OUTLINE
1. INTRODUCTION
2. SCOPE OF WORK FOR SLOPE
REMEDIAL WORK
3. PARAMETERS OF COST
ESTIMATION
4. EXTERNAL FACTOR OF COST
ESTIMATION
5. EXAMPLE OF COST ESTIMATION
6. CONCLUSION
1.0 INTRODUCTION1. Generally, slope remedial work will be carried
out on existing failed slope.2. Normally, the application of remedial work is
subjected to the suitability of site condition,such as the location of site, site difficulty, type offailure, soil profile, etc.
3. Thus, the cost of slope remedial at particularlocation might be differ with another location.
4. Cost estimation of the remedial work isnecessary to carried out to ensure the costapplied for the remedial in range with themarket value.
5. Cost estimation is an approximation of theprobable cost of a project on the basis ofavailable information.
6. A problem with a cost overrun can be avoidedwith a credible, reliable and accurate costestimate.
19-Apr-16
2
DIAGRAM OF COST ESTIMATION
SCOPE OF REMEDIAL WORK
1. Preliminary Work
2. Earthwork (excavation & backfilling)
3. Slope Stabilization Work
4. Surface Protection Work
5. Drainage System Work
6. Road Work
19-Apr-16
3
PRELIMINARY WORK
UTILITIES – Mapping/Relocation/SupplySITE FACILITIES - Site OfficeRequirement & Provision , etcTESTING - Prelim Test
Example
EARTHWORK (EXCAVATION &BACKFILLING)
Example
Photo example ofexcavation &
backfilling work
SLOPE STABILIZATION WORK
Stone pitching
Example of Rubble Wall & Stone pitching
19-Apr-16
4
SLOPE STABILIZATION WORK
Example of Soil Nailing & Shotcrete
SLOPE STABILIZATION WORK
Example of Gabion Wall
SLOPE STABILIZATION WORK
Example of Crib Wall
19-Apr-16
5
SURFACE PROTECTION WORK
Shotcrete
Hydroseeding
DRAINAGE SYSTEM WORK
ROAD WORK
Filling Chrusher Run Premix Work
19-Apr-16
6
EXAMPLE BILL OF QUANTITY(Preliminary Work)
Bill No. 1: General Items and Preliminaries
All quantities are provisional
1 General Items and Preliminaries
1.1 Contractual Requirements
1.1.1 Allow for the provision of Performance Bond in the form of sum
approved Bank/Insurance Guarantee/Wang Jaminan
Perlaksanaan equal to five (5) percent of the Contract Sum
for performance and observance of this contract.
1.1.2 Allow for the provision of insurances as per condition sum
of contract.
i. Insurance of Works including insurance against personal
injuries and damaged properties.
ii. Workmen's Compensation and/or SOCSO.
1.2 Inspection and Testing
1.2.1 All quality control and testing requirements including preparation of sum
report, test records complete with colour photographs, throughout
the contract period.
1.3 Progress Report
1.3.1 Preparation and submission of monthly progress report including sum
traffic management report complete with colour photographs,
throughout the contract period.
1.4 As-Built Drawing
1.4.1 Allow for the preparation of as-built drawings and completion sum
report duly certified by licensed surveyor as per requirements
of the specification.
1.5 Work Programme
1.5.1 Allow for submission of Programme of Works prior to sum
commencement of works throughout the contract period.
1.6 Site Cleaning and Clearing
1.6.1 Allow for site cleaning and clearing of construction debris through sum
out the construction and upon completion of works and dispose
surplus from site to contractor's own tip.
1.7 Compliance With Statutory Requirements
1.7.1 Allow for Statutory Obligation including levy payment to the sum
Statutory Requirements and Lembaga Industri Pembinaan Malaysia
under Part VIII of the LPIPM Act 1994.
1.8 Contractor's Site Office and Accommodation
1.8.1 Allow for the establishment of the contractor's site office and sum
workmen's accommodation.
1.8.2 Allow for the maintenance of the contractor's site office sum
throughout construction period.
1.8.3 Allow for the removal of the contractor's site office on sum
completion of works.
Item Unit QuantityPrice/Unit
(RM)Amount(RM)
CADANGAN KAJIAN GEOTEKNIKAL DAN KERJA REKABENTUK TERPERINCI BAGI RUNTUHAN CERUN DI DEWAN FLATTAMAN MULIA, BANDAR TUN RAZAK, WILAYAH PERSEKUTUAN
CARRIED FORWARD
Bill No. 1: General Items and Preliminaries
All quantities are provisional
B/F
1.8.4 Provision of all costs incurred by complying with all safety, health sum
and welfare regulation orders or by laws relating to all work people
(personal protective equipments, etc.).
1.9 Mobilization and Demobilization
1.9.1 Allow for the mobilization of all labour, plant, equipment and sum
and incidentals necessary to satisfactorily perform the
contract works and demobilization of the same on completion
of works.
1.10 Survey and Setting Out Works
1.10.1 Provide setting out, levelling and checking of construction of sum
all works under the contract by a licensed surveyor.
1.11 Temporary Works
1.11.1 To provide temporary silt-sump/sediment traps,silt fence, earth drains, sum
etc, to contain possible spillage of silt to adjacent site and
to maintain during construction stage.
1.11.2 Supply, lay and maintain Grade A tarpaulin sheet for slope protection sum
during construction works as directed by the S.O.
1.11.3 Provide and maintain temporary access road from/to working sum
platform.
1.12 Miscellaneous
1.12.1 Allow sum for temporary relocation and/or other related protection sum
of utilities works due to construction as directed by the S.O.
1.13 S.O.'s Office Requirement
1.13.1 Provide, service and remove upon completion of work S.O.'s sum
site office (cabin) complete with air-cond. and necessary furnitures/
equipments as specified by S.O.
1.13.2 Allow maintenance for S.O.'s office as directed by S.O. sum
1.14 Site Office Provision
1.14.1 The contractor shall provide and maintain the following to the
approval and for the use of S.O and his staff within two (2)
weeks from the commencement date of the works until the
insurance of Certificate of Practical Completion by the S.O.:
1.14.1.1 Provide and maintain one (1) new computer facilities comprising sum
of laptop computer system including all accessories as specified
in Appendix 1B of the specification or requested by S.O.
1.14.1.2 Provide and maintain one (1) new digital camera with photografic sum
record as specified in Appendix 1A of the specification or requested
by S.O.
Item Description Unit QuantityPrice/Unit
(RM)Amount(RM)
CADANGAN KAJIAN GEOTEKNIKAL DAN KERJA REKABENTUK TERPERINCI BAGI RUNTUHAN CERUN DI DEWAN FLATTAMAN MULIA, BANDAR TUN RAZAK, WILAYAH PERSEKUTUAN
CARRIED FORWARD
Bill No. 1: General Items and Preliminaries
All quantities are provisional
B/F
1.14.1.3 Provide and maintain safety equipments as per specified in sum
Appendix 1A or requested by S.O.
1.15 Project Signboard
1.15.1 Provide and maintain one (1) project signboard for the duration sum
of work and remove on completion of works.
Amount(RM)
TOTAL CARRIED TO SUMMARY
Item Description Unit QuantityPrice/Unit
(RM)
CADANGAN KAJIAN GEOTEKNIKAL DAN KERJA REKABENTUK TERPERINCI BAGI RUNTUHAN CERUN DI DEWAN FLATTAMAN MULIA, BANDAR TUN RAZAK, WILAYAH PERSEKUTUAN
EXAMPLE BILL OF QUANTITY(Earthwork, Slope Stabilization & Surface Protection)
Bill No. 2: Slope Remedial and Mitigation Works
All quantities are provisional
2 Slope Remedial and Mitigation Works
2.1 Site Clearing
2.1.1 Clear and remove from site all obstacles over the areas for ha. 0.5
the construction of slope remedial and mitigation works
including trees, shrubs, roots, fences, existing road, structures
and utilities, and disposal of all materials to Contractor's
own dump site as directed by S.O.
2.1.2 Pruning and cutting all trees and dispose off the site including grubbing nr 7
of the tree's roots exceeding 2m girth for slope protection works.
2.2 Excavation & Trimming
2.2.1 Excavate by mechanical equipment to obtain formation level, load m3 6500
and transport unsuitable excavated material to contractor's own
dumping source.
2.3 Horizontal Subsoil Drain
2.3.1 Supply and install 75mm dia, 9m length horizontal subsoil drain m 126at 3m c/c spacing, consisting of perforated UPVC pipe wrappedwith a layer of non-woven geotextile as specified in drawing no.
2.3.2 Supply and construct cast in situ outlet drain made of Grade 25 nr 14concrete, inclusive reinforcement, as specified in Engineer'sdrawing no.
2.5 Soil Nail2.5.1 Supply and install T25, 6m length galvanized reinforcement steel nr 14
as soil nails complete with centralizers and grout injection (Grade
30 Concrete) through 100mm dia. Drill hole at 1.5m c/c spacing
as specified in Engineer's drawing and specification, in any
strata (rock or soil). Works also include supply and fix nail head
and all necessary works for proper completion inclusive
UPVC pipe as casing for soil nailing average length
as per drawing no.
2.5.2 Supply and install T25, 9m length galvanized reinforcement steel nr 50
as soil nails complete with centralizers and grout injection (Grade
30 Concrete) through 100mm dia. Drill hole at 1.5m c/c spacing
as specified in Engineer's drawing and specification, in any
strata (rock or soil). Works also include supply and fix nail head
and all necessary works for proper completion inclusive
UPVC pipe as casing for soil nailing average length
as per drawing no.
2.5.3 Allow for preliminary pull out test for soil nail as directed by the S.O nr 2
(Location to be determined on site)
2.5.4 Allow for pull out test for soil nail to 1.5 × Working Load as nr 2
specified in Engineer's specification.
2.4 Turfing
2.4.1 Close turfing on level surfaces including 50mm bed of black earth m2 5200
as specified in Engineer's drawing.
CADANGAN KAJIAN GEOTEKNIKAL DAN KERJA REKABENTUK TERPERINCI BAGI RUNTUHAN CERUN DI DEWAN FLAT TAMANMULIA, BANDAR TUN RAZAK, WILAYAH PERSEKUTUAN
Amount(RM)
CARRIED FORWARD
Item Description Unit QuantityPrice/Unit
(RM)
Earthwork
Slope Stabilization
Surface Protection
EXAMPLE BILL OF QUANTITY(Road Work & Drainage Work)
Bill No. 2: Slope Remedial and Mitigation Works
All quantities are provisional
B/F
4.8 Roadworks
4.8.1 Fill, spread, grade and compact 50mm thk. sand bedding as m3 30
specified in drawing and specification.
4.8.2 Fill, spread, grade and compact 300mm thk. crusher run material as m3 62
road base (compact to 95% max. dry density) as specified in
drawing and specification.
4.8.3 Supply and apply tack coat (Grade RC2) applied at a nominal spray m2 205
rate of 1.20 ± 0.1 litres per square meter.
4.8.4 Supply, lay and compact 60mm thk. Asphaltic Concrete Binder m2 205
Course (ACBC) as specified in drawing and specification.
4.8.5 Supply, lay and compact 40mm thk. Asphaltic Concrete Wearing m2 205
Course (ACWC) as specified in drawing and specification.
4.8.6 Supply all the materials and apply/re-apply reflective thermoplastic m2
marking (white), 200mm width single "Broken/Continuous RoadLine" as directed by S.O. or as specified in drawing.
4.6 Handrail4.6.1 Supply and install galvanised steel pipes handrail m 55
complete with post as specified along capping beam includingcutting, welding and painting.
CARRIED TO GRAND SUMMARY
CADANGAN KAJIAN GEOTEKNIKAL DAN KERJA REKABENTUK TERPERINCI BAGI RUNTUHAN CERUN DI DEWAN FLAT TAMANMULIA, BANDAR TUN RAZAK, WILAYAH PERSEKUTUAN
Item Description Unit QuantityPrice/Unit
(RM)Amount(RM)
Bill No. 3: Drainage Work
All quantities are provisional
3 Drainage Work
3.1 Surface Drainage System
3.1.1 Supply and install cast in-situ Grade 25 concrete U-shape intercepter drain m 95
(type D1) top width not exceeding 600mm and depth to invert
not exceeding 300mm. Rate inclusive excavation, formwork, lean
concrete, demolished existing drain, reinforcement and removal
of surplus material. Refer drawing no.
3.1.2 Supply and install cast in-situ Grade 25 concrete V-shape berm drain m 104
(type BD1), top width not exceeding 600mm and depth to invert not
exceeding 300mm. Rate inclusive excavation, formwork, lean
concrete, demolished existing drain, reinforcement and removal
of surplus material. Refer drawing no.
3.1.3 Supply and construct U-shaped toe drain (type D2), m 300
top width not exceeding 1500mm and depth to invert not
exceeding 1200mm. Rate inclusive excavation, formwork, lean
concrete, demolished existing drain, reinforcement and removalof surplus material. Refer drawing no.
3.1.4 Supply and construct 600mm (W) × 600mm (D) U-shaped channel m 50cascade drain Type CD1 made of Grade 25 concrete as specified inEngineer's drawing. Rate include hacking-off, removal of existingdrains, excavation, lean concrete, reinforcement, formworks anddisposal of surplus material.
3.1.5 Supply and construct 750mm (W) × 750mm (L) × 750mm (D) nr 4reinforced concrete sump (Type A) made of Grade 25 concrete asspecified in Engineer's drawing. Rate include hacking-off, removalof existing sump, excavation, lean concrete, reinforcement,formworks and disposal of surplus material.
3.1.6 Supply and construct 1000mm (W) × 1000mm (L) × 1000mm (D) nr 5
reinforced concrete sump (Type B) made of Grade 25 concrete as
specified in Engineer's drawing. Rate include hacking-off, removal
of existing sump, excavation, lean concrete, reinforcement,
formworks and disposal of surplus material.
3.1.6 Upgrade existing drains, culverts, sumps and etc within residential area sum
as specified in the drawing and specification.
CADANGAN KAJIAN GEOTEKNIKAL DAN KERJA REKABENTUK TERPERINCI BAGI RUNTUHAN CERUN DI DEWAN FLAT TAMANMULIA, BANDAR TUN RAZAK, WILAYAH PERSEKUTUAN
CARRIED FORWARD
Item Description Unit QuantityPrice/Unit
(RM)Amount(RM)
Road Work Drainage Work
19-Apr-16
7
3M 1P
1. Man Power
2. Materials
3. Machinery
4. Production
MAN POWER
1. Man power is person that probably involve to
complete the work.
2. It can be divide into few category such as:
I. Site Administration Staff
II. Machine Operator
III. Skill Worker
IV. General Worker
3. Number of worker need to be estimate to
ensure the work can be carried out efficiently
and match with production required.
4. The estimation of rate of salary for the workers
involve in particular work must be in range of
current market.
19-Apr-16
8
MATERIALS
1. The materials required for the particular work
must be identified for quantity estimation
purpose
2. Quantity estimation
3. Rate of materials
MACHINERY
1. Type of machinery required must be listed
2. Number of machinery
3. Rate of rental
4. Duration required
5. Consumption for the used machinery must be
identified (fuel, diesel, maintenance)
PRODUCTION
1. Understand the process to carry out the work.
2. Estimation of completion per day.
3. Consideration of work delay possibility.
19-Apr-16
9
EXTERNAL FACTOR
1. Type of remedial.
2. Location of site.
3. Difficulty of site.
4. Currency exchange.
5. Market value of construction materials and machinery
rental.
DOES THE EXTERNAL FACTOR
AFFECT THE COST ESTIMATIONFOR REMEDIAL WORK???...
YESHOW??..
19-Apr-16
10
Type of remedial is one of the factor will be affect the cost
estimation because of:
1. Different work scope will be involve.
2. Different material will be used.
TYPE OF REMEDIAL
FACTOR OF LOCATION(Rate of Machinery)
Different rate of
machinery depend
on site location
(state).
Source: JKR
FACTOR OF LOCATION(Rate of Man Power)
Different rate of
man power
depend on site
location (state).
Source: JKR
19-Apr-16
11
SITE DIFFICULTY(Limited Access to Failure Area)
Less of production perday will increase the
cost of operation work
House
Approximate2.5m
Approximate4.5m
SITE DIFFICULTY(Limited Work Space)
Need the highskill/experience manpower to carry out
the work.Working Area
House Working Area
House
Working Area
HouseWorking Area
PAPER CUTTING ON CURRENCYEXCHANGE
19-Apr-16
12
PAPER CUTTING ON INCREAMENT OF MARKETVALUE FOR CONSTRUCTION MATERIALS
EXAMPLE OF COST ESTIMATION
19-Apr-16
13
CONCLUSION
1. Cost estimation of slope remedial work must be carried
out to prevent the overrun of cost.
2. The estimator must experience on the market rate of man
power, materials and machinery.