1 BROOKHAVEN SCIENCE ASSOCIATES
NSLS-II Beam Containment System
R. CaseyAccelerator Systems Advisory Committee
October 22, 2009
2 BROOKHAVEN SCIENCE ASSOCIATES
Beam Containment System
• Beam containment system (BCS) is the term used to describe the various active and passive devices designed to: • Localize electron beam losses to selected (well shielded) areas in the
accelerator enclosures• Detect excessive beam loss outside of well shielded areas• Provide linkage to other systems to mitigate excessive losses when
detected
• Area radiation monitoring systems complement BCS function by providing direct measurement of radiation levels in occupied areas.
3 BROOKHAVEN SCIENCE ASSOCIATES
Beam Containment System (cont.)
• Objective - alert operators to excessive beam losses that create potential for increased radiation levels in occupied areas and provide mitigation as required.
• Mitigation measures include:• operator warnings and alarms• direct curtailment of injection
4 BROOKHAVEN SCIENCE ASSOCIATES
Beam Loss Assumptions in Shielding Design
Extraction region shielded for 3 GeV at 1 Hz extraction rate
Injection region shielded for 200 MeV and I Hz injection rate
Injection region shielded for 3 GeV at 1 Hz injection rate
5 BROOKHAVEN SCIENCE ASSOCIATES
Implications of Shielding Design
• Abnormal operating conditions need to be evaluated.
• Additional engineering or administrative controls will be specified based on severity of radiation levels under fault conditions.
• An area radiation monitoring system is needed to detect excessive radiation in occupied areas and will serve as the primary safety system to protect against radiation producing faults.
• BCS is provided to detect abnormal conditions or abnormal beam losses and provide warning to machine operators. System will also inhibit injection systems on alarm.
6 BROOKHAVEN SCIENCE ASSOCIATES
Actions Taken to Define BCS Systems
• The radiological consequences of abnormal operating conditions have been described and analyzed as part of on-going safety assessments
• BCS task force appointed and work is underway to finalize design
• BCS functional requirements based on radiological analyses have been presented
• BCS components identified
7 BROOKHAVEN SCIENCE ASSOCIATES
BCS Task Force Setup to Define and Document BCS
• Task Force Members: S. Kramer, Y. Li, I. Pinayev, P.K. Job, D. Hseuh
• Other stake-holders: R. Casey, O. Singh, P. Cameron, B. Delasio
• Working Group has been meeting regularly since Spring, 2009
8 BROOKHAVEN SCIENCE ASSOCIATES
Examples of Abnormal Events and Consequences
• Full beam loss in Linac at design beam current (15 nA)• Max. dose rate – 8 mRem/h
• Full beam loss in Booster injection region at 200 MeV• Max. dose rate – 1 mRem/h with 1 Hz injection
• Full beam loss in Booster extraction region at 3 GeV• Max. dose rate – 2.5 mRem/h with 1 Hz injection
9 BROOKHAVEN SCIENCE ASSOCIATES
Abnormal Events and Consequences (cont.)
• Full beam loss in remainder of booster at 3 GeV• Max. dose rate – 1500 mRem/h above berm, 375 mRem/h in injection
building with 1 Hz injection
• Full injected beam loss in Storage Ring (SR) injection region• Max. dose rate – 2.5 mRem/h with 1 Hz injection
• Full injected beam loss at one point in SR non-injection region• Max. dose rate – 400 mRem/h with 1 Hz injection
10 BROOKHAVEN SCIENCE ASSOCIATES
Current Definition of BCS Components• Scrapers in SR injection region (4)
• R& D at NSLS for thin scraper design planned for FY 10
• Current Transformers (5)• Linac (ICT)• Linac to Booster transfer line (ICT)• Booster (DCCT)• Booster to SR transfer line (ICT)• SR (DCCT)
• Beam loss monitors (Type and # TBD)• SR at potential high loss points (steering and energy dispersive
maxima)• R & D at NSLS for Cerenkov BLM planned for FY 10
11 BROOKHAVEN SCIENCE ASSOCIATES
Area Radiation Monitors
• 2 - linac klystron gallery
• 6 - injection building
• 30 - Storage ring wall (1 per cell)
• 6 - FOE wall
Budgeted for 60 monitors
12 BROOKHAVEN SCIENCE ASSOCIATES
BCS Functions• Monitor and limit beam current in injection system and SR
• Detect high beam losses in injection or extraction processes in booster by comparison of current transformers (CTs) in transport line and booster
• Detect high beam losses in injection to SR by comparison of CTs in transport line and SR
• Provide scrapers and monitors in SR injection region to localize and confirm losses in that region (need for additional monitors in non-injection areas being evaluated)
• Alert machine operators to abnormal conditions and inhibit continued injection as warranted
13 BROOKHAVEN SCIENCE ASSOCIATES
Interface between Systems for BCS•Insure signals are available at rate needed, insure integrity of communication link
•Define the responsibility for calibration of these signals and their maintenance
•Issue Warnings if beam loss limit is being approached, suggest operator action needed
•Limit exceeded at present injection rate, issue Alarm that action is required within prescribed time.
•If exceeded for significant time interval, remove injection permit through BCS control network
Linac & transport CT signals
BCS Micro
Booster injection OK
Storage ring injection OK
Beam loss location OK
Permit Injection On/Off
BCS Controlled Device Interface Box
Injection On/Off
Booster and transport CT signals
SR CT signals
Beam loss location monitors
Warnings & Alarms to systems and operator
14 BROOKHAVEN SCIENCE ASSOCIATES
BCS Summary & Look Ahead• BCS task force is appointed and work is underway. BCS function specified.
• Specification of BCS components is almost complete, more work required to specify location and type of beam loss monitors and ddesign of scrapers.
• Warning and alarm set points for BCS will be established through fault testing and radiation measurements during commissioning.
• BCS components will be subject to configuration control during installation, testing, operation, maintenance, and modification.
• BCS interlocking functions are intended for routine operation. During commissioning and other times of machine studies, BCS interlocking may be temporarily removed. Protective function will be provided through work controls approved for the time period of the study.
15 BROOKHAVEN SCIENCE ASSOCIATES
Questions or Comments?