Construction 1Drum Plants
HMA Production
Senior/GraduateHMA Course
Construction 2Drum Plants
What you will learn….
• How gradation is controlled in a drum-mixer• How asphalt is controlled in a drum-mixer• Different styles of drum-mixers• Using RAP with a drum plant
Construction 3Drum Plants
Drum-Mix Production
Hot Mix Asphalt production characterized by:
• Gradation Control at Cold Feed• Measure aggregate flow with belt scale• Meter asphalt binder to aggregate flow• Produce HMA continuously
Construction 4Drum Plants
Construction 5Drum Plants
Cold Feed Proportioning
Composite gradation is controlled at cold feed by proportioning material from individual bins.
Gradation and quality of the individual materials is controlled at the quarry.
Construction 6Drum Plants
Construction 7Drum Plants
Cold Feed Proportioning
Variation in material flow from individual bins:
• Based on variable speed motor on belt• Adjustable manual gates help control
minimum and maximum flow
Construction 8Drum Plants
Cold Feed Proportioning
• Accomplished by calibrating the feeders• Material output is charted against belt speed
in calibration charts• Different charts are created for different gate
settings on the same feeder
Construction 9Drum Plants
Construction 10Drum Plants
Cold Feed Gradation Control
Many styles of feeder controls found in field.
All can perform satisfactory proportioning.
Construction 11Drum Plants
Construction 12Drum Plants
Asphalt Binder Proportioning
Asphalt binder must proportion to aggregate flow.
First step in asphalt binder proportioning is measuring aggregate flow.
Belt scale is used.
Construction 13Drum Plants
Construction 14Drum Plants
How a Belt Scale Works
• Weigh bridge measures weight of aggregate.• Speed sensor measures speed of belt.• “Integrator / Totalizer” calculates aggregate
flow in ton (tonnes) per hour• “Integrator / Totalizer” reports flow rate to
plant control system
Construction 15Drum Plants
Construction 16Drum Plants
Construction 17Drum Plants
Asphalt Binder Proportioning
Asphalt binder must proportion to aggregate flow.
Second step is regulating asphalt binder flow.
Asphalt binder pumping / metering unit is used.
Construction 18Drum Plants
Construction 19Drum Plants
Construction 20Drum Plants
How the Asphalt Binder Proportioning System Works
• Controls system reads wet aggregate flow from belt scale.• Controls accepts moisture content entered by operator to
establish dry flow rate of aggregate• Control system accepts target asphalt content entered by
operator.• Control system drives pumping/metering unit flow control
device.• Control system adjusts asphalt binder flow control system
based on signal received back from meter
Construction 21Drum Plants
Construction 22Drum Plants
Plant Automation
Many types of systems and levels of complexity found in the field.
Construction 23Drum Plants
Construction 24Drum Plants
QUESTIONS ?