7/30/2019 Document #10C.1 - Capital Projects and Facilities Mgt Report
1/15
Document #10C.1
Board of Library Trustees MeetingJanuary 16, 2013
The District of Columbia Public Library
Capital Construction and FacilitiesManagement Report
January 16, 2013
Active Capital Projects Report
Small Capital Projects Report
Completed Projects
7/30/2019 Document #10C.1 - Capital Projects and Facilities Mgt Report
2/15
2
Active Capital Projects
Northeast LibraryDesign-Build Renovations Contacts Progress
Councilmember Tommy Wells
Design Work is Complete
Contract Approved by DC Council
Selective demolition work is complete
Project is fully funded.
Ward 6 202.724.8072
ArchitectBell/Vines
Architects
David Bell
Victor Vines
Project
ManagerChris Wright
202.727.4913
Design-Builder Whiting-Turner
Andrew Easter
West End LibraryMixed Use Development Contacts Progress
Councilmember Jack Evans
New ground floor library will be part of mixed use
development.
Library designs are in design development phase.
Project has received preliminary PUD approval
from DC Zoning Commission on February 13,2012.
Ward 2 202.724.8058
Architect Ten Arquitectos
Erik Lang
Project
ManagerKim Fuller
202.442.6069
Developer EastBanc
Gareth Eckmann
202.737.1000
This project is a major interior renovation of the 1930s era
library. Renovations will create a 21st
Century library while
maintaining the historic integrity of the buildings interior.
7/30/2019 Document #10C.1 - Capital Projects and Facilities Mgt Report
3/15
3
West End Interim Library Contacts Progress
Councilmember Jack Evans
DC Department of General Services (DGS) is inlease negotiations on a potential storefront space.
Librarys Design-Build team has started the
design process on interim space.
Schedule pending final execution of lease
Ward 2 202.724.8058
Architect Franck and Lohsen
Art Lohsen
Project
ManagerChris Wright
202.727.4792
Contractor GCS/Sigal
Taryn Morgan
202-944-6634
Woodridge LibraryDesign Contacts Progress
Councilmember Kenyen McDuffie
CFA approved conceptual plan
Mentor-Protg Construction Manager selectedCoakley-Williams and Blue Skye
Initial pricing is underway.
Ward 5 (202) 724-8028
Architect Wiencek + Assoc
Bing Thom Arch
Project
ManagerKim Fuller
202.442.6069
Contractor Coakley-Williams
Terrance Caulfield
301.693.5000
7/30/2019 Document #10C.1 - Capital Projects and Facilities Mgt Report
4/15
4
Woodridge Modular Library Contacts Progress
Councilmember Kenyen McDuffie
Modular Units will be utilized at 18th
Street and
Douglass Avenue NE (District controlled parcel).
Awaiting Special Use Permit from DGS.
Solicitation for contractor to provide modularunits to be issued this month.
Ward 5 (202) 724-8028
Architect
Project
ManagerChris Wright
202.727.4913
Contractor
MLK Jr. LibraryRenovations to Great Hall & Digital Commons Contacts Progress
Councilmember
Designed Approved by HPRB, October 2012
Contract Approved by DC Counsel December 20,2012
Asbestos Abetment work complete.
Construction of reconfigured space commenced onJanuary 14, 2012.
Ward 2 Jack Evans
202.724.8058
Architect The Freelon Group
Derek Jones
919-941-9790
Project
ManagerKim Fuller
202-442-6069
Contractor MCN Build
Joseph Kourney
202.333.3424Improvements and upgrades to west reading room. Entire
first floor is under the Historic Landmark Designation. The
MLK Design Guidelines will be utilized.
7/30/2019 Document #10C.1 - Capital Projects and Facilities Mgt Report
5/15
5
Proj.
No.Location Project Description Estimate Cost Actual Cost Status
1 Takoma Park Foundation Walls 155,000.00$
2 Lamond Riggs West Lower Roof Replacement 30,000.00$ Scope of work under devel opment
3 Palisades & Southwest Re-Pave Parking Lot 85,000.00$4 Chevy Chase ADA Restroom Improvments 24,500.00$ 24,500.00$ Capital to transfer money to existing contract.
5 Shepherd Park Additional Roof and Masonary Repairs 25,000.00$ Scope of work under devel opment
6 Palisades New Air Handler 108,880.00$ Need funding source
7 MLK New Exterior Lighting 110,000.00$ Preparing Scope of Work
8 Benning Replace Chiller Need Estimated Cost
9 MLK
REPLACE EXHAUST MOTORS AND LOUVERS AND HAVE
SUPPLY AND RETURN DAMPERS PROGRAMMED INTO
EMS (USE AHU 1 AS BASES FOR OTHER AHUS)
Need Estimated Cost
10 MLK
REPLACE/OVERHAUL MAIN ELECTRICAL TRANSFORMER
FOR BUILDING LOCATED ON M LEVEL IN ELECTRICAL
VAULT
Need Estimated Cost
11 Cleveland Park Boiler Replacment Need Estimated Cost
12 Chevy Chase New Coolling Tower 60,000.00$Project will be handled as a modification to existing RSC
contract.
13 Georgetown Replacement of Aeraway Drains 25,000.00$
14 Shepherd Park New Roof Top A/C Units Need Estimated Cost
Southeast Foundation Wall Issues
15 Takoma Park Replace Boiler with existing boiler from Northeast Need Estimated Cost
16 Takoma Park Drainage Issues 68,000.00$ 65,000.00$ PO450049 was issued
17 Benning Interim Site Site Restoration for NPS 175,000.00$ 107,000.00$Bids received. Awaiting confirmation on DSLBD on CBE
status of low bidder
18 Tenley Installation of Historical Letters 15,000.00$ 14,730.00$ PO449150 was issued. Work is underway.
19 MLK Replace Bearings on AHU No. 2 23,000.00$ 23,000.00$ Work has been completed
20 MLK & Neighborhoods Misc window replacements 60,000.00$ 60,000.00$ Work is completed "as needed"
Total Overall Cost of Small Capital Improvments 855,500.00$ 403,110.00$
Small Capital Projects
7/30/2019 Document #10C.1 - Capital Projects and Facilities Mgt Report
6/15
6
Completed Capital ProjectsAnacostia LibraryNew Building Construction Contacts Progress
Councilmember
Opened to the public April 26, 2010
Ward 7 Yvette Alexander
202.724.8068
Architect Freelon Group
Philip Freelon919.941.9790
Project
ManagerDedric Boyd
202.727.1127
ContractorForrester
Construction
Tom Willerton
301.816.1700
DCPL PM
Firm Hill International
Benning LibraryNew Building Design Contacts Progress
Councilmember
Opened to the public April 5, 2010
Ward 7 Yvette Alexander
202.724.8068
ArchitectDavis, Brody,
Bond & Aedas
Peter Cook
202.449.1190
Project
ManagerKim Fuller
202.442.6069
Contractor Forrester
Jon McGee
301.255.1750
DCPL PM
FirmA-1 Consulting
New State of the Art Library on Good Hope Road SE is open.
New State of the Art Library located at 3935 Benning Road NE
is open.
7/30/2019 Document #10C.1 - Capital Projects and Facilities Mgt Report
7/15
7
William O. Lockridge Bellevue Library Contacts Progress
Councilmember
Library OpenedJune 13, 2012
Ward 8 Marion Barry
202.724.8045
Architect Wiencek/Adjaye
Scott Knudson
301.948.6220
Project
ManagerLisa Deanes
202.727.5181
Contractor Coakley-Williams
DCPL PM
Firm
Jair Lynch
Development
Partners
Cleveland ParkNew Ceiling and Lighting Contacts Progress
Councilmember
Project Complete
Ward 3 Mary Cheh
202.724.8062
Architect N/A
Project
ManagerEd Hampton
202.442.6067
ContractorEagle
Construction
Project consists of installing a new ceiling and lighting system.
7/30/2019 Document #10C.1 - Capital Projects and Facilities Mgt Report
8/15
8
The Library has received Federal Stimulus Money for energy
enhancements. Projects will take place at the above locations,
focusing on window replacements, energy efficient lighting,
and automated building heating and cooling controls
DeanwoodNew Community Center and Library Contacts Progress
Councilmember
Opened to the public June 25, 2010
Ward 7 Yvette Alexander
202.724.8068
Architect EEK
Sean ODonnell
Project
Manager
Contractor
Energy Enhancement ProjectsVarious Locations Contacts Progress
Capitol View, Cleveland Park,Shepherd Park, Lamond Riggs, Palisades, Southwest, West
End and Woodridge
Councilmember
Energy Efficient Lighting Projects areCOMPLETE
Window and Door work is complete
Various
Architect T.B.D
Project
ManagerEd Hampton
202.442.6067
Contractor
DCPL PM
Firm
Project is a partnership with the Department of Parks and
Recreation to co-locate a 10,000 square foot library within a
54,000 square foot aquatic center and community center.
Library and Community Center would share such space as
computer lab, senior rooms, tutor rooms and community
meeting rooms. Project location is 49
th
and Quarles St. NE
7/30/2019 Document #10C.1 - Capital Projects and Facilities Mgt Report
9/15
9
Francis A. Gregory LibraryNew Library Contacts Progress
Councilmember
Library OpenedJune 19, 2012
Ward 7 Yvette Alexander
202.724.8068
Architect Wiencek/Adjaye
Scott Knudson
301.948.6220
Project
ManagerLisa Deanes
202.727.5181
Contractor Hess Construction
Jair Lynch
Development
PartnersDCPL PM
Firm
Francis A. Gregory LibraryInterim Library Contacts Progress
Councilmember
Opened June 10, 2010
Ward 7 Yvette Alexander
202.724.8068
Architect
Project
ManagerLisa Deanes
202.727.5181
ContractorWilliam Scotsman
Greg Bichell
DCPL PM
Firm
Project consists of building a 4,200 square foot interim library
to serve the community during construction; the interim will
have 30 computers, books on CD as well as traditional
collection material for all age sets
Design of the new Francis Gregory Library will include
community input on planning and programming phase. Project
is fully funded.
7/30/2019 Document #10C.1 - Capital Projects and Facilities Mgt Report
10/15
10
Georgetown LibraryBuilding Renovation Contacts Progress
Councilmember
Opened to the Public October 18, 2010
Ward 2 Jack Evans
202.724.8058
Architect Martinez & Johnson
Tom Johnson
202.333.4480
Project
ManagerChris Wright
202.272.4913
Contractor N/A
DCPL PM
Firm
Smoot
Construction
Mount PleasantInterim Library Contacts Progress
Councilmember Jim Graham
Opened to the public April 26, 2010Re-opened to the public May 15, 2010
Ward 1 202.724.8181
Architect Core Architects
Dale Stewart
202.466.6116Project
ManagerDedric Boyd
202.727.1127
Contractor MCN Build
Bassem Boustany
202.333.3424
Renovation complete and Library open to the public.
Project consists of building a 3,600 square foot interim library to
serve the community during construction; the interim will have
30 computers, books on CD as well as traditional collection
material for all age sets
7/30/2019 Document #10C.1 - Capital Projects and Facilities Mgt Report
11/15
11
Mount PleasantInterior Restoration Contacts Progress
Councilmember Jim Graham
Opened to Public September 12, 2012
Ward 1 202.724.8181
Architect Core Architects
Dale Stewart
202.466.6116
Project
ManagerChris Wright
202.727.4913
Contractor T.B.D
DCPL Project
Management
Smoot
Construction
Northeast LibraryExterior Restoration Contacts Progress
Councilmember Tommy Wells
Construction
Substantial completion May 15, 2010
Ward 6 202.724.8072
Architect Bell Architects
David Bell
202.548.7570Project
ManagerChris Wright
202.727.4913
ContractorMonarc
Construction
C. McDermott,
703.201.1747Project consists of Exterior Improvements to windows,
doors, security lighting, masonry restoration, landscaping
and signage.
7/30/2019 Document #10C.1 - Capital Projects and Facilities Mgt Report
12/15
12
Northwest OneNew Co-location Facility Contacts Progress
Councilmember Tommy Wells
Library Open December 7, 2009Open to the Public
Ward 6
Architect Hord Cort Plan
Project
ManagerReagan Assoc
Contractor Forrester
Parklands-TurnerNew Storefront Library Contacts Progress
Councilmember Marion Barry
Ribbon Cutting October 5, 2009OPEN TO THE PUBLIC
Ward 8 202.724.8045
Architect Mood Nolan - DC
Patrick Williams
202.244.Project
ManagerDedric Boyd
202.727.1129
Contractor Lexx Group
Ken Postell
202.393.
Project to fit out approximately 5,000 Sq Ft of storefront space
to replace the existing Parklands-Turner kiosk. The storefront
library is similar in size, scope, computers, and collections to the
Georgetown Interim and Tenley-Friendship Interim Libraries.
Project consists of 6,500 SQ FT Library facility as part of
Elementary School and Recreation Center. This facility
replaces the Sursum Corda kiosk.
7/30/2019 Document #10C.1 - Capital Projects and Facilities Mgt Report
13/15
13
Petworth LibraryInterim Library Contacts Progress
Councilmember
Opened to public on January 11, 2010
Closed February 5, 2011
Ward 4 Muriel Bowser
202.724.8052
Architect N/A
Project
ManagerLisa Deanes
202.727.5181
Contractor Sigal Construction
Sarah Norman
DCPL PM
Firm
PetworthInterior Renovations Contacts Progress
Councilmember
Open February 28, 2011
Councilmember Muriel Bowser
Ward 4 202.724.8052
Architect Frank and Loshen
Fletcher Farr
Anoyte
Project
ManagerChris Wright
202.727.4913
Contractor Sigal Construction
Sarah Norman
DCPL PM
Firm
McKissack and
McKissack
Project updates the interior of the Petworth Library to be a
fully functional state of the art 21st
Century Library, while
still being respectful of the buildings historic character.
Project consists of building a 4,200 square foot interim library
to serve the community during construction; the interim will
have 30 computers, books on CD as well as traditional
collection material for all age sets
7/30/2019 Document #10C.1 - Capital Projects and Facilities Mgt Report
14/15
14
Tenley FriendshipNew Building Contacts Progress
Councilmember
Opened January 24, 2011
Ward 3 Mary Cheh
202.724.8062
Architect Freelon Group
Philip Freelon
919.941.9790
Project
ManagerDedric Boyd
202.727.1113
Contractor Forrester.
Joe Ockershausen
301.255.1794
DCPL PM
FirmHill International
Washington HighlandsInterim Library Contacts Progress
Councilmember
Open to the public December 21, 2009
Ward 8 Marion Barry
202.724.8045
Architect Cooper Carry
Project
ManagerLisa Deanes
202.727.5181
Contractor MCN Build
DCPL PM
Firm
Jair Lynch
Development
Design of the new Tenley Branch Library will include
community input on planning and programming phase. Design
and construction is fully funded.
Project consists of building a 5,000 square foot interim library
for the Washington Highlands Community; the interim will
have 20 computers, books on CD as well as traditional
collection material for all age sets.
7/30/2019 Document #10C.1 - Capital Projects and Facilities Mgt Report
15/15
15
Watha T. Daniel / ShawNew Building Design Contacts Progress
Councilmember
Opened to the public August 2, 2010
Ward 2 Jack Evans
202.724.8058
ArchitectDavis, Brody
Bond & Aedas
Peter Cook
202.449.1190Project
ManagerKim Fuller
202.442.6069
Contractor Forrester.
Joe Ockershausen
301.255.1794
DCPL PM
FirmA-1 Construction
Martin Luther King Jr. LibraryNew Teen Spot andCollege Information Center
Contacts Progress
Councilmember
Project Complete
Ward 2 Jack Evans
202.724.8058
Architect Sorg Associates
Suman Sorg
ProjectManager
Kim Fuller
202.442.6070
Contractor Bennett Group
Kolar Bowen
202. 625.3330
Project complete and Library is open to the public.
.
New Teen Spot and College Information Center is a
destination for teens. It provides stimulating learning
opportunities that support their success in life. This destination
provides opportunities to meet their need for homework help,
exam preparation, and using computers and software
applications. High quality program events are a key to the
success of the library in assisting teens.
Top Related