ID ALILA RESORT-KOH RUSSEY M&E SCHEDULE Duration Start Finish

1 ALILA RESORT - KOH RUSSEY M&E CONSTRUCTION SCHEDULE PHASE 1 390 days Fri 8/1/14 Mon 8/31/15

2 MATERIAL AND SHOP DRAWING WORK 260 days Thu 8/14/14 Wed 5/6/15

3 Material & Shop drawing submission 90 days Thu 8/14/14Tue 11/11/14

4 Material submission 90 days Thu 8/14/14Tue 11/11/14

5 Shop drawing sumission 90 days Thu 8/14/14Tue 11/11/14

6 Location surveying and marking 90 days Thu 8/14/14Tue 11/11/14

7 Material Procurement schedule 210 days Fri 10/3/14 Wed 5/6/15

8 First phase material ordering 180 days Fri 10/3/14 Tue 3/31/15

9 Plumbing material 90 days Fri 10/3/14Wed 12/31/14

10 Domestic Water Pipe 90 days Fri 10/3/14Wed 12/31/14

11 Waste Water pipe 90 days Fri 10/3/14Wed 12/31/14

12 Storm water pipe 90 days Fri 10/3/14Wed 12/31/14

13 LV & ELV Electrical material 150 days Fri 10/3/14 Sun 3/1/15

14 Electrical pipe 90 days Fri 10/3/14Wed 12/31/14

15 LV Cable 60 days Thu 1/1/15 Sun 3/1/15

16 ELV Cable 60 days Thu 1/1/15 Sun 3/1/15

17 Material delivery to site 150 days Sun 11/2/14 Tue 3/31/15

18 Domestic water pipe 90 days Sun 11/2/14 Fri 1/30/15

19 Waste water pipe 90 days Sun 11/2/14 Fri 1/30/15

20 Storm Water pipe 90 days Sun 11/2/14 Fri 1/30/15

21 Electrical Pipe 90 days Sun 11/2/14 Fri 1/30/15

22 LV cable 60 days Sat 1/31/15 Tue 3/31/15

23 ELV Cable 60 days Sat 1/31/15 Tue 3/31/15

24 Second phase material ordering 200 days Mon 10/13/14 Wed 5/6/15

25 Mock-up second phase material 47 days Mon 10/13/14 Fri 11/28/14

26 Plumbing material 45 days Mon 10/13/14Wed 11/26/14

27 Swimming Pool equipment 45 days Mon 10/13/14Wed 11/26/14

28 Electrical and A/C equipment 45 days Mon 10/13/14Wed 11/26/14

29 Electrical Panel 30 days Tue 10/28/14Wed 11/26/14

30 Lighting 30 days Tue 10/28/14Wed 11/26/14

31 A/C unit 45 days Mon 10/13/14Wed 11/26/14

32 Material delivery to site 2 days Thu 11/27/14 Fri 11/28/14

33 Swimming Pool equipment 2 days Thu 11/27/14 Fri 11/28/14

34 Electrical Panel 2 days Thu 11/27/14 Fri 11/28/14

35 Lighting 2 days Thu 11/27/14 Fri 11/28/14

36 A/C unit 2 days Thu 11/27/14 Fri 11/28/14

37 Second phase Material 105 days Fri 1/16/15 Wed 5/6/15

38 Plumbing material 45 days Fri 1/16/15 Sun 3/1/15

39 Water Pump 45 days Fri 1/16/15 Sun 3/1/15

40 Swimming Pool equipment 45 days Fri 1/16/15 Sun 3/1/15

41 Hydrant equipment 45 days Fri 1/16/15 Sun 3/1/15

42 Electrical and A/C equipment 57 days Mon 3/2/15 Sun 5/3/15

43 Electrical Panel 57 days Mon 3/2/15 Sun 5/3/15

44 Lighting 57 days Mon 3/2/15 Sun 5/3/15

45 A/C unit 57 days Mon 3/2/15 Sun 5/3/15

46 Fan 57 days Mon 3/2/15 Sun 5/3/15

47 Material delivery to site 60 days Mon 3/2/15 Wed 5/6/15

48 Water Pump 3 days Mon 3/2/15 Wed 3/4/15

49 Swimming Pool equipment 3 days Mon 3/2/15 Wed 3/4/15

50 Hydrant equipment 3 days Mon 3/2/15 Wed 3/4/15

51 Electrical Panel 3 days Mon 5/4/15 Wed 5/6/15

52 Lighting 3 days Mon 5/4/15 Wed 5/6/15

53 A/C unit 3 days Mon 5/4/15 Wed 5/6/15

54 Fan 3 days Mon 5/4/15 Wed 5/6/15

55 ALILA RESORT - KOH RUSSEY M&E CONSTRUCTION SCHEDULE FOR INFRAS 260 days Wed 12/3/14 Tue 8/25/15

56 M&E PHASE 1 Infrastructure Part 260 days Wed 12/3/14 Tue 8/25/15

57 Milestone Starting Infrastructure work 0 days Wed 12/3/14 Wed 12/3/14

58 Plumbing Work 248 days Wed 12/3/14 Thu 8/13/15

59 Zone 1 Plumbing Work 76 days Wed 12/3/14 Mon 2/16/15

60 Step 1 Plumbing work behind Unit (Unit 1001 to 1006 & unit 20 38 days Wed 12/3/14 Fri 1/9/15

61 Storm water pipe installation work 38 days Wed 12/3/14 Fri 1/9/15

62 Trench excavation 7 days Wed 12/3/14 Tue 12/9/14

63 Sand bedding, leveling and pipe installation work 14 days Wed 12/10/14 Tue 12/23/14

64 Manhole and Pit construction 21 days Sun 12/14/14 Sat 1/3/15

65 Testing and Inspection work by consultant before back fil 3 days Sun 1/4/15 Tue 1/6/15

66 Trench backfilling 3 days Wed 1/7/15 Fri 1/9/15

67 Waste Water pipe installation work 38 days Wed 12/3/14 Fri 1/9/15

68 Trench excavation 7 days Wed 12/3/14 Tue 12/9/14

69 Sand bedding, leveling and pipe installation work 14 days Wed 12/10/14 Tue 12/23/14

70 Manhole and Pit construction 21 days Sun 12/14/14 Sat 1/3/15

71 Testing and Inspection work by consultant before back fil 3 days Sun 1/4/15 Tue 1/6/15

72 Trench backfilling 3 days Wed 1/7/15 Fri 1/9/15

73 Step 2 Plumbing work behind Unit (Unit 001 to 019) 38 days Sat 1/10/15 Mon 2/16/15

74 Storm water pipe installation work 38 days Sat 1/10/15 Mon 2/16/15

75 Trench excavation 7 days Sat 1/10/15 Fri 1/16/15

76 Sand bedding, leveling and pipe installation work 14 days Sat 1/17/15 Fri 1/30/15

77 Manhole and Pit construction 21 days Wed 1/21/15 Tue 2/10/15

78 Testing and Inspection work by consultant before back fil 3 days Wed 2/11/15 Fri 2/13/15

79 Trench backfilling 3 days Sat 2/14/15 Mon 2/16/15

80 Waste Water pipe installation work 38 days Sat 1/10/15 Mon 2/16/15

81 Trench excavation 7 days Sat 1/10/15 Fri 1/16/15

82 Sand bedding, leveling and pipe installation work 14 days Sat 1/17/15 Fri 1/30/15

83 Manhole and Pit construction 21 days Wed 1/21/15 Tue 2/10/15

84 Testing and Inspection work by consultant before back fil 3 days Wed 2/11/15 Fri 2/13/15

85 Trench backfilling 3 days Sat 2/14/15 Mon 2/16/15

86 Zone 2 Plumbing Work 76 days Tue 2/17/15 Sat 5/9/15

87 Step 1 Plumbing work behind Main arrival building 38 days Tue 2/17/15 Thu 3/26/15

88 Storm water pipe installation work 38 days Tue 2/17/15 Thu 3/26/15

89 Trench excavation 7 days Tue 2/17/15 Mon 2/23/15

90 Sand bedding, leveling and pipe installation work 14 days Tue 2/24/15 Mon 3/9/15

91 Manhole and Pit construction 21 days Sat 2/28/15 Fri 3/20/15

92 Testing and Inspection work by consultant before back fil 3 days Sat 3/21/15 Mon 3/23/15

93 Trench backfilling 3 days Tue 3/24/15 Thu 3/26/15

94 waste Water pipe installation work 38 days Tue 2/17/15 Thu 3/26/15

95 Trench excavation 7 days Tue 2/17/15 Mon 2/23/15

96 Sand bedding, leveling and pipe installation work 14 days Tue 2/24/15 Mon 3/9/15

97 Manhole and Pit construction 21 days Sat 2/28/15 Fri 3/20/15

98 Testing and Inspection work by consultant before back fil 3 days Sat 3/21/15 Mon 3/23/15

99 Trench backfilling 3 days Tue 3/24/15 Thu 3/26/15

100 Step 2 Plumbing work behind Unit V-01 & V-02 38 days Fri 3/27/15 Sat 5/9/15

101 Storm water pipe installation work 38 days Fri 3/27/15 Sat 5/9/15

102 Trench excavation 7 days Fri 3/27/15 Thu 4/2/15

103 Sand bedding, leveling and pipe installation work 14 days Fri 4/3/15 Wed 4/22/15

104 Manhole and Pit construction 21 days Tue 4/7/15 Sun 5/3/15

105 Testing and Inspection work by consultant before back fil 3 days Mon 5/4/15 Wed 5/6/15

106 Trench backfilling 3 days Thu 5/7/15 Sat 5/9/15

107 Waste Water pipe installation work 38 days Fri 3/27/15 Sat 5/9/15

108 Trench excavation 7 days Fri 3/27/15 Thu 4/2/15

109 Sand bedding, leveling and pipe installation work 14 days Fri 4/3/15 Wed 4/22/15

110 Manhole and Pit construction 21 days Tue 4/7/15 Sun 5/3/15

111 Testing and Inspection work by consultant before back fil 3 days Mon 5/4/15 Wed 5/6/15

112 Trench backfilling 3 days Thu 5/7/15 Sat 5/9/15

113 Zone 3 Plumbing Work 67 days Sun 5/10/15 Wed 7/15/15

114 Step 1 Plumbing work from Unit 203 to waste treament plan (fi 37 days Sun 5/10/15 Mon 6/15/15

115 Storm water pipe installation work 37 days Sun 5/10/15 Mon 6/15/15

116 Trench excavation 7 days Sun 5/10/15 Sat 5/16/15

117 Sand bedding, leveling and pipe installation work 20 days Sun 5/17/15 Fri 6/5/15

118 Manhole and Pit construction 20 days Fri 5/22/15 Wed 6/10/15

119 Testing and Inspection work by consultant before back fil 2 days Thu 6/11/15 Fri 6/12/15

120 Trench backfilling 3 days Sat 6/13/15 Mon 6/15/15

121 Waste Water pipe installation work 37 days Sun 5/10/15 Mon 6/15/15

122 Trench excavation 7 days Sun 5/10/15 Sat 5/16/15

123 Sand bedding, leveling and pipe installation work 20 days Sun 5/17/15 Fri 6/5/15

124 Manhole and Pit construction 20 days Fri 5/22/15 Wed 6/10/15

125 Testing and Inspection work by consultant before back fil 2 days Thu 6/11/15 Fri 6/12/15

126 Trench backfilling 3 days Sat 6/13/15 Mon 6/15/15

127 Domestic water pipe installation work 30 days Sun 5/10/15 Mon 6/8/15

8/1 8/31

8/14 5/6

8/14 11/11

8/14 11/11

8/14 11/11

8/14 11/11

10/3 5/6

10/3 3/31

10/3 12/31

10/3 12/31

10/3 12/31

10/3 12/31

10/3 3/1

10/3 12/31

1/1 3/1

1/1 3/1

11/2 3/31

11/2 1/30

11/2 1/30

11/2 1/30

11/2 1/30

1/31 3/31

1/31 3/31

10/13 5/6

10/13 11/28

10/13 11/26

10/13 11/26

10/13 11/26

10/28 11/26

10/28 11/26

10/13 11/26

11/27 11/28

11/27 11/28

11/27 11/28

11/27 11/28

11/27 11/28

1/16 5/6

1/16 3/1

1/16 3/1

1/16 3/1

1/16 3/1

3/2 5/3

3/2 5/3

3/2 5/3

3/2 5/3

3/2 5/3

3/2 5/6

3/2 3/4

3/2 3/4

3/2 3/4

5/4 5/6

5/4 5/6

5/4 5/6

5/4 5/6

12/3 8/25

12/3 8/25

12/3 Milestone Starting Infrastructure work

12/3 8/13

12/3 2/16

12/3 1/9

12/3 1/9

12/3 12/9

12/10 12/23

12/14 1/3

1/4 1/6

1/7 1/9

12/3 1/9

12/3 12/9

12/10 12/23

12/14 1/3

1/4 1/6

1/7 1/9

1/10 2/16

1/10 2/16

1/10 1/16

1/17 1/30

1/21 2/10

2/11 2/13

2/14 2/16

1/10 2/16

1/10 1/16

1/17 1/30

1/21 2/10

2/11 2/13

2/14 2/16

2/17 5/9

2/17 3/26

2/17 3/26

2/17 2/23

2/24 3/9

2/28 3/20

3/21 3/23

3/24 3/26

2/17 3/26

2/17 2/23

2/24 3/9

2/28 3/20

3/21 3/23

3/24 3/26

3/27 5/9

3/27 5/9

3/27 4/2

4/3 4/22

4/7 5/3

5/4 5/6

5/7 5/9

3/27 5/9

3/27 4/2

4/3 4/22

4/7 5/3

5/4 5/6

5/7 5/9

5/10 7/15

5/10 6/15

5/10 6/15

5/10 5/16

5/17 6/5

5/22 6/10

6/11 6/12

6/13 6/15

5/10 6/15

5/10 5/16

5/17 6/5

5/22 6/10

6/11 6/12

6/13 6/15

5/10 6/8

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep OctJuly August Septemb October Novembe Decembe January February March April May June July August Septemb October

Task

Split

Progress

Milestone

Summary

Project Summary

External Tasks

External Milestone

Deadline

MASTER SCHEDULE ALILA RESORT - KOH RUSSEY

Prepared by: Soly

Project: KRU-MEP ScheduleDate: Fri 10/24/14

ID ALILA RESORT-KOH RUSSEY M&E SCHEDULE Duration Start Finish

128 Trench excavation 7 days Sun 5/10/15 Sat 5/16/15

129 Sand bedding, leveling and pipe installation work 20 days Fri 5/15/15 Wed 6/3/15

130 Testing and Inspection work by consultant before back fil 2 days Thu 6/4/15 Fri 6/5/15

131 Trench backfilling 3 days Sat 6/6/15 Mon 6/8/15

132 Step 2 Plumbing work from step 1 to waste water treament bu 37 days Tue 6/9/15 Wed 7/15/15

133 Storm water pipe installation work 37 days Tue 6/9/15 Wed 7/15/15

134 Trench excavation 7 days Tue 6/9/15 Mon 6/15/15

135 Sand bedding, leveling and pipe installation work 20 days Tue 6/16/15 Sun 7/5/15

136 Manhole and Pit construction 20 days Sun 6/21/15 Fri 7/10/15

137 Testing and Inspection work by consultant before back fil 2 days Sat 7/11/15 Sun 7/12/15

138 Trench backfilling 3 days Mon 7/13/15 Wed 7/15/15

139 Waste Water pipe installation work 37 days Tue 6/9/15 Wed 7/15/15

140 Trench excavation 7 days Tue 6/9/15 Mon 6/15/15

141 Sand bedding, leveling and pipe installation work 20 days Tue 6/16/15 Sun 7/5/15

142 Manhole and Pit construction 20 days Sun 6/21/15 Fri 7/10/15

143 Testing and Inspection work by consultant before back fil 2 days Sat 7/11/15 Sun 7/12/15

144 Trench backfilling 3 days Mon 7/13/15 Wed 7/15/15

145 Domestic water pipe installation work 30 days Tue 6/9/15 Wed 7/8/15

146 Trench excavation 7 days Tue 6/9/15 Mon 6/15/15

147 Sand bedding, leveling and pipe installation work 20 days Sun 6/14/15 Fri 7/3/15

148 Testing and Inspection work by consultant before back fil 2 days Sat 7/4/15 Sun 7/5/15

149 Trench backfilling 3 days Mon 7/6/15 Wed 7/8/15

150 Zone 4 Plumbing Work 136 days Wed 12/24/14 Thu 5/14/15

151 Step 1 Plumbing work infront unit (Unit 1001 to 1006 & unit 20 22 days Wed 12/24/14 Wed 1/14/15

152 Storm water pipe installation work 22 days Wed 12/24/14 Wed 1/14/15

153 Trench excavation 4 days Wed 12/24/14 Sat 12/27/14

154 Sand bedding, leveling and pipe installation work 10 days Sun 12/28/14 Tue 1/6/15

155 Manhole and Pit construction 10 days Thu 1/1/15 Sat 1/10/15

156 Testing and Inspection work by consultant before back fil 2 days Sun 1/11/15 Mon 1/12/15

157 Trench backfilling 2 days Tue 1/13/15 Wed 1/14/15

158 waste Water pipe installation work 22 days Wed 12/24/14 Wed 1/14/15

159 Trench excavation 4 days Wed 12/24/14 Sat 12/27/14

160 Sand bedding, leveling and pipe installation work 10 days Sun 12/28/14 Tue 1/6/15

161 Manhole and Pit construction 10 days Thu 1/1/15 Sat 1/10/15

162 Testing and Inspection work by consultant before back fil 2 days Sun 1/11/15 Mon 1/12/15

163 Trench backfilling 2 days Tue 1/13/15 Wed 1/14/15

164 Domestic water pipe installation work 22 days Wed 12/24/14 Wed 1/14/15

165 Trench excavation 4 days Wed 12/24/14 Sat 12/27/14

166 Sand bedding, leveling and pipe installation work 14 days Sun 12/28/14 Sat 1/10/15

167 Testing and Inspection work by consultant before back fil 2 days Sun 1/11/15 Mon 1/12/15

168 Trench backfilling 2 days Tue 1/13/15 Wed 1/14/15

169 Step 2 Plumbing work for unit 204, 205 & 1009 19 days Thu 1/15/15 Mon 2/2/15

170 Storm water pipe installation work 19 days Thu 1/15/15 Mon 2/2/15

171 Trench excavation 4 days Thu 1/15/15 Sun 1/18/15

172 Sand bedding, leveling and pipe installation work 10 days Mon 1/19/15 Wed 1/28/15

173 Manhole and Pit construction 10 days Thu 1/22/15 Sat 1/31/15

174 Testing and Inspection work by consultant before back fil 1 day Sun 2/1/15 Sun 2/1/15

175 Trench backfilling 1 day Mon 2/2/15 Mon 2/2/15

176 waste Water pipe installation work 14 days Thu 1/15/15 Wed 1/28/15

177 Trench excavation 2 days Thu 1/15/15 Fri 1/16/15

178 Sand bedding, leveling and pipe installation work 7 days Sat 1/17/15 Fri 1/23/15

179 Manhole and Pit construction 7 days Tue 1/20/15 Mon 1/26/15

180 Testing and Inspection work by consultant before back fil 1 day Tue 1/27/15 Tue 1/27/15

181 Trench backfilling 1 day Wed 1/28/15 Wed 1/28/15

182 Domestic water pipe installation work 19 days Thu 1/15/15 Mon 2/2/15

183 Trench excavation 4 days Thu 1/15/15 Sun 1/18/15

184 Sand bedding, leveling and pipe installation work 14 days Sun 1/18/15 Sat 1/31/15

185 Testing and Inspection work by consultant before back fil 1 day Sun 2/1/15 Sun 2/1/15

186 Trench backfilling 1 day Mon 2/2/15 Mon 2/2/15

187 Step 3 Plumbing work infront unit 001 to unit 019 21 days Thu 1/29/15 Wed 2/18/15

188 Domestic water pipe installation work 21 days Thu 1/29/15 Wed 2/18/15

189 Trench excavation 5 days Thu 1/29/15 Mon 2/2/15

190 Sand bedding, leveling and pipe installation work 14 days Sat 1/31/15 Fri 2/13/15

191 Testing and Inspection work by consultant before back fil 2 days Sat 2/14/15 Sun 2/15/15

192 Trench backfilling 3 days Mon 2/16/15 Wed 2/18/15

193 Step 4 Plumbing work infront Mian building 27 days Thu 2/19/15 Tue 3/17/15

194 Storm water pipe installation work 27 days Thu 2/19/15 Tue 3/17/15

195 Trench excavation 4 days Thu 2/19/15 Sun 2/22/15

196 Sand bedding, leveling and pipe installation work 14 days Mon 2/23/15 Sun 3/8/15

197 Manhole and Pit construction 14 days Fri 2/27/15 Thu 3/12/15

198 Testing and Inspection work by consultant before back fil 2 days Fri 3/13/15 Sat 3/14/15

199 Trench backfilling 3 days Sun 3/15/15 Tue 3/17/15

200 waste Water pipe installation work 27 days Thu 2/19/15 Tue 3/17/15

201 Trench excavation 4 days Thu 2/19/15 Sun 2/22/15

202 Sand bedding, leveling and pipe installation work 14 days Mon 2/23/15 Sun 3/8/15

203 Manhole and Pit construction 14 days Fri 2/27/15 Thu 3/12/15

204 Testing and Inspection work by consultant before back fil 2 days Fri 3/13/15 Sat 3/14/15

205 Trench backfilling 3 days Sun 3/15/15 Tue 3/17/15

206 Domestic water pipe installation work 21 days Thu 2/19/15 Wed 3/11/15

207 Trench excavation 4 days Thu 2/19/15 Sun 2/22/15

208 Sand bedding, leveling and pipe installation work 14 days Sat 2/21/15 Fri 3/6/15

209 Testing and Inspection work by consultant before back fil 2 days Sat 3/7/15 Sun 3/8/15

210 Trench backfilling 3 days Mon 3/9/15 Wed 3/11/15

211 Step 5 Plumbing work for unit 039 to unit 044 27 days Thu 3/12/15 Tue 4/7/15

212 Storm water pipe installation work 27 days Thu 3/12/15 Tue 4/7/15

213 Trench excavation 4 days Thu 3/12/15 Sun 3/15/15

214 Sand bedding, leveling and pipe installation work 14 days Mon 3/16/15 Sun 3/29/15

215 Manhole and Pit construction 14 days Fri 3/20/15 Thu 4/2/15

216 Testing and Inspection work by consultant before back fil 2 days Fri 4/3/15 Sat 4/4/15

217 Trench backfilling 3 days Sun 4/5/15 Tue 4/7/15

218 waste Water pipe installation work 27 days Thu 3/12/15 Tue 4/7/15

219 Trench excavation 4 days Thu 3/12/15 Sun 3/15/15

220 Sand bedding, leveling and pipe installation work 14 days Mon 3/16/15 Sun 3/29/15

221 Manhole and Pit construction 14 days Fri 3/20/15 Thu 4/2/15

222 Testing and Inspection work by consultant before back fil 2 days Fri 4/3/15 Sat 4/4/15

223 Trench backfilling 3 days Sun 4/5/15 Tue 4/7/15

224 Domestic water pipe installation work 17 days Thu 3/12/15 Sat 3/28/15

225 Trench excavation 4 days Thu 3/12/15 Sun 3/15/15

226 Sand bedding, leveling and pipe installation work 10 days Sat 3/14/15 Mon 3/23/15

227 Testing and Inspection work by consultant before back fil 2 days Tue 3/24/15 Wed 3/25/15

228 Trench backfilling 3 days Thu 3/26/15 Sat 3/28/15

229 Step 6 Plumbing work for V-01, V-02 & Guest Jetty 31 days Wed 4/8/15 Thu 5/14/15

230 Storm water pipe installation work 31 days Wed 4/8/15 Thu 5/14/15

231 Trench excavation 5 days Wed 4/8/15 Sun 4/12/15

232 Sand bedding, leveling and pipe installation work 14 days Sun 4/19/15 Sat 5/2/15

233 Manhole and Pit construction 14 days Fri 4/24/15 Thu 5/7/15

234 Testing and Inspection work by consultant before back fil 3 days Fri 5/8/15 Sun 5/10/15

235 Trench backfilling 4 days Mon 5/11/15 Thu 5/14/15

236 waste Water pipe installation work 30 days Wed 4/8/15 Wed 5/13/15

237 Trench excavation 5 days Wed 4/8/15 Sun 4/12/15

238 Sand bedding, leveling and pipe installation work 14 days Sun 4/19/15 Sat 5/2/15

239 Manhole and Pit construction 14 days Thu 4/23/15 Wed 5/6/15

240 Testing and Inspection work by consultant before back fil 3 days Thu 5/7/15 Sat 5/9/15

241 Trench backfilling 4 days Sun 5/10/15 Wed 5/13/15

242 Domestic water pipe installation work 26 days Wed 4/8/15 Sat 5/9/15

243 Trench excavation 5 days Wed 4/8/15 Sun 4/12/15

244 Sand bedding, leveling and pipe installation work 14 days Sun 4/19/15 Sat 5/2/15

245 Testing and Inspection work by consultant before back fil 3 days Sun 5/3/15 Tue 5/5/15

246 Trench backfilling 4 days Wed 5/6/15 Sat 5/9/15

247 Pipe Work in the pump room 18 days Thu 7/9/15 Sun 7/26/15

248 Installation the pipe pump room 5 days Thu 7/9/15 Mon 7/13/15

249 Fixing the accessory at pump room 5 days Thu 7/9/15 Mon 7/13/15

250 Pump installation 10 days Tue 7/14/15 Thu 7/23/15

251 Pump testing and commissioning 3 days Fri 7/24/15 Sun 7/26/15

252 Pit Pump installation 8 days Mon 7/27/15 Mon 8/3/15

253 Waste water pit pump installation 4 days Mon 7/27/15 Thu 7/30/15

254 Storm water pit pump installation 4 days Fri 7/31/15 Mon 8/3/15

5/10 5/16

5/15 6/3

6/4 6/5

6/6 6/8

6/9 7/15

6/9 7/15

6/9 6/15

6/16 7/5

6/21 7/10

7/11 7/12

7/13 7/15

6/9 7/15

6/9 6/15

6/16 7/5

6/21 7/10

7/11 7/12

7/13 7/15

6/9 7/8

6/9 6/15

6/14 7/3

7/4 7/5

7/6 7/8

12/24 5/14

12/24 1/14

12/24 1/14

12/24 12/27

12/28 1/6

1/1 1/10

1/11 1/12

1/13 1/14

12/24 1/14

12/24 12/27

12/28 1/6

1/1 1/10

1/11 1/12

1/13 1/14

12/24 1/14

12/24 12/27

12/28 1/10

1/11 1/12

1/13 1/14

1/15 2/2

1/15 2/2

1/15 1/18

1/19 1/28

1/22 1/31

2/1 2/1

2/2 2/2

1/15 1/28

1/15 1/16

1/17 1/23

1/20 1/26

1/27 1/27

1/28 1/28

1/15 2/2

1/15 1/18

1/18 1/31

2/1 2/1

2/2 2/2

1/29 2/18

1/29 2/18

1/29 2/2

1/31 2/13

2/14 2/15

2/16 2/18

2/19 3/17

2/19 3/17

2/19 2/22

2/23 3/8

2/27 3/12

3/13 3/14

3/15 3/17

2/19 3/17

2/19 2/22

2/23 3/8

2/27 3/12

3/13 3/14

3/15 3/17

2/19 3/11

2/19 2/22

2/21 3/6

3/7 3/8

3/9 3/11

3/12 4/7

3/12 4/7

3/12 3/15

3/16 3/29

3/20 4/2

4/3 4/4

4/5 4/7

3/12 4/7

3/12 3/15

3/16 3/29

3/20 4/2

4/3 4/4

4/5 4/7

3/12 3/28

3/12 3/15

3/14 3/23

3/24 3/25

3/26 3/28

4/8 5/14

4/8 5/14

4/8 4/12

4/19 5/2

4/24 5/7

5/8 5/10

5/11 5/14

4/8 5/13

4/8 4/12

4/19 5/2

4/23 5/6

5/7 5/9

5/10 5/13

4/8 5/9

4/8 4/12

4/19 5/2

5/3 5/5

5/6 5/9

7/9 7/26

7/9 7/13

7/9 7/13

7/14 7/23

7/24 7/26

7/27 8/3

7/27 7/30

7/31 8/3

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep OctJuly August Septemb October Novembe Decembe January February March April May June July August Septemb October

Task

Split

Progress

Milestone

Summary

Project Summary

External Tasks

External Milestone

Deadline

MASTER SCHEDULE ALILA RESORT - KOH RUSSEY

Prepared by: Soly

Project: KRU-MEP ScheduleDate: Fri 10/24/14

ID ALILA RESORT-KOH RUSSEY M&E SCHEDULE Duration Start Finish

255 Hydrants & hosereels 41 days Sun 5/10/15 Fri 6/19/15

256 Underground pipe work 26 days Sun 5/10/15 Thu 6/4/15

257 Trench excavation 7 days Sun 5/10/15 Sat 5/16/15

258 Sand bedding, leveling and pipe installation work 14 days Sun 5/17/15 Sat 5/30/15

259 Testing and Inspection work by consultant before back filling 3 days Sun 5/31/15 Tue 6/2/15

260 Trench backfilling 2 days Wed 6/3/15 Thu 6/4/15

261 Cabinet Hydrant and Pillar Hydrant 15 days Fri 6/5/15 Fri 6/19/15

262 Installation outdoor cabinet hydrant 5 days Fri 6/5/15 Tue 6/9/15

263 Installation Pillar hydrant 7 days Wed 6/10/15 Tue 6/16/15

264 Check and inspection by consultant 3 days Wed 6/17/15 Fri 6/19/15

265 Plumbing system testing and commissioning 10 days Tue 8/4/15 Thu 8/13/15

266 Testing & commissioning storm water system 10 days Tue 8/4/15 Thu 8/13/15

267 Testing & commissioning sanitary drain system 10 days Tue 8/4/15 Thu 8/13/15

268 Testing & commissioning domestic water system 10 days Tue 8/4/15 Thu 8/13/15

269 Testing & commissioning fire hydrant system 10 days Tue 8/4/15 Thu 8/13/15

270 Electical Work 226 days Wed 12/24/14 Wed 8/12/15

271 Cable support & Cable counduit 175 days Wed 12/24/14 Mon 6/22/15

272 Zone 1 electrical conduit 130 days Wed 12/24/14 Fri 5/8/15

273 Step 1 electrica lconduit infront of unit ( unit 1001 to 1006 18 days Wed 12/24/14 Sat 1/10/15

274 Trench excavation and manhole 4 days Wed 12/24/14 Sat 12/27/14

275 Sand bedding, leveling and pipe installation work 7 days Sun 12/28/14 Sat 1/3/15

276 Electrical Manhole construction 7 days Wed 12/31/14 Tue 1/6/15

277 Testing and Inspection work by consultant before back fil 2 days Wed 1/7/15 Thu 1/8/15

278 Trench backfilling 2 days Fri 1/9/15 Sat 1/10/15

279 Step 2 electrical conduit for unit 204 & 205 13 days Sun 1/11/15 Fri 1/23/15

280 Trench excavation and manhole 3 days Sun 1/11/15 Tue 1/13/15

281 Sand bedding, leveling and pipe installation work 5 days Wed 1/14/15 Sun 1/18/15

282 Electrical Manhole construction 5 days Sat 1/17/15 Wed 1/21/15

283 Testing and Inspection work by consultant before back fil 1 day Thu 1/22/15 Thu 1/22/15

284 Trench backfilling 1 day Fri 1/23/15 Fri 1/23/15

285 Step 3 electrical conduit infront of unit 001 to 019 18 days Sat 1/24/15 Tue 2/10/15

286 Trench excavation and manhole 4 days Sat 1/24/15 Tue 1/27/15

287 Sand bedding, leveling and pipe installation work 7 days Wed 1/28/15 Tue 2/3/15

288 Electrical Manhole construction 7 days Sat 1/31/15 Fri 2/6/15

289 Testing and Inspection work by consultant before back fil 2 days Sat 2/7/15 Sun 2/8/15

290 Trench backfilling 2 days Mon 2/9/15 Tue 2/10/15

291 Step 4 electrical conduit from unit 007 to DB-6 12 days Wed 2/11/15 Sun 2/22/15

292 Trench excavation and manhole 2 days Wed 2/11/15 Thu 2/12/15

293 Sand bedding, leveling and pipe installation work 4 days Fri 2/13/15 Mon 2/16/15

294 Electrical Manhole construction 5 days Mon 2/16/15 Fri 2/20/15

295 Testing and Inspection work by consultant before back fil 1 day Sat 2/21/15 Sat 2/21/15

296 Trench backfilling 1 day Sun 2/22/15 Sun 2/22/15

297 Step 5 electrical conduit from MSB buidling to DB-7 12 days Mon 2/23/15 Fri 3/6/15

298 Trench excavation and manhole 2 days Mon 2/23/15 Tue 2/24/15

299 Sand bedding, leveling and pipe installation work 4 days Wed 2/25/15 Sat 2/28/15

300 Electrical Manhole construction 5 days Sat 2/28/15 Wed 3/4/15

301 Testing and Inspection work by consultant before back fil 1 day Thu 3/5/15 Thu 3/5/15

302 Trench backfilling 1 day Fri 3/6/15 Fri 3/6/15

303 Step 6 electrical conduit from MSB buidling to DB-SPA 12 days Sat 3/7/15 Wed 3/18/15

304 Trench excavation and manhole 2 days Sat 3/7/15 Sun 3/8/15

305 Sand bedding, leveling and pipe installation work 4 days Mon 3/9/15 Thu 3/12/15

306 Electrical Manhole construction 5 days Thu 3/12/15 Mon 3/16/15

307 Testing and Inspection work by consultant before back fil 1 day Tue 3/17/15 Tue 3/17/15

308 Trench backfilling 1 day Wed 3/18/15 Wed 3/18/15

309 Step 7 electrical conduit from MSB buidling to DB-05 17 days Thu 3/19/15 Sat 4/4/15

310 Trench excavation and manhole 3 days Thu 3/19/15 Sat 3/21/15

311 Sand bedding, leveling and pipe installation work 5 days Sun 3/22/15 Thu 3/26/15

312 Electrical Manhole construction 6 days Thu 3/26/15 Tue 3/31/15

313 Testing and Inspection work by consultant before back fil 2 days Wed 4/1/15 Thu 4/2/15

314 Trench backfilling 2 days Fri 4/3/15 Sat 4/4/15

315 Step 8 electrical conduit from DB-05 to Unit 1086 & Unit 1 12 days Sun 4/5/15 Wed 4/22/15

316 Trench excavation and manhole 2 days Sun 4/5/15 Mon 4/6/15

317 Sand bedding, leveling and pipe installation work 4 days Tue 4/7/15 Fri 4/10/15

318 Electrical Manhole construction 5 days Fri 4/10/15 Mon 4/20/15

319 Testing and Inspection work by consultant before back fil 1 day Tue 4/21/15 Tue 4/21/15

320 Trench backfilling 1 day Wed 4/22/15 Wed 4/22/15

321 Step 8 electrical conduit from DB-05 to DB-Jetty 16 days Thu 4/23/15 Fri 5/8/15

322 Trench excavation and manhole 3 days Thu 4/23/15 Sat 4/25/15

323 Sand bedding, leveling and pipe installation work 5 days Sun 4/26/15 Thu 4/30/15

324 Electrical Manhole construction 6 days Wed 4/29/15 Mon 5/4/15

325 Testing and Inspection work by consultant before back fil 2 days Tue 5/5/15 Wed 5/6/15

326 Trench backfilling 2 days Thu 5/7/15 Fri 5/8/15

327 Zone 1 electrical conduit 44 days Sun 5/10/15 Mon 6/22/15

328 Step 1 electrica lconduit from unit 203 to Waste Water Tre 22 days Sun 5/10/15 Sun 5/31/15

329 Trench excavation and manhole 5 days Sun 5/10/15 Thu 5/14/15

330 Sand bedding, leveling and pipe installation work 6 days Fri 5/15/15 Wed 5/20/15

331 Electrical Manhole construction 7 days Wed 5/20/15 Tue 5/26/15

332 Testing and Inspection work by consultant before back fil 2 days Wed 5/27/15 Thu 5/28/15

333 Trench backfilling 3 days Fri 5/29/15 Sun 5/31/15

334 Step 1 electrica lconduit from step1 to waste water treatm 22 days Mon 6/1/15 Mon 6/22/15

335 Trench excavation and manhole 5 days Mon 6/1/15 Fri 6/5/15

336 Sand bedding, leveling and pipe installation work 6 days Sat 6/6/15 Thu 6/11/15

337 Electrical Manhole construction 7 days Thu 6/11/15 Wed 6/17/15

338 Testing and Inspection work by consultant before back fil 2 days Thu 6/18/15 Fri 6/19/15

339 Trench backfilling 3 days Sat 6/20/15 Mon 6/22/15

340 Pulling Main Cable 30 days Sat 6/20/15 Sun 7/19/15

341 LV Power Cable 30 days Sat 6/20/15 Sun 7/19/15

342 From MDB-0 to DB-1 6 days Tue 6/23/15 Sun 6/28/15

343 From DB-1 to DB-2 6 days Mon 6/29/15 Sat 7/4/15

344 From DB-2 to DB-3 5 days Sun 7/5/15 Thu 7/9/15

345 From MDB-0 to DB-4 5 days Fri 7/10/15 Tue 7/14/15

346 From DB-4 to DB-WT 5 days Wed 7/15/15 Sun 7/19/15

347 From MDB-0 to DB-7 4 days Sat 6/20/15 Tue 6/23/15

348 From MDB-0 to DB-7 4 days Wed 6/24/15 Sat 6/27/15

349 From MDB-0 to DB-Main Building 4 days Sun 6/28/15 Wed 7/1/15

350 From each DB to unit 4 days Thu 7/2/15 Sun 7/5/15

351 Testing Cable 4 days Mon 7/6/15 Thu 7/9/15

352 ELV cable 10 days Fri 7/10/15 Sun 7/19/15

353 Pulling the ELV cable 7 days Fri 7/10/15 Thu 7/16/15

354 Fire Alarm cable 7 days Fri 7/10/15 Thu 7/16/15

355 Check and testing by consultant 3 days Fri 7/17/15 Sun 7/19/15

356 Earthing and lightning Protection system 30 days Sat 6/20/15 Sun 7/19/15

357 Installation earting rod 12 days Sat 6/20/15 Wed 7/1/15

358 Connectiong earthing cable 5 days Thu 7/2/15 Mon 7/6/15

359 Installation Air terminal for lightining 10 days Tue 7/7/15 Thu 7/16/15

360 Check and inspect by consultant 3 days Fri 7/17/15 Sun 7/19/15

361 Switchboards 17 days Mon 7/20/15 Wed 8/5/15

362 Installation the Power switch board, FA panel and ELV cabinet 7 days Mon 7/20/15 Sun 7/26/15

363 Dressing the switch board 7 days Sat 7/25/15 Fri 7/31/15

364 Check and test by consultant 5 days Sat 8/1/15 Wed 8/5/15

365 Electrical commissioning 7 days Thu 8/6/15 Wed 8/12/15

366 Testing & commissioning LV system 7 days Thu 8/6/15 Wed 8/12/15

367 Testing & commissioning FA system 7 days Thu 8/6/15 Wed 8/12/15

368 Testing & commissioning ELV system 7 days Thu 8/6/15 Wed 8/12/15

369 Testing & commissioning Earthing system 7 days Thu 8/6/15 Wed 8/12/15

370 Training and Handover Infrastructure part 12 days Fri 8/14/15 Tue 8/25/15

371 Training for infrastructure 12 days Fri 8/14/15 Tue 8/25/15

372 Hand Over 0 days Tue 8/25/15 Tue 8/25/15

373 ALILA RESORT - KOH RUSSEY M&E CONSTRUCTION SCHEDULE FOR BUILDIN 390 days Fri 8/1/14 Mon 8/31/15

374 IV. Villa 2 Bed Room 204 (Mock up) 130 days Fri 8/1/14 Mon 12/8/14

375 A. Drawing preparation 18 days Fri 8/1/14 Mon 8/18/14

376 B. Material procurement and transportation 91 days Fri 8/1/14Thu 10/30/14

377 C. Clearing and grubbing / Cut and filling work 5 days Fri 8/8/14 Tue 8/12/14

378 C. Structure work 94 days Wed 8/13/14 Fri 11/14/14

379 1. Foundation / Stump Column and back filling work 51 days Wed 8/13/14 Thu 10/2/14

380 2. Ground beam and slab work 15 days Mon 9/29/14Mon 10/13/14

381 4. Column work 11 days Mon 9/29/14 Thu 10/9/14

5/10 6/19

5/10 6/4

5/10 5/16

5/17 5/30

5/31 6/2

6/3 6/4

6/5 6/19

6/5 6/9

6/10 6/16

6/17 6/19

8/4 8/13

8/4 8/13

8/4 8/13

8/4 8/13

8/4 8/13

12/24 8/12

12/24 6/22

12/24 5/8

12/24 1/10

12/24 12/27

12/28 1/3

12/31 1/6

1/7 1/8

1/9 1/10

1/11 1/23

1/11 1/13

1/14 1/18

1/17 1/21

1/22 1/22

1/23 1/23

1/24 2/10

1/24 1/27

1/28 2/3

1/31 2/6

2/7 2/8

2/9 2/10

2/11 2/22

2/11 2/12

2/13 2/16

2/16 2/20

2/21 2/21

2/22 2/22

2/23 3/6

2/23 2/24

2/25 2/28

2/28 3/4

3/5 3/5

3/6 3/6

3/7 3/18

3/7 3/8

3/9 3/12

3/12 3/16

3/17 3/17

3/18 3/18

3/19 4/4

3/19 3/21

3/22 3/26

3/26 3/31

4/1 4/2

4/3 4/4

4/5 4/22

4/5 4/6

4/7 4/10

4/10 4/20

4/21 4/21

4/22 4/22

4/23 5/8

4/23 4/25

4/26 4/30

4/29 5/4

5/5 5/6

5/7 5/8

5/10 6/22

5/10 5/31

5/10 5/14

5/15 5/20

5/20 5/26

5/27 5/28

5/29 5/31

6/1 6/22

6/1 6/5

6/6 6/11

6/11 6/17

6/18 6/19

6/20 6/22

6/20 7/19

6/20 7/19

6/23 6/28

6/29 7/4

7/5 7/9

7/10 7/14

7/15 7/19

6/20 6/23

6/24 6/27

6/28 7/1

7/2 7/5

7/6 7/9

7/10 7/19

7/10 7/16

7/10 7/16

7/17 7/19

6/20 7/19

6/20 7/1

7/2 7/6

7/7 7/16

7/17 7/19

7/20 8/5

7/20 7/26

7/25 7/31

8/1 8/5

8/6 8/12

8/6 8/12

8/6 8/12

8/6 8/12

8/6 8/12

8/14 8/25

8/14 8/25

8/25 Hand Over

8/1 8/31

8/1 12/8

8/1 8/18

8/1 10/30

8/8 8/12

8/13 11/14

8/13 10/2

9/29 10/13

9/29 10/9

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep OctJuly August Septemb October Novembe Decembe January February March April May June July August Septemb October

Task

Split

Progress

Milestone

Summary

Project Summary

External Tasks

External Milestone

Deadline

MASTER SCHEDULE ALILA RESORT - KOH RUSSEY

Prepared by: Soly

Project: KRU-MEP ScheduleDate: Fri 10/24/14

ID ALILA RESORT-KOH RUSSEY M&E SCHEDULE Duration Start Finish

382 5. Roof beam and slab 13 days Fri 10/10/14Wed 10/22/14

383 D. Finishing work 22 days Mon 10/20/14Mon 11/10/14

384 1.Masonry work 11 days Mon 10/20/14 Thu 10/30/14

385 2. Plastering work 11 days Fri 10/31/14Mon 11/10/14

386 E. Steel work 48 days Sat 9/27/14 Fri 11/14/14

387 1. All steel work 30 days Thu 10/16/14 Fri 11/14/14

388 F. Water proofing work 9 days Wed 10/29/14 Thu 11/6/14

389 1. Water proof for roof ..tec. 9 days Wed 10/29/14 Thu 11/6/14

390 G. Swimming Pool 30 days Tue 10/14/14Wed 11/12/14

391 H. Septic Tank 15 days Mon 9/29/14Mon 10/13/14

392 milestone PHV (Villa 2 Bed Room 204 ( Mock up)) 0 days Sat 9/27/14 Sat 9/27/14

393 M&E first phase 35 days Sun 9/28/14 Sat 11/1/14

394 Electrical System 35 days Sun 9/28/14 Sat 11/1/14

395 Pipe sleeve and pipe installation underground 3 days Sun 9/28/14 Tue 9/30/14

396 Installation conduit above the ceiling & embedded in wall 14 days Thu 10/16/14Wed 10/29/14

397 Pulling the Cable for LV and ELV 3 days Thu 10/30/14 Sat 11/1/14

398 A/C and Ventilation System 26 days Sun 9/28/14Thu 10/23/14

399 Prepare the sleeve for refrigerant pipe and drain pipe installation 4 days Sun 9/28/14 Wed 10/1/14

400 Installation Refregerant pipe and insulation 5 days Fri 10/17/14Tue 10/21/14

401 Installatin drain pipe and insulation 5 days Fri 10/17/14Tue 10/21/14

402 Installation ducting system 7 days Fri 10/17/14Thu 10/23/14

403 Plumbing and Pool system 31 days Sun 9/28/14Tue 10/28/14

404 Installation Underground pipe for waste water, storm water, cold w 4 days Sun 9/28/14 Wed 10/1/14

405 Installation above ground pipe for waste water, storm water, pool a 12 days Fri 10/17/14Tue 10/28/14

406 J. Final inspection and Hand over for PHV 0 days Fri 11/14/14 Fri 11/14/14

407 milestone ID (Villa 2 Bed Room 204 ( Mock up)) 0 days Sat 11/29/14 Sat 11/29/14

408 M&E Second phase 9 days Sun 11/30/14 Mon 12/8/14

409 Electrical System 9 days Sun 11/30/14 Mon 12/8/14

410 Installation electrical panel 2 days Sun 11/30/14 Mon 12/1/14

411 Installation lighting 3 days Tue 12/2/14 Thu 12/4/14

412 Installation wiring device 2 days Fri 12/5/14 Sat 12/6/14

413 Installation ELV equipment 2 days Sun 12/7/14 Mon 12/8/14

414 A/C and Ventilation System 9 days Sun 11/30/14 Mon 12/8/14

415 Installation A/C unit 5 days Sun 11/30/14 Thu 12/4/14

416 Installatin exhaust fan 4 days Fri 12/5/14 Mon 12/8/14

417 Plumbing and Pool system 9 days Sun 11/30/14 Mon 12/8/14

418 Installation Pool equipment 4 days Sun 11/30/14 Wed 12/3/14

419 Installation sanitary ware 5 days Thu 12/4/14 Mon 12/8/14

420 Final inspection for CEMP 0 days Mon 12/8/14 Mon 12/8/14

421 Villa 2 Bed Room 205 186 days Fri 8/1/14 Mon 2/2/15

422 A. Drawing preparation 18 days Fri 8/1/14 Mon 8/18/14

423 B. Material procurement and transportation 91 days Fri 8/15/14Thu 11/13/14

424 C. Clearing and grubbing / Cut and filling work 5 days Tue 8/19/14 Sat 8/23/14

425 C. Structure work 56 days Wed 10/1/14Tue 11/25/14

426 1. Foundation / Stump Column and back filling work 22 days Wed 10/1/14Wed 10/22/14

427 2. Ground beam and slab work 15 days Sat 10/18/14 Sat 11/1/14

428 4. Column work 12 days Thu 10/30/14Mon 11/10/14

429 5. Roof beam and slab 15 days Tue 11/11/14Tue 11/25/14

430 D. Finishing work 35 days Wed 11/26/14Tue 12/30/14

431 1.Masonry work 20 days Wed 11/26/14Mon 12/15/14

432 2. Plastering work 20 days Thu 12/11/14Tue 12/30/14

433 E. Steel work 30 days Sun 11/2/14 Mon 12/1/14

434 1. All steel work 30 days Sun 11/2/14 Mon 12/1/14

435 F. Water proofing work 20 days Wed 11/26/14Mon 12/15/14

436 1. Water proof for roof ..tec. 20 days Wed 11/26/14Mon 12/15/14

437 G. Swimming Pool 60 days Thu 10/23/14Sun 12/21/14

438 H. Septic Tank 20 days Thu 10/23/14Tue 11/11/14

439 milestone PHV (Villa 2 Bed Room 205) 0 days Sat 10/18/14 Sat 10/18/14

440 M&E first phase 54 days Sat 10/18/14Wed 12/10/14

441 Electrical System 48 days Sat 10/18/14 Thu 12/4/14

442 Pipe sleeve installation 7 days Sat 10/18/14 Fri 10/24/14

443 Installation conduit above the ceiling & embedded in wall 14 days Fri 11/14/14Thu 11/27/14

444 Pulling the Cable for LV and ELV 7 days Fri 11/28/14 Thu 12/4/14

445 A/C and Ventilation System 54 days Sat 10/18/14Wed 12/10/14

446 Prepare the sleeve for refrigerant pipe installation 7 days Sat 10/18/14 Fri 10/24/14

447 Installation Refregerant pipe and insulation 10 days Fri 11/14/14Sun 11/23/14

448 Installatin drain pipe and insulation 7 days Mon 11/24/14Sun 11/30/14

449 Installation ducting system 10 days Mon 12/1/14Wed 12/10/14

450 Plumbing and Pool system 47 days Sat 10/18/14 Wed 12/3/14

451 Installation Underground pipe for waste water, storm water, cold w 7 days Sat 10/18/14 Fri 10/24/14

452 Installation above ground pipe for waste water, storm water, pool a 20 days Fri 11/14/14 Wed 12/3/14

453 J. Final inspection/ Punch Listing and Hand over for PHV 10 days Wed 12/31/14 Fri 1/9/15

454 milestone ID (Villa 2 Bed Room 205) 0 days Sat 1/24/15 Sat 1/24/15

455 M&E Second phase 9 days Sun 1/25/15 Mon 2/2/15

456 Electrical System 9 days Sun 1/25/15 Mon 2/2/15

457 Installation electrical panel 2 days Sun 1/25/15 Mon 1/26/15

458 Installation lighting 3 days Tue 1/27/15 Thu 1/29/15

459 Installation wiring device 2 days Fri 1/30/15 Sat 1/31/15

460 Installation ELV equipment 2 days Sun 2/1/15 Mon 2/2/15

461 A/C and Ventilation System 9 days Sun 1/25/15 Mon 2/2/15

462 Installation A/C unit 5 days Sun 1/25/15 Thu 1/29/15

463 Installatin exhaust fan 4 days Fri 1/30/15 Mon 2/2/15

464 Plumbing and Pool system 9 days Sun 1/25/15 Mon 2/2/15

465 Installation Pool equipment 4 days Sun 1/25/15 Wed 1/28/15

466 Installation sanitary ware 5 days Thu 1/29/15 Mon 2/2/15

467 Final inspection for CEMP 0 days Mon 2/2/15 Mon 2/2/15

468 Hotel suit block 1 (001 to 006) 306 days Mon 9/1/14 Thu 7/9/15

469 A. Drawing preparation 15 days Mon 9/1/14 Mon 9/15/14

470 B. Material procurement and transportation 150 days Mon 9/8/14 Wed 2/4/15

471 C. Clearing and grubbing / Cut and filling work 7 days Tue 9/16/14 Mon 9/22/14

472 F. Ground floor 159 days Mon 9/29/14 Fri 3/6/15

473 a. Structure work 84 days Mon 9/29/14Sun 12/21/14

474 1. Foundation / Stump Column and back filling work 42 days Mon 9/29/14 Sun 11/9/14

475 2. Ground beam and slab work 28 days Mon 11/3/14Sun 11/30/14

476 4. Column work 25 days Thu 11/27/14Sun 12/21/14

477 b. Finishing work 50 days Fri 1/16/15 Fri 3/6/15

478 1.Masonry work 25 days Fri 1/16/15 Mon 2/9/15

479 2. Plastering work 25 days Tue 2/10/15 Fri 3/6/15

480 G. First floor 123 days Fri 12/19/14 Sun 4/26/15

481 a. Structure work 77 days Fri 12/19/14 Thu 3/5/15

482 1. First floor beam and slab 28 days Fri 12/19/14 Thu 1/15/15

483 2. Column work 27 days Fri 1/16/15 Wed 2/11/15

484 3. Roof beam and slab 25 days Mon 2/9/15 Thu 3/5/15

485 b. Finishing work 50 days Mon 3/2/15 Sun 4/26/15

486 1.Masonry work 25 days Mon 3/2/15 Thu 3/26/15

487 2. Plastering work 25 days Fri 3/27/15 Sun 4/26/15

488 H. Water proofing work 30 days Tue 3/10/15 Wed 4/8/15

489 milestone PHV (Hotel suit block 1 (001 to 006)) 0 days Mon 11/3/14 Mon 11/3/14

490 Hotel suit block 1 (001 to 006) M&E first phase 120 days Mon 11/3/14 Mon 3/2/15

491 HS unit 001 first phase 40 days Mon 11/3/14 Fri 12/12/14

492 M&E first phase 40 days Mon 11/3/14 Fri 12/12/14

493 Electrical System 39 days Mon 11/3/14Thu 12/11/14

494 Pipe sleeve installation 3 days Mon 11/3/14 Wed 11/5/14

495 Installation conduit above the ceiling & embedded in wall 10 days Thu 11/27/14 Sat 12/6/14

496 Pulling the Cable for LV and ELV 5 days Sun 12/7/14 Thu 12/11/14

497 A/C and Ventilation System 40 days Mon 11/3/14 Fri 12/12/14

498 Prepare the sleeve for refrigerant pipe installation 3 days Mon 11/3/14 Wed 11/5/14

499 Installation Refregerant pipe and insulation 5 days Thu 11/27/14 Mon 12/1/14

500 Installation drain pipe and insulation 4 days Tue 12/2/14 Fri 12/5/14

501 Installation ducting system 7 days Sat 12/6/14 Fri 12/12/14

502 Plumbing System 36 days Mon 11/3/14 Mon 12/8/14

503 Installation Underground pipe for waste water, rain water 5 days Mon 11/3/14 Fri 11/7/14

504 Installation above ground pipe for waste water, rain wate 10 days Sat 11/29/14 Mon 12/8/14

505 HS unit 002 first phase 40 days Mon 11/3/14 Fri 12/12/14

506 M&E first phase 40 days Mon 11/3/14 Fri 12/12/14

507 Electrical System 39 days Mon 11/3/14Thu 12/11/14

508 Pipe sleeve installation 3 days Mon 11/3/14 Wed 11/5/14

10/10 10/22

10/20 11/10

10/20 10/30

10/31 11/10

9/27 11/14

10/16 11/14

10/29 11/6

10/29 11/6

10/14 11/12

9/29 10/13

9/27 milestone PHV (Villa 2 Bed Room 204 ( Mock up))

9/28 11/1

9/28 11/1

9/28 9/30

10/16 10/29

10/30 11/1

9/28 10/23

9/28 10/1

10/17 10/21

10/17 10/21

10/17 10/23

9/28 10/28

9/28 10/1

10/17 10/28

11/14 J. Final inspection and Hand over for PHV

11/29 milestone ID (Villa 2 Bed Room 204 ( Mock up))

11/30 12/8

11/30 12/8

11/30 12/1

12/2 12/4

12/5 12/6

12/7 12/8

11/30 12/8

11/30 12/4

12/5 12/8

11/30 12/8

11/30 12/3

12/4 12/8

12/8 Final inspection for CEMP

8/1 2/2

8/1 8/18

8/15 11/13

8/19 8/23

10/1 11/25

10/1 10/22

10/18 11/1

10/30 11/10

11/11 11/25

11/26 12/30

11/26 12/15

12/11 12/30

11/2 12/1

11/2 12/1

11/26 12/15

11/26 12/15

10/23 12/21

10/23 11/11

10/18 milestone PHV (Villa 2 Bed Room 205)

10/18 12/10

10/18 12/4

10/18 10/24

11/14 11/27

11/28 12/4

10/18 12/10

10/18 10/24

11/14 11/23

11/24 11/30

12/1 12/10

10/18 12/3

10/18 10/24

11/14 12/3

12/31 1/9

1/24 milestone ID (Villa 2 Bed Room 205)

1/25 2/2

1/25 2/2

1/25 1/26

1/27 1/29

1/30 1/31

2/1 2/2

1/25 2/2

1/25 1/29

1/30 2/2

1/25 2/2

1/25 1/28

1/29 2/2

2/2 Final inspection for CEMP

9/1 7/9

9/1 9/15

9/8 2/4

9/16 9/22

9/29 3/6

9/29 12/21

9/29 11/9

11/3 11/30

11/27 12/21

1/16 3/6

1/16 2/9

2/10 3/6

12/19 4/26

12/19 3/5

12/19 1/15

1/16 2/11

2/9 3/5

3/2 4/26

3/2 3/26

3/27 4/26

3/10 4/8

11/3 milestone PHV (Hotel suit block 1 (001 to 006))

11/3 3/2

11/3 12/12

11/3 12/12

11/3 12/11

11/3 11/5

11/27 12/6

12/7 12/11

11/3 12/12

11/3 11/5

11/27 12/1

12/2 12/5

12/6 12/12

11/3 12/8

11/3 11/7

11/29 12/8

11/3 12/12

11/3 12/12

11/3 12/11

11/3 11/5

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep OctJuly August Septemb October Novembe Decembe January February March April May June July August Septemb October

Task

Split

Progress

Milestone

Summary

Project Summary

External Tasks

External Milestone

Deadline

MASTER SCHEDULE ALILA RESORT - KOH RUSSEY

Prepared by: Soly

Project: KRU-MEP ScheduleDate: Fri 10/24/14

ID ALILA RESORT-KOH RUSSEY M&E SCHEDULE Duration Start Finish

509 Installation conduit above the ceiling & embedded in wall 10 days Thu 11/27/14 Sat 12/6/14

510 Pulling the Cable for LV and ELV 5 days Sun 12/7/14 Thu 12/11/14

511 A/C and Ventilation System 40 days Mon 11/3/14 Fri 12/12/14

512 Prepare the sleeve for refrigerant pipe installation 3 days Mon 11/3/14 Wed 11/5/14

513 Installation Refregerant pipe and insulation 5 days Thu 11/27/14 Mon 12/1/14

514 Installatin drain pipe and insulation 4 days Tue 12/2/14 Fri 12/5/14

515 Installation ducting system 7 days Sat 12/6/14 Fri 12/12/14

516 Plumbing System 36 days Mon 11/3/14 Mon 12/8/14

517 Installation Underground pipe for waste water, rain water 5 days Mon 11/3/14 Fri 11/7/14

518 Installation above ground pipe for waste water, rain wate 10 days Sat 11/29/14 Mon 12/8/14

519 HS unit 003 first phase 40 days Sat 12/13/14 Wed 1/21/15

520 M&E first phase 40 days Sat 12/13/14 Wed 1/21/15

521 Electrical System 39 days Sat 12/13/14 Tue 1/20/15

522 Pipe sleeve installation 3 days Sat 12/13/14Mon 12/15/14

523 Installation conduit above the ceiling & embedded in wall 10 days Tue 1/6/15 Thu 1/15/15

524 Pulling the Cable for LV and ELV 5 days Fri 1/16/15 Tue 1/20/15

525 A/C and Ventilation System 40 days Sat 12/13/14 Wed 1/21/15

526 Prepare the sleeve for refrigerant pipe installation 3 days Sat 12/13/14Mon 12/15/14

527 Installation Refregerant pipe and insulation 5 days Tue 1/6/15 Sat 1/10/15

528 Installatin drain pipe and insulation 4 days Sun 1/11/15 Wed 1/14/15

529 Installation ducting system 7 days Thu 1/15/15 Wed 1/21/15

530 Plumbing System 36 days Sat 12/13/14 Sat 1/17/15

531 Installation Underground pipe for waste water, rain water 5 days Sat 12/13/14Wed 12/17/14

532 Installation above ground pipe for waste water, rain wate 10 days Thu 1/8/15 Sat 1/17/15

533 HS unit 004 first phase 40 days Sat 12/13/14 Wed 1/21/15

534 M&E first phase 40 days Sat 12/13/14 Wed 1/21/15

535 Electrical System 39 days Sat 12/13/14 Tue 1/20/15

536 Pipe sleeve installation 3 days Sat 12/13/14Mon 12/15/14

537 Installation conduit above the ceiling & embedded in wall 10 days Tue 1/6/15 Thu 1/15/15

538 Pulling the Cable for LV and ELV 5 days Fri 1/16/15 Tue 1/20/15

539 A/C and Ventilation System 40 days Sat 12/13/14 Wed 1/21/15

540 Prepare the sleeve for refrigerant pipe installation 3 days Sat 12/13/14Mon 12/15/14

541 Installation Refregerant pipe and insulation 5 days Tue 1/6/15 Sat 1/10/15

542 Installatin drain pipe and insulation 4 days Sun 1/11/15 Wed 1/14/15

543 Installation ducting system 7 days Thu 1/15/15 Wed 1/21/15

544 Plumbing System 36 days Sat 12/13/14 Sat 1/17/15

545 Installation Underground pipe for waste water, rain water 5 days Sat 12/13/14Wed 12/17/14

546 Installation above ground pipe for waste water, rain wate 10 days Thu 1/8/15 Sat 1/17/15

547 HS unit 005 first phase 40 days Thu 1/22/15 Mon 3/2/15

548 M&E first phase 40 days Thu 1/22/15 Mon 3/2/15

549 Electrical System 34 days Thu 1/22/15 Tue 2/24/15

550 Pipe sleeve installation 3 days Thu 1/22/15 Sat 1/24/15

551 Installation conduit above the ceiling & embedded in wall 10 days Sun 2/15/15 Tue 2/24/15

552 Pulling the Cable for LV and ELV 5 days Sun 1/25/15 Thu 1/29/15

553 A/C and Ventilation System 40 days Thu 1/22/15 Mon 3/2/15

554 Prepare the sleeve for refrigerant pipe installation 3 days Thu 1/22/15 Sat 1/24/15

555 Installation Refregerant pipe and insulation 5 days Sun 2/15/15 Thu 2/19/15

556 Installatin drain pipe and insulation 4 days Fri 2/20/15 Mon 2/23/15

557 Installation ducting system 7 days Tue 2/24/15 Mon 3/2/15

558 Plumbing System 36 days Thu 1/22/15 Thu 2/26/15

559 Installation Underground pipe for waste water, rain water 5 days Thu 1/22/15 Mon 1/26/15

560 Installation above ground pipe for waste water, rain wate 10 days Tue 2/17/15 Thu 2/26/15

561 HS unit 006 first phase 40 days Thu 1/22/15 Mon 3/2/15

562 M&E first phase 40 days Thu 1/22/15 Mon 3/2/15

563 Electrical System 39 days Thu 1/22/15 Sun 3/1/15

564 Pipe sleeve installation 3 days Thu 1/22/15 Sat 1/24/15

565 Installation conduit above the ceiling & embedded in wall 10 days Sun 2/15/15 Tue 2/24/15

566 Pulling the Cable for LV and ELV 5 days Wed 2/25/15 Sun 3/1/15

567 A/C and Ventilation System 40 days Thu 1/22/15 Mon 3/2/15

568 Prepare the sleeve for refrigerant pipe installation 3 days Thu 1/22/15 Sat 1/24/15

569 Installation Refregerant pipe and insulation 5 days Sun 2/15/15 Thu 2/19/15

570 Installatin drain pipe and insulation 4 days Fri 2/20/15 Mon 2/23/15

571 Installation ducting system 7 days Tue 2/24/15 Mon 3/2/15

572 Plumbing System 36 days Thu 1/22/15 Thu 2/26/15

573 Installation Underground pipe for waste water, rain water 5 days Thu 1/22/15 Mon 1/26/15

574 Installation above ground pipe for waste water, rain wate 10 days Tue 2/17/15 Thu 2/26/15

575 J. Final inspection/ Punch Listing and Punch Listing PHV 11 days Mon 4/27/15 Thu 5/7/15

576 milestone ID (Hotel suit block 1 (001 to 006)) 0 days Fri 5/22/15 Fri 5/22/15

577 Hotel suit block 1 (001 to 006) M&E Second phase 48 days Sat 5/23/15 Thu 7/9/15

578 HS unit 001 Second phase 16 days Sat 5/23/15 Sun 6/7/15

579 M&E Second phase 16 days Sat 5/23/15 Sun 6/7/15

580 Electrical System 16 days Sat 5/23/15 Sun 6/7/15

581 Installation electrical panel 2 days Sat 5/23/15 Sun 5/24/15

582 Installation lighting 6 days Mon 5/25/15 Sat 5/30/15

583 Installation wiring device 6 days Sun 5/31/15 Fri 6/5/15

584 Installation ELV equipment 2 days Sat 6/6/15 Sun 6/7/15

585 A/C and Ventilation System 16 days Sat 5/23/15 Sun 6/7/15

586 Installation A/C unit 10 days Sat 5/23/15 Mon 6/1/15

587 Installatin exhaust fan 6 days Tue 6/2/15 Sun 6/7/15

588 Plumbing System 8 days Sat 5/23/15 Sat 5/30/15

589 Installation sanitary ware 8 days Sat 5/23/15 Sat 5/30/15

590 HS unit 002 Second phase 16 days Sat 5/23/15 Sun 6/7/15

591 M&E Second phase 16 days Sat 5/23/15 Sun 6/7/15

592 Electrical System 16 days Sat 5/23/15 Sun 6/7/15

593 Installation electrical panel 2 days Sat 5/23/15 Sun 5/24/15

594 Installation lighting 6 days Mon 5/25/15 Sat 5/30/15

595 Installation wiring device 6 days Sun 5/31/15 Fri 6/5/15

596 Installation ELV equipment 2 days Sat 6/6/15 Sun 6/7/15

597 A/C and Ventilation System 16 days Sat 5/23/15 Sun 6/7/15

598 Installation A/C unit 10 days Sat 5/23/15 Mon 6/1/15

599 Installatin exhaust fan 6 days Tue 6/2/15 Sun 6/7/15

600 Plumbing System 8 days Sat 5/23/15 Sat 5/30/15

601 Installation sanitary ware 8 days Sat 5/23/15 Sat 5/30/15

602 HS unit 003 Second phase 16 days Mon 6/8/15 Tue 6/23/15

603 M&E Second phase 16 days Mon 6/8/15 Tue 6/23/15

604 Electrical System 16 days Mon 6/8/15 Tue 6/23/15

605 Installation electrical panel 2 days Mon 6/8/15 Tue 6/9/15

606 Installation lighting 6 days Wed 6/10/15 Mon 6/15/15

607 Installation wiring device 6 days Tue 6/16/15 Sun 6/21/15

608 Installation ELV equipment 2 days Mon 6/22/15 Tue 6/23/15

609 A/C and Ventilation System 16 days Mon 6/8/15 Tue 6/23/15

610 Installation A/C unit 10 days Mon 6/8/15 Wed 6/17/15

611 Installatin exhaust fan 6 days Thu 6/18/15 Tue 6/23/15

612 Plumbing system 8 days Mon 6/8/15 Mon 6/15/15

613 Installation sanitary ware 8 days Mon 6/8/15 Mon 6/15/15

614 HS unit 004 Second phase 16 days Mon 6/8/15 Tue 6/23/15

615 M&E Second phase 16 days Mon 6/8/15 Tue 6/23/15

616 Electrical System 16 days Mon 6/8/15 Tue 6/23/15

617 Installation electrical panel 2 days Mon 6/8/15 Tue 6/9/15

618 Installation lighting 6 days Wed 6/10/15 Mon 6/15/15

619 Installation wiring device 6 days Tue 6/16/15 Sun 6/21/15

620 Installation ELV equipment 2 days Mon 6/22/15 Tue 6/23/15

621 A/C and Ventilation System 16 days Mon 6/8/15 Tue 6/23/15

622 Installation A/C unit 10 days Mon 6/8/15 Wed 6/17/15

623 Installatin exhaust fan 6 days Thu 6/18/15 Tue 6/23/15

624 Plumbing system 8 days Mon 6/8/15 Mon 6/15/15

625 Installation sanitary ware 8 days Mon 6/8/15 Mon 6/15/15

626 HS unit 005 Second phase 16 days Wed 6/24/15 Thu 7/9/15

627 M&E Second phase 16 days Wed 6/24/15 Thu 7/9/15

628 Electrical System 16 days Wed 6/24/15 Thu 7/9/15

629 Installation electrical panel 2 days Wed 6/24/15 Thu 6/25/15

630 Installation lighting 6 days Fri 6/26/15 Wed 7/1/15

631 Installation wiring device 6 days Thu 7/2/15 Tue 7/7/15

632 Installation ELV equipment 2 days Wed 7/8/15 Thu 7/9/15

633 A/C and Ventilation System 16 days Wed 6/24/15 Thu 7/9/15

634 Installation A/C unit 10 days Wed 6/24/15 Fri 7/3/15

635 Installatin exhaust fan 6 days Sat 7/4/15 Thu 7/9/15

11/27 12/6

12/7 12/11

11/3 12/12

11/3 11/5

11/27 12/1

12/2 12/5

12/6 12/12

11/3 12/8

11/3 11/7

11/29 12/8

12/13 1/21

12/13 1/21

12/13 1/20

12/13 12/15

1/6 1/15

1/16 1/20

12/13 1/21

12/13 12/15

1/6 1/10

1/11 1/14

1/15 1/21

12/13 1/17

12/13 12/17

1/8 1/17

12/13 1/21

12/13 1/21

12/13 1/20

12/13 12/15

1/6 1/15

1/16 1/20

12/13 1/21

12/13 12/15

1/6 1/10

1/11 1/14

1/15 1/21

12/13 1/17

12/13 12/17

1/8 1/17

1/22 3/2

1/22 3/2

1/22 2/24

1/22 1/24

2/15 2/24

1/25 1/29

1/22 3/2

1/22 1/24

2/15 2/19

2/20 2/23

2/24 3/2

1/22 2/26

1/22 1/26

2/17 2/26

1/22 3/2

1/22 3/2

1/22 3/1

1/22 1/24

2/15 2/24

2/25 3/1

1/22 3/2

1/22 1/24

2/15 2/19

2/20 2/23

2/24 3/2

1/22 2/26

1/22 1/26

2/17 2/26

4/27 5/7

5/22 milestone ID (Hotel suit block 1 (001 to 006))

5/23 7/9

5/23 6/7

5/23 6/7

5/23 6/7

5/23 5/24

5/25 5/30

5/31 6/5

6/6 6/7

5/23 6/7

5/23 6/1

6/2 6/7

5/23 5/30

5/23 5/30

5/23 6/7

5/23 6/7

5/23 6/7

5/23 5/24

5/25 5/30

5/31 6/5

6/6 6/7

5/23 6/7

5/23 6/1

6/2 6/7

5/23 5/30

5/23 5/30

6/8 6/23

6/8 6/23

6/8 6/23

6/8 6/9

6/10 6/15

6/16 6/21

6/22 6/23

6/8 6/23

6/8 6/17

6/18 6/23

6/8 6/15

6/8 6/15

6/8 6/23

6/8 6/23

6/8 6/23

6/8 6/9

6/10 6/15

6/16 6/21

6/22 6/23

6/8 6/23

6/8 6/17

6/18 6/23

6/8 6/15

6/8 6/15

6/24 7/9

6/24 7/9

6/24 7/9

6/24 6/25

6/26 7/1

7/2 7/7

7/8 7/9

6/24 7/9

6/24 7/3

7/4 7/9

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep OctJuly August Septemb October Novembe Decembe January February March April May June July August Septemb October

Task

Split

Progress

Milestone

Summary

Project Summary

External Tasks

External Milestone

Deadline

MASTER SCHEDULE ALILA RESORT - KOH RUSSEY

Prepared by: Soly

Project: KRU-MEP ScheduleDate: Fri 10/24/14

ID ALILA RESORT-KOH RUSSEY M&E SCHEDULE Duration Start Finish

636 Plumbing system 8 days Wed 6/24/15 Wed 7/1/15

637 Installation sanitary ware 8 days Wed 6/24/15 Wed 7/1/15

638 HS unit 006 Second phase 16 days Wed 6/24/15 Thu 7/9/15

639 M&E Second phase 16 days Wed 6/24/15 Thu 7/9/15

640 Electrical System 16 days Wed 6/24/15 Thu 7/9/15

641 Installation electrical panel 2 days Wed 6/24/15 Thu 6/25/15

642 Installation lighting 6 days Fri 6/26/15 Wed 7/1/15

643 Installation wiring device 6 days Thu 7/2/15 Tue 7/7/15

644 Installation ELV equipment 2 days Wed 7/8/15 Thu 7/9/15

645 A/C and Ventilation System 16 days Wed 6/24/15 Thu 7/9/15

646 Installation A/C unit 10 days Wed 6/24/15 Fri 7/3/15

647 Installatin exhaust fan 6 days Sat 7/4/15 Thu 7/9/15

648 Plumbing system 8 days Wed 6/24/15 Wed 7/1/15

649 Installation sanitary ware 8 days Wed 6/24/15 Wed 7/1/15

650 Final inspection for CEMP 0 days Thu 7/9/15 Thu 7/9/15

651 Hotel suit block 4 (039 to 044) 303 days Tue 10/7/14 Tue 8/11/15

652 A. Drawing preparation 15 days Tue 10/7/14Tue 10/21/14

653 B. Material procurement and transportation 150 days Tue 10/14/14 Thu 3/12/15

654 C. Clearing and grubbing / and filling work 7 days Wed 10/22/14 Tue 10/28/14

655 F. Ground floor 165 days Wed 10/29/14 Sat 4/11/15

656 a. Structure work 78 days Wed 10/29/14 Wed 1/14/15

657 1. Foundation / Stump Column and back filling work 40 days Wed 10/29/14 Sun 12/7/14

658 2. Ground beam and slab work 30 days Mon 12/1/14 Tue 12/30/14

659 3. Column work 20 days Fri 12/26/14 Wed 1/14/15

660 b. Finishing work 50 days Sat 2/21/15 Sat 4/11/15

661 1.Masonry work 25 days Sat 2/21/15 Tue 3/17/15

662 2. Plastering work 25 days Wed 3/18/15 Sat 4/11/15

663 G. First floor 130 days Thu 1/15/15 Sat 5/30/15

664 a. Structure work 80 days Thu 1/15/15 Sat 4/4/15

665 1. First floor beam and slab 30 days Thu 1/15/15 Fri 2/13/15

666 2. Column work 20 days Sat 2/14/15 Thu 3/5/15

667 3. Roof beam and slab 30 days Fri 3/6/15 Sat 4/4/15

668 b. Finishing work 50 days Sun 4/5/15 Sat 5/30/15

669 1.Masonry work 25 days Sun 4/5/15 Tue 5/5/15

670 2. Plastering work 25 days Wed 5/6/15 Sat 5/30/15

671 H. Water proofing work 30 days Wed 4/8/15 Wed 5/13/15

672 milestone PHV (Hotel Suit Block 4 (039-t0 044)) 0 days Sun 11/30/14Sun 11/30/14

673 Hotel suit block 4 (039 to 044) M&E first phase 120 days Sun 11/30/14 Sun 3/29/15

674 HS unit 039 first phase 40 days Sun 11/30/14 Thu 1/8/15

675 M&E first phase 40 days Sun 11/30/14 Thu 1/8/15

676 Electrical System 39 days Sun 11/30/14 Wed 1/7/15

677 Pipe sleeve installation 3 days Sun 11/30/14 Tue 12/2/14

678 Installation conduit above the ceiling & embedded in wall 10 days Wed 12/24/14 Fri 1/2/15

679 Pulling the Cable for LV and ELV 5 days Sat 1/3/15 Wed 1/7/15

680 A/C and Ventilation System 40 days Sun 11/30/14 Thu 1/8/15

681 Prepare the sleeve for refrigerant pipe installation 3 days Sun 11/30/14 Tue 12/2/14

682 Installation Refregerant pipe and insulation 5 days Wed 12/24/14Sun 12/28/14

683 Installatin drain pipe and insulation 4 days Mon 12/29/14 Thu 1/1/15

684 Installation ducting system 7 days Fri 1/2/15 Thu 1/8/15

685 Plumbing System 36 days Sun 11/30/14 Sun 1/4/15

686 Installation Underground pipe for waste water, rain water 5 days Sun 11/30/14 Thu 12/4/14

687 Installation above ground pipe for waste water, rain wate 10 days Fri 12/26/14 Sun 1/4/15

688 HS unit 040 first phase 40 days Sun 11/30/14 Thu 1/8/15

689 M&E first phase 40 days Sun 11/30/14 Thu 1/8/15

690 Electrical System 39 days Sun 11/30/14 Wed 1/7/15

691 Pipe sleeve installation 3 days Sun 11/30/14 Tue 12/2/14

692 Installation conduit above the ceiling & embedded in wall 10 days Wed 12/24/14 Fri 1/2/15

693 Pulling the Cable for LV and ELV 5 days Sat 1/3/15 Wed 1/7/15

694 A/C and Ventilation System 40 days Sun 11/30/14 Thu 1/8/15

695 Prepare the sleeve for refrigerant pipe installation 3 days Sun 11/30/14 Tue 12/2/14

696 Installation Refregerant pipe and insulation 5 days Wed 12/24/14Sun 12/28/14

697 Installatin drain pipe and insulation 4 days Mon 12/29/14 Thu 1/1/15

698 Installation ducting system 7 days Fri 1/2/15 Thu 1/8/15

699 Plumbing System 36 days Sun 11/30/14 Sun 1/4/15

700 Installation Underground pipe for waste water, rain water 5 days Sun 11/30/14 Thu 12/4/14

701 Installation above ground pipe for waste water, rain wate 10 days Fri 12/26/14 Sun 1/4/15

702 HS unit 041 first phase 40 days Fri 1/9/15 Tue 2/17/15

703 M&E first phase 40 days Fri 1/9/15 Tue 2/17/15

704 Electrical System 39 days Fri 1/9/15 Mon 2/16/15

705 Pipe sleeve installation 3 days Fri 1/9/15 Sun 1/11/15

706 Installation conduit above the ceiling & embedded in wall 10 days Mon 2/2/15 Wed 2/11/15

707 Pulling the Cable for LV and ELV 5 days Thu 2/12/15 Mon 2/16/15

708 A/C and Ventilation System 40 days Fri 1/9/15 Tue 2/17/15

709 Prepare the sleeve for refrigerant pipe installation 3 days Fri 1/9/15 Sun 1/11/15

710 Installation Refregerant pipe and insulation 5 days Mon 2/2/15 Fri 2/6/15

711 Installatin drain pipe and insulation 4 days Sat 2/7/15 Tue 2/10/15

712 Installation ducting system 7 days Wed 2/11/15 Tue 2/17/15

713 Plumbing System 36 days Fri 1/9/15 Fri 2/13/15

714 Installation Underground pipe for waste water, rain water 5 days Fri 1/9/15 Tue 1/13/15

715 Installation above ground pipe for waste water, rain wate 10 days Wed 2/4/15 Fri 2/13/15

716 HS unit 042 first phase 40 days Fri 1/9/15 Tue 2/17/15

717 M&E first phase 40 days Fri 1/9/15 Tue 2/17/15

718 Electrical System 39 days Fri 1/9/15 Mon 2/16/15

719 Pipe sleeve installation 3 days Fri 1/9/15 Sun 1/11/15

720 Installation conduit above the ceiling & embedded in wall 10 days Mon 2/2/15 Wed 2/11/15

721 Pulling the Cable for LV and ELV 5 days Thu 2/12/15 Mon 2/16/15

722 A/C and Ventilation System 40 days Fri 1/9/15 Tue 2/17/15

723 Prepare the sleeve for refrigerant pipe installation 3 days Fri 1/9/15 Sun 1/11/15

724 Installation Refregerant pipe and insulation 5 days Mon 2/2/15 Fri 2/6/15

725 Installatin drain pipe and insulation 4 days Sat 2/7/15 Tue 2/10/15

726 Installation ducting system 7 days Wed 2/11/15 Tue 2/17/15

727 Plumbing System 36 days Fri 1/9/15 Fri 2/13/15

728 Installation Underground pipe for waste water, rain water 5 days Fri 1/9/15 Tue 1/13/15

729 Installation above ground pipe for waste water, rain wate 10 days Wed 2/4/15 Fri 2/13/15

730 HS unit 043 first phase 40 days Wed 2/18/15 Sun 3/29/15

731 M&E first phase 40 days Wed 2/18/15 Sun 3/29/15

732 Electrical System 39 days Wed 2/18/15 Sat 3/28/15

733 Pipe sleeve installation 3 days Wed 2/18/15 Fri 2/20/15

734 Installation conduit above the ceiling & embedded in wall 10 days Sat 3/14/15 Mon 3/23/15

735 Pulling the Cable for LV and ELV 5 days Tue 3/24/15 Sat 3/28/15

736 A/C and Ventilation System 40 days Wed 2/18/15 Sun 3/29/15

737 Prepare the sleeve for refrigerant pipe installation 3 days Wed 2/18/15 Fri 2/20/15

738 Installation Refregerant pipe and insulation 5 days Sat 3/14/15 Wed 3/18/15

739 Installatin drain pipe and insulation 4 days Thu 3/19/15 Sun 3/22/15

740 Installation ducting system 7 days Mon 3/23/15 Sun 3/29/15

741 Plumbing System 36 days Wed 2/18/15 Wed 3/25/15

742 Installation Underground pipe for waste water, rain water 5 days Wed 2/18/15 Sun 2/22/15

743 Installation above ground pipe for waste water, rain wate 10 days Mon 3/16/15 Wed 3/25/15

744 HS unit 044 first phase 40 days Wed 2/18/15 Sun 3/29/15

745 M&E first phase 40 days Wed 2/18/15 Sun 3/29/15

746 Electrical System 39 days Wed 2/18/15 Sat 3/28/15

747 Pipe sleeve installation 3 days Wed 2/18/15 Fri 2/20/15

748 Installation conduit above the ceiling & embedded in wall 10 days Sat 3/14/15 Mon 3/23/15

749 Pulling the Cable for LV and ELV 5 days Tue 3/24/15 Sat 3/28/15

750 A/C and Ventilation System 40 days Wed 2/18/15 Sun 3/29/15

751 Prepare the sleeve for refrigerant pipe installation 3 days Wed 2/18/15 Fri 2/20/15

752 Installation Refregerant pipe and insulation 5 days Sat 3/14/15 Wed 3/18/15

753 Installatin drain pipe and insulation 4 days Thu 3/19/15 Sun 3/22/15

754 Installation ducting system 7 days Mon 3/23/15 Sun 3/29/15

755 Plumbing System 36 days Wed 2/18/15 Wed 3/25/15

756 Installation Underground pipe for waste water, rain water 5 days Wed 2/18/15 Sun 2/22/15

757 Installation above ground pipe for waste water, rain wate 10 days Mon 3/16/15 Wed 3/25/15

758 J. Final inspection/Punch Listing and Hand over 10 days Sun 5/31/15 Tue 6/9/15

759 milestone ID (Hotel Suit Block 4 (039-t0 044)) 0 days Wed 6/24/15 Wed 6/24/15

760 Hotel suit block 4 (039 to 044) M&E Second phase 48 days Thu 6/25/15 Tue 8/11/15

761 HS unit 039 second phase 16 days Thu 6/25/15 Fri 7/10/15

762 M&E Second phase 16 days Thu 6/25/15 Fri 7/10/15

6/24 7/1

6/24 7/1

6/24 7/9

6/24 7/9

6/24 7/9

6/24 6/25

6/26 7/1

7/2 7/7

7/8 7/9

6/24 7/9

6/24 7/3

7/4 7/9

6/24 7/1

6/24 7/1

7/9 Final inspection for CEMP

10/7 8/11

10/7 10/21

10/14 3/12

10/22 10/28

10/29 4/11

10/29 1/14

10/29 12/7

12/1 12/30

12/26 1/14

2/21 4/11

2/21 3/17

3/18 4/11

1/15 5/30

1/15 4/4

1/15 2/13

2/14 3/5

3/6 4/4

4/5 5/30

4/5 5/5

5/6 5/30

4/8 5/13

11/30 milestone PHV (Hotel Suit Block 4 (039-t0 044))

11/30 3/29

11/30 1/8

11/30 1/8

11/30 1/7

11/30 12/2

12/24 1/2

1/3 1/7

11/30 1/8

11/30 12/2

12/24 12/28

12/29 1/1

1/2 1/8

11/30 1/4

11/30 12/4

12/26 1/4

11/30 1/8

11/30 1/8

11/30 1/7

11/30 12/2

12/24 1/2

1/3 1/7

11/30 1/8

11/30 12/2

12/24 12/28

12/29 1/1

1/2 1/8

11/30 1/4

11/30 12/4

12/26 1/4

1/9 2/17

1/9 2/17

1/9 2/16

1/9 1/11

2/2 2/11

2/12 2/16

1/9 2/17

1/9 1/11

2/2 2/6

2/7 2/10

2/11 2/17

1/9 2/13

1/9 1/13

2/4 2/13

1/9 2/17

1/9 2/17

1/9 2/16

1/9 1/11

2/2 2/11

2/12 2/16

1/9 2/17

1/9 1/11

2/2 2/6

2/7 2/10

2/11 2/17

1/9 2/13

1/9 1/13

2/4 2/13

2/18 3/29

2/18 3/29

2/18 3/28

2/18 2/20

3/14 3/23

3/24 3/28

2/18 3/29

2/18 2/20

3/14 3/18

3/19 3/22

3/23 3/29

2/18 3/25

2/18 2/22

3/16 3/25

2/18 3/29

2/18 3/29

2/18 3/28

2/18 2/20

3/14 3/23

3/24 3/28

2/18 3/29

2/18 2/20

3/14 3/18

3/19 3/22

3/23 3/29

2/18 3/25

2/18 2/22

3/16 3/25

5/31 6/9

6/24 milestone ID (Hotel Suit Block 4 (039-t0 0

6/25 8/11

6/25 7/10

6/25 7/10

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep OctJuly August Septemb October Novembe Decembe January February March April May June July August Septemb October

Task

Split

Progress

Milestone

Summary

Project Summary

External Tasks

External Milestone

Deadline

MASTER SCHEDULE ALILA RESORT - KOH RUSSEY

Prepared by: Soly

Project: KRU-MEP ScheduleDate: Fri 10/24/14

ID ALILA RESORT-KOH RUSSEY M&E SCHEDULE Duration Start Finish

763 Electrical System 16 days Thu 6/25/15 Fri 7/10/15

764 Installation electrical panel 2 days Thu 6/25/15 Fri 6/26/15

765 Installation lighting 6 days Sat 6/27/15 Thu 7/2/15

766 Installation wiring device 6 days Fri 7/3/15 Wed 7/8/15

767 Installation ELV equipment 2 days Thu 7/9/15 Fri 7/10/15

768 A/C and Ventilation System 16 days Thu 6/25/15 Fri 7/10/15

769 Installation A/C unit 10 days Thu 6/25/15 Sat 7/4/15

770 Installatin exhaust fan 6 days Sun 7/5/15 Fri 7/10/15

771 Plumbing System 8 days Thu 6/25/15 Thu 7/2/15

772 Installation sanitary ware 8 days Thu 6/25/15 Thu 7/2/15

773 HS unit 040 Second phase 16 days Thu 6/25/15 Fri 7/10/15

774 M&E Second phase 16 days Thu 6/25/15 Fri 7/10/15

775 Electrical System 16 days Thu 6/25/15 Fri 7/10/15

776 Installation electrical panel 2 days Thu 6/25/15 Fri 6/26/15

777 Installation lighting 6 days Sat 6/27/15 Thu 7/2/15

778 Installation wiring device 6 days Fri 7/3/15 Wed 7/8/15

779 Installation ELV equipment 2 days Thu 7/9/15 Fri 7/10/15

780 A/C and Ventilation System 16 days Thu 6/25/15 Fri 7/10/15

781 Installation A/C unit 10 days Thu 6/25/15 Sat 7/4/15

782 Installatin exhaust fan 6 days Sun 7/5/15 Fri 7/10/15

783 Plumbing System 8 days Thu 6/25/15 Thu 7/2/15

784 Installation sanitary ware 8 days Thu 6/25/15 Thu 7/2/15

785 HS unit 041 Second phase 16 days Sat 7/11/15 Sun 7/26/15

786 M&E Second phase 16 days Sat 7/11/15 Sun 7/26/15

787 Electrical System 16 days Sat 7/11/15 Sun 7/26/15

788 Installation electrical panel 2 days Sat 7/11/15 Sun 7/12/15

789 Installation lighting 6 days Mon 7/13/15 Sat 7/18/15

790 Installation wiring device 6 days Sun 7/19/15 Fri 7/24/15

791 Installation ELV equipment 2 days Sat 7/25/15 Sun 7/26/15

792 A/C and Ventilation System 16 days Sat 7/11/15 Sun 7/26/15

793 Installation A/C unit 10 days Sat 7/11/15 Mon 7/20/15

794 Installatin exhaust fan 6 days Tue 7/21/15 Sun 7/26/15

795 Plumbing System 8 days Sat 7/11/15 Sat 7/18/15

796 Installation sanitary ware 8 days Sat 7/11/15 Sat 7/18/15

797 HS unit 042 Second phase 16 days Sat 7/11/15 Sun 7/26/15

798 M&E Second phase 16 days Sat 7/11/15 Sun 7/26/15

799 Electrical System 16 days Sat 7/11/15 Sun 7/26/15

800 Installation electrical panel 2 days Sat 7/11/15 Sun 7/12/15

801 Installation lighting 6 days Mon 7/13/15 Sat 7/18/15

802 Installation wiring device 6 days Sun 7/19/15 Fri 7/24/15

803 Installation ELV equipment 2 days Sat 7/25/15 Sun 7/26/15

804 A/C and Ventilation System 16 days Sat 7/11/15 Sun 7/26/15

805 Installation A/C unit 10 days Sat 7/11/15 Mon 7/20/15

806 Installatin exhaust fan 6 days Tue 7/21/15 Sun 7/26/15

807 Plumbing System 8 days Sat 7/11/15 Sat 7/18/15

808 Installation sanitary ware 8 days Sat 7/11/15 Sat 7/18/15

809 HS unit 043 Second phase 16 days Mon 7/27/15 Tue 8/11/15

810 M&E Second phase 16 days Mon 7/27/15 Tue 8/11/15

811 Electrical System 16 days Mon 7/27/15 Tue 8/11/15

812 Installation electrical panel 2 days Mon 7/27/15 Tue 7/28/15

813 Installation lighting 6 days Wed 7/29/15 Mon 8/3/15

814 Installation wiring device 6 days Tue 8/4/15 Sun 8/9/15

815 Installation ELV equipment 2 days Mon 8/10/15 Tue 8/11/15

816 A/C and Ventilation System 16 days Mon 7/27/15 Tue 8/11/15

817 Installation A/C unit 10 days Mon 7/27/15 Wed 8/5/15

818 Installatin exhaust fan 6 days Thu 8/6/15 Tue 8/11/15

819 Plumbing System 8 days Mon 7/27/15 Mon 8/3/15

820 Installation sanitary ware 8 days Mon 7/27/15 Mon 8/3/15

821 HS unit 044 Second phase 16 days Mon 7/27/15 Tue 8/11/15

822 M&E Second phase 16 days Mon 7/27/15 Tue 8/11/15

823 Electrical System 16 days Mon 7/27/15 Tue 8/11/15

824 Installation electrical panel 2 days Mon 7/27/15 Tue 7/28/15

825 Installation lighting 6 days Wed 7/29/15 Mon 8/3/15

826 Installation wiring device 6 days Tue 8/4/15 Sun 8/9/15

827 Installation ELV equipment 2 days Mon 8/10/15 Tue 8/11/15

828 A/C and Ventilation System 16 days Mon 7/27/15 Tue 8/11/15

829 Installation A/C unit 10 days Mon 7/27/15 Wed 8/5/15

830 Installatin exhaust fan 6 days Thu 8/6/15 Tue 8/11/15

831 Plumbing System 8 days Mon 7/27/15 Mon 8/3/15

832 Installation sanitary ware 8 days Mon 7/27/15 Mon 8/3/15

833 Final inspection for CEMP 0 days Tue 8/11/15 Tue 8/11/15

834 Central Area Building 274 days Mon 9/15/14 Sun 6/21/15

835 A. Drawing preparation 30 days Mon 9/15/14 Tue 10/14/14

836 B. Material procurement and transportation 200 days Mon 9/15/14 Thu 4/2/15

837 C. Clearing and grubbing / Cut and filling/Disposal of Excess Soil 31 days Tue 9/30/14Thu 10/30/14

838 Back House 228 days Fri 10/31/14 Sun 6/21/15

839 1. Foundation / Stump Column and back filling work 40 days Fri 10/31/14 Tue 12/9/14

840 2. Ground beam and slab work 44 days Tue 12/2/14 Wed 1/14/15

841 3. Column work 35 days Thu 1/8/15 Wed 2/11/15

842 4. Beam, Roof slab and First Floor 42 days Thu 2/5/15 Wed 3/18/15

843 5. Column Works 12 days Tue 3/17/15 Sat 3/28/15

844 6. Beam and Roof Slab Works 16 days Fri 3/27/15 Sat 4/11/15

845 5. Water Proofing Work 41 days Sat 3/14/15 Sat 5/16/15

846 6.Masonry Works 65 days Thu 2/26/15 Mon 5/11/15

847 milestone PHV (Back House) 0 days Mon 12/1/14 Mon 12/1/14

848 M&E first phase 70 days Mon 12/1/14 Sun 2/8/15

849 Electrical System 69 days Mon 12/1/14 Sat 2/7/15

850 Pipe sleeve installation 5 days Mon 12/1/14 Fri 12/5/14

851 Installation conduit above the ceiling & embedded in wall 12 days Tue 1/20/15 Sat 1/31/15

852 Pulling the Cable for LV and ELV 7 days Sun 2/1/15 Sat 2/7/15

853 A/C and Ventilation System 70 days Mon 12/1/14 Sun 2/8/15

854 Prepare the sleeve for refrigerant pipe installation 5 days Mon 12/1/14 Fri 12/5/14

855 Installation Refregerant pipe and insulation 6 days Tue 1/20/15 Sun 1/25/15

856 Installatin drain pipe and insulation 7 days Mon 1/26/15 Sun 2/1/15

857 Installation ducting system 7 days Mon 2/2/15 Sun 2/8/15

858 Plumbing System 64 days Mon 12/1/14 Mon 2/2/15

859 Installation Underground pipe for waste water, rain water and 7 days Mon 12/1/14 Sun 12/7/14

860 Installation above ground pipe for waste water, rain water, co 12 days Thu 1/22/15 Mon 2/2/15

861 8. Final Inspection/ Punch Listing and Hand Over PHV 10 days Sun 5/17/15 Tue 5/26/15

862 milestone ID (Back House) 0 days Wed 6/10/15 Wed 6/10/15

863 M&E Second phase 11 days Thu 6/11/15 Sun 6/21/15

864 Electrical System 11 days Thu 6/11/15 Sun 6/21/15

865 Installation electrical panel 2 days Thu 6/11/15 Fri 6/12/15

866 Installation lighting 4 days Sat 6/13/15 Tue 6/16/15

867 Installation wiring device 2 days Wed 6/17/15 Thu 6/18/15

868 Installation ELV equipment 3 days Fri 6/19/15 Sun 6/21/15

869 A/C and Ventilation System 11 days Thu 6/11/15 Sun 6/21/15

870 Installation A/C unit 6 days Thu 6/11/15 Tue 6/16/15

871 Installatin exhaust fan 5 days Wed 6/17/15 Sun 6/21/15

872 Plumbing System 6 days Thu 6/11/15 Tue 6/16/15

873 Installation sanitary ware 6 days Thu 6/11/15 Tue 6/16/15

874 Final inspection for CEMP 0 days Sun 6/21/15 Sun 6/21/15

875 Arrival Building 114 days Sat 12/20/14 Sun 4/12/15

876 1. Foundation / Stump Column and back filling work 20 days Sat 12/20/14 Thu 1/8/15

877 2. Ground beam and slab work 15 days Fri 1/9/15 Fri 1/23/15

878 3. Column work 10 days Sat 1/24/15 Mon 2/2/15

879 4. Roof beam and slab 15 days Tue 2/3/15 Tue 2/17/15

880 5. Water Proofing Work 15 days Wed 2/18/15 Wed 3/4/15

881 6.Masonry Works 15 days Sat 2/21/15 Sat 3/7/15

882 milestone PHV (Arrrival Building) 0 days Sun 1/4/15 Sun 1/4/15

883 M&E first phase 42 days Sun 1/4/15 Sat 2/14/15

884 Electrical System 42 days Sun 1/4/15 Sat 2/14/15

885 Pipe sleeve installation 4 days Sun 1/4/15 Wed 1/7/15

886 Installation conduit above the ceiling & embedded in wall 11 days Thu 1/29/15 Sun 2/8/15

887 Pulling the Cable for LV and ELV 6 days Mon 2/9/15 Sat 2/14/15

888 A/C and Ventilation System 42 days Sun 1/4/15 Sat 2/14/15

889 Prepare the sleeve for refrigerant pipe installation 4 days Sun 1/4/15 Wed 1/7/15

6/25 7/10

6/25 6/26

6/27 7/2

7/3 7/8

7/9 7/10

6/25 7/10

6/25 7/4

7/5 7/10

6/25 7/2

6/25 7/2

6/25 7/10

6/25 7/10

6/25 7/10

6/25 6/26

6/27 7/2

7/3 7/8

7/9 7/10

6/25 7/10

6/25 7/4

7/5 7/10

6/25 7/2

6/25 7/2

7/11 7/26

7/11 7/26

7/11 7/26

7/11 7/12

7/13 7/18

7/19 7/24

7/25 7/26

7/11 7/26

7/11 7/20

7/21 7/26

7/11 7/18

7/11 7/18

7/11 7/26

7/11 7/26

7/11 7/26

7/11 7/12

7/13 7/18

7/19 7/24

7/25 7/26

7/11 7/26

7/11 7/20

7/21 7/26

7/11 7/18

7/11 7/18

7/27 8/11

7/27 8/11

7/27 8/11

7/27 7/28

7/29 8/3

8/4 8/9

8/10 8/11

7/27 8/11

7/27 8/5

8/6 8/11

7/27 8/3

7/27 8/3

7/27 8/11

7/27 8/11

7/27 8/11

7/27 7/28

7/29 8/3

8/4 8/9

8/10 8/11

7/27 8/11

7/27 8/5

8/6 8/11

7/27 8/3

7/27 8/3

8/11 Final inspection for CEM

9/15 6/21

9/15 10/14

9/15 4/2

9/30 10/30

10/31 6/21

10/31 12/9

12/2 1/14

1/8 2/11

2/5 3/18

3/17 3/28

3/27 4/11

3/14 5/16

2/26 5/11

12/1 milestone PHV (Back House)

12/1 2/8

12/1 2/7

12/1 12/5

1/20 1/31

2/1 2/7

12/1 2/8

12/1 12/5

1/20 1/25

1/26 2/1

2/2 2/8

12/1 2/2

12/1 12/7

1/22 2/2

5/17 5/26

6/10 milestone ID (Back House)

6/11 6/21

6/11 6/21

6/11 6/12

6/13 6/16

6/17 6/18

6/19 6/21

6/11 6/21

6/11 6/16

6/17 6/21

6/11 6/16

6/11 6/16

6/21 Final inspection for CEMP

12/20 4/12

12/20 1/8

1/9 1/23

1/24 2/2

2/3 2/17

2/18 3/4

2/21 3/7

1/4 milestone PHV (Arrrival Building)

1/4 2/14

1/4 2/14

1/4 1/7

1/29 2/8

2/9 2/14

1/4 2/14

1/4 1/7

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep OctJuly August Septemb October Novembe Decembe January February March April May June July August Septemb October

Task

Split

Progress

Milestone

Summary

Project Summary

External Tasks

External Milestone

Deadline

MASTER SCHEDULE ALILA RESORT - KOH RUSSEY

Prepared by: Soly

Project: KRU-MEP ScheduleDate: Fri 10/24/14

ID ALILA RESORT-KOH RUSSEY M&E SCHEDULE Duration Start Finish

890 Installation Refregerant pipe and insulation 5 days Thu 1/29/15 Mon 2/2/15

891 Installatin drain pipe and insulation 5 days Tue 2/3/15 Sat 2/7/15

892 Installation ducting system 7 days Sun 2/8/15 Sat 2/14/15

893 Plumbing System 42 days Sun 1/4/15 Sat 2/14/15

894 Installation Underground pipe for waste water, rain water and 7 days Sun 1/4/15 Sat 1/10/15

895 Installation above ground pipe for waste water, rain water, co 14 days Sun 2/1/15 Sat 2/14/15

896 8. Final Inspection/Punch Listing and Hand Over PHV 10 days Sun 3/8/15 Tue 3/17/15

897 milestone ID (Arrrival Building) 0 days Wed 4/1/15 Wed 4/1/15

898 M&E Second phase 11 days Thu 4/2/15 Sun 4/12/15

899 Electrical System 11 days Thu 4/2/15 Sun 4/12/15

900 Installation electrical panel 2 days Thu 4/2/15 Fri 4/3/15

901 Installation lighting 5 days Sat 4/4/15 Wed 4/8/15

902 Installation wiring device 2 days Thu 4/9/15 Fri 4/10/15

903 Installation ELV equipment 2 days Sat 4/11/15 Sun 4/12/15

904 A/C and Ventilation System 11 days Thu 4/2/15 Sun 4/12/15

905 Installation A/C unit 7 days Thu 4/2/15 Wed 4/8/15

906 Installation exhaust fan 4 days Thu 4/9/15 Sun 4/12/15

907 Plumbing System 6 days Thu 4/2/15 Tue 4/7/15

908 Installation sanitary ware 6 days Thu 4/2/15 Tue 4/7/15

909 Final inspection CEMP 0 days Sun 4/12/15 Sun 4/12/15

910 Main Restaurant & kitchen building 156 days Thu 11/20/14 Thu 4/30/15

911 1. Foundation / Stump Column and back filling work 42 days Thu 11/20/14Wed 12/31/14

912 2. Ground beam and slab work 35 days Thu 12/18/14 Wed 1/21/15

913 3. Column work 24 days Mon 1/12/15 Wed 2/4/15

914 4. Roof beam and slab 31 days Mon 1/26/15 Wed 2/25/15

915 5. Water Proofing Work 25 days Sat 2/21/15 Tue 3/17/15

916 6.Masonry Works 35 days Thu 2/12/15 Wed 3/18/15

917 milestone PHV ( Main Restaurant/ kitchen) 0 days Wed 12/17/14Wed 12/17/14

918 M&E first phase 51 days Wed 12/17/14 Thu 2/5/15

919 Electrical System 44 days Wed 12/17/14 Thu 1/29/15

920 Pipe sleeve installation 4 days Wed 12/17/14 Sat 12/20/14

921 Installation conduit above the ceiling & embedded in wall 12 days Sun 1/11/15 Thu 1/22/15

922 Pulling the Cable for LV and ELV 7 days Fri 1/23/15 Thu 1/29/15

923 A/C and Ventilation System 51 days Wed 12/17/14 Thu 2/5/15

924 Prepare the sleeve for refrigerant pipe installation 4 days Wed 12/17/14 Sat 12/20/14

925 Installation Refregerant pipe and insulation 8 days Sun 1/11/15 Sun 1/18/15

926 Installatin drain pipe and insulation 8 days Mon 1/19/15 Mon 1/26/15

927 Installation ducting system 10 days Tue 1/27/15 Thu 2/5/15

928 Plumbing System 40 days Wed 12/17/14 Sun 1/25/15

929 Installation Underground pipe for waste water, rain water and 7 days Wed 12/17/14 Tue 12/23/14

930 Installation above ground pipe for waste water, rain water, co 12 days Wed 1/14/15 Sun 1/25/15

931 8. Final Inspection/ Punch Listing and Hand Over PHV 10 days Thu 3/19/15 Sat 3/28/15

932 milestone ID ( Main Restaurant/ kitchen) 0 days Sun 4/12/15 Sun 4/12/15

933 M&E Second phase 12 days Sun 4/19/15 Thu 4/30/15

934 Electrical System 11 days Sun 4/19/15 Wed 4/29/15

935 Installation electrical panel 2 days Sun 4/19/15 Mon 4/20/15

936 Installation lighting 5 days Tue 4/21/15 Sat 4/25/15

937 Installation wiring device 2 days Sun 4/26/15 Mon 4/27/15

938 Installation ELV equipment 2 days Tue 4/28/15 Wed 4/29/15

939 A/C and Ventilation System 12 days Sun 4/19/15 Thu 4/30/15

940 Installation A/C unit 7 days Sun 4/19/15 Sat 4/25/15

941 Installatin exhaust fan 5 days Sun 4/26/15 Thu 4/30/15

942 Plumbing System 8 days Sun 4/19/15 Sun 4/26/15

943 Installation sanitary ware 8 days Sun 4/19/15 Sun 4/26/15

944 Final inspection CEMP 0 days Thu 4/30/15 Thu 4/30/15

945 Spa & Shack building 161 days Thu 12/18/14 Tue 6/2/15

946 1. Foundation / Stump Column and back filling work 42 days Thu 12/18/14 Wed 1/28/15

947 2. Ground beam and slab work 30 days Tue 1/20/15 Wed 2/18/15

948 3. Column work 21 days Thu 2/12/15 Wed 3/4/15

949 4. Roof beam and slab 28 days Thu 2/26/15 Wed 3/25/15

950 5. Water Proofing Work 25 days Sun 3/29/15 Tue 4/28/15

951 6.Masonry Works 35 days Thu 3/19/15 Tue 4/28/15

952 milestone PHV Spa/Shack 0 days Thu 1/15/15 Thu 1/15/15

953 M&E first phase 54 days Thu 1/15/15 Mon 3/9/15

954 Electrical System 45 days Thu 1/15/15 Sat 2/28/15

955 Pipe sleeve installation 3 days Thu 1/15/15 Sat 1/17/15

956 Installation conduit above the ceiling & embedded in wall 7 days Tue 2/17/15 Mon 2/23/15

957 Pulling the Cable for LV and ELV 5 days Tue 2/24/15 Sat 2/28/15

958 A/C and Ventilation System 54 days Thu 1/15/15 Mon 3/9/15

959 Prepare the sleeve for refrigerant pipe installation 4 days Thu 1/15/15 Sun 1/18/15

960 Installation Refregerant pipe and insulation 7 days Wed 2/18/15 Tue 2/24/15

961 Installatin drain pipe and insulation 3 days Wed 2/25/15 Fri 2/27/15

962 Installation ducting system 10 days Sat 2/28/15 Mon 3/9/15

963 Plumbing System 46 days Thu 1/15/15 Sun 3/1/15

964 Installation Underground pipe for waste water, rain water and 6 days Thu 1/15/15 Tue 1/20/15

965 Installation above ground pipe for waste water, rain water, co 10 days Fri 2/20/15 Sun 3/1/15

966 8. Final Inspection/Punch Listing and Hand Over PHV 10 days Wed 4/29/15 Fri 5/8/15

967 milestone ID Spa/Shack 0 days Sat 5/23/15 Sat 5/23/15

968 M&E Second phase 10 days Sun 5/24/15 Tue 6/2/15

969 Electrical System 10 days Sun 5/24/15 Tue 6/2/15

970 Installation electrical panel 2 days Sun 5/24/15 Mon 5/25/15

971 Installation lighting 4 days Tue 5/26/15 Fri 5/29/15

972 Installation wiring device 2 days Sat 5/30/15 Sun 5/31/15

973 Installation ELV equipment 2 days Mon 6/1/15 Tue 6/2/15

974 A/C and Ventilation System 9 days Sun 5/24/15 Mon 6/1/15

975 Installation A/C unit 4 days Sun 5/24/15 Wed 5/27/15

976 Installatin exhaust fan 5 days Thu 5/28/15 Mon 6/1/15

977 Plumbing System 6 days Sun 5/24/15 Fri 5/29/15

978 Installation sanitary ware 6 days Sun 5/24/15 Fri 5/29/15

979 Final Inspection CEMP 0 days Tue 6/2/15 Tue 6/2/15

980 Main Pool Area 78 days Thu 1/22/15 Thu 4/9/15

981 1. Excavation/ Lean Concrete /Concrete Slab Works 35 days Thu 1/22/15 Wed 2/25/15

982 2. Concrete Wall Works 35 days Thu 2/26/15 Wed 4/1/15

983 milestone PHV Main Pool 0 days Wed 2/11/15 Wed 2/11/15

984 M&E first phase 12 days Wed 2/11/15 Sun 2/22/15

985 Piping work 12 days Wed 2/11/15 Sun 2/22/15

986 Installation underground pipe work for pool system 5 days Wed 2/11/15 Sun 2/15/15

987 Installation above ground pipe work for pool system 7 days Mon 2/16/15 Sun 2/22/15

988 M&E second phase 6 days Sat 4/4/15 Thu 4/9/15

989 Pool equipment 6 days Sat 4/4/15 Thu 4/9/15

990 Installation pool motor 3 days Sat 4/4/15 Mon 4/6/15

991 Installation pool filter and accessory 3 days Tue 4/7/15 Thu 4/9/15

992 Final Inspection CEMP 0 days Thu 4/9/15 Thu 4/9/15

993 Villa 2 Bed Room 201 167 days Sat 11/15/14 Wed 5/6/15

994 A. Drawing preparation 15 days Sat 11/15/14 Sat 11/29/14

995 B. Material procurement and transportation 91 days Thu 11/20/14 Wed 2/18/15

996 C. Clearing and grubbing / Cut and filling work 7 days Sun 11/30/14 Sat 12/6/14

997 C. Structure work 67 days Mon 12/8/14 Thu 2/12/15

998 1. Foundation / Stump Column and back filling work 25 days Mon 12/8/14 Thu 1/1/15

999 2. Ground beam and slab work 20 days Sun 12/28/14 Fri 1/16/15

1000 3. Column work 15 days Wed 1/14/15 Wed 1/28/15

1001 4. Roof beam and slab 15 days Thu 1/29/15 Thu 2/12/15

1002 D. Finishing work 35 days Mon 2/16/15 Sun 3/22/15

1003 1.Masonry work 20 days Mon 2/16/15 Sat 3/7/15

1004 2. Plastering work 20 days Tue 3/3/15 Sun 3/22/15

1005 E. Steel work 30 days Sat 1/17/15 Sun 2/15/15

1006 1. All steel work 30 days Sat 1/17/15 Sun 2/15/15

1007 F. Water proofing work 30 days Fri 2/13/15 Sat 3/14/15

1008 1. Water proof for roof ..tec. 30 days Fri 2/13/15 Sat 3/14/15

1009 G. Swimming Pool 40 days Fri 1/2/15 Tue 2/10/15

1010 H. Septic Tank 20 days Fri 1/2/15 Wed 1/21/15

1011 milestone PHV (Villa 2 Bed Room 201) 0 days Tue 12/23/14Tue 12/23/14

1012 M&E first phase 73 days Tue 12/23/14 Thu 3/5/15

1013 Electrical System 73 days Tue 12/23/14 Thu 3/5/15

1014 Pipe sleeve installation 7 days Tue 12/23/14Mon 12/29/14

1015 Installation conduit above the ceiling & embedded in wall 14 days Fri 2/13/15 Thu 2/26/15

1016 Pulling the Cable for LV and ELV 7 days Fri 2/27/15 Thu 3/5/15

1/29 2/2

2/3 2/7

2/8 2/14

1/4 2/14

1/4 1/10

2/1 2/14

3/8 3/17

4/1 milestone ID (Arrrival Building)

4/2 4/12

4/2 4/12

4/2 4/3

4/4 4/8

4/9 4/10

4/11 4/12

4/2 4/12

4/2 4/8

4/9 4/12

4/2 4/7

4/2 4/7

4/12 Final inspection CEMP

11/20 4/30

11/20 12/31

12/18 1/21

1/12 2/4

1/26 2/25

2/21 3/17

2/12 3/18

12/17 milestone PHV ( Main Restaurant/ kitchen)

12/17 2/5

12/17 1/29

12/17 12/20

1/11 1/22

1/23 1/29

12/17 2/5

12/17 12/20

1/11 1/18

1/19 1/26

1/27 2/5

12/17 1/25

12/17 12/23

1/14 1/25

3/19 3/28

4/12 milestone ID ( Main Restaurant/ kitchen)

4/19 4/30

4/19 4/29

4/19 4/20

4/21 4/25

4/26 4/27

4/28 4/29

4/19 4/30

4/19 4/25

4/26 4/30

4/19 4/26

4/19 4/26

4/30 Final inspection CEMP

12/18 6/2

12/18 1/28

1/20 2/18

2/12 3/4

2/26 3/25

3/29 4/28

3/19 4/28

1/15 milestone PHV Spa/Shack

1/15 3/9

1/15 2/28

1/15 1/17

2/17 2/23

2/24 2/28

1/15 3/9

1/15 1/18

2/18 2/24

2/25 2/27

2/28 3/9

1/15 3/1

1/15 1/20

2/20 3/1

4/29 5/8

5/23 milestone ID Spa/Shack

5/24 6/2

5/24 6/2

5/24 5/25

5/26 5/29

5/30 5/31

6/1 6/2

5/24 6/1

5/24 5/27

5/28 6/1

5/24 5/29

5/24 5/29

6/2 Final Inspection CEMP

1/22 4/9

1/22 2/25

2/26 4/1

2/11 milestone PHV Main Pool

2/11 2/22

2/11 2/22

2/11 2/15

2/16 2/22

4/4 4/9

4/4 4/9

4/4 4/6

4/7 4/9

4/9 Final Inspection CEMP

11/15 5/6

11/15 11/29

11/20 2/18

11/30 12/6

12/8 2/12

12/8 1/1

12/28 1/16

1/14 1/28

1/29 2/12

2/16 3/22

2/16 3/7

3/3 3/22

1/17 2/15

1/17 2/15

2/13 3/14

2/13 3/14

1/2 2/10

1/2 1/21

12/23 milestone PHV (Villa 2 Bed Room 201)

12/23 3/5

12/23 3/5

12/23 12/29

2/13 2/26

2/27 3/5

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep OctJuly August Septemb October Novembe Decembe January February March April May June July August Septemb October

Task

Split

Progress

Milestone

Summary

Project Summary

External Tasks

External Milestone

Deadline

MASTER SCHEDULE ALILA RESORT - KOH RUSSEY

Prepared by: Soly

Project: KRU-MEP ScheduleDate: Fri 10/24/14

ID ALILA RESORT-KOH RUSSEY M&E SCHEDULE Duration Start Finish

1017 A/C and Ventilation System 73 days Tue 12/23/14 Thu 3/5/15

1018 Prepare the sleeve for refrigerant pipe installation 7 days Tue 12/23/14Mon 12/29/14

1019 Installation Refregerant pipe and insulation 10 days Sat 2/7/15 Mon 2/16/15

1020 Installatin drain pipe and insulation 7 days Tue 2/17/15 Mon 2/23/15

1021 Installation ducting system 10 days Tue 2/24/15 Thu 3/5/15

1022 Plumbing and Pool system 72 days Tue 12/23/14 Wed 3/4/15

1023 Installation Underground pipe for waste water, storm water, cold w 7 days Tue 12/23/14Mon 12/29/14

1024 Installation above ground pipe for waste water, storm water, pool a 20 days Fri 2/13/15 Wed 3/4/15

1025 J. Final inspection/Punch Listing and Hand over PHV 15 days Mon 3/23/15 Mon 4/6/15

1026 milestone ID (Villa 2 Bed Room 201) 0 days Mon 4/27/15 Mon 4/27/15

1027 M&E Second phase 9 days Tue 4/28/15 Wed 5/6/15

1028 Electrical System 9 days Tue 4/28/15 Wed 5/6/15

1029 Installation electrical panel 2 days Tue 4/28/15 Wed 4/29/15

1030 Installation lighting 3 days Thu 4/30/15 Sat 5/2/15

1031 Installation wiring device 2 days Sun 5/3/15 Mon 5/4/15

1032 Installation ELV equipment 2 days Tue 5/5/15 Wed 5/6/15

1033 A/C and Ventilation System 9 days Tue 4/28/15 Wed 5/6/15

1034 Installation A/C unit 5 days Tue 4/28/15 Sat 5/2/15

1035 Installatin exhaust fan 4 days Sun 5/3/15 Wed 5/6/15

1036 Plumbing and Pool system 9 days Tue 4/28/15 Wed 5/6/15

1037 Installation Pool equipment 4 days Tue 4/28/15 Fri 5/1/15

1038 Installation sanitary ware 5 days Sat 5/2/15 Wed 5/6/15

1039 Final inspection CEMP 0 days Wed 5/6/15 Wed 5/6/15

1040 Villa 2 Bed Room 202 167 days Mon 12/15/14 Fri 6/5/15

1041 A. Drawing preparation 15 days Mon 12/15/14Mon 12/29/14

1042 B. Material procurement and transportation 91 days Sat 12/20/14 Fri 3/20/15

1043 C. Clearing and grubbing / Cut and filling work 5 days Thu 12/25/14Mon 12/29/14

1044 C. Structure work 65 days Tue 12/30/14 Wed 3/4/15

1045 1. Foundation / Stump Column and back filling work 25 days Tue 12/30/14 Fri 1/23/15

1046 2. Ground beam and slab work 20 days Sat 1/17/15 Thu 2/5/15

1047 3. Column work 15 days Tue 2/3/15 Tue 2/17/15

1048 4. Roof beam and slab 15 days Wed 2/18/15 Wed 3/4/15

1049 D. Finishing work 45 days Sun 3/8/15 Mon 4/27/15

1050 1.Masonry work 25 days Sun 3/8/15 Wed 4/1/15

1051 2. Plastering work 25 days Sat 3/28/15 Mon 4/27/15

1052 E. Steel work 30 days Fri 2/6/15 Sat 3/7/15

1053 1. All steel work 30 days Fri 2/6/15 Sat 3/7/15

1054 F. Water proofing work 30 days Thu 3/5/15 Fri 4/3/15

1055 1. Water proof for roof ..tec. 30 days Thu 3/5/15 Fri 4/3/15

1056 G. Swimming Pool 40 days Sat 1/24/15 Wed 3/4/15

1057 H. Septic Tank 20 days Sat 1/24/15 Thu 2/12/15

1058 milestone PHV (Villa 2 Bed Room 201) 0 days Wed 1/14/15 Wed 1/14/15

1059 M&E first phase 55 days Wed 1/14/15 Mon 3/9/15

1060 Electrical System 49 days Wed 1/14/15 Tue 3/3/15

1061 Pipe sleeve installation 7 days Wed 1/14/15 Tue 1/20/15

1062 Installation conduit above the ceiling & embedded in wall 14 days Wed 2/11/15 Tue 2/24/15

1063 Pulling the Cable for LV and ELV 7 days Wed 2/25/15 Tue 3/3/15

1064 A/C and Ventilation System 55 days Wed 1/14/15 Mon 3/9/15

1065 Prepare the sleeve for refrigerant pipe installation 7 days Wed 1/14/15 Tue 1/20/15

1066 Installation Refregerant pipe and insulation 10 days Wed 2/11/15 Fri 2/20/15

1067 Installatin drain pipe and insulation 7 days Sat 2/21/15 Fri 2/27/15

1068 Installation ducting system 10 days Sat 2/28/15 Mon 3/9/15

1069 Plumbing and Pool system 48 days Wed 1/14/15 Mon 3/2/15

1070 Installation Underground pipe for waste water, storm water, cold w 7 days Wed 1/14/15 Tue 1/20/15

1071 Installation above ground pipe for waste water, storm water, pool a 20 days Wed 2/11/15 Mon 3/2/15

1072 J. Final inspection/ Punch Listing and Hand over 15 days Tue 4/28/15 Tue 5/12/15

1073 milestone ID (Villa 2 Bed Room 202) 0 days Wed 5/27/15 Wed 5/27/15

1074 M&E Second phase 9 days Thu 5/28/15 Fri 6/5/15

1075 Electrical System 9 days Thu 5/28/15 Fri 6/5/15

1076 Installation electrical panel 2 days Thu 5/28/15 Fri 5/29/15

1077 Installation lighting 3 days Sat 5/30/15 Mon 6/1/15

1078 Installation wiring device 2 days Tue 6/2/15 Wed 6/3/15

1079 Installation ELV equipment 2 days Thu 6/4/15 Fri 6/5/15

1080 A/C and Ventilation System 9 days Thu 5/28/15 Fri 6/5/15

1081 Installation A/C unit 5 days Thu 5/28/15 Mon 6/1/15

1082 Installatin exhaust fan 4 days Tue 6/2/15 Fri 6/5/15

1083 Plumbing and Pool system 9 days Thu 5/28/15 Fri 6/5/15

1084 Installation Pool equipment 4 days Thu 5/28/15 Sun 5/31/15

1085 Installation sanitary ware 5 days Mon 6/1/15 Fri 6/5/15

1086 Final Inspection CEMP 0 days Fri 6/5/15 Fri 6/5/15

1087 Villa 2 Bed Room 203 168 days Thu 1/15/15 Tue 7/7/15

1088 A. Drawing preparation 15 days Thu 1/15/15 Thu 1/29/15

1089 B. Material procurement and transportation 80 days Thu 1/15/15 Sat 4/4/15

1090 C. Clearing and grubbing / Cut and filling work 7 days Sun 1/25/15 Sat 1/31/15

1091 C. Structure work 67 days Sun 2/1/15 Wed 4/8/15

1092 1. Foundation / Stump Column and back filling work 25 days Sun 2/1/15 Wed 2/25/15

1093 2. Ground beam and slab work 20 days Sat 2/21/15 Thu 3/12/15

1094 3. Column work 15 days Tue 3/10/15 Tue 3/24/15

1095 4. Roof beam and slab 15 days Wed 3/25/15 Wed 4/8/15

1096 D. Finishing work 45 days Thu 4/9/15 Fri 5/29/15

1097 1.Masonry work 25 days Thu 4/9/15 Sat 5/9/15

1098 2. Plastering work 25 days Tue 5/5/15 Fri 5/29/15

1099 E. Steel work 30 days Fri 3/13/15 Sat 4/11/15

1100 1. All steel work 30 days Fri 3/13/15 Sat 4/11/15

1101 F. Water proofing work 30 days Thu 4/9/15 Thu 5/14/15

1102 1. Water proof for roof ..tec. 30 days Thu 4/9/15 Thu 5/14/15

1103 G. Swimming Pool 40 days Thu 2/26/15 Mon 4/6/15

1104 H. Septic Tank 20 days Thu 2/26/15 Tue 3/17/15

1105 milestone PHV (2 bed room 203 ) 0 days Mon 2/16/15 Mon 2/16/15

1106 M&E first phase 50 days Mon 2/16/15 Mon 4/6/15

1107 Electrical System 49 days Mon 2/16/15 Sun 4/5/15

1108 Pipe sleeve installation 7 days Mon 2/16/15 Sun 2/22/15

1109 Installation conduit above the ceiling & embedded in wall 14 days Mon 3/16/15 Sun 3/29/15

1110 Pulling the Cable for LV and ELV 7 days Mon 3/30/15 Sun 4/5/15

1111 A/C and Ventilation System 50 days Mon 2/16/15 Mon 4/6/15

1112 Prepare the sleeve for refrigerant pipe installation 5 days Mon 2/16/15 Fri 2/20/15

1113 Installation Refregerant pipe and insulation 7 days Sat 3/14/15 Fri 3/20/15

1114 Installatin drain pipe and insulation 7 days Sat 3/21/15 Fri 3/27/15

1115 Installation ducting system 10 days Sat 3/28/15 Mon 4/6/15

1116 Plumbing and Pool system 48 days Mon 2/16/15 Sat 4/4/15

1117 Installation Underground pipe for waste water, storm water, cold w 7 days Mon 2/16/15 Sun 2/22/15

1118 Installation above ground pipe for waste water, storm water, pool a 20 days Mon 3/16/15 Sat 4/4/15

1119 J. Final inspection/ Punch Listing and Hand over 15 days Sat 5/30/15 Sat 6/13/15

1120 milestone ID (2 bed room 203) 0 days Sun 6/28/15 Sun 6/28/15

1121 M&E Second phase 9 days Mon 6/29/15 Tue 7/7/15

1122 Electrical System 9 days Mon 6/29/15 Tue 7/7/15

1123 Installation electrical panel 2 days Mon 6/29/15 Tue 6/30/15

1124 Installation lighting 3 days Wed 7/1/15 Fri 7/3/15

1125 Installation wiring device 2 days Sat 7/4/15 Sun 7/5/15

1126 Installation ELV equipment 2 days Mon 7/6/15 Tue 7/7/15

1127 A/C and Ventilation System 9 days Mon 6/29/15 Tue 7/7/15

1128 Installation A/C unit 5 days Mon 6/29/15 Fri 7/3/15

1129 Installatin exhaust fan 4 days Sat 7/4/15 Tue 7/7/15

1130 Plumbing and Pool system 9 days Mon 6/29/15 Tue 7/7/15

1131 Installation Pool equipment 4 days Mon 6/29/15 Thu 7/2/15

1132 Installation sanitary ware 5 days Fri 7/3/15 Tue 7/7/15

1133 Final inspection CEMP 0 days Tue 7/7/15 Tue 7/7/15

1134 Villa 1 Bed Room 1001 and 1002 161 days Thu 1/15/15 Tue 6/30/15

1135 A. Drawing preparation 15 days Thu 1/15/15 Thu 1/29/15

1136 B. Material procurement and transportation 91 days Thu 1/15/15 Tue 4/21/15

1137 C. Clearing and grubbing / Cut and filling work 5 days Tue 1/27/15 Sat 1/31/15

1138 C. Structure work 62 days Sun 2/1/15 Fri 4/3/15

1139 1. Foundation / Stump Column and back filling work 25 days Sun 2/1/15 Wed 2/25/15

1140 2. Ground beam and slab work 20 days Sat 2/21/15 Thu 3/12/15

1141 3. Column work 10 days Tue 3/10/15 Thu 3/19/15

1142 4. Roof beam and slab 15 days Fri 3/20/15 Fri 4/3/15

1143 D. Finishing work 40 days Sat 4/4/15 Tue 5/19/15

12/23 3/5

12/23 12/29

2/7 2/16

2/17 2/23

2/24 3/5

12/23 3/4

12/23 12/29

2/13 3/4

3/23 4/6

4/27 milestone ID (Villa 2 Bed Room 201)

4/28 5/6

4/28 5/6

4/28 4/29

4/30 5/2

5/3 5/4

5/5 5/6

4/28 5/6

4/28 5/2

5/3 5/6

4/28 5/6

4/28 5/1

5/2 5/6

5/6 Final inspection CEMP

12/15 6/5

12/15 12/29

12/20 3/20

12/25 12/29

12/30 3/4

12/30 1/23

1/17 2/5

2/3 2/17

2/18 3/4

3/8 4/27

3/8 4/1

3/28 4/27

2/6 3/7

2/6 3/7

3/5 4/3

3/5 4/3

1/24 3/4

1/24 2/12

1/14 milestone PHV (Villa 2 Bed Room 201)

1/14 3/9

1/14 3/3

1/14 1/20

2/11 2/24

2/25 3/3

1/14 3/9

1/14 1/20

2/11 2/20

2/21 2/27

2/28 3/9

1/14 3/2

1/14 1/20

2/11 3/2

4/28 5/12

5/27 milestone ID (Villa 2 Bed Room 202)

5/28 6/5

5/28 6/5

5/28 5/29

5/30 6/1

6/2 6/3

6/4 6/5

5/28 6/5

5/28 6/1

6/2 6/5

5/28 6/5

5/28 5/31

6/1 6/5

6/5 Final Inspection CEMP

1/15 7/7

1/15 1/29

1/15 4/4

1/25 1/31

2/1 4/8

2/1 2/25

2/21 3/12

3/10 3/24

3/25 4/8

4/9 5/29

4/9 5/9

5/5 5/29

3/13 4/11

3/13 4/11

4/9 5/14

4/9 5/14

2/26 4/6

2/26 3/17

2/16 milestone PHV (2 bed room 203 )

2/16 4/6

2/16 4/5

2/16 2/22

3/16 3/29

3/30 4/5

2/16 4/6

2/16 2/20

3/14 3/20

3/21 3/27

3/28 4/6

2/16 4/4

2/16 2/22

3/16 4/4

5/30 6/13

6/28 milestone ID (2 bed room 203)

6/29 7/7

6/29 7/7

6/29 6/30

7/1 7/3

7/4 7/5

7/6 7/7

6/29 7/7

6/29 7/3

7/4 7/7

6/29 7/7

6/29 7/2

7/3 7/7

7/7 Final inspection CEMP

1/15 6/30

1/15 1/29

1/15 4/21

1/27 1/31

2/1 4/3

2/1 2/25

2/21 3/12

3/10 3/19

3/20 4/3

4/4 5/19

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep OctJuly August Septemb October Novembe Decembe January February March April May June July August Septemb October

Task

Split

Progress

Milestone

Summary

Project Summary

External Tasks

External Milestone

Deadline

MASTER SCHEDULE ALILA RESORT - KOH RUSSEY

Prepared by: Soly

Project: KRU-MEP ScheduleDate: Fri 10/24/14

ID ALILA RESORT-KOH RUSSEY M&E SCHEDULE Duration Start Finish

1144 1.Masonry work 20 days Sat 4/4/15 Wed 4/29/15

1145 2. Plastering work 20 days Thu 4/30/15 Tue 5/19/15

1146 E. Steel work 30 days Fri 3/13/15 Sat 4/11/15

1147 1. All steel work 30 days Fri 3/13/15 Sat 4/11/15

1148 F. Water proofing work 25 days Sat 4/4/15 Mon 5/4/15

1149 1. Water proof for roof ..tec. 25 days Sat 4/4/15 Mon 5/4/15

1150 G. Swimming Pool 30 days Thu 2/26/15 Fri 3/27/15

1151 H. Septic Tank 20 days Thu 2/26/15 Tue 3/17/15

1152 milestone PHV (1 bed room 1001 and 1002) 0 days Mon 2/16/15 Mon 2/16/15

1153 Villa 1 Bed Room 1001 and 1002 M&E first phase 54 days Mon 2/16/15 Fri 4/10/15

1154 Villa 1 Bed Room 1001 M&E first phase 54 days Mon 2/16/15 Fri 4/10/15

1155 M&E first phase 54 days Mon 2/16/15 Fri 4/10/15

1156 Electrical System 45 days Mon 2/16/15 Wed 4/1/15

1157 Pipe sleeve installation 6 days Mon 2/16/15 Sat 2/21/15

1158 Installation conduit above the ceiling & embedded in wall 10 days Sun 3/15/15 Tue 3/24/15

1159 Pulling the Cable for LV and ELV 8 days Wed 3/25/15 Wed 4/1/15

1160 A/C and Ventilation System 54 days Mon 2/16/15 Fri 4/10/15

1161 Prepare the sleeve for refrigerant pipe installation 5 days Mon 2/16/15 Fri 2/20/15

1162 Installation Refregerant pipe and insulation 10 days Sat 3/14/15 Mon 3/23/15

1163 Installation drain pipe and insulation 6 days Tue 3/24/15 Sun 3/29/15

1164 Installation ducting system 12 days Mon 3/30/15 Fri 4/10/15

1165 Plumbing and Pool system 41 days Mon 2/16/15 Sat 3/28/15

1166 Installation Underground pipe for waste water, storm wat 6 days Mon 2/16/15 Sat 2/21/15

1167 Installation above ground pipe for waste water, storm wa 14 days Sun 3/15/15 Sat 3/28/15

1168 Villa 1 Bed Room 1002 M&E first phase 54 days Mon 2/16/15 Fri 4/10/15

1169 M&E first phase 54 days Mon 2/16/15 Fri 4/10/15

1170 Electrical System 45 days Mon 2/16/15 Wed 4/1/15

1171 Pipe sleeve installation 6 days Mon 2/16/15 Sat 2/21/15

1172 Installation conduit above the ceiling & embedded in wall 10 days Sun 3/15/15 Tue 3/24/15

1173 Pulling the Cable for LV and ELV 8 days Wed 3/25/15 Wed 4/1/15

1174 A/C and Ventilation System 54 days Mon 2/16/15 Fri 4/10/15

1175 Prepare the sleeve for refrigerant pipe installation 5 days Mon 2/16/15 Fri 2/20/15

1176 Installation Refregerant pipe and insulation 10 days Sat 3/14/15 Mon 3/23/15

1177 Installatin drain pipe and insulation 6 days Tue 3/24/15 Sun 3/29/15

1178 Installation ducting system 12 days Mon 3/30/15 Fri 4/10/15

1179 Plumbing and Pool system 41 days Mon 2/16/15 Sat 3/28/15

1180 Installation Underground pipe for waste water, storm wat 6 days Mon 2/16/15 Sat 2/21/15

1181 Installation above ground pipe for waste water, storm wa 14 days Sun 3/15/15 Sat 3/28/15

1182 J. Final inspection/Punch Listing and Hand over PHV 15 days Wed 5/20/15 Wed 6/3/15

1183 milestone ID (1 bed room 1001 and 1002) 0 days Thu 6/18/15 Thu 6/18/15

1184 Villa 1 Bed Room 1001 and 1002 M&E Second phase 12 days Fri 6/19/15 Tue 6/30/15

1185 Villa 1 Bed Room 1001 M&E Second phase 12 days Fri 6/19/15 Tue 6/30/15

1186 M&E Second phase 12 days Fri 6/19/15 Tue 6/30/15

1187 Electrical System 12 days Fri 6/19/15 Tue 6/30/15

1188 Installation electrical panel 2 days Fri 6/19/15 Sat 6/20/15

1189 Installation lighting 6 days Sun 6/21/15 Fri 6/26/15

1190 Installation wiring device 2 days Sat 6/27/15 Sun 6/28/15

1191 Installation ELV equipment 2 days Mon 6/29/15 Tue 6/30/15

1192 A/C and Ventilation System 12 days Fri 6/19/15 Tue 6/30/15

1193 Installation A/C unit 7 days Fri 6/19/15 Thu 6/25/15

1194 Installatin exhaust fan 5 days Fri 6/26/15 Tue 6/30/15

1195 Plumbing and Pool system 12 days Fri 6/19/15 Tue 6/30/15

1196 Installation Pool equipment 5 days Fri 6/19/15 Tue 6/23/15

1197 Installation sanitary ware 7 days Wed 6/24/15 Tue 6/30/15

1198 Villa 1 Bed Room 1002 M&E Second phase 12 days Fri 6/19/15 Tue 6/30/15

1199 M&E Second phase 12 days Fri 6/19/15 Tue 6/30/15

1200 Electrical System 12 days Fri 6/19/15 Tue 6/30/15

1201 Installation electrical panel 2 days Fri 6/19/15 Sat 6/20/15

1202 Installation lighting 6 days Sun 6/21/15 Fri 6/26/15

1203 Installation wiring device 2 days Sat 6/27/15 Sun 6/28/15

1204 Installation ELV equipment 2 days Mon 6/29/15 Tue 6/30/15

1205 A/C and Ventilation System 12 days Fri 6/19/15 Tue 6/30/15

1206 Installation A/C unit 7 days Fri 6/19/15 Thu 6/25/15

1207 Installatin exhaust fan 5 days Fri 6/26/15 Tue 6/30/15

1208 Plumbing and Pool system 12 days Fri 6/19/15 Tue 6/30/15

1209 Installation Pool equipment 5 days Fri 6/19/15 Tue 6/23/15

1210 Installation sanitary ware 7 days Wed 6/24/15 Tue 6/30/15

1211 Final inspection CEMP 0 days Tue 6/30/15 Tue 6/30/15

1212 Villa 1 Bed Room 1003 and 1004 163 days Sun 2/1/15 Sun 7/19/15

1213 A. Drawing preparation 15 days Sun 2/1/15 Sun 2/15/15

1214 B. Material procurement and transportation 91 days Sun 2/1/15 Fri 5/8/15

1215 C. Clearing and grubbing / Cut and filling work 7 days Fri 2/13/15 Thu 2/19/15

1216 C. Structure work 62 days Fri 2/20/15 Tue 4/28/15

1217 1. Foundation / Stump Column and back filling work 25 days Fri 2/20/15 Mon 3/16/15

1218 2. Ground beam and slab work 20 days Thu 3/12/15 Tue 3/31/15

1219 3. Column work 10 days Sun 3/29/15 Tue 4/7/15

1220 4. Roof beam and slab 15 days Wed 4/8/15 Tue 4/28/15

1221 D. Finishing work 40 days Wed 4/29/15 Sun 6/7/15

1222 1.Masonry work 20 days Wed 4/29/15 Mon 5/18/15

1223 2. Plastering work 20 days Tue 5/19/15 Sun 6/7/15

1224 E. Steel work 30 days Wed 4/1/15 Wed 5/6/15

1225 1. All steel work 30 days Wed 4/1/15 Wed 5/6/15

1226 F. Water proofing work 25 days Wed 4/29/15 Sat 5/23/15

1227 1. Water proof for roof ..tec. 25 days Wed 4/29/15 Sat 5/23/15

1228 G. Swimming Pool 30 days Tue 3/17/15 Tue 4/21/15

1229 H. Septic Tank 20 days Tue 3/17/15 Sun 4/5/15

1230 milestone PHV (1 bed room 1003 and 1004) 0 days Tue 3/10/15 Tue 3/10/15

1231 Villa 1 Bed Room 1003 and 1004 M&E first phase 45 days Tue 3/10/15 Wed 4/29/15

1232 Villa 1 Bed Room 1003 M&E first phase 45 days Tue 3/10/15 Wed 4/29/15

1233 M&E first phase 45 days Tue 3/10/15 Wed 4/29/15

1234 Electrical System 45 days Tue 3/10/15 Wed 4/29/15

1235 Pipe sleeve installation 6 days Tue 3/10/15 Sun 3/15/15

1236 Installation conduit above the ceiling & embedded in wall 10 days Mon 4/6/15 Tue 4/21/15

1237 Pulling the Cable for LV and ELV 8 days Wed 4/22/15 Wed 4/29/15

1238 A/C and Ventilation System 45 days Tue 3/10/15 Wed 4/29/15

1239 Prepare the sleeve for refrigerant pipe installation 5 days Tue 3/10/15 Sat 3/14/15

1240 Installation Refregerant pipe and insulation 7 days Sun 4/5/15 Sat 4/11/15

1241 Installatin drain pipe and insulation 4 days Sun 4/12/15 Tue 4/21/15

1242 Installation ducting system 8 days Wed 4/22/15 Wed 4/29/15

1243 Plumbing and Pool system 41 days Tue 3/10/15 Sat 4/25/15

1244 Installation Underground pipe for waste water, storm wat 6 days Tue 3/10/15 Sun 3/15/15

1245 Installation above ground pipe for waste water, storm wa 14 days Mon 4/6/15 Sat 4/25/15

1246 Villa 1 Bed Room 1004 M&E first phase 45 days Tue 3/10/15 Wed 4/29/15

1247 M&E first phase 45 days Tue 3/10/15 Wed 4/29/15

1248 Electrical System 45 days Tue 3/10/15 Wed 4/29/15

1249 Pipe sleeve installation 6 days Tue 3/10/15 Sun 3/15/15

1250 Installation conduit above the ceiling & embedded in wall 10 days Mon 4/6/15 Tue 4/21/15

1251 Pulling the Cable for LV and ELV 8 days Wed 4/22/15 Wed 4/29/15

1252 A/C and Ventilation System 45 days Tue 3/10/15 Wed 4/29/15

1253 Prepare the sleeve for refrigerant pipe installation 5 days Tue 3/10/15 Sat 3/14/15

1254 Installation Refregerant pipe and insulation 7 days Sun 4/5/15 Sat 4/11/15

1255 Installatin drain pipe and insulation 4 days Sun 4/12/15 Tue 4/21/15

1256 Installation ducting system 8 days Wed 4/22/15 Wed 4/29/15

1257 Plumbing and Pool system 41 days Tue 3/10/15 Sat 4/25/15

1258 Installation Underground pipe for waste water, storm wat 6 days Tue 3/10/15 Sun 3/15/15

1259 Installation above ground pipe for waste water, storm wa 14 days Mon 4/6/15 Sat 4/25/15

1260 J. Final inspection/Punch Listing and hand over 15 days Mon 6/8/15 Mon 6/22/15

1261 milestone ID (1 bed room 1003 and 1004) 0 days Tue 7/7/15 Tue 7/7/15

1262 Villa 1 Bed Room 1003 and 1004 M&E Second phase 12 days Wed 7/8/15 Sun 7/19/15

1263 Villa 1 Bed Room 1003 M&E Second phase 12 days Wed 7/8/15 Sun 7/19/15

1264 M&E Second phase 12 days Wed 7/8/15 Sun 7/19/15

1265 Electrical System 12 days Wed 7/8/15 Sun 7/19/15

1266 Installation electrical panel 2 days Wed 7/8/15 Thu 7/9/15

1267 Installation lighting 6 days Fri 7/10/15 Wed 7/15/15

1268 Installation wiring device 2 days Thu 7/16/15 Fri 7/17/15

1269 Installation ELV equipment 2 days Sat 7/18/15 Sun 7/19/15

1270 A/C and Ventilation System 12 days Wed 7/8/15 Sun 7/19/15

4/4 4/29

4/30 5/19

3/13 4/11

3/13 4/11

4/4 5/4

4/4 5/4

2/26 3/27

2/26 3/17

2/16 milestone PHV (1 bed room 1001 and 1002)

2/16 4/10

2/16 4/10

2/16 4/10

2/16 4/1

2/16 2/21

3/15 3/24

3/25 4/1

2/16 4/10

2/16 2/20

3/14 3/23

3/24 3/29

3/30 4/10

2/16 3/28

2/16 2/21

3/15 3/28

2/16 4/10

2/16 4/10

2/16 4/1

2/16 2/21

3/15 3/24

3/25 4/1

2/16 4/10

2/16 2/20

3/14 3/23

3/24 3/29

3/30 4/10

2/16 3/28

2/16 2/21

3/15 3/28

5/20 6/3

6/18 milestone ID (1 bed room 1001 and 1002)

6/19 6/30

6/19 6/30

6/19 6/30

6/19 6/30

6/19 6/20

6/21 6/26

6/27 6/28

6/29 6/30

6/19 6/30

6/19 6/25

6/26 6/30

6/19 6/30

6/19 6/23

6/24 6/30

6/19 6/30

6/19 6/30

6/19 6/30

6/19 6/20

6/21 6/26

6/27 6/28

6/29 6/30

6/19 6/30

6/19 6/25

6/26 6/30

6/19 6/30

6/19 6/23

6/24 6/30

6/30 Final inspection CEMP

2/1 7/19

2/1 2/15

2/1 5/8

2/13 2/19

2/20 4/28

2/20 3/16

3/12 3/31

3/29 4/7

4/8 4/28

4/29 6/7

4/29 5/18

5/19 6/7

4/1 5/6

4/1 5/6

4/29 5/23

4/29 5/23

3/17 4/21

3/17 4/5

3/10 milestone PHV (1 bed room 1003 and 1004)

3/10 4/29

3/10 4/29

3/10 4/29

3/10 4/29

3/10 3/15

4/6 4/21

4/22 4/29

3/10 4/29

3/10 3/14

4/5 4/11

4/12 4/21

4/22 4/29

3/10 4/25

3/10 3/15

4/6 4/25

3/10 4/29

3/10 4/29

3/10 4/29

3/10 3/15

4/6 4/21

4/22 4/29

3/10 4/29

3/10 3/14

4/5 4/11

4/12 4/21

4/22 4/29

3/10 4/25

3/10 3/15

4/6 4/25

6/8 6/22

7/7 milestone ID (1 bed room 1003 and 1

7/8 7/19

7/8 7/19

7/8 7/19

7/8 7/19

7/8 7/9

7/10 7/15

7/16 7/17

7/18 7/19

7/8 7/19

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep OctJuly August Septemb October Novembe Decembe January February March April May June July August Septemb October

Task

Split

Progress

Milestone

Summary

Project Summary

External Tasks

External Milestone

Deadline

MASTER SCHEDULE ALILA RESORT - KOH RUSSEY

Prepared by: Soly

Project: KRU-MEP ScheduleDate: Fri 10/24/14

ID ALILA RESORT-KOH RUSSEY M&E SCHEDULE Duration Start Finish

1271 Installation A/C unit 7 days Wed 7/8/15 Tue 7/14/15

1272 Installatin exhaust fan 5 days Wed 7/15/15 Sun 7/19/15

1273 Plumbing and Pool system 12 days Wed 7/8/15 Sun 7/19/15

1274 Installation Pool equipment 5 days Wed 7/8/15 Sun 7/12/15

1275 Installation sanitary ware 7 days Mon 7/13/15 Sun 7/19/15

1276 Villa 1 Bed Room 1004 M&E Second phase 12 days Wed 7/8/15 Sun 7/19/15

1277 M&E Second phase 12 days Wed 7/8/15 Sun 7/19/15

1278 Electrical System 12 days Wed 7/8/15 Sun 7/19/15

1279 Installation electrical panel 2 days Wed 7/8/15 Thu 7/9/15

1280 Installation lighting 6 days Fri 7/10/15 Wed 7/15/15

1281 Installation wiring device 2 days Thu 7/16/15 Fri 7/17/15

1282 Installation ELV equipment 2 days Sat 7/18/15 Sun 7/19/15

1283 A/C and Ventilation System 12 days Wed 7/8/15 Sun 7/19/15

1284 Installation A/C unit 7 days Wed 7/8/15 Tue 7/14/15

1285 Installatin exhaust fan 5 days Wed 7/15/15 Sun 7/19/15

1286 Plumbing and Pool system 12 days Wed 7/8/15 Sun 7/19/15

1287 Installation Pool equipment 5 days Wed 7/8/15 Sun 7/12/15

1288 Installation sanitary ware 7 days Mon 7/13/15 Sun 7/19/15

1289 Final inspection CEMP 0 days Sun 7/19/15 Sun 7/19/15

1290 Villa 1 Bed Room 1005 and 1006 161 days Sun 2/15/15 Fri 7/31/15

1291 A. Drawing preparation 15 days Sun 2/15/15 Sun 3/1/15

1292 B. Material procurement and transportation 91 days Sun 2/15/15 Fri 5/22/15

1293 C. Clearing and grubbing / Cut and filling work 7 days Wed 2/25/15 Tue 3/3/15

1294 C. Structure work 62 days Wed 3/4/15 Sun 5/10/15

1295 1. Foundation / Stump Column and back filling work 25 days Wed 3/4/15 Sat 3/28/15

1296 2. Ground beam and slab work 20 days Tue 3/24/15 Sun 4/12/15

1297 3. Column work 10 days Fri 4/10/15 Sat 4/25/15

1298 4. Roof beam and slab 15 days Sun 4/26/15 Sun 5/10/15

1299 D. Finishing work 40 days Mon 5/11/15 Fri 6/19/15

1300 1.Masonry work 20 days Mon 5/11/15 Sat 5/30/15

1301 2. Plastering work 20 days Sun 5/31/15 Fri 6/19/15

1302 E. Steel work 30 days Sun 4/19/15 Mon 5/18/15

1303 1. All steel work 30 days Sun 4/19/15 Mon 5/18/15

1304 F. Water proofing work 25 days Mon 5/11/15 Thu 6/4/15

1305 1. Water proof for roof ..tec. 25 days Mon 5/11/15 Thu 6/4/15

1306 G. Swimming Pool 30 days Sun 3/29/15 Sun 5/3/15

1307 H. Septic Tank 20 days Sun 3/29/15 Thu 4/23/15

1308 milestone PHV (1 bed room 1005 and 1006) 0 days Thu 3/19/15 Thu 3/19/15

1309 Villa 1 Bed Room 1005 and 1006 M&E first phase 45 days Thu 3/19/15 Fri 5/8/15

1310 Villa 1 Bed Room 1005 M&E first phase 45 days Thu 3/19/15 Fri 5/8/15

1311 M&E first phase 45 days Thu 3/19/15 Fri 5/8/15

1312 Electrical System 45 days Thu 3/19/15 Fri 5/8/15

1313 Pipe sleeve installation 6 days Thu 3/19/15 Tue 3/24/15

1314 Installation conduit above the ceiling & embedded in wall 10 days Tue 4/21/15 Thu 4/30/15

1315 Pulling the Cable for LV and ELV 8 days Fri 5/1/15 Fri 5/8/15

1316 A/C and Ventilation System 45 days Thu 3/19/15 Fri 5/8/15

1317 Prepare the sleeve for refrigerant pipe installation 5 days Thu 3/19/15 Mon 3/23/15

1318 Installation Refregerant pipe and insulation 7 days Mon 4/20/15 Sun 4/26/15

1319 Installatin drain pipe and insulation 4 days Mon 4/27/15 Thu 4/30/15

1320 Installation ducting system 8 days Fri 5/1/15 Fri 5/8/15

1321 Plumbing and Pool system 41 days Thu 3/19/15 Mon 5/4/15

1322 Installation Underground pipe for waste water, storm wat 6 days Thu 3/19/15 Tue 3/24/15

1323 Installation above ground pipe for waste water, storm wa 14 days Tue 4/21/15 Mon 5/4/15

1324 Villa 1 Bed Room 1006 M&E first phase 45 days Thu 3/19/15 Fri 5/8/15

1325 M&E first fix 45 days Thu 3/19/15 Fri 5/8/15

1326 Electrical System 45 days Thu 3/19/15 Fri 5/8/15

1327 Pipe sleeve installation 6 days Thu 3/19/15 Tue 3/24/15

1328 Installation conduit above the ceiling & embedded in wall 10 days Tue 4/21/15 Thu 4/30/15

1329 Pulling the Cable for LV and ELV 8 days Fri 5/1/15 Fri 5/8/15

1330 A/C and Ventilation System 45 days Thu 3/19/15 Fri 5/8/15

1331 Prepare the sleeve for refrigerant pipe installation 5 days Thu 3/19/15 Mon 3/23/15

1332 Installation Refregerant pipe and insulation 7 days Mon 4/20/15 Sun 4/26/15

1333 Installatin drain pipe and insulation 4 days Mon 4/27/15 Thu 4/30/15

1334 Installation ducting system 8 days Fri 5/1/15 Fri 5/8/15

1335 Plumbing and Pool system 41 days Thu 3/19/15 Mon 5/4/15

1336 Installation Underground pipe for waste water, storm wat 6 days Thu 3/19/15 Tue 3/24/15

1337 Installation above ground pipe for waste water, storm wa 14 days Tue 4/21/15 Mon 5/4/15

1338 J. Final inspection/Punch Listing and Hnad over 15 days Sat 6/20/15 Sat 7/4/15

1339 milestone ID (1 bed room 1005 and 1006) 0 days Sun 7/19/15 Sun 7/19/15

1340 Villa 1 Bed Room 1005 and 1006 M&E Second phase 12 days Mon 7/20/15 Fri 7/31/15

1341 Villa 1 Bed Room 1005 M&E Second phase 12 days Mon 7/20/15 Fri 7/31/15

1342 M&E Second phase 12 days Mon 7/20/15 Fri 7/31/15

1343 Electrical System 12 days Mon 7/20/15 Fri 7/31/15

1344 Installation electrical panel 2 days Mon 7/20/15 Tue 7/21/15

1345 Installation lighting 6 days Wed 7/22/15 Mon 7/27/15

1346 Installation wiring device 2 days Tue 7/28/15 Wed 7/29/15

1347 Installation ELV equipment 2 days Thu 7/30/15 Fri 7/31/15

1348 A/C and Ventilation System 12 days Mon 7/20/15 Fri 7/31/15

1349 Installation A/C unit 7 days Mon 7/20/15 Sun 7/26/15

1350 Installatin exhaust fan 5 days Mon 7/27/15 Fri 7/31/15

1351 Plumbing and Pool system 12 days Mon 7/20/15 Fri 7/31/15

1352 Installation Pool equipment 5 days Mon 7/20/15 Fri 7/24/15

1353 Installation sanitary ware 7 days Sat 7/25/15 Fri 7/31/15

1354 Villa 1 Bed Room 1006 M&E Second phase 12 days Mon 7/20/15 Fri 7/31/15

1355 M&E Second phase 12 days Mon 7/20/15 Fri 7/31/15

1356 Electrical System 12 days Mon 7/20/15 Fri 7/31/15

1357 Installation electrical panel 2 days Mon 7/20/15 Tue 7/21/15

1358 Installation lighting 6 days Wed 7/22/15 Mon 7/27/15

1359 Installation wiring device 2 days Tue 7/28/15 Wed 7/29/15

1360 Installation ELV equipment 2 days Thu 7/30/15 Fri 7/31/15

1361 A/C and Ventilation System 12 days Mon 7/20/15 Fri 7/31/15

1362 Installation A/C unit 7 days Mon 7/20/15 Sun 7/26/15

1363 Installatin exhaust fan 5 days Mon 7/27/15 Fri 7/31/15

1364 Plumbing and Pool system 12 days Mon 7/20/15 Fri 7/31/15

1365 Installation Pool equipment 5 days Mon 7/20/15 Fri 7/24/15

1366 Installation sanitary ware 7 days Sat 7/25/15 Fri 7/31/15

1367 Final Inspection CEMP 0 days Fri 7/31/15 Fri 7/31/15

1368 Villa 1 Bed Room 1085 and 1086 166 days Sun 2/15/15 Wed 8/5/15

1369 A. Drawing preparation 15 days Sun 2/15/15 Sun 3/1/15

1370 B. Material procurement and transportation 91 days Sun 2/15/15 Fri 5/22/15

1371 C. Clearing and grubbing / Cut and filling work 7 days Mon 3/2/15 Sun 3/8/15

1372 C. Structure work 62 days Mon 3/9/15 Fri 5/15/15

1373 1. Foundation / Stump Column and back filling work 25 days Mon 3/9/15 Thu 4/2/15

1374 2. Ground beam and slab work 20 days Sun 3/29/15 Thu 4/23/15

1375 3. Column work 10 days Tue 4/21/15 Thu 4/30/15

1376 4. Roof beam and slab 15 days Fri 5/1/15 Fri 5/15/15

1377 D. Finishing work 40 days Sat 5/16/15 Wed 6/24/15

1378 1.Masonry work 20 days Sat 5/16/15 Thu 6/4/15

1379 2. Plastering work 20 days Fri 6/5/15 Wed 6/24/15

1380 E. Steel work 30 days Fri 4/24/15 Sat 5/23/15

1381 1. All steel work 30 days Fri 4/24/15 Sat 5/23/15

1382 F. Water proofing work 25 days Sat 5/16/15 Tue 6/9/15

1383 1. Water proof for roof ..tec. 25 days Sat 5/16/15 Tue 6/9/15

1384 G. Swimming Pool 30 days Fri 4/3/15 Fri 5/8/15

1385 H. Septic Tank 20 days Fri 4/3/15 Tue 4/28/15

1386 milestone PHV (1 bed room 1085 and 1086) 0 days Tue 3/24/15 Tue 3/24/15

1387 Villa 1 Bed Room 1085 and 1086 M&E first phase 45 days Tue 3/24/15 Wed 5/13/15

1388 Villa 1 Bed Room 1085 M&E First phase 45 days Tue 3/24/15 Wed 5/13/15

1389 M&E first phase 45 days Tue 3/24/15 Wed 5/13/15

1390 Electrical System 45 days Tue 3/24/15 Wed 5/13/15

1391 Pipe sleeve installation 6 days Tue 3/24/15 Sun 3/29/15

1392 Installation conduit above the ceiling & embedded in wall 10 days Sun 4/26/15 Tue 5/5/15

1393 Pulling the Cable for LV and ELV 8 days Wed 5/6/15 Wed 5/13/15

1394 A/C and Ventilation System 45 days Tue 3/24/15 Wed 5/13/15

1395 Prepare the sleeve for refrigerant pipe installation 5 days Tue 3/24/15 Sat 3/28/15

1396 Installation Refregerant pipe and insulation 7 days Sat 4/25/15 Fri 5/1/15

1397 Installatin drain pipe and insulation 4 days Sat 5/2/15 Tue 5/5/15

7/8 7/14

7/15 7/19

7/8 7/19

7/8 7/12

7/13 7/19

7/8 7/19

7/8 7/19

7/8 7/19

7/8 7/9

7/10 7/15

7/16 7/17

7/18 7/19

7/8 7/19

7/8 7/14

7/15 7/19

7/8 7/19

7/8 7/12

7/13 7/19

7/19 Final inspection CEMP

2/15 7/31

2/15 3/1

2/15 5/22

2/25 3/3

3/4 5/10

3/4 3/28

3/24 4/12

4/10 4/25

4/26 5/10

5/11 6/19

5/11 5/30

5/31 6/19

4/19 5/18

4/19 5/18

5/11 6/4

5/11 6/4

3/29 5/3

3/29 4/23

3/19 milestone PHV (1 bed room 1005 and 1006)

3/19 5/8

3/19 5/8

3/19 5/8

3/19 5/8

3/19 3/24

4/21 4/30

5/1 5/8

3/19 5/8

3/19 3/23

4/20 4/26

4/27 4/30

5/1 5/8

3/19 5/4

3/19 3/24

4/21 5/4

3/19 5/8

3/19 5/8

3/19 5/8

3/19 3/24

4/21 4/30

5/1 5/8

3/19 5/8

3/19 3/23

4/20 4/26

4/27 4/30

5/1 5/8

3/19 5/4

3/19 3/24

4/21 5/4

6/20 7/4

7/19 milestone ID (1 bed room 1005 a

7/20 7/31

7/20 7/31

7/20 7/31

7/20 7/31

7/20 7/21

7/22 7/27

7/28 7/29

7/30 7/31

7/20 7/31

7/20 7/26

7/27 7/31

7/20 7/31

7/20 7/24

7/25 7/31

7/20 7/31

7/20 7/31

7/20 7/31

7/20 7/21

7/22 7/27

7/28 7/29

7/30 7/31

7/20 7/31

7/20 7/26

7/27 7/31

7/20 7/31

7/20 7/24

7/25 7/31

7/31 Final Inspection CEMP

2/15 8/5

2/15 3/1

2/15 5/22

3/2 3/8

3/9 5/15

3/9 4/2

3/29 4/23

4/21 4/30

5/1 5/15

5/16 6/24

5/16 6/4

6/5 6/24

4/24 5/23

4/24 5/23

5/16 6/9

5/16 6/9

4/3 5/8

4/3 4/28

3/24 milestone PHV (1 bed room 1085 and 1086)

3/24 5/13

3/24 5/13

3/24 5/13

3/24 5/13

3/24 3/29

4/26 5/5

5/6 5/13

3/24 5/13

3/24 3/28

4/25 5/1

5/2 5/5

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep OctJuly August Septemb October Novembe Decembe January February March April May June July August Septemb October

Task

Split

Progress

Milestone

Summary

Project Summary

External Tasks

External Milestone

Deadline

MASTER SCHEDULE ALILA RESORT - KOH RUSSEY

Prepared by: Soly

Project: KRU-MEP ScheduleDate: Fri 10/24/14

ID ALILA RESORT-KOH RUSSEY M&E SCHEDULE Duration Start Finish

1398 Installation ducting system 8 days Wed 5/6/15 Wed 5/13/15

1399 Plumbing and Pool system 41 days Tue 3/24/15 Sat 5/9/15

1400 Installation Underground pipe for waste water, storm wat 6 days Tue 3/24/15 Sun 3/29/15

1401 Installation above ground pipe for waste water, storm wa 14 days Sun 4/26/15 Sat 5/9/15

1402 Villa 1 Bed Room 1086 M&E first phase 45 days Tue 3/24/15 Wed 5/13/15

1403 M&E first phase 45 days Tue 3/24/15 Wed 5/13/15

1404 Electrical System 45 days Tue 3/24/15 Wed 5/13/15

1405 Pipe sleeve installation 6 days Tue 3/24/15 Sun 3/29/15

1406 Installation conduit above the ceiling & embedded in wall 10 days Sun 4/26/15 Tue 5/5/15

1407 Pulling the Cable for LV and ELV 8 days Wed 5/6/15 Wed 5/13/15

1408 A/C and Ventilation System 45 days Tue 3/24/15 Wed 5/13/15

1409 Prepare the sleeve for refrigerant pipe installation 5 days Tue 3/24/15 Sat 3/28/15

1410 Installation Refregerant pipe and insulation 7 days Sat 4/25/15 Fri 5/1/15

1411 Installatin drain pipe and insulation 4 days Sat 5/2/15 Tue 5/5/15

1412 Installation ducting system 8 days Wed 5/6/15 Wed 5/13/15

1413 Plumbing and Pool system 41 days Tue 3/24/15 Sat 5/9/15

1414 Installation Underground pipe for waste water, storm wat 6 days Tue 3/24/15 Sun 3/29/15

1415 Installation above ground pipe for waste water, storm wa 14 days Sun 4/26/15 Sat 5/9/15

1416 J. Final inspection/Punch listing/Hand Over PHV 15 days Thu 6/25/15 Thu 7/9/15

1417 milestone ID (1 bed room 1085 and 1086) 0 days Fri 7/24/15 Fri 7/24/15

1418 Villa 1 Bed Room 1085 and 1086 M&E Second phase 12 days Sat 7/25/15 Wed 8/5/15

1419 Villa 1 Bed Room 1085 M&E Second phase 12 days Sat 7/25/15 Wed 8/5/15

1420 M&E Second phase 12 days Sat 7/25/15 Wed 8/5/15

1421 Electrical System 12 days Sat 7/25/15 Wed 8/5/15

1422 Installation electrical panel 2 days Sat 7/25/15 Sun 7/26/15

1423 Installation lighting 6 days Mon 7/27/15 Sat 8/1/15

1424 Installation wiring device 2 days Sun 8/2/15 Mon 8/3/15

1425 Installation ELV equipment 2 days Tue 8/4/15 Wed 8/5/15

1426 A/C and Ventilation System 12 days Sat 7/25/15 Wed 8/5/15

1427 Installation A/C unit 7 days Sat 7/25/15 Fri 7/31/15

1428 Installatin exhaust fan 5 days Sat 8/1/15 Wed 8/5/15

1429 Plumbing and Pool system 12 days Sat 7/25/15 Wed 8/5/15

1430 Installation Pool equipment 5 days Sat 7/25/15 Wed 7/29/15

1431 Installation sanitary ware 7 days Thu 7/30/15 Wed 8/5/15

1432 Villa 1 Bed Room 1086 M&E Second phase 12 days Sat 7/25/15 Wed 8/5/15

1433 M&E Second phase 12 days Sat 7/25/15 Wed 8/5/15

1434 Electrical System 12 days Sat 7/25/15 Wed 8/5/15

1435 Installation electrical panel 2 days Sat 7/25/15 Sun 7/26/15

1436 Installation lighting 6 days Mon 7/27/15 Sat 8/1/15

1437 Installation wiring device 2 days Sun 8/2/15 Mon 8/3/15

1438 Installation ELV equipment 2 days Tue 8/4/15 Wed 8/5/15

1439 A/C and Ventilation System 12 days Sat 7/25/15 Wed 8/5/15

1440 Installation A/C unit 7 days Sat 7/25/15 Fri 7/31/15

1441 Installatin exhaust fan 5 days Sat 8/1/15 Wed 8/5/15

1442 Plumbing and Pool system 12 days Sat 7/25/15 Wed 8/5/15

1443 Installation Pool equipment 5 days Sat 7/25/15 Wed 7/29/15

1444 Installation sanitary ware 7 days Thu 7/30/15 Wed 8/5/15

1445 Final Inspection CEMP 0 days Wed 8/5/15 Wed 8/5/15

1446 Villa 4 Bed Room V-01 and V-02 219 days Fri 1/2/15 Fri 8/14/15

1447 A. Drawing preparation 15 days Fri 1/2/15 Fri 1/16/15

1448 B. Material procurement and transportation 91 days Fri 1/2/15 Thu 4/2/15

1449 C. Clearing and grubbing / Cut and filling work 5 days Wed 1/14/15 Sun 1/18/15

1450 C. Structure work 120 days Mon 1/19/15 Sun 5/24/15

1451 1. Foundation / Stump Column and back filling work 50 days Mon 1/19/15 Mon 3/9/15

1452 2. Ground beam and slab work 30 days Thu 3/5/15 Fri 4/3/15

1453 3. Column work 18 days Wed 4/1/15 Fri 4/24/15

1454 4. Roof beam and slab 30 days Sat 4/25/15 Sun 5/24/15

1455 D. Finishing work 45 days Thu 5/28/15 Sat 7/11/15

1456 1.Masonry work 25 days Thu 5/28/15 Sun 6/21/15

1457 2. Plastering work 20 days Mon 6/22/15 Sat 7/11/15

1458 E. Steel work 30 days Sat 4/4/15 Sat 5/9/15

1459 1. All steel work 30 days Sat 4/4/15 Sat 5/9/15

1460 F. Water proofing work 40 days Mon 5/25/15 Fri 7/3/15

1461 1. Water proof for roof ..tec. 40 days Mon 5/25/15 Fri 7/3/15

1462 G. Swimming Pool 50 days Tue 3/10/15 Mon 5/4/15

1463 H. Septic Tank 30 days Tue 3/10/15 Wed 4/8/15

1464 milestone PHV (4 Bed Room V-01 and V-02) 0 days Wed 2/18/15 Wed 2/18/15

1465 Villa 4 Bed Room V-01 and V-02 M&E first phase 79 days Wed 2/18/15 Wed 5/13/15

1466 V-01 M&E First phase 41 days Wed 2/18/15 Mon 3/30/15

1467 M&E first phase 41 days Wed 2/18/15 Mon 3/30/15

1468 Electrical System 38 days Wed 2/18/15 Fri 3/27/15

1469 Pipe sleeve installation 5 days Wed 2/18/15 Sun 2/22/15

1470 Installation conduit above the ceiling & embedded in wall 7 days Mon 3/16/15 Sun 3/22/15

1471 Pulling the Cable for LV and ELV 5 days Mon 3/23/15 Fri 3/27/15

1472 A/C and Ventilation System 41 days Wed 2/18/15 Mon 3/30/15

1473 Prepare the sleeve for refrigerant pipe installation 4 days Wed 2/18/15 Sat 2/21/15

1474 Installation Refregerant pipe and insulation 5 days Sun 3/15/15 Thu 3/19/15

1475 Installatin drain pipe and insulation 4 days Fri 3/20/15 Mon 3/23/15

1476 Installation ducting system 7 days Tue 3/24/15 Mon 3/30/15

1477 Plumbing and Pool system 40 days Wed 2/18/15 Sun 3/29/15

1478 Installation Underground pipe for waste water, storm wat 5 days Wed 2/18/15 Sun 2/22/15

1479 Installation above ground pipe for waste water, storm wa 14 days Mon 3/16/15 Sun 3/29/15

1480 V-02 M&E first phase 38 days Tue 3/31/15 Wed 5/13/15

1481 M&E first phase 38 days Tue 3/31/15 Wed 5/13/15

1482 Electrical System 38 days Tue 3/31/15 Wed 5/13/15

1483 Pipe sleeve installation 5 days Tue 3/31/15 Sat 4/4/15

1484 Installation conduit above the ceiling & embedded in wall 7 days Sat 5/2/15 Fri 5/8/15

1485 Pulling the Cable for LV and ELV 5 days Sat 5/9/15 Wed 5/13/15

1486 A/C and Ventilation System 38 days Tue 3/31/15 Wed 5/13/15

1487 Prepare the sleeve for refrigerant pipe installation 4 days Tue 3/31/15 Fri 4/3/15

1488 Installation Refregerant pipe and insulation 5 days Tue 4/28/15 Sat 5/2/15

1489 Installatin drain pipe and insulation 4 days Sun 5/3/15 Wed 5/6/15

1490 Installation ducting system 7 days Thu 5/7/15 Wed 5/13/15

1491 Plumbing and Pool system 38 days Tue 3/31/15 Wed 5/13/15

1492 Installation Underground pipe for waste water, storm wat 5 days Tue 3/31/15 Sat 4/4/15

1493 Installation above ground pipe for waste water, storm wa 14 days Thu 4/30/15 Wed 5/13/15

1494 J. Final inspection/Punch Listing and Hnad over 10 days Sun 7/12/15 Tue 7/21/15

1495 milestone ID (4 Bed Room V-01 and V-02) 0 days Wed 8/5/15 Wed 8/5/15

1496 Villa 4 Bed Room V-01 and V-02 M&E Second phase 9 days Thu 8/6/15 Fri 8/14/15

1497 V-01 M&E Second phase 9 days Thu 8/6/15 Fri 8/14/15

1498 M&E Second phase 9 days Thu 8/6/15 Fri 8/14/15

1499 Electrical System 9 days Thu 8/6/15 Fri 8/14/15

1500 Installation electrical panel 2 days Thu 8/6/15 Fri 8/7/15

1501 Installation lighting 4 days Sat 8/8/15 Tue 8/11/15

1502 Installation wiring device 2 days Wed 8/12/15 Thu 8/13/15

1503 Installation ELV equipment 1 day Fri 8/14/15 Fri 8/14/15

1504 A/C and Ventilation System 9 days Thu 8/6/15 Fri 8/14/15

1505 Installation A/C unit 4 days Thu 8/6/15 Sun 8/9/15

1506 Installatin exhaust fan 5 days Mon 8/10/15 Fri 8/14/15

1507 Plumbing and Pool system 9 days Thu 8/6/15 Fri 8/14/15

1508 Installation Pool equipment 4 days Thu 8/6/15 Sun 8/9/15

1509 Installation sanitary ware 5 days Mon 8/10/15 Fri 8/14/15

1510 V-02 M&E Second phase 9 days Thu 8/6/15 Fri 8/14/15

1511 M&E Second phase 9 days Thu 8/6/15 Fri 8/14/15

1512 Electrical System 9 days Thu 8/6/15 Fri 8/14/15

1513 Installation electrical panel 2 days Thu 8/6/15 Fri 8/7/15

1514 Installation lighting 4 days Sat 8/8/15 Tue 8/11/15

1515 Installation wiring device 2 days Wed 8/12/15 Thu 8/13/15

1516 Installation ELV equipment 1 day Fri 8/14/15 Fri 8/14/15

1517 A/C and Ventilation System 9 days Thu 8/6/15 Fri 8/14/15

1518 Installation A/C unit 4 days Thu 8/6/15 Sun 8/9/15

1519 Installatin exhaust fan 5 days Mon 8/10/15 Fri 8/14/15

1520 Plumbing and Pool system 9 days Thu 8/6/15 Fri 8/14/15

1521 Installation Pool equipment 4 days Thu 8/6/15 Sun 8/9/15

1522 Installation sanitary ware 5 days Mon 8/10/15 Fri 8/14/15

1523 Final inspection CEMP 0 days Fri 8/14/15 Fri 8/14/15

1524 Hotel suit block 2 (007 to 0012) 289 days Wed 10/15/14 Wed 8/5/15

5/6 5/13

3/24 5/9

3/24 3/29

4/26 5/9

3/24 5/13

3/24 5/13

3/24 5/13

3/24 3/29

4/26 5/5

5/6 5/13

3/24 5/13

3/24 3/28

4/25 5/1

5/2 5/5

5/6 5/13

3/24 5/9

3/24 3/29

4/26 5/9

6/25 7/9

7/24 milestone ID (1 bed room 1085

7/25 8/5

7/25 8/5

7/25 8/5

7/25 8/5

7/25 7/26

7/27 8/1

8/2 8/3

8/4 8/5

7/25 8/5

7/25 7/31

8/1 8/5

7/25 8/5

7/25 7/29

7/30 8/5

7/25 8/5

7/25 8/5

7/25 8/5

7/25 7/26

7/27 8/1

8/2 8/3

8/4 8/5

7/25 8/5

7/25 7/31

8/1 8/5

7/25 8/5

7/25 7/29

7/30 8/5

8/5 Final Inspection CEMP

1/2 8/14

1/2 1/16

1/2 4/2

1/14 1/18

1/19 5/24

1/19 3/9

3/5 4/3

4/1 4/24

4/25 5/24

5/28 7/11

5/28 6/21

6/22 7/11

4/4 5/9

4/4 5/9

5/25 7/3

5/25 7/3

3/10 5/4

3/10 4/8

2/18 milestone PHV (4 Bed Room V-01 and V-02)

2/18 5/13

2/18 3/30

2/18 3/30

2/18 3/27

2/18 2/22

3/16 3/22

3/23 3/27

2/18 3/30

2/18 2/21

3/15 3/19

3/20 3/23

3/24 3/30

2/18 3/29

2/18 2/22

3/16 3/29

3/31 5/13

3/31 5/13

3/31 5/13

3/31 4/4

5/2 5/8

5/9 5/13

3/31 5/13

3/31 4/3

4/28 5/2

5/3 5/6

5/7 5/13

3/31 5/13

3/31 4/4

4/30 5/13

7/12 7/21

8/5 milestone ID (4 Bed Room

8/6 8/14

8/6 8/14

8/6 8/14

8/6 8/14

8/6 8/7

8/8 8/11

8/12 8/13

8/14 8/14

8/6 8/14

8/6 8/9

8/10 8/14

8/6 8/14

8/6 8/9

8/10 8/14

8/6 8/14

8/6 8/14

8/6 8/14

8/6 8/7

8/8 8/11

8/12 8/13

8/14 8/14

8/6 8/14

8/6 8/9

8/10 8/14

8/6 8/14

8/6 8/9

8/10 8/14

8/14 Final inspection CEMP

10/15 8/5

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep OctJuly August Septemb October Novembe Decembe January February March April May June July August Septemb October

Task

Split

Progress

Milestone

Summary

Project Summary

External Tasks

External Milestone

Deadline

MASTER SCHEDULE ALILA RESORT - KOH RUSSEY

Prepared by: Soly

Project: KRU-MEP ScheduleDate: Fri 10/24/14

ID ALILA RESORT-KOH RUSSEY M&E SCHEDULE Duration Start Finish

1525 A. Drawing preparation 15 days Wed 10/15/14Wed 10/29/14

1526 B. Material procurement and transportation 200 days Wed 10/15/14 Fri 5/8/15

1527 C. Clearing and grubbing / Cut and filling work 7 days Sat 10/25/14 Fri 10/31/14

1528 F. Ground floor 154 days Sat 11/1/14 Fri 4/3/15

1529 a. Structure work 83 days Sat 11/1/14 Thu 1/22/15

1530 1. Foundation / Stump Column and back filling work 45 days Sat 11/1/14Mon 12/15/14

1531 2. Ground beam and slab work 25 days Tue 12/9/14 Fri 1/2/15

1532 3. Column work 25 days Mon 12/29/14 Thu 1/22/15

1533 b. Finishing work 50 days Fri 2/13/15 Fri 4/3/15

1534 1.Masonry work 25 days Fri 2/13/15 Mon 3/9/15

1535 2. Plastering work 25 days Tue 3/10/15 Fri 4/3/15

1536 G. First floor 123 days Fri 1/16/15 Sun 5/24/15

1537 a. Structure work 70 days Fri 1/16/15 Thu 3/26/15

1538 1. First floor beam and slab 25 days Fri 1/16/15 Mon 2/9/15

1539 2. Column work 25 days Thu 2/5/15 Sun 3/1/15

1540 3. Roof beam and slab 25 days Mon 3/2/15 Thu 3/26/15

1541 b. Finishing work 50 days Mon 3/30/15 Sun 5/24/15

1542 1.Masonry work 25 days Mon 3/30/15 Wed 4/29/15

1543 2. Plastering work 25 days Thu 4/30/15 Sun 5/24/15

1544 H. Water proofing work 40 days Mon 3/30/15 Thu 5/14/15

1545 milestone PHV Hotel Suit block 2 (007 to 012) 0 days Wed 11/26/14Wed 11/26/14

1546 Hotel suit block 2 (0007 to 0012) M&E first phase 89 days Wed 11/26/14 Sun 2/22/15

1547 HS unit 007 first phase 40 days Wed 11/26/14 Sun 1/4/15

1548 M&E first phase 40 days Wed 11/26/14 Sun 1/4/15

1549 Electrical System 39 days Wed 11/26/14 Sat 1/3/15

1550 Pipe sleeve installation 3 days Wed 11/26/14 Fri 11/28/14

1551 Installation conduit above the ceiling & embedded in wall 10 days Sat 12/20/14Mon 12/29/14

1552 Pulling the Cable for LV and ELV 5 days Tue 12/30/14 Sat 1/3/15

1553 A/C and Ventilation System 40 days Wed 11/26/14 Sun 1/4/15

1554 Prepare the sleeve for refrigerant pipe installation 3 days Wed 11/26/14 Fri 11/28/14

1555 Installation Refregerant pipe and insulation 5 days Sat 12/20/14Wed 12/24/14

1556 Installation drain pipe and insulation 4 days Thu 12/25/14Sun 12/28/14

1557 Installation ducting system 7 days Mon 12/29/14 Sun 1/4/15

1558 Plumbing System 36 days Wed 11/26/14Wed 12/31/14

1559 Installation Underground pipe for waste water, rain water 5 days Wed 11/26/14Sun 11/30/14

1560 Installation above ground pipe for waste water, rain wate 10 days Mon 12/22/14Wed 12/31/14

1561 HS unit 008 first phase 40 days Wed 11/26/14 Sun 1/4/15

1562 M&E first phase 40 days Wed 11/26/14 Sun 1/4/15

1563 Electrical System 39 days Wed 11/26/14 Sat 1/3/15

1564 Pipe sleeve installation 3 days Wed 11/26/14 Fri 11/28/14

1565 Installation conduit above the ceiling & embedded in wall 10 days Sat 12/20/14Mon 12/29/14

1566 Pulling the Cable for LV and ELV 5 days Tue 12/30/14 Sat 1/3/15

1567 A/C and Ventilation System 40 days Wed 11/26/14 Sun 1/4/15

1568 Prepare the sleeve for refrigerant pipe installation 3 days Wed 11/26/14 Fri 11/28/14

1569 Installation Refregerant pipe and insulation 5 days Sat 12/20/14Wed 12/24/14

1570 Installatin drain pipe and insulation 4 days Thu 12/25/14Sun 12/28/14

1571 Installation ducting system 7 days Mon 12/29/14 Sun 1/4/15

1572 Plumbing System 36 days Wed 11/26/14Wed 12/31/14

1573 Installation Underground pipe for waste water, rain water 5 days Wed 11/26/14Sun 11/30/14

1574 Installation above ground pipe for waste water, rain wate 10 days Mon 12/22/14Wed 12/31/14

1575 HS unit 009 first phase 40 days Mon 1/5/15 Fri 2/13/15

1576 M&E first phase 40 days Mon 1/5/15 Fri 2/13/15

1577 Electrical System 39 days Mon 1/5/15 Thu 2/12/15

1578 Pipe sleeve installation 3 days Mon 1/5/15 Wed 1/7/15

1579 Installation conduit above the ceiling & embedded in wall 10 days Thu 1/29/15 Sat 2/7/15

1580 Pulling the Cable for LV and ELV 5 days Sun 2/8/15 Thu 2/12/15

1581 A/C and Ventilation System 40 days Mon 1/5/15 Fri 2/13/15

1582 Prepare the sleeve for refrigerant pipe installation 3 days Mon 1/5/15 Wed 1/7/15

1583 Installation Refregerant pipe and insulation 5 days Thu 1/29/15 Mon 2/2/15

1584 Installatin drain pipe and insulation 4 days Tue 2/3/15 Fri 2/6/15

1585 Installation ducting system 7 days Sat 2/7/15 Fri 2/13/15

1586 Plumbing System 36 days Mon 1/5/15 Mon 2/9/15

1587 Installation Underground pipe for waste water, rain water 5 days Mon 1/5/15 Fri 1/9/15

1588 Installation above ground pipe for waste water, rain wate 10 days Sat 1/31/15 Mon 2/9/15

1589 HS unit 0010 first phase 40 days Wed 11/26/14 Sun 1/4/15

1590 M&E first phase 40 days Wed 11/26/14 Sun 1/4/15

1591 Electrical System 39 days Wed 11/26/14 Sat 1/3/15

1592 Pipe sleeve installation 3 days Wed 11/26/14 Fri 11/28/14

1593 Installation conduit above the ceiling & embedded in wall 10 days Sat 12/20/14Mon 12/29/14

1594 Pulling the Cable for LV and ELV 5 days Tue 12/30/14 Sat 1/3/15

1595 A/C and Ventilation System 40 days Wed 11/26/14 Sun 1/4/15

1596 Prepare the sleeve for refrigerant pipe installation 3 days Wed 11/26/14 Fri 11/28/14

1597 Installation Refregerant pipe and insulation 5 days Sat 12/20/14Wed 12/24/14

1598 Installatin drain pipe and insulation 4 days Thu 12/25/14Sun 12/28/14

1599 Installation ducting system 7 days Mon 12/29/14 Sun 1/4/15

1600 Plumbing System 36 days Wed 11/26/14Wed 12/31/14

1601 Installation Underground pipe for waste water, rain water 5 days Wed 11/26/14Sun 11/30/14

1602 Installation above ground pipe for waste water, rain wate 10 days Mon 12/22/14Wed 12/31/14

1603 HS unit 0011 first phase 49 days Mon 1/5/15 Sun 2/22/15

1604 M&E first phase 49 days Mon 1/5/15 Sun 2/22/15

1605 Electrical System 48 days Mon 1/5/15 Sat 2/21/15

1606 Pipe sleeve installation 3 days Mon 1/5/15 Wed 1/7/15

1607 Installation conduit above the ceiling & embedded in wall 10 days Sat 2/7/15 Mon 2/16/15

1608 Pulling the Cable for LV and ELV 5 days Tue 2/17/15 Sat 2/21/15

1609 A/C and Ventilation System 49 days Mon 1/5/15 Sun 2/22/15

1610 Prepare the sleeve for refrigerant pipe installation 3 days Mon 1/5/15 Wed 1/7/15

1611 Installation Refregerant pipe and insulation 5 days Sat 2/7/15 Wed 2/11/15

1612 Installatin drain pipe and insulation 4 days Thu 2/12/15 Sun 2/15/15

1613 Installation ducting system 7 days Mon 2/16/15 Sun 2/22/15

1614 Plumbing System 45 days Mon 1/5/15 Wed 2/18/15

1615 Installation Underground pipe for waste water, rain water 5 days Mon 1/5/15 Fri 1/9/15

1616 Installation above ground pipe for waste water, rain wate 10 days Mon 2/9/15 Wed 2/18/15

1617 HS unit 0012 first phase 49 days Mon 1/5/15 Sun 2/22/15

1618 M&E first phase 49 days Mon 1/5/15 Sun 2/22/15

1619 Electrical System 48 days Mon 1/5/15 Sat 2/21/15

1620 Pipe sleeve installation 3 days Mon 1/5/15 Wed 1/7/15

1621 Installation conduit above the ceiling & embedded in wall 10 days Sat 2/7/15 Mon 2/16/15

1622 Pulling the Cable for LV and ELV 5 days Tue 2/17/15 Sat 2/21/15

1623 A/C and Ventilation System 49 days Mon 1/5/15 Sun 2/22/15

1624 Prepare the sleeve for refrigerant pipe installation 3 days Mon 1/5/15 Wed 1/7/15

1625 Installation Refregerant pipe and insulation 5 days Sat 2/7/15 Wed 2/11/15

1626 Installatin drain pipe and insulation 4 days Thu 2/12/15 Sun 2/15/15

1627 Installation ducting system 7 days Mon 2/16/15 Sun 2/22/15

1628 Plumbing System 45 days Mon 1/5/15 Wed 2/18/15

1629 Installation Underground pipe for waste water, rain water 5 days Mon 1/5/15 Fri 1/9/15

1630 Installation above ground pipe for waste water, rain wate 10 days Mon 2/9/15 Wed 2/18/15

1631 J. Final inspection/Punch Listing and Hand over 10 days Mon 5/25/15 Wed 6/3/15

1632 milestone ID Hotel Suit block 2 (007 to 012) 0 days Thu 6/18/15 Thu 6/18/15

1633 Hotel suit block 1 (0007 to 0012) M&E Second phase 48 days Fri 6/19/15 Wed 8/5/15

1634 HS unit 007 Second phase 16 days Fri 6/19/15 Sat 7/4/15

1635 M&E Second phase 16 days Fri 6/19/15 Sat 7/4/15

1636 Electrical System 16 days Fri 6/19/15 Sat 7/4/15

1637 Installation electrical panel 2 days Fri 6/19/15 Sat 6/20/15

1638 Installation lighting 6 days Sun 6/21/15 Fri 6/26/15

1639 Installation wiring device 6 days Sat 6/27/15 Thu 7/2/15

1640 Installation ELV equipment 2 days Fri 7/3/15 Sat 7/4/15

1641 A/C and Ventilation System 16 days Fri 6/19/15 Sat 7/4/15

1642 Installation A/C unit 10 days Fri 6/19/15 Sun 6/28/15

1643 Installatin exhaust fan 6 days Mon 6/29/15 Sat 7/4/15

1644 Plumbing System 8 days Fri 6/19/15 Fri 6/26/15

1645 Installation sanitary ware 8 days Fri 6/19/15 Fri 6/26/15

1646 HS unit 008 Second phase 16 days Fri 6/19/15 Sat 7/4/15

1647 M&E Second phase 16 days Fri 6/19/15 Sat 7/4/15

1648 Electrical System 16 days Fri 6/19/15 Sat 7/4/15

1649 Installation electrical panel 2 days Fri 6/19/15 Sat 6/20/15

1650 Installation lighting 6 days Sun 6/21/15 Fri 6/26/15

1651 Installation wiring device 6 days Sat 6/27/15 Thu 7/2/15

10/15 10/29

10/15 5/8

10/25 10/31

11/1 4/3

11/1 1/22

11/1 12/15

12/9 1/2

12/29 1/22

2/13 4/3

2/13 3/9

3/10 4/3

1/16 5/24

1/16 3/26

1/16 2/9

2/5 3/1

3/2 3/26

3/30 5/24

3/30 4/29

4/30 5/24

3/30 5/14

11/26 milestone PHV Hotel Suit block 2 (007 to 012)

11/26 2/22

11/26 1/4

11/26 1/4

11/26 1/3

11/26 11/28

12/20 12/29

12/30 1/3

11/26 1/4

11/26 11/28

12/20 12/24

12/25 12/28

12/29 1/4

11/26 12/31

11/26 11/30

12/22 12/31

11/26 1/4

11/26 1/4

11/26 1/3

11/26 11/28

12/20 12/29

12/30 1/3

11/26 1/4

11/26 11/28

12/20 12/24

12/25 12/28

12/29 1/4

11/26 12/31

11/26 11/30

12/22 12/31

1/5 2/13

1/5 2/13

1/5 2/12

1/5 1/7

1/29 2/7

2/8 2/12

1/5 2/13

1/5 1/7

1/29 2/2

2/3 2/6

2/7 2/13

1/5 2/9

1/5 1/9

1/31 2/9

11/26 1/4

11/26 1/4

11/26 1/3

11/26 11/28

12/20 12/29

12/30 1/3

11/26 1/4

11/26 11/28

12/20 12/24

12/25 12/28

12/29 1/4

11/26 12/31

11/26 11/30

12/22 12/31

1/5 2/22

1/5 2/22

1/5 2/21

1/5 1/7

2/7 2/16

2/17 2/21

1/5 2/22

1/5 1/7

2/7 2/11

2/12 2/15

2/16 2/22

1/5 2/18

1/5 1/9

2/9 2/18

1/5 2/22

1/5 2/22

1/5 2/21

1/5 1/7

2/7 2/16

2/17 2/21

1/5 2/22

1/5 1/7

2/7 2/11

2/12 2/15

2/16 2/22

1/5 2/18

1/5 1/9

2/9 2/18

5/25 6/3

6/18 milestone ID Hotel Suit block 2 (007 to 012)

6/19 8/5

6/19 7/4

6/19 7/4

6/19 7/4

6/19 6/20

6/21 6/26

6/27 7/2

7/3 7/4

6/19 7/4

6/19 6/28

6/29 7/4

6/19 6/26

6/19 6/26

6/19 7/4

6/19 7/4

6/19 7/4

6/19 6/20

6/21 6/26

6/27 7/2

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep OctJuly August Septemb October Novembe Decembe January February March April May June July August Septemb October

Task

Split

Progress

Milestone

Summary

Project Summary

External Tasks

External Milestone

Deadline

MASTER SCHEDULE ALILA RESORT - KOH RUSSEY

Prepared by: Soly

Project: KRU-MEP ScheduleDate: Fri 10/24/14

ID ALILA RESORT-KOH RUSSEY M&E SCHEDULE Duration Start Finish

1652 Installation ELV equipment 2 days Fri 7/3/15 Sat 7/4/15

1653 A/C and Ventilation System 16 days Fri 6/19/15 Sat 7/4/15

1654 Installation A/C unit 10 days Fri 6/19/15 Sun 6/28/15

1655 Installatin exhaust fan 6 days Mon 6/29/15 Sat 7/4/15

1656 Plumbing System 8 days Fri 6/19/15 Fri 6/26/15

1657 Installation sanitary ware 8 days Fri 6/19/15 Fri 6/26/15

1658 HS unit 009 Second phase 16 days Sun 7/5/15 Mon 7/20/15

1659 M&E Second phase 16 days Sun 7/5/15 Mon 7/20/15

1660 Electrical System 16 days Sun 7/5/15 Mon 7/20/15

1661 Installation electrical panel 2 days Sun 7/5/15 Mon 7/6/15

1662 Installation lighting 6 days Tue 7/7/15 Sun 7/12/15

1663 Installation wiring device 6 days Mon 7/13/15 Sat 7/18/15

1664 Installation ELV equipment 2 days Sun 7/19/15 Mon 7/20/15

1665 A/C and Ventilation System 16 days Sun 7/5/15 Mon 7/20/15

1666 Installation A/C unit 10 days Sun 7/5/15 Tue 7/14/15

1667 Installatin exhaust fan 6 days Wed 7/15/15 Mon 7/20/15

1668 Plumbing system 8 days Sun 7/5/15 Sun 7/12/15

1669 Installation sanitary ware 8 days Sun 7/5/15 Sun 7/12/15

1670 HS unit 010 Second phase 16 days Sun 7/5/15 Mon 7/20/15

1671 M&E Second phase 16 days Sun 7/5/15 Mon 7/20/15

1672 Electrical System 16 days Sun 7/5/15 Mon 7/20/15

1673 Installation electrical panel 2 days Sun 7/5/15 Mon 7/6/15

1674 Installation lighting 6 days Tue 7/7/15 Sun 7/12/15

1675 Installation wiring device 6 days Mon 7/13/15 Sat 7/18/15

1676 Installation ELV equipment 2 days Sun 7/19/15 Mon 7/20/15

1677 A/C and Ventilation System 16 days Sun 7/5/15 Mon 7/20/15

1678 Installation A/C unit 10 days Sun 7/5/15 Tue 7/14/15

1679 Installatin exhaust fan 6 days Wed 7/15/15 Mon 7/20/15

1680 Plumbing system 8 days Sun 7/5/15 Sun 7/12/15

1681 Installation sanitary ware 8 days Sun 7/5/15 Sun 7/12/15

1682 HS unit 0011 Second phase 16 days Tue 7/21/15 Wed 8/5/15

1683 M&E Second phase 16 days Tue 7/21/15 Wed 8/5/15

1684 Electrical System 16 days Tue 7/21/15 Wed 8/5/15

1685 Installation electrical panel 2 days Tue 7/21/15 Wed 7/22/15

1686 Installation lighting 6 days Thu 7/23/15 Tue 7/28/15

1687 Installation wiring device 6 days Wed 7/29/15 Mon 8/3/15

1688 Installation ELV equipment 2 days Tue 8/4/15 Wed 8/5/15

1689 A/C and Ventilation System 16 days Tue 7/21/15 Wed 8/5/15

1690 Installation A/C unit 10 days Tue 7/21/15 Thu 7/30/15

1691 Installatin exhaust fan 6 days Fri 7/31/15 Wed 8/5/15

1692 Plumbing system 8 days Tue 7/21/15 Tue 7/28/15

1693 Installation sanitary ware 8 days Tue 7/21/15 Tue 7/28/15

1694 HS unit 0012 Second phase 16 days Tue 7/21/15 Wed 8/5/15

1695 M&E Second phase 16 days Tue 7/21/15 Wed 8/5/15

1696 Electrical System 16 days Tue 7/21/15 Wed 8/5/15

1697 Installation electrical panel 2 days Tue 7/21/15 Wed 7/22/15

1698 Installation lighting 6 days Thu 7/23/15 Tue 7/28/15

1699 Installation wiring device 6 days Wed 7/29/15 Mon 8/3/15

1700 Installation ELV equipment 2 days Tue 8/4/15 Wed 8/5/15

1701 A/C and Ventilation System 16 days Tue 7/21/15 Wed 8/5/15

1702 Installation A/C unit 10 days Tue 7/21/15 Thu 7/30/15

1703 Installatin exhaust fan 6 days Fri 7/31/15 Wed 8/5/15

1704 Plumbing system 8 days Tue 7/21/15 Tue 7/28/15

1705 Installation sanitary ware 8 days Tue 7/21/15 Tue 7/28/15

1706 Final inspection CEMP 0 days Wed 8/5/15 Wed 8/5/15

1707 Hotel suit block 3 (0013 to 0019) 302 days Wed 10/15/14 Tue 8/18/15

1708 A. Drawing preparation 15 days Wed 10/15/14Wed 10/29/14

1709 B. Material procurement and transportation 200 days Wed 10/15/14 Fri 5/8/15

1710 C. Clearing and grubbing / Cut and filling work 7 days Sat 11/1/14 Fri 11/7/14

1711 F. Ground floor 163 days Mon 12/1/14 Mon 5/18/15

1712 a. Structure work 88 days Mon 12/1/14 Thu 2/26/15

1713 1. Foundation / Stump Column and back filling work 45 days Mon 12/1/14 Wed 1/14/15

1714 2. Ground beam and slab work 30 days Thu 1/8/15 Fri 2/6/15

1715 3. Column work 25 days Mon 2/2/15 Thu 2/26/15

1716 b. Finishing work 50 days Tue 3/24/15 Mon 5/18/15

1717 1.Masonry work 25 days Tue 3/24/15 Thu 4/23/15

1718 2. Plastering work 25 days Fri 4/24/15 Mon 5/18/15

1719 G. First floor 127 days Sun 2/22/15 Sat 7/4/15

1720 a. Structure work 72 days Sun 2/22/15 Sun 5/10/15

1721 1. First floor beam and slab 25 days Sun 2/22/15 Wed 3/18/15

1722 2. Column work 25 days Mon 3/16/15 Thu 4/9/15

1723 3. Roof beam and slab 25 days Fri 4/10/15 Sun 5/10/15

1724 b. Finishing work 50 days Sat 5/16/15 Sat 7/4/15

1725 1.Masonry work 25 days Sat 5/16/15 Tue 6/9/15

1726 2. Plastering work 25 days Wed 6/10/15 Sat 7/4/15

1727 H. Water proofing work 30 days Thu 5/14/15 Fri 6/12/15

1728 milestone PHV (Hotel Suit block 2 (0013 to 0019)) 0 days Fri 12/26/14 Fri 12/26/14

1729 Hotel suit block 3 (0013 to 0019) M&E first phase 120 days Fri 12/26/14 Thu 4/30/15

1730 HS unit 0013 first phase 40 days Fri 12/26/14 Tue 2/3/15

1731 M&E first phase 40 days Fri 12/26/14 Tue 2/3/15

1732 Electrical System 39 days Fri 12/26/14 Mon 2/2/15

1733 Pipe sleeve installation 3 days Fri 12/26/14Sun 12/28/14

1734 Installation conduit above the ceiling & embedded in wall 10 days Mon 1/19/15 Wed 1/28/15

1735 Pulling the Cable for LV and ELV 5 days Thu 1/29/15 Mon 2/2/15

1736 A/C and Ventilation System 40 days Fri 12/26/14 Tue 2/3/15

1737 Prepare the sleeve for refrigerant pipe installation 3 days Fri 12/26/14Sun 12/28/14

1738 Installation Refregerant pipe and insulation 5 days Mon 1/19/15 Fri 1/23/15

1739 Installation drain pipe and insulation 4 days Sat 1/24/15 Tue 1/27/15

1740 Installation ducting system 7 days Wed 1/28/15 Tue 2/3/15

1741 Plumbing System 36 days Fri 12/26/14 Fri 1/30/15

1742 Installation Underground pipe for waste water, rain water 5 days Fri 12/26/14Tue 12/30/14

1743 Installation above ground pipe for waste water, rain wate 10 days Wed 1/21/15 Fri 1/30/15

1744 HS unit 0014 first phase 40 days Fri 12/26/14 Tue 2/3/15

1745 M&E first phase 40 days Fri 12/26/14 Tue 2/3/15

1746 Electrical System 39 days Fri 12/26/14 Mon 2/2/15

1747 Pipe sleeve installation 3 days Fri 12/26/14Sun 12/28/14

1748 Installation conduit above the ceiling & embedded in wall 10 days Mon 1/19/15 Wed 1/28/15

1749 Pulling the Cable for LV and ELV 5 days Thu 1/29/15 Mon 2/2/15

1750 A/C and Ventilation System 40 days Fri 12/26/14 Tue 2/3/15

1751 Prepare the sleeve for refrigerant pipe installation 3 days Fri 12/26/14Sun 12/28/14

1752 Installation Refregerant pipe and insulation 5 days Mon 1/19/15 Fri 1/23/15

1753 Installatin drain pipe and insulation 4 days Sat 1/24/15 Tue 1/27/15

1754 Installation ducting system 7 days Wed 1/28/15 Tue 2/3/15

1755 Plumbing System 36 days Fri 12/26/14 Fri 1/30/15

1756 Installation Underground pipe for waste water, rain water 5 days Fri 12/26/14Tue 12/30/14

1757 Installation above ground pipe for waste water, rain wate 10 days Wed 1/21/15 Fri 1/30/15

1758 HS unit 0015 first phase 40 days Wed 2/4/15 Sun 3/15/15

1759 M&E first phase 40 days Wed 2/4/15 Sun 3/15/15

1760 Electrical System 39 days Wed 2/4/15 Sat 3/14/15

1761 Pipe sleeve installation 3 days Wed 2/4/15 Fri 2/6/15

1762 Installation conduit above the ceiling & embedded in wall 10 days Sat 2/28/15 Mon 3/9/15

1763 Pulling the Cable for LV and ELV 5 days Tue 3/10/15 Sat 3/14/15

1764 A/C and Ventilation System 40 days Wed 2/4/15 Sun 3/15/15

1765 Prepare the sleeve for refrigerant pipe installation 3 days Wed 2/4/15 Fri 2/6/15

1766 Installation Refregerant pipe and insulation 5 days Sat 2/28/15 Wed 3/4/15

1767 Installatin drain pipe and insulation 4 days Thu 3/5/15 Sun 3/8/15

1768 Installation ducting system 7 days Mon 3/9/15 Sun 3/15/15

1769 Plumbing System 36 days Wed 2/4/15 Wed 3/11/15

1770 Installation Underground pipe for waste water, rain water 5 days Wed 2/4/15 Sun 2/8/15

1771 Installation above ground pipe for waste water, rain wate 10 days Mon 3/2/15 Wed 3/11/15

1772 HS unit 0016 first phase 40 days Wed 2/4/15 Sun 3/15/15

1773 M&E first phase 40 days Wed 2/4/15 Sun 3/15/15

1774 Electrical System 39 days Wed 2/4/15 Sat 3/14/15

1775 Pipe sleeve installation 3 days Wed 2/4/15 Fri 2/6/15

1776 Installation conduit above the ceiling & embedded in wall 10 days Sat 2/28/15 Mon 3/9/15

1777 Pulling the Cable for LV and ELV 5 days Tue 3/10/15 Sat 3/14/15

1778 A/C and Ventilation System 40 days Wed 2/4/15 Sun 3/15/15

7/3 7/4

6/19 7/4

6/19 6/28

6/29 7/4

6/19 6/26

6/19 6/26

7/5 7/20

7/5 7/20

7/5 7/20

7/5 7/6

7/7 7/12

7/13 7/18

7/19 7/20

7/5 7/20

7/5 7/14

7/15 7/20

7/5 7/12

7/5 7/12

7/5 7/20

7/5 7/20

7/5 7/20

7/5 7/6

7/7 7/12

7/13 7/18

7/19 7/20

7/5 7/20

7/5 7/14

7/15 7/20

7/5 7/12

7/5 7/12

7/21 8/5

7/21 8/5

7/21 8/5

7/21 7/22

7/23 7/28

7/29 8/3

8/4 8/5

7/21 8/5

7/21 7/30

7/31 8/5

7/21 7/28

7/21 7/28

7/21 8/5

7/21 8/5

7/21 8/5

7/21 7/22

7/23 7/28

7/29 8/3

8/4 8/5

7/21 8/5

7/21 7/30

7/31 8/5

7/21 7/28

7/21 7/28

8/5 Final inspection CEMP

10/15 8/18

10/15 10/29

10/15 5/8

11/1 11/7

12/1 5/18

12/1 2/26

12/1 1/14

1/8 2/6

2/2 2/26

3/24 5/18

3/24 4/23

4/24 5/18

2/22 7/4

2/22 5/10

2/22 3/18

3/16 4/9

4/10 5/10

5/16 7/4

5/16 6/9

6/10 7/4

5/14 6/12

12/26 milestone PHV (Hotel Suit block 2 (0013 to 0019))

12/26 4/30

12/26 2/3

12/26 2/3

12/26 2/2

12/26 12/28

1/19 1/28

1/29 2/2

12/26 2/3

12/26 12/28

1/19 1/23

1/24 1/27

1/28 2/3

12/26 1/30

12/26 12/30

1/21 1/30

12/26 2/3

12/26 2/3

12/26 2/2

12/26 12/28

1/19 1/28

1/29 2/2

12/26 2/3

12/26 12/28

1/19 1/23

1/24 1/27

1/28 2/3

12/26 1/30

12/26 12/30

1/21 1/30

2/4 3/15

2/4 3/15

2/4 3/14

2/4 2/6

2/28 3/9

3/10 3/14

2/4 3/15

2/4 2/6

2/28 3/4

3/5 3/8

3/9 3/15

2/4 3/11

2/4 2/8

3/2 3/11

2/4 3/15

2/4 3/15

2/4 3/14

2/4 2/6

2/28 3/9

3/10 3/14

2/4 3/15

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep OctJuly August Septemb October Novembe Decembe January February March April May June July August Septemb October

Task

Split

Progress

Milestone

Summary

Project Summary

External Tasks

External Milestone

Deadline

MASTER SCHEDULE ALILA RESORT - KOH RUSSEY

Prepared by: Soly

Project: KRU-MEP ScheduleDate: Fri 10/24/14

ID ALILA RESORT-KOH RUSSEY M&E SCHEDULE Duration Start Finish

1779 Prepare the sleeve for refrigerant pipe installation 3 days Wed 2/4/15 Fri 2/6/15

1780 Installation Refregerant pipe and insulation 5 days Sat 2/28/15 Wed 3/4/15

1781 Installatin drain pipe and insulation 4 days Thu 3/5/15 Sun 3/8/15

1782 Installation ducting system 7 days Mon 3/9/15 Sun 3/15/15

1783 Plumbing System 36 days Wed 2/4/15 Wed 3/11/15

1784 Installation Underground pipe for waste water, rain water 5 days Wed 2/4/15 Sun 2/8/15

1785 Installation above ground pipe for waste water, rain wate 10 days Mon 3/2/15 Wed 3/11/15

1786 HS unit 0017 first phase 40 days Mon 3/16/15 Thu 4/30/15

1787 M&E first phase 40 days Mon 3/16/15 Thu 4/30/15

1788 Electrical System 39 days Mon 3/16/15 Wed 4/29/15

1789 Pipe sleeve installation 3 days Mon 3/16/15 Wed 3/18/15

1790 Installation conduit above the ceiling & embedded in wall 10 days Thu 4/9/15 Fri 4/24/15

1791 Pulling the Cable for LV and ELV 5 days Sat 4/25/15 Wed 4/29/15

1792 A/C and Ventilation System 40 days Mon 3/16/15 Thu 4/30/15

1793 Prepare the sleeve for refrigerant pipe installation 3 days Mon 3/16/15 Wed 3/18/15

1794 Installation Refregerant pipe and insulation 5 days Thu 4/9/15 Sun 4/19/15

1795 Installatin drain pipe and insulation 4 days Mon 4/20/15 Thu 4/23/15

1796 Installation ducting system 7 days Fri 4/24/15 Thu 4/30/15

1797 Plumbing System 36 days Mon 3/16/15 Sun 4/26/15

1798 Installation Underground pipe for waste water, rain water 5 days Mon 3/16/15 Fri 3/20/15

1799 Installation above ground pipe for waste water, rain wate 10 days Sat 4/11/15 Sun 4/26/15

1800 HS unit 0018 first phase 40 days Mon 3/16/15 Thu 4/30/15

1801 M&E first phase 40 days Mon 3/16/15 Thu 4/30/15

1802 Electrical System 39 days Mon 3/16/15 Wed 4/29/15

1803 Pipe sleeve installation 3 days Mon 3/16/15 Wed 3/18/15

1804 Installation conduit above the ceiling & embedded in wall 10 days Thu 4/9/15 Fri 4/24/15

1805 Pulling the Cable for LV and ELV 5 days Sat 4/25/15 Wed 4/29/15

1806 A/C and Ventilation System 40 days Mon 3/16/15 Thu 4/30/15

1807 Prepare the sleeve for refrigerant pipe installation 3 days Mon 3/16/15 Wed 3/18/15

1808 Installation Refregerant pipe and insulation 5 days Thu 4/9/15 Sun 4/19/15

1809 Installatin drain pipe and insulation 4 days Mon 4/20/15 Thu 4/23/15

1810 Installation ducting system 7 days Fri 4/24/15 Thu 4/30/15

1811 Plumbing System 36 days Mon 3/16/15 Sun 4/26/15

1812 Installation Underground pipe for waste water, rain water 5 days Mon 3/16/15 Fri 3/20/15

1813 Installation above ground pipe for waste water, rain wate 10 days Sat 4/11/15 Sun 4/26/15

1814 HS unit 0019 first phase 40 days Mon 3/16/15 Thu 4/30/15

1815 M&E first phase 40 days Mon 3/16/15 Thu 4/30/15

1816 Electrical System 39 days Mon 3/16/15 Wed 4/29/15

1817 Pipe sleeve installation 3 days Mon 3/16/15 Wed 3/18/15

1818 Installation conduit above the ceiling & embedded in wall 10 days Thu 4/9/15 Fri 4/24/15

1819 Pulling the Cable for LV and ELV 5 days Sat 4/25/15 Wed 4/29/15

1820 A/C and Ventilation System 40 days Mon 3/16/15 Thu 4/30/15

1821 Prepare the sleeve for refrigerant pipe installation 3 days Mon 3/16/15 Wed 3/18/15

1822 Installation Refregerant pipe and insulation 5 days Thu 4/9/15 Sun 4/19/15

1823 Installatin drain pipe and insulation 4 days Mon 4/20/15 Thu 4/23/15

1824 Installation ducting system 7 days Fri 4/24/15 Thu 4/30/15

1825 Plumbing System 36 days Mon 3/16/15 Sun 4/26/15

1826 Installation Underground pipe for waste water, rain water 5 days Mon 3/16/15 Fri 3/20/15

1827 Installation above ground pipe for waste water, rain wate 10 days Sat 4/11/15 Sun 4/26/15

1828 J. Final inspection/Punch Listing and Hand over 10 days Sun 7/5/15 Tue 7/14/15

1829 milestone ID (Hotel Suit block 2 (0013 to 0019)) 0 days Wed 7/29/15 Wed 7/29/15

1830 Hotel suit block 1 (0013 to 0019) M&E Second phase 20 days Thu 7/30/15 Tue 8/18/15

1831 HS unit 0013 Second phase 10 days Thu 7/30/15 Sat 8/8/15

1832 M&E Second phase 10 days Thu 7/30/15 Sat 8/8/15

1833 Electrical System 10 days Thu 7/30/15 Sat 8/8/15

1834 Installation electrical panel 2 days Thu 7/30/15 Fri 7/31/15

1835 Installation lighting 4 days Sat 8/1/15 Tue 8/4/15

1836 Installation wiring device 2 days Wed 8/5/15 Thu 8/6/15

1837 Installation ELV equipment 2 days Fri 8/7/15 Sat 8/8/15

1838 A/C and Ventilation System 10 days Thu 7/30/15 Sat 8/8/15

1839 Installation A/C unit 6 days Thu 7/30/15 Tue 8/4/15

1840 Installatin exhaust fan 4 days Wed 8/5/15 Sat 8/8/15

1841 Plumbing System 8 days Thu 7/30/15 Thu 8/6/15

1842 Installation sanitary ware 8 days Thu 7/30/15 Thu 8/6/15

1843 HS unit 0014 Second phase 10 days Thu 7/30/15 Sat 8/8/15

1844 M&E Second phase 10 days Thu 7/30/15 Sat 8/8/15

1845 Electrical System 10 days Thu 7/30/15 Sat 8/8/15

1846 Installation electrical panel 2 days Thu 7/30/15 Fri 7/31/15

1847 Installation lighting 4 days Sat 8/1/15 Tue 8/4/15

1848 Installation wiring device 2 days Wed 8/5/15 Thu 8/6/15

1849 Installation ELV equipment 2 days Fri 8/7/15 Sat 8/8/15

1850 A/C and Ventilation System 10 days Thu 7/30/15 Sat 8/8/15

1851 Installation A/C unit 6 days Thu 7/30/15 Tue 8/4/15

1852 Installatin exhaust fan 4 days Wed 8/5/15 Sat 8/8/15

1853 Plumbing System 8 days Thu 7/30/15 Thu 8/6/15

1854 Installation sanitary ware 8 days Thu 7/30/15 Thu 8/6/15

1855 HS unit 0015 Second phase 10 days Thu 7/30/15 Sat 8/8/15

1856 M&E Second phase 10 days Thu 7/30/15 Sat 8/8/15

1857 Electrical System 10 days Thu 7/30/15 Sat 8/8/15

1858 Installation electrical panel 2 days Thu 7/30/15 Fri 7/31/15

1859 Installation lighting 4 days Sat 8/1/15 Tue 8/4/15

1860 Installation wiring device 2 days Wed 8/5/15 Thu 8/6/15

1861 Installation ELV equipment 2 days Fri 8/7/15 Sat 8/8/15

1862 A/C and Ventilation System 10 days Thu 7/30/15 Sat 8/8/15

1863 Installation A/C unit 6 days Thu 7/30/15 Tue 8/4/15

1864 Installatin exhaust fan 4 days Wed 8/5/15 Sat 8/8/15

1865 Plumbing system 8 days Thu 7/30/15 Thu 8/6/15

1866 Installation sanitary ware 8 days Thu 7/30/15 Thu 8/6/15

1867 HS unit 016 Second phase 10 days Sun 8/9/15 Tue 8/18/15

1868 M&E Second phase 10 days Sun 8/9/15 Tue 8/18/15

1869 Electrical System 10 days Sun 8/9/15 Tue 8/18/15

1870 Installation electrical panel 2 days Sun 8/9/15 Mon 8/10/15

1871 Installation lighting 4 days Tue 8/11/15 Fri 8/14/15

1872 Installation wiring device 2 days Sat 8/15/15 Sun 8/16/15

1873 Installation ELV equipment 2 days Mon 8/17/15 Tue 8/18/15

1874 A/C and Ventilation System 10 days Sun 8/9/15 Tue 8/18/15

1875 Installation A/C unit 6 days Sun 8/9/15 Fri 8/14/15

1876 Installatin exhaust fan 4 days Sat 8/15/15 Tue 8/18/15

1877 Plumbing system 8 days Sun 8/9/15 Sun 8/16/15

1878 Installation sanitary ware 8 days Sun 8/9/15 Sun 8/16/15

1879 HS unit 0017 Second phase 10 days Sun 8/9/15 Tue 8/18/15

1880 M&E Second phase 10 days Sun 8/9/15 Tue 8/18/15

1881 Electrical System 10 days Sun 8/9/15 Tue 8/18/15

1882 Installation electrical panel 2 days Sun 8/9/15 Mon 8/10/15

1883 Installation lighting 4 days Tue 8/11/15 Fri 8/14/15

1884 Installation wiring device 2 days Sat 8/15/15 Sun 8/16/15

1885 Installation ELV equipment 2 days Mon 8/17/15 Tue 8/18/15

1886 A/C and Ventilation System 10 days Sun 8/9/15 Tue 8/18/15

1887 Installation A/C unit 6 days Sun 8/9/15 Fri 8/14/15

1888 Installatin exhaust fan 4 days Sat 8/15/15 Tue 8/18/15

1889 Plumbing system 8 days Sun 8/9/15 Sun 8/16/15

1890 Installation sanitary ware 8 days Sun 8/9/15 Sun 8/16/15

1891 HS unit 0018 Second phase 10 days Sun 8/9/15 Tue 8/18/15

1892 M&E Second phase 10 days Sun 8/9/15 Tue 8/18/15

1893 Electrical System 10 days Sun 8/9/15 Tue 8/18/15

1894 Installation electrical panel 2 days Sun 8/9/15 Mon 8/10/15

1895 Installation lighting 4 days Tue 8/11/15 Fri 8/14/15

1896 Installation wiring device 2 days Sat 8/15/15 Sun 8/16/15

1897 Installation ELV equipment 2 days Mon 8/17/15 Tue 8/18/15

1898 A/C and Ventilation System 10 days Sun 8/9/15 Tue 8/18/15

1899 Installation A/C unit 6 days Sun 8/9/15 Fri 8/14/15

1900 Installatin exhaust fan 4 days Sat 8/15/15 Tue 8/18/15

1901 Plumbing system 8 days Sun 8/9/15 Sun 8/16/15

1902 Installation sanitary ware 8 days Sun 8/9/15 Sun 8/16/15

1903 HS unit 0019 Second phase 10 days Sun 8/9/15 Tue 8/18/15

1904 M&E Second phase 10 days Sun 8/9/15 Tue 8/18/15

1905 Electrical System 10 days Sun 8/9/15 Tue 8/18/15

2/4 2/6

2/28 3/4

3/5 3/8

3/9 3/15

2/4 3/11

2/4 2/8

3/2 3/11

3/16 4/30

3/16 4/30

3/16 4/29

3/16 3/18

4/9 4/24

4/25 4/29

3/16 4/30

3/16 3/18

4/9 4/19

4/20 4/23

4/24 4/30

3/16 4/26

3/16 3/20

4/11 4/26

3/16 4/30

3/16 4/30

3/16 4/29

3/16 3/18

4/9 4/24

4/25 4/29

3/16 4/30

3/16 3/18

4/9 4/19

4/20 4/23

4/24 4/30

3/16 4/26

3/16 3/20

4/11 4/26

3/16 4/30

3/16 4/30

3/16 4/29

3/16 3/18

4/9 4/24

4/25 4/29

3/16 4/30

3/16 3/18

4/9 4/19

4/20 4/23

4/24 4/30

3/16 4/26

3/16 3/20

4/11 4/26

7/5 7/14

7/29 milestone ID (Hotel Suit bloc

7/30 8/18

7/30 8/8

7/30 8/8

7/30 8/8

7/30 7/31

8/1 8/4

8/5 8/6

8/7 8/8

7/30 8/8

7/30 8/4

8/5 8/8

7/30 8/6

7/30 8/6

7/30 8/8

7/30 8/8

7/30 8/8

7/30 7/31

8/1 8/4

8/5 8/6

8/7 8/8

7/30 8/8

7/30 8/4

8/5 8/8

7/30 8/6

7/30 8/6

7/30 8/8

7/30 8/8

7/30 8/8

7/30 7/31

8/1 8/4

8/5 8/6

8/7 8/8

7/30 8/8

7/30 8/4

8/5 8/8

7/30 8/6

7/30 8/6

8/9 8/18

8/9 8/18

8/9 8/18

8/9 8/10

8/11 8/14

8/15 8/16

8/17 8/18

8/9 8/18

8/9 8/14

8/15 8/18

8/9 8/16

8/9 8/16

8/9 8/18

8/9 8/18

8/9 8/18

8/9 8/10

8/11 8/14

8/15 8/16

8/17 8/18

8/9 8/18

8/9 8/14

8/15 8/18

8/9 8/16

8/9 8/16

8/9 8/18

8/9 8/18

8/9 8/18

8/9 8/10

8/11 8/14

8/15 8/16

8/17 8/18

8/9 8/18

8/9 8/14

8/15 8/18

8/9 8/16

8/9 8/16

8/9 8/18

8/9 8/18

8/9 8/18

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep OctJuly August Septemb October Novembe Decembe January February March April May June July August Septemb October

Task

Split

Progress

Milestone

Summary

Project Summary

External Tasks

External Milestone

Deadline

MASTER SCHEDULE ALILA RESORT - KOH RUSSEY

Prepared by: Soly

Project: KRU-MEP ScheduleDate: Fri 10/24/14

ID ALILA RESORT-KOH RUSSEY M&E SCHEDULE Duration Start Finish

1906 Installation electrical panel 2 days Sun 8/9/15 Mon 8/10/15

1907 Installation lighting 4 days Tue 8/11/15 Fri 8/14/15

1908 Installation wiring device 2 days Sat 8/15/15 Sun 8/16/15

1909 Installation ELV equipment 2 days Mon 8/17/15 Tue 8/18/15

1910 A/C and Ventilation System 10 days Sun 8/9/15 Tue 8/18/15

1911 Installation A/C unit 6 days Sun 8/9/15 Fri 8/14/15

1912 Installatin exhaust fan 4 days Sat 8/15/15 Tue 8/18/15

1913 Plumbing system 8 days Sun 8/9/15 Sun 8/16/15

1914 Installation sanitary ware 8 days Sun 8/9/15 Sun 8/16/15

1915 Final Inspection CEMP 0 days Tue 8/18/15 Tue 8/18/15

1916 Guest Jetty 144 days Mon 12/1/14 Wed 4/29/15

1917 A. Drawing preparation 15 days Mon 12/1/14Mon 12/15/14

1918 B. Material procurement and transportation 65 days Mon 12/1/14 Tue 2/3/15

1919 C. Piling work 60 days Tue 12/16/14 Fri 2/13/15

1920 D. Structural Works 40 days Sat 2/14/15 Wed 3/25/15

1921 E. Masonry Works 25 days Thu 3/26/15 Sat 4/25/15

1922 milestone PHV (Guest Jetty) 0 days Sun 3/29/15 Sun 3/29/15

1923 M&E first phase 11 days Mon 3/30/15 Thu 4/9/15

1924 Electrical System 11 days Mon 3/30/15 Thu 4/9/15

1925 Pipe sleeve installation 3 days Mon 3/30/15 Wed 4/1/15

1926 Installation conduit above the ceiling & embedded in wall 5 days Thu 4/2/15 Mon 4/6/15

1927 Pulling the Cable for LV and ELV 3 days Tue 4/7/15 Thu 4/9/15

1928 J. Final Inspection/Punch Listing and Hand Over 3 days Sun 4/26/15 Tue 4/28/15

1929 M&E Second phase 1 day Wed 4/29/15 Wed 4/29/15

1930 Electrical System 1 day Wed 4/29/15 Wed 4/29/15

1931 Installation electrical panel 1 day Wed 4/29/15 Wed 4/29/15

1932 Installation lighting 1 day Wed 4/29/15 Wed 4/29/15

1933 Installation wiring device 1 day Wed 4/29/15 Wed 4/29/15

1934 Installation ELV equipment 1 day Wed 4/29/15 Wed 4/29/15

1935 Final Inspection CEMP 0 days Wed 4/29/15 Wed 4/29/15

1936 Water Management 158 days Fri 12/19/14 Sun 5/31/15

1937 A. Drawing preparation 15 days Fri 12/19/14 Fri 1/2/15

1938 B. Material procurement and transportation 60 days Fri 12/26/14 Mon 2/23/15

1939 C. Clearing and grubbing / Cut and filling work 15 days Sat 1/3/15 Sat 1/17/15

1940 D. Excavation/Lean concrete /Foundation work 30 days Tue 2/3/15 Wed 3/4/15

1941 E. Column Works 20 days Thu 3/5/15 Tue 3/24/15

1942 F. Beam/Slab and Cantilever 20 days Wed 3/25/15 Sun 4/19/15

1943 G . Masonry Works 30 days Mon 4/20/15 Tue 5/19/15

1944 H. Water Proofing Works 20 days Sun 3/8/15 Fri 3/27/15

1945 milestone PHV (Water Management) 0 days Tue 3/3/15 Tue 3/3/15

1946 M&E first phase 11 days Tue 3/3/15 Fri 3/13/15

1947 Electrical System 11 days Tue 3/3/15 Fri 3/13/15

1948 Pipe sleeve installation 2 days Tue 3/3/15 Wed 3/4/15

1949 Installation conduit above the ceiling & embedded in wall 5 days Thu 3/5/15 Mon 3/9/15

1950 Pulling the Cable for LV and ELV 4 days Tue 3/10/15 Fri 3/13/15

1951 Plumbing System 6 days Tue 3/3/15 Sun 3/8/15

1952 Prepairation pipe sleeve for domestic water system 2 days Tue 3/3/15 Wed 3/4/15

1953 Prepairation pipe sleeve for waste water system 2 days Thu 3/5/15 Fri 3/6/15

1954 Preparation for storm water pipe system 2 days Sat 3/7/15 Sun 3/8/15

1955 J. Final Inspection/Punch Listing and Hand Over PHV 7 days Wed 5/20/15 Tue 5/26/15

1956 M&E Second phase 5 days Wed 5/27/15 Sun 5/31/15

1957 Electrical System 4 days Wed 5/27/15 Sat 5/30/15

1958 Installation electrical panel box 1 day Wed 5/27/15 Wed 5/27/15

1959 Installation lighting 1 day Thu 5/28/15 Thu 5/28/15

1960 Installation wiring device 1 day Fri 5/29/15 Fri 5/29/15

1961 Installation ELV equipment 1 day Sat 5/30/15 Sat 5/30/15

1962 Plumbing System 5 days Wed 5/27/15 Sun 5/31/15

1963 Pump installation 5 days Wed 5/27/15 Sun 5/31/15

1964 Final Inspection CEMP 0 days Sun 5/31/15 Sun 5/31/15

1965 Power station 129 days Thu 1/15/15 Fri 5/29/15

1966 A. Drawing preparation 15 days Thu 1/15/15 Thu 1/29/15

1967 B. Material procurement and transportation 45 days Fri 1/30/15 Sun 3/15/15

1968 C. Clearing and grubbing / Cut and filling work 15 days Fri 1/30/15 Fri 2/13/15

1969 D. Excavation/Lean Concrete,Ground Slab/Stump Column 20 days Sat 2/14/15 Thu 3/5/15

1970 E. Ground Beam and Slab 20 days Fri 3/6/15 Wed 3/25/15

1971 F. Column 10 days Thu 3/26/15 Sat 4/4/15

1972 G. Roof Beam and Slab 15 days Sun 4/5/15 Sat 4/25/15

1973 H. Masonry Works 15 days Sun 4/26/15 Sun 5/10/15

1974 I. Water Proofing Works 15 days Wed 4/29/15 Wed 5/13/15

1975 milestone PHV Power Station 0 days Sun 3/1/15 Sun 3/1/15

1976 M&E first phase 8 days Sun 3/1/15 Sun 3/8/15

1977 Electrical System 8 days Sun 3/1/15 Sun 3/8/15

1978 Pipe sleeve installation 2 days Sun 3/1/15 Mon 3/2/15

1979 Installation conduit above the ceiling & embedded in wall 4 days Tue 3/3/15 Fri 3/6/15

1980 Pulling the Cable for LV 2 days Sat 3/7/15 Sun 3/8/15

1981 J. Final Inspection/Punch Listing and Hand Over PHV 7 days Thu 5/14/15 Wed 5/20/15

1982 M&E Second phase 9 days Thu 5/21/15 Fri 5/29/15

1983 Electrical System 9 days Thu 5/21/15 Fri 5/29/15

1984 Installation electrical panel box 5 days Thu 5/21/15 Mon 5/25/15

1985 Installation lighting 3 days Tue 5/26/15 Thu 5/28/15

1986 Installation wiring device 1 day Fri 5/29/15 Fri 5/29/15

1987 Final Inspection CEMP 0 days Fri 5/29/15 Fri 5/29/15

1988 Inspection, Training and Handover 13 days Wed 8/19/15 Mon 8/31/15

1989 Testing for building part 10 days Wed 8/19/15 Fri 8/28/15

1990 Training 3 days Sat 8/29/15 Mon 8/31/15

1991 Handover 0 days Mon 8/31/15 Mon 8/31/15

8/9 8/10

8/11 8/14

8/15 8/16

8/17 8/18

8/9 8/18

8/9 8/14

8/15 8/18

8/9 8/16

8/9 8/16

8/18 Final Inspection CEMP

12/1 4/29

12/1 12/15

12/1 2/3

12/16 2/13

2/14 3/25

3/26 4/25

3/29 milestone PHV (Guest Jetty)

3/30 4/9

3/30 4/9

3/30 4/1

4/2 4/6

4/7 4/9

4/26 4/28

4/29 4/29

4/29 4/29

4/29 4/29

4/29 4/29

4/29 4/29

4/29 4/29

4/29 Final Inspection CEMP

12/19 5/31

12/19 1/2

12/26 2/23

1/3 1/17

2/3 3/4

3/5 3/24

3/25 4/19

4/20 5/19

3/8 3/27

3/3 milestone PHV (Water Management)

3/3 3/13

3/3 3/13

3/3 3/4

3/5 3/9

3/10 3/13

3/3 3/8

3/3 3/4

3/5 3/6

3/7 3/8

5/20 5/26

5/27 5/31

5/27 5/30

5/27 5/27

5/28 5/28

5/29 5/29

5/30 5/30

5/27 5/31

5/27 5/31

5/31 Final Inspection CEMP

1/15 5/29

1/15 1/29

1/30 3/15

1/30 2/13

2/14 3/5

3/6 3/25

3/26 4/4

4/5 4/25

4/26 5/10

4/29 5/13

3/1 milestone PHV Power Station

3/1 3/8

3/1 3/8

3/1 3/2

3/3 3/6

3/7 3/8

5/14 5/20

5/21 5/29

5/21 5/29

5/21 5/25

5/26 5/28

5/29 5/29

5/29 Final Inspection CEMP

8/19 8/31

8/19 8/28

8/29 8/31

8/31 Handover

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep OctJuly August Septemb October Novembe Decembe January February March April May June July August Septemb October

Task

Split

Progress

Milestone

Summary

Project Summary

External Tasks

External Milestone

Deadline

MASTER SCHEDULE ALILA RESORT - KOH RUSSEY

Prepared by: Soly

Project: KRU-MEP ScheduleDate: Fri 10/24/14