Download - Earned value management

Transcript
Page 1: Earned value management

EARNED VALUE MANAGEMENT

ASHIF A [email protected] No. - 9745350127

Page 2: Earned value management

INTRODUCTION

• Project management technique for measuring project progress in an objective manner.

• Combine measurements of scope, schedule, and cost in a single integrated system.

• Provides an early warning of performance problems.

• Improve

• the definition of project scope,

• prevent scope creep,

• communicate objective progress to stakeholders,

• keep the project team focused on achieving progress.

Page 3: Earned value management

Elements of Project Control

• Creation of a Baseline Schedule

• Measurement of Performance

• Effective Corrective Actions

Page 4: Earned value management

Project Monitoring

Page 5: Earned value management

Project Monitoring

• Planning and scheduling play an important role in project management

• But without monitoring the project, chances of completing the project on schedule is difficult

• Two parameters are monitored

• Cost

• Time

• The following graph shows the Time-cost relationship for a project

Page 6: Earned value management

Project Monitoring

Co

st

Time

Cost over-run with schedule

Time over-run

IdealCurve

This graph shows Project Progress

Page 7: Earned value management

Concepts of Earned Value

Page 8: Earned value management

Concept of Earned Value

• Consider the following example:

• Wall constructionWall is divided into 4 sectionsFor 4-sections - 100 man-hours are requiredHence if 2-sections are completed,

(2/4) × 100= 50 man-hours

• We say that 50 man-hours have been EARNED

• The actual man-hours spent to construct these two sections can be more than or less than the Earned Value of man-hours

Page 9: Earned value management

Concept of Earned Value

• Wall constructionIf 4 sections cost Rs. 1000/-then the cost of constructing 2 sections = Rs. 500/-

We say that Rs. 500/- is the EARNED value of moneyThe actual cost incurred in constructing these two sections can be more than or less than the Earned Value of money

It is important to note that Earned Value is based on the Actual quantities installed or Actual quantity of work done

Hence output is considered in the Earned Value concept

Page 10: Earned value management

Concept of Earned Value

• Calculation of Earned Value

• Earned Value of man-hours or money for an activity can be calculated as follows:

Page 11: Earned value management

Components of Earned Value

Page 12: Earned value management

Components of Earned value Analysis

• Budgeted Cost of Work Scheduled (BCWS)

• It is the budgeted cost of work scheduled to be performed

• It is also called the Planned Value (PV)

• It tells how much work have been completed

Page 13: Earned value management

Components of Earned value Analysis

• Budgeted Cost of Work Performed (BCWP)

• It is the budgeted cost of work actually performed

• The Earned Value for the work actually completed

• It tells how much work is actually completed

Page 14: Earned value management

Components of Earned value Analysis

• Actual Cost of Work Performed (ACWP)

• It is the amount actually spent on the work completed

• This could be more or less than the Earned Value

Page 15: Earned value management

Components of Earned value Analysis

• Scheduled Variance (SC)

• It compares work completed vs work planned

• It helps to identify whether the project is ahead or behind schedule

• Negative value indicated that the project is behind schedule

Page 16: Earned value management

Components of Earned value Analysis

• Scheduled Performance Index (SPI)

• It helps to identify whether the project is ahead or behind schedule

• Less than 1 indicates that the project is behind schedule

• It can be used to forecast how long it will take for the project to complete

Page 17: Earned value management

Components of Earned value Analysis

• Cost Variance (CV)

• It compares what was planned to be spent on the work completed vs. what was actually spent

• It helps to identify whether the project is ahead or behind schedule

• Negative value indicates that the project is over budget

Page 18: Earned value management

Components of Earned value Analysis

• Cost Performance Index (CPI)

• It helps to identify weather the project is above or below budget

• Less than 1 means the project is over budget

• It can be utilised to forecast how much amount will be required to complete the project

Page 19: Earned value management

Components of Earned value Analysis

• Budget at Completion (BAC)

• It is the amount that was originally budgeted to complete the project

Page 20: Earned value management

Components of Earned value Analysis

• Estimate at Completion (EAC)

• It is the estimated amount required to complete the project

Page 21: Earned value management

Components of Earned value Analysis

http://www.iceincusa.com/16CSP/content/4_ev/gifs/image1.gif (17.01.2007)

Page 22: Earned value management