PALM-3000
HOWFS - 7/24/09
C. Baranec
PALM-3000 Current Status Summary
2
• Telescope simulator assembled
• HOWFS assembled and tested
• Alignment plan (CIN 636) is halfway finished
• Alignment feedback GUI developed and tested
PALM-3000 Telescope Simulator
3
• On-axis green laser
• Red laser fiber source
• On x-y-z translation stage
• F/# ~15.7 (needs to be confirmed)
PALM-3000 HOWFS Mechanical
4
Pieces needed for WFS fabricated and assembled.
Alignment feedback GUI developed and tested.
PALM-3000 Alignment feedback GUI
5
PALM-3000 s16
6
PALM-3000 s32
7
PALM-3000 s64
8
PALM-3000 Demo…
• Switch to remote desktop
9
PALM-3000 Analysis/Discussion
• Pupil ellipticity at 2.0% (1.70% desired for AOI of 10.5)– There are degrees of freedom to change the ellipticity
• Pupil size at 9.645 mm (9.600 target)• We need to establish exact pupil sizes in the
different modes before specifying collimator• Different focus measurement in different modes
– Many possible contributors, will require investigation• CCD50 focus positions not yet established
– Will require use of Pixelink camera
10
PALM-3000 Flexure analysis
• Flexure – ATS150 roll compliance is excellent. Still awaiting pitch compliance. Expect 0.1”/hour. Khanh’s description of flexure analysis however is confusing. What priority should we place on having him document this properly?
11
PALM-3000 Outstanding tasks - summary
• CCD50 readout modes – awaiting SciMeasure.• Test the camera modes – RN/DC (JR, ? days)• Finish alignment plan - (CB, 1 day)• Further alignment investigation – (CB, 1 day)• Amendments to alignment procedure – (CB, 1 day)• Internal flexure testing – (CB, 1 day)• Spec new optics – (CB, ½ day)• Alignment with the testbed – (CB, 2 days)• Plan for testing and incorporating new optics – (CB, 1
day)• Mechanical…
12
PALM-3000 Mechanical Engineering Update
13
Task # Priority Description Status1 CCD50 cover In shop2 HOWFS cover Conceptual, in solidworks3 Field stop with ACam mirror Fab. drawings4 ACam optics mounts Conceptual, in solidworks 5 ACam camera mount Conceptual, in solidworks
Khahn expects to be finished working on the HOWFS/Acam by end of next week.
PALM-3000 Schedule
• Mechanical finished – next few weeks
• SciMeasure modes - ?
• Integration with testbed (no DM) – 3-4 weeks
• Order testbed collimator/cylinder – after F/# established
• Integration with DM in testbed – 6-10 weeks
• Integration on PALM-AO bench – next year
14
PALM-3000 Management Summary
Total labor:• CB – ~8 days• JR – CCD testing modes, integration• ME – 1 week from Khanh Bui• AB – integration
Equipment costs:• SciMeasure camera modes - ?• New optics (col, cyl) ~ $1000