Download - ESS Cryogenic Distribution System for the Elliptical Linac MBL/HBL - CDS requirements Preliminary Design Review Meeting, 20 May 2015, ESS, Lund, Sweden.

Transcript
Page 1: ESS Cryogenic Distribution System for the Elliptical Linac MBL/HBL - CDS requirements Preliminary Design Review Meeting, 20 May 2015, ESS, Lund, Sweden.

ESS Cryogenic Distribution Systemfor the Elliptical Linac

MBL/HBL - CDS requirements

Preliminary Design Review Meeting, 20 May 2015, ESS, Lund, Sweden

J. Polinski

Page 2: ESS Cryogenic Distribution System for the Elliptical Linac MBL/HBL - CDS requirements Preliminary Design Review Meeting, 20 May 2015, ESS, Lund, Sweden.

CDS-HBL-L4-010

The CDS for the elliptical linac (HBL and MBL) shall consist of a four-channeled vacuum-insulated cryogenic transfer line and cryogenic distribution line as well as four auxiliary process lines. The cryogenic distribution line shall include 30 valve boxes (21 for high beta cryomodules and 9 for medium beta cryomodules)

CTL

Aux. Lines

Valve Box

Page 3: ESS Cryogenic Distribution System for the Elliptical Linac MBL/HBL - CDS requirements Preliminary Design Review Meeting, 20 May 2015, ESS, Lund, Sweden.

CDS-HBL-L4-010

The CDS for the elliptical linac (HBL and MBL) shall consist of a four-channeled vacuum-insulated cryogenic transfer line and cryogenic distribution line as well as four auxiliary process. The cryogenic distribution line shall include 30 valve boxes (21 for high beta cryomodules and 9 for medium beta cryomodules)

CTL

Cold Box - ACCP

Page 4: ESS Cryogenic Distribution System for the Elliptical Linac MBL/HBL - CDS requirements Preliminary Design Review Meeting, 20 May 2015, ESS, Lund, Sweden.

CDS-HBL-L4-020

The CDS for the elliptical linac shall allow for warming up and cooling down a single cryomodule, while keeping the rest of the system at cryogenic temperatures.

1.Usage of the CV05 and the CV62 valve for providing the warm helium during warm-up phase of the single CM

2.Usage of the CV06 and the CV63 valve for by-passing the helium vapor/gas return during warm-up and cool-down phases of the single CM

Page 5: ESS Cryogenic Distribution System for the Elliptical Linac MBL/HBL - CDS requirements Preliminary Design Review Meeting, 20 May 2015, ESS, Lund, Sweden.

CDS-HBL-L4-030

The CDS valve box shall allow for transferring the required cooling power from the main headers to the cryomodule.

1. Requirement of the specific helium flow (up to 130 g/s) at the inlet to the CDS MC line from the ACCP side - ACCP-CDS-L4-070,

2. Limitation of the heat flux to the CDS MC process line by thermo-mechanical optimization of the pipe supports design and thermal insulation system design,

3. Specified helium mass flow from the CDL to the CM – 6.6 g/s for cooling down, 3.3 g/s for nominal operation

4. Requirement of the max. temperature in the BC Line as 5.2K – CDS-HBL-L4-050

Page 6: ESS Cryogenic Distribution System for the Elliptical Linac MBL/HBL - CDS requirements Preliminary Design Review Meeting, 20 May 2015, ESS, Lund, Sweden.

CDS-HBL-L4-040

The CDS valve box shall allow for separating a related cryomodule from the cryogenic distribution line.

1.Dismountable design of the jumper connection,2.Using of the cut-off valve at the lines connecting the CDS with the CM,3. Application of the vacuum barrier in the jumper connection.

Page 7: ESS Cryogenic Distribution System for the Elliptical Linac MBL/HBL - CDS requirements Preliminary Design Review Meeting, 20 May 2015, ESS, Lund, Sweden.

CDS-HBL-L4-050

Maximum temperature in the helium supply main and branch lines shall not exceed 5.2 K

1. Requirement of 4.5K temperature helium inlet to the He Supply line from the ACCP side ACCP-CDS-L4-060

2. Limitation of the heat flux to the CDS MC process line by the mechanical optimization of the pipe support system,

3. Thermo-mechanical optimization of the supports design and appropriate thermal insulation system design.

4. Requirement of the specific helium flow at the inlet to the CDS MC line from the ACCP side.

Page 8: ESS Cryogenic Distribution System for the Elliptical Linac MBL/HBL - CDS requirements Preliminary Design Review Meeting, 20 May 2015, ESS, Lund, Sweden.

CDS-HBL-L4-060, 070, 080, 090

Maximum allowable heat loads to the helium supply line including the main header and side pipes shall not be higher than 81.4 W

Maximum allowable heat loads to the Very Low Pressure (VLP) line including the main header and side pipes shall not be higher than 235.6 W

Maximum allowable heat loads to the Thermal Shield (TS) supply line including the main header and side pipes shall not be higher than 42.7 W

Maximum allowable heat loads to the Thermal Shield (TS) return line including main headers and side pipes shall not be higher than 2282 W

See separate presentation

Page 9: ESS Cryogenic Distribution System for the Elliptical Linac MBL/HBL - CDS requirements Preliminary Design Review Meeting, 20 May 2015, ESS, Lund, Sweden.

CDS-HBL-L4-100

Maximum allowable pressure drop in the Very Low Pressure (VLP) line including the main header and side pipes shall be not higher than 2.0 mbar at the total flow rate of 113 g/s at 28 mbar of operating pressure and 4.0 K of average operating temperature

Calculation of the required cross-section area (diameter) of the VLP line with respect of allowed flow pressure drop.

Page 10: ESS Cryogenic Distribution System for the Elliptical Linac MBL/HBL - CDS requirements Preliminary Design Review Meeting, 20 May 2015, ESS, Lund, Sweden.

CDS-HBL-L4-100

qm from SPK – 26 g/s

qm from each CM – 2.9 g/s

Tin– 4.0K

pout – 28 mabr

CDL VLP size – DN200CTL VLP size – DN250

0

0,2

0,4

0,6

0,8

1

1,2

1,4

1,6

1,8

0 50 100 150 200 250 300 350

CDS Length, m

VL

P f

low

pre

ssu

re d

rop

, m

bar CDL CTL

Page 11: ESS Cryogenic Distribution System for the Elliptical Linac MBL/HBL - CDS requirements Preliminary Design Review Meeting, 20 May 2015, ESS, Lund, Sweden.

CDS-HBL-L4-110, 120

The helium leak rate across the valve seat of each process valve shall not exceed 1*10E-4 mbar*l/sec at design pressure and room temperature against vacuum

The helium leak rate across the valve seat of each safety valve shall not exceed 1*10E-4 mbar*l/sec at operating pressure and room temperature against ambient pressure

He leak test certificate from the manufacturer

Page 12: ESS Cryogenic Distribution System for the Elliptical Linac MBL/HBL - CDS requirements Preliminary Design Review Meeting, 20 May 2015, ESS, Lund, Sweden.

CDS-HBL-L4-130

All materials and components of the CDL placed in the linac tunnel shall tolerate the radiation dose of 5*10E5 Gy.

1. Appropriate material selection,2. Teflon will be avoided,3. The EDPM rubber gasket will be used for the warm vacuum

flange connections

Page 13: ESS Cryogenic Distribution System for the Elliptical Linac MBL/HBL - CDS requirements Preliminary Design Review Meeting, 20 May 2015, ESS, Lund, Sweden.

CDS-HBL-L4-140

Under cryogenic operating conditions, the measured integral helium leak rate into the insulation vacuum shall not exceed 5*10E-7 mbar*l/sec

1.Appropriate welding technique,2.Non-destructive (X-ray, leak tightness) test after the weld realization

Page 14: ESS Cryogenic Distribution System for the Elliptical Linac MBL/HBL - CDS requirements Preliminary Design Review Meeting, 20 May 2015, ESS, Lund, Sweden.

CDS-HBL-L4-150

Insulation vacuum pressure at ambient temperature with active pumping shall be not higher than 5*10E-3 mbar after a pumping time not longer than 96 hours

1. The CDS line supports design with respect of the gas molecular flow resistance lowering,

2. Selection of the main vacuum pump appropriative pumping speed,

3. Using the temporary vacuum pumps, if necessary,4. Collaboration with ESS vacuum group in this task is agreed.