CIVIL WORKS for Power Plants:
• Surveydrawings
• Geotechnicalinvestigation&reporting
• Architectural(Basic/Detailed/Forconstruction/Asbuilt),
• Structural Analysis (Formworks, Rebar schedules, Steel Structure GA/Assembly/Shop
drawings,TEKLAmodel).
• Gas&SteamTurbinepedestalsdynamicanalysis.
• Excavationdiagrams
• CoordinationdrawingswithE&M
• Mobilizationdrawings
• UndergroundNetworksDesign&Coordination
• Drawingsforprotectionofexistingstructures
Design and Coordination of Track Works (Metro Projects)
Coordination of Construction Works (CW)
CW Project Management
CW Construction Management
R&DofEngineeringSoftware
The Company
ARDECOwasestablishedbyEngineerswith longstandingactivityandexperience in
engineering,constructionandprojectmanagement.
ARDECO’sfieldofexpertisehasexpandedthroughouttheyearsandnowcoversabroad
spectrumofPublicandPrivateProjects.
Mainfieldsofexpertiseareshortlysummarizedbelow.
OUR SCOPE OF WORKS Engineering Services:
ManagementandcoordinationofCivilWorksStudies
• Surveydrawings
• Geotechnicalinvestigation&reporting
• Architectural(Basic/Detailed/Forconstruction/Asbuilt),
• StructuralAnalysis(Formworks,Rebarschedules,SteelStructureGA/Assembly/Shopdrawings,TEKLAmodel).
• Gas&SteamTurbinepedestalsdynamicanalysis.
• Excavationdiagrams
• CoordinationdrawingswithE&M
• Mobilizationdrawings
• UndergroundNetworksDesign&Coordination
• Drawingsforprotectionofexistingstructures
QualityControl.
Management Services:
SupervisionofallCW:
• Earthworks
• ConcreteWorks(Foundations,RetainingWalls,Anchoring,Plinthsandbasis,CableTrenches,Shafts,etc.
• ConstructionofBuildingsonaTurn-Keybasis.
• ErectionofSteelStructureworks
• UndergroundNetworks(Sewagenetwork,Rainwaternetwork,DrainageSystemnetworkandFireFightingSystemnetwork.
• InternalRoadsnetwork
1. Syria, Deir Ali II ,
EXTENSION OF COMBINED CYCLE POWER PLANT 701MW
2. Jordan, Samra,
ADD-ON COMBINED CYCLE PROJECT
3. Iraq, Shat Al Bashra,
10x125MW, 9E – GAS TURBINES POWER PLANT PROJECT
4. Greece, Revithousa,
THERMAL AND ELECTRICAL ENERGY 15,5 MW
POWER PROJECTSCivil Works Design, Coordination & Management
PROJECT PRESENTATION GENERAL DESCRIPRION OF THE PROJECT
PROJECT TITLE EXTENSION OF COMBINED CYCLE POWER PLANT 701MW
PROJECT AREASYRIA – DAMASCUS – DEIR ALI
PROJECT BUDGET650.000.000 €
CIVIL WORKS BUDGET65.500.000 €
PROJECT OWNER PEEGT (SYRIAN PUBLIC COMPANY)PUBLIC ESTABLISHMENT OF ELECTRICITY FORGENERATION & TRANSMITION
PROJECT MAIN CONTRACTOR J/V METKA SA – ANSALDO ENERGIA S.P.A
TIMESCHEDULE36 Months Mid 2010 to End 2013
SHORT PROJECT DESCRIPTIONInstallation of 2 GT AEV94.3A4 284MW each and one ST type RT 270MW turbines with the appropriate adjacent and auxiliaries structures, working on nat-ural gas and fuel (LDO).
One Cooling Tower (Steel Structure 125m height) and one fin fan cooler unit.
Two Open type Substations one 400kV with five diameters and one 132kV with four diameters. Total area 50.000 m2.
Buildings: Administration Office, Main Control Build-ing, Water Treatment & Water Pretreatment Plant Buildings, etc.
MAIN CIVIL WORKS SUMMARY Power Plant Area: 100.000 m2 , Substation Area: 50.000 m2Road Works: 3.400 m, Earthworks: 410.000 m3Concrete Works: 75.000 m3 ,Steel Structures: 5.575 tnArchitectural Finishing: 5.260 m2
PROJECT TITLE SAMRA PHASE III ADD-ON COMBINED CYCLE PROJECT
PROJECT AREAJORDAN, SAMRA (35km Northeast from Amman)
PROJECT BUDGET151.000.000 $
CIVIL WORKS BUDGET16.300.000 $
PROJECT OWNER
SAMRA ELECTRIC POWER COMPANY – SEPCO
PROJECT MAIN CONTRACTOR
METKA SA
TIMESCHEDULE28 Months - Autumn 2012 to early 2015
SHORT PROJECT DESCRIPTIONInstallation of one ST 148.20MW turbine with the appropriate adjacent and auxiliaries structures.
One ACC cooling unit and one fin fan cooler unit.
Buildings: Main Control Building, Water Treatment & Water Pretreatment Plant Buildings, Fire Ser-vice Building etc.
MAIN CIVIL WORKS SUMMARY
Power Plant Area: 30.000 m2
Road Works: 500 m , Earthworks: 55.000 m3
Concrete Works: 18.500 m3 , Steel Structures: 2.200 tn
Architectural Finishing: 5.000 m2
ar.DE.CO.
PROJECT TITLE SHAT AL BASRA, 10x125MW, 9E – GAS TURBINES POWER PLANT PROJECT
PROJECT AREAIRAQ, BASRA
PROJECT COST348.000.000 $ (complete GT blocks excluded from procurement)
CIVIL ENGINEERING & PROJECT MANAGEMENT COST2.250.000 $
PROJECT OWNER Iraqi Ministry Of Electricity (MoE)
PROJECT MAIN CONTRACTOR METKA SA
TIMESCHEDULE24 Months - Commencement Mid 2012
SHORT PROJECT DESCRIPTIONInstallation of 10 units 9E GE, 10 x 125MW, with the appropriate adjacent and auxiliaries struc-tures, working on natural gas and fuel (LDO), as well as all the relevant service buildings. Two GIS units, one 400kV and one 132kV.Tank farm for LDO storage.Buildings: Administration Office, Bachelor Building, Canteer & Restaurant Building, Water Treatment Plant, Workshop Building, Chemical Storage Building, Store etc.
PROJECT TITLE POWER PLANT FOR COGENERATION OF THERMAL AND ELECTRICAL ENERGY 15,5 MW IN REVITHOUSA
PROJECT AREAGREECE - ATHENS –Revithousa Island
PROJECT COST16.500.000 € (VAT excluded)
CIVIL WORKS COST2.500.000 € (VAT excluded)
PROJECT OWNER Manager of Natural Gas National System (DESFA SA)
PROJECT MAIN CONTRACTOR BURMEISTER & WAIN SCANDINAVIAN CONTRACTOR A/S (BWSC).
TIMESCHEDULE12 Months (achieved ahead schedule)Mid 2008 – mid 2009
SHORT PROJECT DESCRIPTIONInstallation of two GE Turbines 8MW each, with all adjacent auxiliaries and structures, working on nat-ural gas, as well as all the relevant service struc-tures (incl. racks, fin fun cooler, chimney 25m etc).
cons
ulti
ng e
ngin
eers
| r
ail
expe
rts
rail power build soft
ar.DE.CO.arsenis design & construction
τεχνική
ar.D
E.C
O.
power
144, Marathonodromou str. | 15125 Maroussi - Athens | Greece | www.ardeco.grt. +30 210 6123452, +30 210 6143444 | f. +30 210 6123559 | e. [email protected]
Top Related