CE572/Spring 04/JAR 2
Definition of Prestressing
It consists of preloading the structurebefore application of design loads in sucha way so as to improve its general
performance.
8/13/2019 Introduction to Pre Stressing 1
3/21
CE572/Spring 04/JAR 3
Objectives of Prestressing
Control or eliminate tensile stresses in theconcrete (cracking) at least up to serviceload levels.
Control or eliminate deflection at somespecific load level.
Allow the use of high strength steel andconcrete.
8/13/2019 Introduction to Pre Stressing 1
4/21
CE572/Spring 04/JAR 4
Net Result of Prestressing
Improved performance of concrete inordinary design situations (compared to
R/C).
Extended range of application of structuralconcrete (longer spans).
Innovative forms of structures.
8/13/2019 Introduction to Pre Stressing 1
5/21
CE572/Spring 04/JAR 5
Extended Range of Application
8/13/2019 Introduction to Pre Stressing 1
6/21
CE572/Spring 04/JAR 6
Examples of Structures
8/13/2019 Introduction to Pre Stressing 1
7/21
CE572/Spring 04/JAR 7
Partial Prestressing
Intermediate state, in which tension andusually flexure cracking is allowed at fullservice load level. Some advantages are:
- Prevents excessive camber at moretypical loads less than full serviceloads.
- Reduced prestressing force (less $$$)compared to full prestressing (zero
tensile stresses at full service load).
8/13/2019 Introduction to Pre Stressing 1
8/21
CE572/Spring 04/JAR 8
Applications of Prestressed
Concrete in the US and Canada
Figure 1About 200,000 tons of prestressing steel used in
US/Canada each year (~ of the total world
consumption)
8/13/2019 Introduction to Pre Stressing 1
9/21
CE572/Spring 04/JAR 9
8/13/2019 Introduction to Pre Stressing 1
10/21
CE572/Spring 04/JAR 10
Prestressing Methods
Pretensioning: suited for mass production.
*Video (PCI)
8/13/2019 Introduction to Pre Stressing 1
11/21
CE572/Spring 04/JAR 11
Prestressing Methods
Post-Tensioning: jacking against the memberand the eccentricity is easily varied along thelength of the member.
8/13/2019 Introduction to Pre Stressing 1
12/21
CE572/Spring 04/JAR 12
Post-Tensioning Sequence
Place reinforcing cage and post-tensioning ductsinside the formwork.
After casting and curing of the concrete, the
tendons are tensioned and anchored withspecial jacks that react against the member.
Unless unbonded tendons are being used, theduct is then grouted to complete the post-tensioning operation.
Slides (PTI)-------
8/13/2019 Introduction to Pre Stressing 1
13/21
CE572/Spring 04/JAR 13
Profiles of Post-Tensioned Tendons
8/13/2019 Introduction to Pre Stressing 1
14/21
CE572/Spring 04/JAR 14
Geometry of Parabolic Profiles
8/13/2019 Introduction to Pre Stressing 1
15/21
CE572/Spring 04/JAR 15
Location and Eccentricity of
Tendon in Duct After Stressing
8/13/2019 Introduction to Pre Stressing 1
16/21
CE572/Spring 04/JAR 16
Materials: Types of Prestressing
Steel
8/13/2019 Introduction to Pre Stressing 1
17/21
CE572/Spring 04/JAR 17
Production of Seven Wire Strand
Low relaxation versus stress-relieved
8/13/2019 Introduction to Pre Stressing 1
18/21
8/13/2019 Introduction to Pre Stressing 1
19/21
CE572/Spring 04/JAR 19
8/13/2019 Introduction to Pre Stressing 1
20/21
CE572/Spring 04/JAR 20
Concrete
8/13/2019 Introduction to Pre Stressing 1
21/21
CE572/Spring 04/JAR 21
Hognestad Parabola
fc( ) fcmax 2
o
o
2
Calculate o strain corresponding to peak stress, fcmax)using the secant Modulus of Elasticity at 0.5fcmax. Thus, fit
The Hognestad expression through a point corresponding to0.5fcmax and 0.5fcmax/Ec.
Ec 57000
2fcmax( )
1000