GHG PSD Permitting Challenges

Mark Wenclawiak | [email protected] | 678.460.0324 x202

September 24, 2014

Presented at NCASI West Coast Regional Meeting by All4 Inc.

Page 2: Mark Wenclawiak All4 GHG PSD Permitting Challenges

2 Your environmental compliance is clearly our business.

Outline

Project driver

5 challenges encountered

• During application development

• During agency review

Page 3: Mark Wenclawiak All4 GHG PSD Permitting Challenges

GHG PSD Permitting Challenges

Project Driver

Page 4: Mark Wenclawiak All4 GHG PSD Permitting Challenges

4 Your environmental compliance is clearly our business.

Boiler MACT compliance project

• Boilers decommissioned

• Boiler modified

• New boilers installed

Major modification in attainment area

Compressed project schedule

• Pre-application meeting

• Expedited permitting process

Background on Project

Page 5: Mark Wenclawiak All4 GHG PSD Permitting Challenges

5 Your environmental compliance is clearly our business.

Emissions inventory

• PSD applicability evaluation

New and modified units

No affected units

• Actual to projected actual emissions

• Step 1 significant increase for multiple pollutants

Netting

• Step 2 significant increase for GHGs only

Background on Project

Page 6: Mark Wenclawiak All4 GHG PSD Permitting Challenges

GHG PSD Permitting Challenges

Challenges During Application Development

Page 7: Mark Wenclawiak All4 GHG PSD Permitting Challenges

7 Your environmental compliance is clearly our business.

Challenge #1

• Biogenic emissions

Challenge #2

• BACT for modified boiler changes scope of Mill’s project

Retrofit with economizer

First Set of Challenges

Page 8: Mark Wenclawiak All4 GHG PSD Permitting Challenges

GHG PSD Permitting Challenges

Challenges During Agency Review

Page 9: Mark Wenclawiak All4 GHG PSD Permitting Challenges

9 Your environmental compliance is clearly our business.

Initial submittal in early Spring 2014

• Expedited process to issue permit by mid-summer

• 2 iterations of requests for more information

Challenge #3

• Netting calculation procedure

Challenge #4

• Regional Haze

Existing Regulatory Matters

Page 10: Mark Wenclawiak All4 GHG PSD Permitting Challenges

10 Your environmental compliance is clearly our business.

June 23, 2014 SCOTUS ruling during agency review

Challenge #5

• PSD for GHG-only – now what?

• State issues implementation policy

Rules of Game Change

Page 11: Mark Wenclawiak All4 GHG PSD Permitting Challenges

11 Your environmental compliance is clearly our business.

Hold on application

• Revise application to remove PSD references

• Boiler MACT extension request to help with budgeting

Current Path Forward

Page 12: Mark Wenclawiak All4 GHG PSD Permitting Challenges

www.all4inc.com Kimberton, PA | 610.933.5246 Kennesaw, GA | 678.460.0324

Questions & Open Discussions