BASS LAKE ROAD RECONSTRUCTION CSAH 101 TO VICKSBURG LANE | CITY PROJECT NO. 2007-17
Bass Lake Road Reconstruction CSAH 101 to Vicksburg Lane | City Project No. 2007-17
Project History
2001
Corridor Study
defined preferred alternative and right of way
preservation
2008
Preliminary design,
environmental documentation,
final design
SEP 2009
Phase I construction (realign Bass Lake Road / CSAH 101)
JUL 2010
Phase I complete and
open to traffic
APR 2011
Phase II construction (reconstruct
from CSAH 101
east to Vicksburg
Lane)
JUN - JUL 2011
State
Shutdown
NOV 2012
Project complete
Bass Lake Road Reconstruction CSAH 101 to Vicksburg Lane | City Project No. 2007-17
Why Reconstruct?
• Upgrade Bass Lake Road (CSAH 10) to
support area development and expansion
- Need to accommodate growing traffic volumes
- Convert 3.5 miles of two-lane roadway to
four-lane urban corridor
- Correct narrow shoulders, steep side slopes,
limit access points, improve roadway
vertical/horizontal curvature, add new facilities
for non-motorized users
Bass Lake Road Reconstruction CSAH 101 to Vicksburg Lane | City Project No. 2007-17
Existing & Proposed
Alignments for Bass
Lake Road from CSAH
101 to Vicksburg Lane
Bass Lake Road
Recommended
Concept Layout
Bass Lake Road
Final Layout
Bass Lake Road Reconstruction CSAH 101 to Vicksburg Lane | City Project No. 2007-17
Funding Sources
• American Recovery Reinvestment Act (ARRA)
- First ARRA project in Twin Cities metropolitan area to be
administered by a local agency
• Surface Transportation Program (STP)
• State, County and Local monies
- Metropolitan Council Environmental Services, Hennepin
County, City of Maple Grove’s Trunk Transportation & Utilities
and Park Dedication
Bass Lake Road Reconstruction CSAH 101 to Vicksburg Lane | City Project No. 2007-17
Keeping Residents in the Know
Bass Lake Road Reconstruction CSAH 101 to Vicksburg Lane | City Project No. 2007-17
SHPO
After construction
Before construction After construction
Bass Lake Road Reconstruction CSAH 101 to Vicksburg Lane | City Project No. 2007-17
State Shutdown Contingency Plan
• Developed a Detailed Plan for Each Project Phase
- Ensure all MnDOT oversight and independent assurance
tasks were covered by private consultants
- Tasks included materials testing, proper certifications, plant
inspections
• Plans in place continued project momentum seamlessly
• Project completed on time
DESIGNING THE DETAILS
Minimizing environmental impacts through design.
Bass Lake Road Reconstruction CSAH 101 to Vicksburg Lane | City Project No. 2007-17
Bass Lake Road / CSAH 101
Signalized Intersection
Bass Lake Road / CSAH 101 “T”
intersection before construction
After construction After construction
Bass Lake Road Reconstruction CSAH 101 to Vicksburg Lane | City Project No. 2007-17
Bass Lake Road Corridor Improvements
Bass Lake Road Reconstruction CSAH 101 to Vicksburg Lane | City Project No. 2007-17
Environmental Considerations
Endangered Species
Curb sloped for turtle crossing
Bass Lake Road Reconstruction CSAH 101 to Vicksburg Lane | City Project No. 2007-17
Wall Benefits
Bass Lake Road Reconstruction CSAH 101 to Vicksburg Lane | City Project No. 2007-17
Bridge Box Culverts
After construction
Before construction
During construction
Bass Lake Road Reconstruction CSAH 101 to Vicksburg Lane | City Project No. 2007-17
Elm Creek Bridge/Trail/Creek Crossing
• Three-in-One Structure
- Overcome increased roadway elevation
- Provide new trail connections
- Maintains existing flow characteristics of the creek by using
the existing box culverts
- Environmental considerations in preferred alternative
- Dramatic cost savings by incorporating existing box culverts
into design
Bass Lake Road Reconstruction CSAH 101 to Vicksburg Lane | City Project No. 2007-17
Tricking Mother Nature: Net Zero Loading
36,400 tons
(21,600 cubic yards)
unsuitable soils 7,800 tons
of expanded shale
=
PAVEMENT SECTION 28,150 tons of
pavement
450 tons (28,000 cubic yards)
of lightweight expanded polystyrene (EPS)
+
+
Bass Lake Road Reconstruction CSAH 101 to Vicksburg Lane | City Project No. 2007-17
During construction During construction
During construction During construction
Bass Lake Road Reconstruction CSAH 101 to Vicksburg Lane | City Project No. 2007-17
During construction During construction
During construction During construction
Bass Lake Road Reconstruction CSAH 101 to Vicksburg Lane | City Project No. 2007-17
Bass Lake Road Reconstruction CSAH 101 to Vicksburg Lane | City Project No. 2007-17
A SUCCESSFUL OUTCOME
A modern and safe facility for all users.
Bass Lake Road Reconstruction CSAH 101 to Vicksburg Lane | City Project No. 2007-17
• Bass Lake Road Reconstruction
- Completes upgrades of Bass Lake Road from
CSAH 101 to I-494
- Improves corridor mobility and maintains
necessary access
- New facilities for non-motorized users
- Construction created jobs for Minnesotans
- Innovative design and construction techniques
serve as a model for other agencies
Bass Lake Road Reconstruction CSAH 101 to Vicksburg Lane | City Project No. 2007-17
After construction After construction
Bass Lake Road Reconstruction CSAH 101 to Vicksburg Lane | City Project No. 2007-17
After construction