1FAC, 10/12/06D. Schultz
e-Beams Systems Update
Linac Injector Undulator Production MMF commissioning ARR
David Schultz
2FAC, 10/12/06D. Schultz
LCLS Diagnostics and Controls Physicist
Joe Frisch Joining Paul Emma on the LCLS Physics and Commissioning Team Brings extensive experience with diagnostics, RFBPMs, bunch length monitors, timing systems, laser systems, …
3FAC, 10/12/06D. Schultz
2006 Installation
BC1
BLM
LXL1
Ins/SAB
Wall
Laser
stopper
Sector 20
Sector 21
4FAC, 10/12/06D. Schultz
Linac Status
Downtime installation work is underwayRemoval of accelerator structures is done.Next few weeks - installing
Wall region components (this week)L1 and LX accelerator regions (this week)BC1 supports (next week)
Insertion region installation 11/6 (week 12)Table due 10/16
BLM region installation 11/6 (week 12)
5FAC, 10/12/06D. Schultz
Linac Accelerator Section Removal
Before
After
Making room for the Insertion, L-1 and L-X regions
6FAC, 10/12/06D. Schultz
The X-band accelerator section
Klystron, modulator being power tested prior to installation.
7FAC, 10/12/06D. Schultz
Inj/Linac quad magnets ready for installation
8FAC, 10/12/06D. Schultz
Diagnostic devices ready to install.
Wire scanners and profile monitors
9FAC, 10/12/06D. Schultz
Linac Downtime IssuesBPM feed-through welding, many leak.
Leak at ceramic, need UHV QC before weldingLate components:
BC1 Instrument packageBLM 11 (BLM 12 will be in)Toroids (in several locations)Vacuum chambers in insertion region.
Spool pieces are being fabricated to be installed temporarily.
Time will be needed to install these components as they become available.
10FAC, 10/12/06D. Schultz
LCLS Insertion region
Critical vacuum chambers which may be late.
Linac integrity needed for ESA program in Jan.
Linac beam
LCLS Injection
11FAC, 10/12/06D. Schultz
Injector Installation Status
Injector installation has taken second priority to Linac installation.
Injector vault:Floor and cable plant installed
Injector beamline:Accelerator structures, L0a ready, L0b to final bakeRF waveguide needs to go through bakeGun is in hot test, RF on 10/5
2nd gun is in brazingthen final cold-test, final braze.
Support stands are in the vault ready except for the GTL table
12FAC, 10/12/06D. Schultz
The LCLS Drive Laser
Drive Laser installed, operatingLSS installed in laser roomNow working on temporal shaping,
Streak cameraCross correlator
13FAC, 10/12/06D. Schultz
The Injector Vault
Cable plant, vault ready for beamline components.
14FAC, 10/12/06D. Schultz
L0A on the MMF CMM
15FAC, 10/12/06D. Schultz
The LCLS photocathode electron gun
16FAC, 10/12/06D. Schultz
Injector Installation Issues
Water system needs to be installed, installation reqs. out,
BPM feed-through welding, toroids
Late: The GTL stand released to purchasing. Estimate it will be here 11/16 for installation 11/20. Laser table installation begins 11/27 The Gun will be ready by then, needed later. GTL is late, now moving to machining. (next slide)
Working to advance the schedule. What is competing? What can be sent out? Critical path.
17FAC, 10/12/06D. Schultz
Gun-to-Linac area
Gun
Laser table
Spectrometer
L0a
GTL
uv
18FAC, 10/12/06D. Schultz
Controls
Magnet power supplies, vacuum controls, installed in racks and tested. Racks now being installed.Ethernet backbone to the Computer Center installed and connected. Wire scanners controls tested.Linac cable plant phase 2 installation is underway.Coordinating hardware installation schedule now with Controls checkout.
19FAC, 10/12/06D. Schultz
Magnets power racks assembled, tested,prior to installation
20FAC, 10/12/06D. Schultz
Vacuum system racks assembled, tested, prior to installation
21FAC, 10/12/06D. Schultz
Controls - PPS
Personnel Protection System is in the review process with the SLAC RSC.
PLC design conditionally approved! The Committee wants to see the certification procedure.
Beam loss and shielding design approved. Beam Containment System, LCLS FDR 10/6,
RSC review 10/12.
22FAC, 10/12/06D. Schultz
Undulator Systems Design
Quadrupole Order placed, vendor designs, 1st article 2/07Fixed Support/Mover Final Design Review - September 13/14
Go ahead given for production.Beam Finder Wire Final Design Review - September 20, 2006
Go ahead given for production of BFW, except wire card.RF Beam Position Monitor Final Design Review - October 4
Testing program has been interrupted by RF gun failure.Vacuum Chamber Final Design Review - September 27/28
42" chamber welded, machined, to be coated.2 other prototypes in hand for QC, permeability measurements.Plan D design effort initiated at SLAC.
23FAC, 10/12/06D. Schultz
Undulator vacuum chamber 4-Weld Prototype
Issues: flatness, permeability, vacuum, Al coating, surface finish
Vacuum Chamber Design Review - September 27/28
24FAC, 10/12/06D. Schultz
MMF Status
Measurement benches installed and commissioned.CMM installed and in use.Quad measurement station operational.Eight finished undulators are here at SLAC.Six to eight more to be shipped to SLAC by October 20th
Issues:Air cond. mixing valve (new) failed. Now repaired.New breaker panel wiring needed to be worked on.Compressed air system does not meet spec.
Looking for a work-around.Need to move to production fine-tuning.
25FAC, 10/12/06D. Schultz
Six undulator magnets in crates awaiting tuning at the MMF. Six to eight more to arrive at SLAC by October 20th.
Undulator magnets at the MMF
26FAC, 10/12/06D. Schultz
Injector Accelerator Readiness Review
Safety Assessment DocumentDraft LCLS SAD for Injector Commissioning under internal review.
Operating procedures are being written with AD Ops.Commissioning
LCLS Commissioning Workshop October 9-11 Includes a Commissioning Readiness Review.
Accelerator Readiness Review (ARR)LCLS ARR for Injector Commissioning scheduled for October 31st.Committee members, speakers on board.
27FAC, 10/12/06D. Schultz
The downtime schedule is very tight. We got off to a good start. Not all parts are in hand. Injector installation will delay commissioning. Controls checkout (last) is at risk.
The Undulator vacuum chamber is still in the design/prototype stage.
On the critical path. Adding engineering resources from SLAC.
The MMF is late and needs attention.
Issues