Cheney High School Modernization & ExpansionCheney School District
Presentation to City of CheneyApril 2018
Introductions and Purpose Presentation
PURPOSE: Inform City of Cheney Planning Commission and Council members on the status of the Cheney High School Additions and Modernization Project
AGENDA:• Schedule Overview• Site Plan• Exterior, Interior and Elevation Images• Construction Phasing• Questions & Answers
Schedule Overview Including City SEPA, CUP and Safe Route to Schools Collaboration
City of Cheney/Cheney Public SchoolsLand Use, Comp Plan & CUP Process
Activity Date
Pre-Development Meeting 12/14/2017
Application Submitted 1/17/2018
Application Deemed Fully Complete 2/1/2018
Date of Vesting 2/1/2018
Notice of Application Letter 2/2/2018
SEPA Determination: MDNS - Cheney Lead Agency 1/18/2018
Affidavit of Mailing 2/16/2018
Affidavit of Property Posting 2/12/2018
Public Hearing - Hearing Examiner - Recommendation 3/21/2018
Final Decision - City Council April 2018
Deadline for Issuing Decision 6/1/2018
Schedule Overview Including City SEPA, CUP and Safe Route to Schools Collaboration
City of Cheney/Cheney Public Schools Safe Route to School Grants Schedule
Activity Date
Initial Meeting Between City and CPS 2/21/2018
Internal CPS Meeting on Safe Route to Schools Grants 3/6/2018
CPS and Spokane County Initial Meeting on Safe Route to Schools Grants (Snowdon Elementary School) 3/22/2018
Draft Review of Grant Application 3rd Week April
Application Due to State 4/27/2018
Cheney Public Schools Design/Construction Schedule
Activity Date
Design Sept. 2017-June 2018
Construction July 2018-May 2020
Occupy June-August 2020
Projected to Begin Classes Late August or Early September 2020
Cheney High School - Site Plan
“Bond educational and program commitments are intact in this project”• 17 classrooms• New auditorium, fitness, wrestling, auxiliary gym,
commons and kitchen• Site improvements• New chillers/boilers• New GPON (Fiber) Internet• New metal/wood shops• Security Improvements and new administrative/
educational support spaces• 478 parking stalls on campus
Cheney High School Design - Floor Plan
Cheney High School Design
Cheney High School Design
Cheney High School Design
Cheney High School Design
Cheney High School Design
Theatre ¾ Fly Box Orientation/Mass
Theatre ¾ Fly Box Orientation/Mass
Cheney High School - Height Variance Request
Construction Phasing
City of Cheney and CPS/Lydig Construction are collaborating on preliminary phasing plans to provide safe and secure campus for life/safety issues.