7/31/2019 Industrial Training 2012
1/28
Presented by:Amar Karam Chandani(091405)Ankit Shrivastava(091407)Himanshu Jha(091411)Aman Chaturvedi(091440)
7/31/2019 Industrial Training 2012
2/28
Cost estimation is a specialised subject and aprofession in its own right. The design Engineer,however, needs to be able to make quick, rough, costestimates to decide between alternative designs and
for project evaluation. Chemical plants are built tomake a profit, and an estimate of the investmentrequired and the cost of production are needed beforethe profitability of a project can be assessed.
7/31/2019 Industrial Training 2012
3/28
ESTIMATION AT IOCL
Preliminary cost estimate at IOCL is done manually using excel,where all the data is fed into the excel sheet and a X-Y scatterplot is generated then all the points which are distorting thecurve heavily are neglected as they will decrease the accuracy ofthe estimation. After generation of the plot a equation isobtained on excel and the preliminary new cost is estimatedusing the obtained equation. To this cost various factors areadded and the final cost is obtained.
Problems with approach are following: -Arranging the massive amount of data present is a tedious job.Huge input of time is required.Wastage of valuable time is there and if the cost is requiredimmediately it will mean a lot of work.
7/31/2019 Industrial Training 2012
4/28
Working steps of the program are following: -Takes input data from the user like size of heat exchanger, tagnumber etc.Then the program connects to the database and searches for allavailable data points.After obtaining the required data like base cost, base area.Then using the six tenth formulae it does capacity correctionand brings all the data into the required area.Then upgrades it to current time by using CEPCI index.The obtained cost is then multiplied with factors to take intoaccount MOC.
7/31/2019 Industrial Training 2012
5/28
7/31/2019 Industrial Training 2012
6/28
7/31/2019 Industrial Training 2012
7/28
Bharat Oman Refineries has set up 6 million tonne per annumcapacity grass root refinery at Bina, Madhya Pradesh. It is dividedinto 3 major facilities as given below:
Crude Import and Handling facilityCrude transfer and receiving facility through crosscountrypipelines and terminals
Refining and related facilities.
A 935 km pipeline from dispatch terminal of COT Vadinar, Gujaratbrings crude to the Receipt Terminal at Bina.
7/31/2019 Industrial Training 2012
8/28
1.Primary Processing facilities:Crude Distillation Unit(CDU)
Vacuum Distillation Unit(VDU)
2. Secondary Processing Facilities.Motor Spirit Block(MSB)
Hydrocracker Unit(HCU)
Delayed Coker Unit(DCU)
3. Treating Units:
LPG Treating unit
ATF Merox
Diesel Hydrotreater
7/31/2019 Industrial Training 2012
9/28
4.Sulphur Recovery Block(SRB)5.Hydrogen Generation Unit(HGU)
6.Captive Power Plant(CPP)
7.Utilities systems:Raw Water intake system
Raw water treatment plant
Cooling Tower and Cooling water treatment plantReverse Osmosis based Demineralization (RODM)
Nitrogen plant and Effluent Water TreatmentPlant(ETP)
7/31/2019 Industrial Training 2012
10/28
Fuel GasLiquefied Petroleum Gas(LPG)
Naphtha
Euro III Motor Spirit (MS)
Euro IV Motor Spirit (MS)
Aviation Turbine Fuel(ATF)
Euro III HSD
Euro IV HSDSulphur
Pet Coke
7/31/2019 Industrial Training 2012
11/28
The Delayed Coker Unit (DCU) is designed to process1,360,000 MT of Vacuum Residue based on Arab MixCrude
This Unit is based on CB&I Lummus technology.
Delayed Coking Process is a thermal cracking processfor upgrading heavy petroleum residues into lightergaseous & liquid products and solid Coke .
The thermal cracking reaction starts in heater coils and
provided residence time or Delayed for an extendedperiod in the Coke Drum for Polymerisation andCracking reactions to take place
7/31/2019 Industrial Training 2012
12/28
For heating feed from 170oC to 200oC,we require a Shell & Tube Heat
Exchanger of overall heat transfer areaof 1.77 m2
7/31/2019 Industrial Training 2012
13/28
Coker gas
LPG
Coker Naphtha (C5-140C)
Light Coker Gas Oil(140C-370C)
Heavy Coker Gas Oil(370C plus)
Coker Fuel Oil
Pet Coke
7/31/2019 Industrial Training 2012
14/28
DELAYED COKER
UNIT (1.36
MMTPA)
Vacuum
Residue fromCDU/VDU or
Storage Tanks
Coker Gas
LPG (CDU)
Coker Naphtha
(HCU/DHT)
Light Coker Gas Oil
(HCU/DHT)
Heavy Coker Gas Oil
(HCU/DHT)
Pet Coke to CPP
7/31/2019 Industrial Training 2012
15/28
7/31/2019 Industrial Training 2012
16/28
7/31/2019 Industrial Training 2012
17/28
DCU HEATER(14-FF-00-101 A/B) CONFIGURATIONBalanced Draft, Twin Cell, Cabin Type,Horizontal Tubes Double Fired.
Heat Absorption :- 17.2 MMKcal/HrNo of Tubes in Radiation Zone:- Total-64 (32 /Cell)
No of Tubes in Convection Zone:-56
No of Soot Blowers:-16/heater
No of Burners:-32/heater
7/31/2019 Industrial Training 2012
18/28
7/31/2019 Industrial Training 2012
19/28
The following measurements are to be made fordoing the energy balance in oil fired reheatingfurnaces (e.g. Heating Furnace)
i) Weight of stock / Number of billets heated
ii) Temperature of furnace walls, roof etc
iii) Flue gas temperature
iv) Flue gas analysis
v) Fuel Oil consumption
7/31/2019 Industrial Training 2012
20/28
USING APPROXIMATE METHOD:1.) WITH AIR PREHEATER: 89.55%
2.) WITHOUT AIR PREHEATER: 82.05%
B.)USING INDIRECT METHOD:
1.) SENSIBLE HEAT LOSS DUE TO FLUE GAS: 6.45%
2.)LOSSES DUE TO SKIN TEMPERATURE AND RADIATION: 3.01%OVERALL EFFICIENCY OF THE FURNACE: 90.5251%
7/31/2019 Industrial Training 2012
21/28
KCFL began its operation in 1987 at Nimrani near Indore, WestMadhya Pradesh and has earned cash profits each and everyyear, since its inception, even though SSP Industry has gonethrough tumultuous times. Today KCFL has earned the
distinction of being the largest manufacturer ofSSP in IndiaSSP manufactured and sold by Khaitan Chemicals & FertilizersLimited under the brand name "Khaitan Khad is amongst themost sought after brands in Western Madhya Pradesh andsurrounding areas. Being a straight fertilizer with easy
application, low cost per bag and unique 12% sulphur contentmakes it very popular with the farmers. It is extensively used incrops like Oil Seeds, Groundnut, Potato etc. SSP is alsomanufactured in granulated form called GSSP
7/31/2019 Industrial Training 2012
22/28
The Wet Gas compressor is a steam turbinedriven, 2-stage centrifugal compressor withvertically split casing supplied by M/s BHEL,Hyderabad.
The wet gas compressor boosts the pressure ofCoker fractionator column overhead receivergas from 1.13 Kg/cm2 and is delivered to the
absorber at a pressure of 15.92 Kg/cm2
. Thefunction of the Wet Gas Compressor is tocompress Coker Fractionator overhead gases toa higher pressure for enhancing C3, C4 recovery.
7/31/2019 Industrial Training 2012
23/28
The major components of WGC are:1. Casing
2. Diaphragm
3. Rotor4. Balancing Drum
5. Bearings
6. Internal Seal
7/31/2019 Industrial Training 2012
24/28
7/31/2019 Industrial Training 2012
25/28
7/31/2019 Industrial Training 2012
26/28
n/(n-1) = EFp. k/(k-1)0.695 x 1.4 /(1.4-1) = 2.432
7/31/2019 Industrial Training 2012
27/28
With number of impeller = 8 and 2 dimShrouded impeller, uncorrected efficiency =0.72
Corrected efficiency become
EFp = 0.72 x Co = 0.72 x 0.915 = 0.66 or 66% .
7/31/2019 Industrial Training 2012
28/28
Top Related