Variance % (CV%) = CV x 100 BCWP
Schedule indices and variances• Schedule Variance (SV) = BCWP - BCWS
• Schedule Performance Index (SPI) = BCWP BCWS
• Schedule Variance % (SV%) = SV x 100 BCWS
Professional Development Learning Event – 27 March 2007
28
ScheduleVariance (£)
Earned Value (BCWP)
Actual Costs (ACWP)
PlannedCosts(BCWS)
Budget At Completion (BAC)
CostVariance (£)
Time
£
Scheduleslippage(time)
Today
Graphical representation of project progress
Professional Development Learning Event – 27 March 2007
29
Making Projections
Once a project is 10% complete, theoverrun at completion will not be lessthan the current overrun.
Once a project is 20% complete,the CPI does not vary from its currentvalue by more than 10%.
The CPI and SPI are statistically accurate indicators of final cost results.
Source: Defense Acquisition University
Professional Development Learning Event – 27 March 2007
30
• Formula 1 = BAC CPI
Considered to give a minimum EAC
• Formula 2 = BAC CPI x SPI
Provides an EAC that accounts for a schedule change
• Formula 3 = ACWP + BAC – BCWP CPI x
SPIProvides an EAC that accounts for a schedule change, but also takes into account the value of the work done
{ }
Estimate At Completion (EAC)
Professional Development Learning Event – 27 March 2007
31
ScheduleVariance (£)
Earned Value (BCWP)
Actual Costs (ACWP)
PlannedCosts(BCWS)
Budget At Completion (BAC)
Variance atCompletion
Forecastscheduleslippage
CostVariance (£)
Time
Estimate At Completion (EAC)
Today
£
Scheduleslippage(time)
Graphical representation of project progress
Professional Development Learning Event – 27 March 2007
33
Exercise
1. Read the worked example
2. Do the Earned Value exercise
1 hour
Professional Development Learning Event – 27 March 2007
34
• Activities do not always last for a reporting period (week, month etc)
• Some activities do not deliver anything, e.g. management support, but it still a cost to the project
Now the real world!
Professional Development Learning Event – 27 March 2007
35
Activities do not always last for a reporting period – What can be done?
• Use an Earned Value Method of 50/50 • When constructing the BCWS (the plan), you
put 50% of the activity (as a BCWS value) in the period the activity is planned to start and the remaining 50% in the period when the activity is planned to finish.
• The BCWP (Earned Value) is earnt in the same proportions, i.e. 50% when the activity starts and 50% when the activity finishes
Professional Development Learning Event – 27 March 2007
36
EV Methods – Internal resource
Professional Development Learning Event – 27 March 2007
37
Budget is time-phased based as a Primary Cost Activity (including cost of
in-house labour and material). Use Milestone weightings for each A/P's
BCWS or use Estimates method with % of BCWS for each A/P.
Use Milestone Method for sequential milestones; More likely, use Estimates
method. Claim based on % complete of each line item using cost of parts
received/total parts costs or operation hours complete/total hours X labour costs (or
composite of both)
When invoices are booked/posted for material or services; May need to use Estimated Actuals for false, significant
variances.
PRODUCTION PARTS.
STORES MATERIAL.
RECEIPT / USEAGE EQUIVALENT PARTS COMPLETE INVOICE
IN-HOUSE FABRICATIION / MANUFACTURE
DEVELOPMENT PARTS.
VENDOR-TO-VENDOR MATERIAL.
SUBCONTRACTED SERVICES.
STORES MATERIAL.LOW VALUES SERVICES OR MATERIALS.
MISCELANEOUS MATERIALS.
Actual costs are booked/posted based on verified receiver.
FOREIGN RECEIVER
Budget is planned in A/P that item is scheduled for receipt by vendor.
RECEIPT
BCWP on Receipt. Use 0-100 method based on receipt of goods or completion of
service.FOREIGN RECEIVER / RECEIPT
RECEIPT / USEAGE DEPENDS ON EVM INVOICE / RECEIVER
Budget is time-phased based upon planned receipt or usage.
Level of Effort, Estimates, or Apportioned Effort for low value material & services;
Earned value depends on discrete EVM--Material received as % of total material--or
passage of time (for LOE).
When invoices are booked/posted for material or services, or as charges are booked for computer, travel, or other
charges.
INVOICE / RECEIVER
Budget for each unit or lot multiplied by the number of units or lots scheduled
for shipment each A/P.
UNIT / LOT RECEIPT
Milestone or Estimates (more likely) method based upon number of units / lots or
equivalent units received. Earned value is claimed based upon CAM verification of
receipt.UNIT / LOT RECEIPT
Actual costs are booked/posted when goods are received.
RECEIVER
PROGRESS REPORTPROGRESS
MILESTONE COMPLETION
Milestone or Estimates method, using payment milestone values and/or weightings
as % of total Activity. Earned Value is claimed upon CAM verification of milestone
completion.
PROGRESS REPORT
Actual costs are booked/posted when invoice is received.
Budget for each progress payment is planned in A/P that progress is
scheduled.
Actual costs are booked/posted when invoice is received.
INVOICE / RECEIVER
Budget for each milestone payment is planned in A/P that payment milestone
is scheduled for completion.
Milestone or Estimates method depending on vendor or subcontractor inputs. Value is
claimed based on CAM verification of progress.
PARTIAL SHIPMENTS.
MILESTONE PAYMENTS
PROGRESS PAYMENTS
MULTIPLE UNITS
LINE ITEM ON PO.
(WITH NO PROGRESS / PARTIAL PAYMENTS)
SUBCONTRACTED ITEM.
(UNITS OR LOTS)
Should Occur in the Same Period
SINGLE PAYMENT
RECEIPT / COMPLETION
Budget is planned in A/P that item is scheduled for receipt / completion.
BCWP on Receipt. Use 0-100 method based on receipt of goods or completion of
service.RECEIPT / COMPLETION
Actual costs are booked/posted when goods are received or services are
invoiced.
Use Milestone Method for sequential milestones; More likely, use Estimates
method. Claim based on C/SSR, CPR, or Progress Reports provided by
Subcontractor/Supplier.
INVOICE / RECEIVER
TYPES OF ORDER (EVM) TYPICAL EXAMPLES PLAN AND BUDGET (BCWS)
SINGLE ITEM.
SINGLE SERVICE.
DROP SHIPMENT
EARNED VALUE (BCWP) ACTUAL COSTS (ACWP)
When invoices are booked/posted for material or services; May need to use Estimated Actuals for false, significant
variances.
SERVICES
HIGH VALUE MATERIAL
RECEIPT / USEAGE SUPPLIER EARNED VALUE INVOICE
MAJOR SUBCONTRACTOR OR
LARGE PO.
MAJOR SUBCONTRACTOR Budget is time-phased based upon Vendor or Subcontractor's detailed BCWS (usually summarised to one
Activity). Use Milestone weightings for each A/P's BCWS or use Estimates
method with % of BCWS for each A/P.
0/100
0/100
LOE or Estimates
MS or Estimates
MS or Estimates
MS or Estimates
MS or Estimates
MS or Estimates
EV Methods – Material/vendor
Professional Development Learning Event – 27 March 2007
38
Some activities do not deliver anything - What can be done?• Use an Earned Value Method called Level of Effort
• When constructing the BCWS (the plan), spread the activity value evenly throughout the duration
• The BCWP (Earned Value) is earnt in the same proportion to the plan regardless of whether any time has been spent on the activity or not
• BCWP = BCWS therefore SPI = 1.0 and SV = 0 It shows that we are always on schedule for this type of activity
Professional Development Learning Event – 27 March 2007
39
EVMS / EVM / EV / EVAEarned Value Management System:• The executive Cost and Schedule system employed• Can be a single system or many that are working together
Earned Value Management:• Active management of a programme using EV processes & EVA
Earned Value Methods:• Metric selected to provide best possible reflection of Schedule performance• Typically: 0-100, 20-80, 50-50, 40-60, Estimates, Milestones, Apportioned, & Level of Effort
Earned Value:• Budgeted Cost of Work Performed…BCWP• Executed tasks within a baseline having been completed in line with exit criteria
Earned Value Analysis:• Variance Analysis of - Current month, Cumulative to Date, and VAC• EAC Analysis in terms of TCPI(EAC) / Independent EACs if warranted
Professional Development Learning Event – 27 March 2007
40
Key EVMS Components
• Authorisation
• Planning & Budgeting
• Baseline Change Control
• Analysis
• Reporting
Professional Development Learning Event – 27 March 2007
41
Control Account Authorisation CAA:
• Total Allocated Budget (TAB) flow-down to reporting WBS
• Details initial Baseline distribution of Budget
• Provides a narrative (and/or) points to additional documentation detailing deliverables
• Indicates ‘open duration’ of Control Account
• Details specific schedule adherence
• Signed off by both Programme Manager and Control Account Manager
• Usually a one-time event…future budget transactions being dealt with by PCR’s
Authorisation
Professional Development Learning Event – 27 March 2007
42
Planning and Budgeting
• Total Planning or Rolling Wave Planning
• Vertical & Horizontal Integration with Milestones, especially if a Critical Path is required
• Resource allocation and management
• Management Reserve (in-scope arisings)
• Undistributed Budget (WBS earmarked budget)
• Earned Value Method (EVM) selection
• TAB = (DB + UB + MR)
• Where (DB+UB+MR) >TAB = Over Target Baseline !
Professional Development Learning Event – 27 March 2007
43
Baseline Control• Baseline Change Control is performed
using Programme Change Requests (PCRs)
• Baseline distribution = Contract Budget Base (CBB Log)
• Change Control (‘Rubber Baseline’ mitigation) performed by the usage of PCR’s
• PCR’s authorise both BAC/EAC and ‘pure’ EAC changes
• An understanding of MR v EAC is required !
• PCR’s are signed-off by Programme Managers
Professional Development Learning Event – 27 March 2007
44
Analysis • Performance = Current Month, CTD, and Variance at Completion• History = SV, SPI, CV, CPI• Current Management Reserve level & predicted ‘Burn-Down’• Programme flexibility = MR versus VAC delta • Staffing…..Equivalent Heads versus Forecast• Milestones….future forecasted dates versus requirements (Exec,
MWP, Programmatic) • Variance Analysis Reports (VAR’s) and Corrective Actions• Future = TCPI(EAC) and Trending
His
tory
Professional Development Learning Event – 27 March 2007
45
Variance Analysis Report (VAR) Thresholds:• Fixed at Baseline• Current month SV & CV• Cumulative SV & CV• VAC
CAM reports:• Cause of variance• Impact to Cost & Schedule• Corrective Actions
VAR’s:• Discussed at MPR’s• Agreed and signed by PM/PL
Corrective Actions:• Reviewed at subsequent MPR’s
Professional Development Learning Event – 27 March 2007
47
Shortcomings of Earned Value
Quantifying / measuring work progress can be difficult.
Time required for data input, data gathering and calculation
It is not the only way to manage a project
Professional Development Learning Event – 27 March 2007
48
Summary• Use indicators to manage your project and not to be a goal in
itself. They will drive a behaviour.
• EV data is historical. Use it to predict and influence the future
• Look at Indices and Variances together and observe trends
• Concentrate on the parts of the project that ‘trip’ the variances
• Not all projects are the same, i.e. do not expect the same sort of variances and indices on a technically challenging/risky project compared with more straight forward projects
• For EVA to be effective, it requires a credible baselined plan.
Professional Development Learning Event – 27 March 2007
49
Thank you and any questions?
Top Related