7/30/2019 Automated Student Management System for South East Gippsland University - SPMP
1/67
Software Project Management PlanSixSigma, 20
th
August, 2012 SPMP -1.0
P j t M
Project Team:
Emily Maguire, 0608170
Laura Unsworth, 0611093Crista Cullen, 0535368
Anne Panter, 0610024
Hannah Macleod, 0590077
Mark Knowles, 0608715
Jamie Dwyer, 0608896
7/30/2019 Automated Student Management System for South East Gippsland University - SPMP
2/67
Table of Contents
Table of Contents...2List of Figures ....................................................................................................................... 4
List of Tables ........................................................................................................................ 4
Definitions ............................................................................................................................ 5
1) Introduction and Objectives of the Project Plan ................................................................. 6
1.1 Overview of the Organization ...................................................................................... 6
1.2 Current Situation and Problem/ Opportunity Statement................................................ 61.3 Project Objectives........................................................................................................ 7
2) Project .............................................................................................................................. 7
2.1 Project Information ...................................................................................................... 7
2.2 Project objectives ........................................................................................................ 7
2.3 Project approach .......................................................................................................... 8
2.4 Roles and Responsibilities ........................................................................................... 82.5 Project Constraints ...................................................................................................... 9
2.6 Assumptions .............................................................................................................. 10
2.7 Preliminary Schedule and Budget Estimates .............................................................. 10
2.8 Plan Modification Rules ............................................................................................ 11
2.9 Approval Signatures .................................................................................................. 11
3) Project Scope Management plan ..................................................................................... 12
3.1 Product description .................................................................................................... 12
3.2 Project Deliverables................................................................................................... 12
3.3 Scope Statement ........................................................................................................ 13
3.4 Work Breakdown Structure Development .................................................................. 14
3.5 Scope Change Management Process .......................................................................... 25
3.5 Plan Modification Rules ............................................................................................ 27
4) Schedule management plan ............................................................................................. 28
4.1 Project Schedule ........................................................................................................ 28
4.2 Assumptions .............................................................................................................. 29
5) Cost Management Plan ................................................................................................... 29
7/30/2019 Automated Student Management System for South East Gippsland University - SPMP
3/67
6.4 Quality Assurance ..................................................................................................... 34
6.5 Quality Control .......................................................................................................... 37
7) Risk Management ........................................................................................................... 39
7.1 Risk Management Strategies ...................................................................................... 39
7.2 Risk Management Tools ............................................................................................ 41
7.3 Data Sources ............................................................................................................. 41
7.4 Risk Categories ......................................................................................................... 42
7.5 Risk Probability and Impact....................................................................................... 42
8) HR management plan ...................................................................................................... 438.1 Project Organization .................................................................................................. 43
8.1.1.1 Hierarchy of the project team ........................................................................... 44
8.2 Resource Requirements ............................................................................................. 47
8.3 Resource Assignment ................................................................................................ 47
9) Communication plan ....................................................................................................... 50
9.1 Stakeholder Analysis ................................................................................................. 509.2 Project Reports .......................................................................................................... 50
9.3 Project Meetings ........................................................................................................ 51
9.4 Project Information Accessibility ............................................................................... 51
9.5 Communications Summary ........................................................................................ 52
Reference List ..................................................................................................................... 54
Appendices ......................................................................................................................... 55Appendix A: Generic Cost Estimate Classification Matrix .............................................. 55
Appendix B: Project Budget ............................................................................................ 56
Appendix C: Risk Categorization Table ..................................................................... 58-59
Appendix D: Detailed Gantt Chart .............................................................................. 58-59
7/30/2019 Automated Student Management System for South East Gippsland University - SPMP
4/67
List of Figures
Figure 1: Hierarchy of the project team ............................................................................... 44Figure 2: Resource Allocation ............................................................................................. 47
List of Tables
Table 1 Project Approach ..................................................................................................08Table 2 Roles & Responsibilities .................................................................................. 08-09
Table 3 Preliminary Project Schedule ............................................................................... 10Table 4 Preliminary Project Expenditures ......................................................................... 11Table 5 Project Deliverables ........................................................................................ 12-13Table 6 Level 2 WBS .................................................................................................. 16-25Table 7 Roles and Responsibilities Scope Change Management Process ....................... 26Table 8 Project Schedule .................................................................................................. 28Table 9 Summarized Budget ............................................................................................29Table 10 Quality Standards .............................................................................................. 31
Table 11 Quality Metrics ..................................................................................................32Table 12 Quality Management Approach .................................................................... 33-34Table 13 Quality Assurance......................................................................................... 34-36Table 14 Quality Control ............................................................................................. 37-38Table 15 Risk Management Strategies ......................................................................... 39-41Table 16 Risk Management Tools .................................................................................... 41Table 17 Data Sources ................................................................................................. 41-42Table 18 Risk Probability ................................................................................................. 42Table 19 Project Team ..................................................................................................... 43Table 20 Key Stakeholders .......................................................................................... 45-46Table 21 Resource Assignment ...................................................................................47-50Table 22 Project Reports........50Table 23 Project Meetings ................................................................................................ 51Table 24 Communication Summary ............................................................................ 52-53
7/30/2019 Automated Student Management System for South East Gippsland University - SPMP
5/67
Definitions
Term Definition
AD Architectural Design
ADD Architectural Design Document
ATP Acceptance Test Plan
DD Detailed Design
SDS Software Design DocumentITP Integration Test Plan
SCMP Software Configuration Management Plan
SM Senior Management
SPMP Software Project Management Plan
SQAP Software Quality Assurance Plan
SR Software Requirements
SRD Software Requirements DocumentSTD Software Transfer Document
STP Software Test Plan
SUM Software User Manual
SVVP Software Verification and Validation Plan
UR User Requirements
URD User Requirements Document
UTP Unit Test PlanVV Verification & Validation
WBS Work Breakdown Structure
WBS Level 2 WBS, where tasks are sub divided at most into 2 sub tasks
7/30/2019 Automated Student Management System for South East Gippsland University - SPMP
6/67
1) Introduction and Objectives of the Project Plan
1.1 Overview of the Organization
South East Gippsland University is a prestigious university in Australia. The South EastGippsland Student Management System Project is to provide a state of the art system tosupport the universities endeavours, teaching and research.
This project is attempting to revolutionize the service delivery to key stakeholders and fosterexcellence in teaching, research, and public service that will establish the University as a
leader among the nation's major research universities. This project will consolidate ITInfrastructure. Importantly it will:
Enable new voice and data applications to support the University's mission.
Provide a robust, flexible, ways of communication between students and theuniversity to meet the communications needs of our instructional faculty, researchers,and students.
Upgrade aging technology infrastructure and support the organization.
1.2 Current Situation and Problem/ Opportunity Statement
South East Gippsland University needs to replace its aging student management systems. Itruns on old technology, difficult and expensive to maintain, and does not provide theflexibility and services needed in a modern academic organization.
Implementing an appropriate replacement presents an opportunity to integrate newtechnology such as SMS communication with students (ie. for the delivery of results), anduse of social media (such as Facebook, YouTube and Twitter). This new integration increasesthe overall ability of students to communicate with the university and to facilitate thecommunication and feedback with students.
The ASMS Project will modernize the student management services and infrastructure at
South East Gippsland University. In order to achieve that target University will implement astate-of-the-art web based system to provide a higher level of service at lower cost forUniversity customers. The system will integrate the use of SMS and other social mediatechnology with the student management system.
The University's strategy is to replace all of its obsolete student management systems (student
7/30/2019 Automated Student Management System for South East Gippsland University - SPMP
7/67
1.3 Project Objectives
Here are some target benefits that will be accomplished by the Gippsland University afterimplementing the new integrated system.
A modern, state-of-the-art student management system. Integration with othertechnologies and applications.
Improved services for all staff and students (e.g., more streamlined processes formanagement of student enrolments, and results publications).
Quicker and more responsive action on new and change service requests andtroubleshooting.
Simplified billing.
No increase in rates or charges for students.
A more dependable, robust and secure network.
2) Project
2.1 Project Information
Project Start Date 1st of June 2012
Project End Date 2n of May 2015Project Manager Beth Storry
Project Sponsor Information Technology Services (ITS),South East Gippsland University
2.2 Project objectives
Accomplish project within defined budget. Accomplish project phases within relevant time parameters.
Deliver a Software Program which meets the organizational goals.
Deliver Proper Project Documentations. Feasibility Analysis. System Requirement Specification.
7/30/2019 Automated Student Management System for South East Gippsland University - SPMP
8/67
Table 1 Project Approach
Deliver Software documentation. End user manual. Installation documentation.
2.3 Project approach
2.4 Roles and Responsibilities
Name Role Phone Email Address
Project Approach Phases Description
Project Initiation All the project initiation approaches suchas allocating resources, establishing
environmentProject Planning Developing the project plans and
preparing the final Software ManagementProject Plan
Project Execution Under project execution process theresseveral sub processes. Those should haverun as a parallel processes throughoutproject execution phase.
Requirement Identification System Design
Implementation
Verification & Validation
Project Monitoring & Control
Documentation Development
Training
Installation In the installation phase all the hardwareand software systems installed.
Operation and Support Support for further operations of thesystem and required support for thesystem and staff.
Maintenance Maintain the system
Project Closure Finalize and end the project
7/30/2019 Automated Student Management System for South East Gippsland University - SPMP
9/67
Table 2 Roles & Responsibilities
Anne Panter Configuration Manager 0724526264 [email protected]
Hannah Macleod Quality Analyst 0712730729 [email protected]
Mark Knowles Database Engineer 0723424233 [email protected]
Jamie Dwyer Software Designer 0772323097 [email protected]
Liam de Young Validation Engineer 0782382327 [email protected]
Simon Orchard Verification Engineer 0712468075 [email protected]
Glenn Turner Consultant 0771245769 [email protected]
Chris Ciriello Installation Specialist 0729434740 [email protected]
Technical Writer 0783232394 [email protected]
Russell Ford Training Specialist 0773292928 [email protected]
Eddie Ockenden Help Desk Level 1 0718373427 [email protected]
Peter Samuels Human ResourceManager
0715879564 [email protected]
2.5 Project Constraints
Scope:
The solution is covering wide area we have to consider number of variables
when making the decisions
Time Schedule:
Project requires to be implemented within 24 months or less time frame andthe existing services have to be maintained continuously
Quality:
Delivered software should be a highly robust system. Because system will beused for very critical and sensitive processing such as student marks releasing,etc.
Budget Constraints:
7/30/2019 Automated Student Management System for South East Gippsland University - SPMP
10/67
2.6 Assumptions
Project Funding:Funding sources for the project will stably remain during the project execution time.
Hardware Facilities:All the hardware needed for the project will be provided and newly purchased. Therefor the according to the Australian law up to minimum 5 years manufacturers have toprovide insurance and maintain expenses have to bare.
Situational Changes:The Project Plan may change as new information and issues are revealed.
Project Budget:Upon the agreement we have agreed to calculate the profit based on the initial budgetup to 10%. Any change beyond that limit will be considered as the new base for theprofit calculation.
2.7 Preliminary Schedule and Budget Estimates
Schedule Estimated Duration (days)
Project Initiation 150
Project Monitoring &Control
650
Configuration Management 70
Software QualityManagement
150
System Allocation 20
Requirement 60
Design 180
Verification & Validation 350
Documentation Development 80
Training 270
Implementation 210
Installation 150
Operation & Support 21
Maintenance 7
Table 3 Preliminary Project Schedule
7/30/2019 Automated Student Management System for South East Gippsland University - SPMP
11/67
Table 4 Preliminary Project Expenditures
2.8 Plan Modification Rules
Theres several modification rules applied in this project.
General Modifications
All the general modifications which modification is independent from another area of theplan can be requested to modify via the project manager. Project manager is responsiblefor reviewing the requested modification and accept or decline the modification. And ifmodification accepted project manager responsible for inform the relevant stake holdersaffected by that modification.
Critical Modifications
Critical modifications such as critical paths, labor rates, schedules and other budgets thatare more likely to affect other areas by its modification in the project plan. This kind ofmodification also should be requested through project manager. After reviewing themodification, if manager feels that its a critical modification, Project manager shouldcall a meeting consists of relevant stakeholders and review further about the
modification. The modification decision will made according to the meeting conclusion.If any modification done in the project plan, project manager is responsible for informthe stake holders of the project.
2.9 Approval Signatures
Project Manager:
Project Expenditures
EstimatedCost (USD)
Employee Cost 3,000,000.00
Rent Fee 80,000.00
Insurance Cost 7,000.00
Software Cost 1,000,000.00
Hardware Cost 100,000.00
Administrative Cost 30,000.00
Legal Consultation 120,000.00
Total Cost 3,337,000.00
7/30/2019 Automated Student Management System for South East Gippsland University - SPMP
12/67
3) Project Scope Management plan
3.1 Product description
South East Gippsland Universitys SMS (Student Management System) runs on old
technology, difficult and expensive to maintain, and does not provide the flexibility and
services needed in a modern academic organization. Implementing an appropriate
replacement presents an opportunity to integrate new technology such as SMS
communication with students (i.e. for the delivery of results), and use of social media (such
as Facebook, YouTube and Twitter). It increases the overall ability of students to
communicate with the university and to facilitate the communication and feedback with
students.
The existing student management suite: Cannot utilize cost-effective new technology such as SMS and other social media.
Cannot be effectively maintained due to a scarcity of trained systems developers due
to the age of the system and the compartmentalised nature of previous enhancements
of the systems.
The new implementation will provide: A modern, state-of-the-art student management system. Integration with other
technologies and applications.
Improved services for all staff and students. (e.g., more streamlined processes for
management of student enrolments, and results publications)
Quicker and more responsive action on new and change service requests and
troubleshooting.
Simplified billing.
No increase in rates or charges for students.
A more dependable, robust and secure network.
3.2 Project Deliverables
Phase Deliverables To whom Format
UR URD
ATP
SM / Customer
SM / Customer
Paper and electronic form
Paper and electronic form
7/30/2019 Automated Student Management System for South East Gippsland University - SPMP
13/67
Table 5 Project Deliverables
SR SRD
STP
SM / Customer
SM / Customer
Paper and electronic form
Paper and electronic form
AD ADD
ITP
SM / Customer
SM / Customer
Paper and electronic form
Paper and electronic form
DD DDD
UTP
SUM
STD
Source code
SM / Customer
SM / Customer
Paper and electronic form
Paper and electronic form
Paper and electronic form
Paper and electronic form
Electronic form
3.3 Scope Statement
Project Title: Automated Student Management System (ASMS)
Date: 20th June 2012
Prepared by: Beth Storry, Project Manager, [email protected]
Project Justification: South East Gippsland University, requested this project be done toassist the university in meeting its strategic goals. This new system will increase visibility of
the university members as it will integrate new technology such as SMS (i.e. for the delivery
of results) and social media (such as Facebook, YouTube and Twitter). It will also help
improve profitability by reducing internal costs by providing standard tools and techniques.
Product-related deliverables within the scope (Includes)
a) Survey current consultants, university members and business case sponsor to help
determine desired content and features for the new student management system.
b) Evaluation of the requirements for the new system Desired content and features for the
7/30/2019 Automated Student Management System for South East Gippsland University - SPMP
14/67
d) Training sessions will be launched by the team for the university staff and other members.
All the training materials will be provided by the team except IT infrastructure.
e) A test plan will be documented how the site will be tested, who will do the testing, andhow bugs will be reported.
f) Full documentation of the system will be provided at the documentation phase. This will
be useful for the university in their future extensions.
g) Hardware and software installation will be done by the development team.
h)
Project beneficial measurement plan will be prepared in order to measure the financialvalue of the system.
i) IT help/service desk (both pre and post) will be provided by the development company.
j) Maintenance will be provided for the system for 21 days of time free of charge. Further
maintenance will be done under an added cost.
Excludes
a) Space for the system establishment should be provided by the university. Rent fee will be
paid by the development company according to the Australian rate.
b) Air-conditioning for the system establishment will be provided by the university.
c) New servers, wireless broadband hardware and software will be accommodated by theuniversity.
Project Success Criteria: Our goal is to complete this project within 2 years between
$3,500,000/= and $4,000,000/=. The project sponsor, South East Gippsland University, has
emphasized the importance of the project paying for itself within one year after the site is
completed. If the project takes a little longer to complete or costs a little more than planned, it
will still be viewed as a success if it has a good payback and helps promote our companys
image as a world class consulting organization.
3.4 Work Breakdown Structure Development
7/30/2019 Automated Student Management System for South East Gippsland University - SPMP
15/67
Project Manager, Software Architect, Programmer, Requirements Analyst, Configuration
Manager, Quality Analyst, Database Engineer, Software Designer, Verification & Validation
Engineer, Consultants, Technical writers, Installation Specialists, Human Resource Manager
and Programmers engaged in developing the WBS.
Note: Level 2 WBS structure is positioned here and the detailed WBS structure will be on the
Gant chart at the appendices.
7/30/2019 Automated Student Management System for South East Gippsland University - SPMP
16/67
ID SubID
Task Name Sub Task 1 Sub Task 2 ResourceName
Duration
1 1 Project
Initiation2 1.1 Selecting right
process model5 days
3 1.1.1 Analyze currentsituation &problem
ProjectManager
2 days
4 1.1.2 Identifyingobjective for the
project
ProjectManager
1 day
5 1.1.3 Identifying projectcharacteristics
ProjectManager
1 day
6 1.1.4 Selecting the idealprocess model
ProjectManager
1 day
7 1.2 Allocatingproject resources
60 days
8 1.2.1 Identify staffing
requirements
Project
Manager, HRManager
5 days
9 1.2.2 identify the assets ProjectManager
10 days
10 1.3 Establish projectenvironment
60 days
11 1.3.1 Identify & acquireequipments and
tools for theproject
ProjectManager
30 days
12 1.3.2 Installation,operation &maintenancemanual for theproject
ProjectManager
7 days
13 1.3.3 Based on the
requirement createa communicationplan
Project
Manager, HRManager
8 days
14 1.3.4 Establish adocumentationrepository
ProjectManager
1 day
7/30/2019 Automated Student Management System for South East Gippsland University - SPMP
17/67
Programmer
18 1.4.2 Create SPMP subplans
ProjectManager,RequirementsAnalyst,Programmer,Softwarearchitect, HRManager
60 days
26 1.4.3 Assemble baselineSPMP document
ProjectManager
4 days
27 1.4.4 Baseline SPMPcompleted
0 days
28 1.4.5 Create schedulebaseline
ProjectManager
2 days
29 1.4.6 Finalize projectcharter
120 days
30 2 ProjectMonitoring &
Control
650days?
31 2.1 Start the project 1 day
32 2.2 Analyze risks ProjectManager
10 days
33 2.3 Createcontingency plan
ProjectManager
10 days
34 2.4 Manage theproject
450 days
35 2.4.1 Project teammeetings
ProjectManager, HRManager
100 days
36 2.4.2 Retain records ProjectManager
30 days
37 2.4.3 Maintain projectcharter
ProjectManager
400 days
38 2.4.4 SPMP document
updates
Project
Manager
450 days
39 2.3 All projectdeliverables havebeen delivered
0 days
40 2.4 project closeout 0 days
41 3 Configuration 70 days
7/30/2019 Automated Student Management System for South East Gippsland University - SPMP
18/67
Identification
44 3.3 Configurationplan finalization
ConfigurationManager
10 days
45 3.4 SCMPcompleted
0 days
46 3.5 ConfigurationControl
ConfigurationManager
20 days
47 3.6 ConfigurationAuditing/Reporting
ConfigurationManager
20 days
48 4 Software
QualityManagement
150
days?
49 4.1 Plan softwarequalitymanagement
QualityAnalyst
2 days
50 4.2 Create SoftwareQualityAssurance Plan
(SQAP)
QualityAnalyst
25 days
51 4.3 SQAP completed QualityAnalyst
0 days
52 4.4 Define indicators QualityAnalyst
20 days
53 4.5 Manage softwarequality
QualityAnalyst
100 days
54 4.6 Identify quality
improvementneeds
Quality
Analyst
10 days
55 5 SystemAllocation
20 days
56 5.1 Analyzingsystem functions
SoftwareArchitect
5 days
57 5.2 Develop SystemArchitecture
SoftwareArchitect
10 days
58 5.2.1 IdentifyHardware/Software functions
5 days
59 5.3 Decomposesystemrequirements
SoftwareArchitect
5 days
7/30/2019 Automated Student Management System for South East Gippsland University - SPMP
19/67
develop softwarerequirements
Analyst
64 6.2 Define interface
requirements
10 days
65 6.2.1 Define ASMSsoftware interfacerequirements
RequirementsAnalyst
5 days
66 6.2.2 Define ASMShardware interfacerequirements
RequirementsAnalyst
5 days
67 6.2.3 Define ASMS user
interfacerequirements
Requirements
Analyst
5 days
68 6.3 Prioritize andintegraterequirements
20 days
69 Prioritize andintegrate softwarerequirements
RequirementsAnalyst
5 days
70 Prioritize andintegrate hardwarerequirements
RequirementsAnalyst
5 days
71 Prioritize andintegrate allrequirements
RequirementsAnalyst
10 days
72 6.4 Create SoftwareRequirement
Specification(SRS)
RequirementsAnalyst
7 days
73 6.5 SRS Completed 0 days
74 7 Design 180days?
75 7.1 Perform thearchitecturaldesign of the
system
40 days
76 7.1.1 Design thearchitecture of theintegrated system
SoftwareArchitect
20 days
77 7.1.2 Design thesoftware internal
SoftwareArchitect
20 days
7/30/2019 Automated Student Management System for South East Gippsland University - SPMP
20/67
central databasesystem
81 7.2.3 Provide weekly
updates
Database
Engineer
4 days
82 7.3 Design interfaces 50 days
83 7.3.1 Design userinterfaces
15 days
88 7.3.2 Design softwareinterfaces
SoftwareDesigner
10 days
89 7.3.3 Design hardware-software interfaces
SoftwareDesigner
10 days
90 7.4 SelectAlgorithms
SoftwareDesigner
10 days
91 7.5 Detail Design 80 days
92 7.5.1 Detail designsoftware interfaces
SoftwareDesigner
20 days
93 7.5.2 Detail design userinterfaces
SoftwareDesigner
20 days
94 7.5.3 Detail design
admin interfaces
Software
Designer
20 days
95 7.5.4 Create Softwaredesignspecification(SDS)
SoftwareDesigner
20 days
96 7.5.5 SDS completed 0 days
97 8 Verification &Validation
350days?
98 8.1 Plan verification
and validation
250 days
99 8.1.1 Plan requirementsverification andvalidation
Verification,ValidationEngineer andConsultant
15 days
100 8.1.2 Plan architectureverification andvalidation
Verification,ValidationEngineer and
Consultant
15 days
101 8.1.3 Plan interfacedesign verificationand validation
Verification,ValidationEngineer andConsultant
15 days
102 8 1 4 Plan database Verification 15 days
7/30/2019 Automated Student Management System for South East Gippsland University - SPMP
21/67
104 8.1.6 SVVP completed 0 days
105 8.2 Executeverification and
validation tasks
120 days
106 8.2.1 Verifyrequirements
VerificationEngineer
10 days
107 8.2.2 Validaterequirements
VerificationEngineer
10 days
108 8.2.3 Verify architecture VerificationEngineer
10 days
109 8.2.4 Validate
architecture
Verification
Engineer
10 days
110 8.2.5 Verify interfacedesign
VerificationEngineer
10 days
111 8.2.6 Validate interfacedesign
VerificationEngineer
10 days
112 8.2.7 Verify databasedesign
VerificationEngineer
10 days
113 8.2.8 Validate database
design
Verification
Engineer
10 days
114 8.3 Requirements &Design V&Vcompleted
0 days
115 8.4 Plan testing 120 days
116 8.4.1 Plan interfaceblack box testing
VerificationEngineer
8 days
117 8.4.2 Plan end User test Verification
Engineer
4 days
118 8.4.3 Plan admin panelinterface blackbox test
VerificationEngineer
15 days
119 8.4.4 Create SoftwareTest Plan (STP)
VerificationEngineer
10 days
120 8.4.5 STP completed 0 days
121 8.5 Develop test
requirements
40 days
122 8.5.1 Design interfaceblack box testing
VerificationEngineer
10 days
123 8.5.2 Design end Usertest
VerificationEngineer
10 days
124 8 5 3 Design admin Verification 10 days
7/30/2019 Automated Student Management System for South East Gippsland University - SPMP
22/67
128 8.6.3 Execute adminpanel interfaceblack box test
VerificationEngineer
5 days
129 8.7 V&V completed 0 days130 9 Documentation
development80 days
131 9.1 Plandocumentation
80 days
132 9.1.1 Define installationdocumentationcontents
TechnicalWriter
10 days
133 9.1.2 Define ASMSsoftwaredocumentationcontents
TechnicalWriter
10 days
134 9.1.3 Createdocumentationplan
TechnicalWriter
10 days
135 9.2 Implement
documentation
40 days
136 9.2.1 Write installationdocumentation
TechnicalWriter,InstallationSpecialist
10 days
137 9.2.2 Write ASMSdocumentation
TechnicalWriter,Consultant
10 days
138 9.3 Produce anddistributedocumentation
30 days
139 9.3.1 Print installationdocumentation
Help DeskLevel 1
2 days
140 9.3.2 Print ASMSsoftwaredocumentation
Help DeskLevel 2
2 days
141 9.3.3 Distributeinstallationdocumentation toinstallers
ProjectManager
5 days
142 9.4 Documentationcompleted
0 days
7/30/2019 Automated Student Management System for South East Gippsland University - SPMP
23/67
147 10.1.3 Plan softwaremaintenancetraining content
TrainingSpecialist
10 days
148 10.2 Develop trainingmaterials
240 days
149 10.2.1 Create installationtraining content
TrainingSpecialist
10 days
150 10.2.2 Create systemtraining materials
TrainingSpecialist
10 days
10.2.3 Create softwaremaintenance
training materials
TrainingSpecialist
10 days
10.3 Validate trainingprogram
240 days
10.3.1 Validateinstallationtraining content
TrainingSpecialist
2 days
10.3.2 Validate systemtraining materials
TrainingSpecialist
2 days
151 10.3.3 Validate softwaremaintenancetraining
TrainingSpecialist
2 days
152 10.4 Implement thetraining program
240 days
153 10.4.1 Hold trainingsession for endusers
TrainingSpecialist
10 days
154 10.4.2 Hold trainingsession forsoftwaremaintenance team
TrainingSpecialist
20 days
155 10.4 Trainingcompleted
0 days
156 11 Implementation 210days?
157 11.1 Create test data VerificationEngineer
5 days
158 11.2 Create sourcecode
200 days
159 11.2.1 Code ASMSsoftware-to-
Programmer 40 days
7/30/2019 Automated Student Management System for South East Gippsland University - SPMP
24/67
163 11.3.1 Generate ASMSsoftware-to-hardware interface
object code
Programmer 3 days
164 11.3.2 Generate ASMSsoftware interfaceobject code
Programmer 3 days
165 11.3.3 Generate ASMSuser interfaceobject codegeneration
Programmer 3 days
166 11.4 Plan integration 100 days167 11.4.1 Plan integration of
ASMSsoftware/hardwareinterface andsoftware
Programmer 5 days
168 11.4.2 Plan integration ofASMS software
with userinterfaces
Programmer 5 days
169 11.5 Performintegration
80 days
170 11.5.1 Integrate ASMSsoftware/hardwareinterface withsoftware interface.
Programmer,DatabaseEngineer
10 days
171 11.5.2 Integrate ASMSsoftware with userinterfaces
Programmer 10 days
172 11.6 Implementationcompleted
0 days
173 12 Installation 150 days
174 12.1 Plan installationof the ASMS
InstallationSpecialist
10 days
175 12.2 DistributeSoftware 20 days
176 12.2.1 Distribute ASMSto the installationteam
InstallationSpecialist
1 day
177 12.3 Install software 70 days
7/30/2019 Automated Student Management System for South East Gippsland University - SPMP
25/67
Table 6 Level 2 WBS
3.5 Scope Change Management Process
3.5.1 Scope of Change Requests
1. Modifications to software.
2. Acquisition of third party software.
3. Changes to contracted professional services (e.g. additional consultancy assistance).
4. Scope (includes modules, data conversion and migration, interfaces, etc.).
5. Milestone dates and major go-lives.
6. Additional project spending (hardware, training and conferences).
7. Functionality required by policy changes at the university and/or external mandates.
3.5.2. Change Request Process
Specialist
181 12.6 InstallationCompleted
0 days
182 13 Operation &Support
7 days
183 13.1 Operate thesystem
Help DeskLevel 1
2 days
184 13.2 Provide technicalassistance andconsulting
Help DeskLevel 1
2 days
185 13.3 Maintain support
request log
Help Desk
Level 1
4 days
186 14 Maintenance 21 Days
187 14.1 Re-applySoftwareDevelopmentLife Cycle
Consultant 21 days
7/30/2019 Automated Student Management System for South East Gippsland University - SPMP
26/67
3. Project Manager prepares and submits Change Request Impact Analysis section and
submits to the Change Management Team.
4. Institution Implementation Team receives weekly updates of pending change requests andprovides input as needed / requested.
5. Change Management Team approves/denies change request after the clarification, provides
final recommendation on the Change Request Form and advises Project Manager.
6. If appropriate, forward for review and disposition.
7. Project Manager converses the decision to:
a. The Team Lead making the request of the Change Review Team decision.
b. Implementation Team.
c. All appropriate interested parties.
8. Amend Scope Management Plan and documentation as needed to incorporate sanctioned
change.
3.5.2. Roles and Responsibilities
Team Leads Instigate change requests based on implementation
needs using approved forms and communication
processes. Requests from team members should be
discussed with the appropriate Team Lead prior to
submitting an official change request.
Project Manager Facilitate the completion of change requests and
information gathering. Work directly with vendors
and with appropriate IT personnel, administrative
and academic to collect information needed to
complete the request.
Implementation Team Receives updates of completed change requests
awaiting approval. Provide input as
needed/requested.
Change Review Team Evaluates, allow or disallow change requests based
7/30/2019 Automated Student Management System for South East Gippsland University - SPMP
27/67
3.5.3. Notes
Requests resulting in changes to the vendor contract require approval from the Project
Sponsor.
No changes to the contract should be proceeded upon or conveyed as an approved change
until Change Review Team have verified that they are in agreement with the original
contract.
Changes to software, budget, quality and schedule will be reviewed, managed and approved
by the Project Manager.
First priority will be given to change requests for acute functions and services. Other criteria
for evaluating change requests will be approved by the Change Review Team.
Project Scope Change Management Plan Documents:
Change Request Form
Change Request Log
Scope Change Management Plan
3.5 Plan Modification Rules
1.
Analyse the current project scope management plan to determine if this modification mayimpact project costs, resources, quality and the other directions of the project. If it is an
insignificant change for the better, team may not need to escalate this further than those
directly affected by the plan change. Project manager has the authority to change this
plan.
2. Meet with the project team members and vendors potentially impacted by the project plan
change. Gather their feedback on how much time and resources this change may take.
Ask their opinions on the feasibility of the change and if it may cause a barrier to project
completions or time lines.
3. Meet with project sponsors, stakeholders and management to discuss the change. Seek out
their approval before moving forward if this is a significant change to either the outcome
7/30/2019 Automated Student Management System for South East Gippsland University - SPMP
28/67
5. Distribute the project management plan to the project team and sponsors. Post internallyon a shared site or intranet and solicit feedback. Do not hide the change if everyone needsto know it and be forthcoming with how the change may or may not impact the project.
4) Schedule management plan
4.1 Project Schedule
This section contains information about Automated Student Management System (ASMS)project schedule. A list of the milestones and their completion days are included in this
section, while the detailed Gantt chart is included in the appendices.
WBS ID Milestone Date Responsible Roles
1.5.9 Baseline SPMP completed Fri 12-12-07 Project Manager
1.6 Finalize project charter Fri 13-03-15 Project Manager
2.5 All project deliverables have
been delivered
Tue 14-11-17 Project Manager
3.4 SCMP completed Fri 13-07-26 Configuration Manager
4.3 SQAP completed Mon 13-06-24 Quality Analyst
5.4 System allocation completed Mon 13-06-24 Software Architect
6.5 SRS Completed Fri 13-08-23 Requirements Analyst
7.5.5 SDS completed Fri 14-02-28 Software Designer
8.1.6 SVVP completed Thu 14-09-04 Verification Engineer,Validation Engineer, Consultant
8.4.5 STP completed Fri 14-06-27 Verification Engineer
8.7 V&V completed Mon 14-10-27 Verification Engineer
9.4 Documentation completed Thu 14-05-01 Technical Writer, Installation
Specialist, Consultant, HelpDesk Level 1, Project Manager
10.5 Training completed Mon 14-11-17 Training Specialist
11.6 Implementation completed Fri 14-10-10 Programmer
7/30/2019 Automated Student Management System for South East Gippsland University - SPMP
29/67
4.2 Assumptions
1. This schedule is for 2 years of time while Saturdays and Sundays have been left as non-
working days. Corresponding project team members will be working for 8 hours eachworking day.
2. The Project Schedule may change as new information and issues are revealed.
5) Cost Management Plan
5.1 Project Budget
Budget Report - ASMS Project South East Gippsland University (2012-2015)ID Project Expenditures Rate(USD) Cost(USD)
* Stated under assumptions
1 Employee Cost1.1 Labor Cost $2,074,144.00
1.2 Food & Beverage 12$/hour $210,528.00
2 Rent Fee* $800/Week $76,800.00
3 Insurance Cost
3.1 Employee*$150 for $50000Labor cost $6,222.43
3.2 Equipment* $0.00
4 Software Cost4.1 Student Management System(TCO) $900,000.00
4.2 Software Development Kit(SDK) $25,000.00
4.3Microsoft Office 2010
$495/Year $2,970.00
4.4 Testing Tools $1000/machine $3,000.00
5 Hardware Cost5.1 New Servers TCO $30,000.00
5.2 Wireless Broadband Hardware $50,000.005.3 Wireless Broadband Hardware Maintenance $5000/annum $10,000.00
6 Administrative Costs6.1 IT Service Desk $20,000.00
6 2 Ad i i t ti b d t $5 000 00
7/30/2019 Automated Student Management System for South East Gippsland University - SPMP
30/67
5.2 Budget Assumptions & Constraints
Assumptions
1. All the cost calculations will be calculated in the form of United States Dollars (USD).
2. Since the workspace is given by the university, we assume that all electricity, water andsanitary facilities will be provided by the university.
3.
In Australia an employer have to spend $150 per every $50000 as insurance cost.
4. All the equipments will be purchased newly for the project and according to theAustralian low seller have to bare the insurance cost for the equipments for first 5 years.
5. Upon the agreement we have agreed to calculate the profit based on the initial budget upto 10%. Any change beyond that limit will be considered as the new base for the profitcalculation.
6. Funding sources for the project will stably remain during the project execution time.
Constraints
1. All the labor costs are calculated based on the rates available on the current marketsituation and it signifies 55.6% of total cost ($2,289,864/ $4,113,034). Since we donthave direct control over human resources and we are directly exposed to fluctuations of
the market rates.
2. Since the project team is allocated after a tendering procedure, SixSigma has to use theirprevious knowledge in budget estimation which is a crucial point of a plan.
3. Since the profit was calculated based on the initial budget any expenditure beyond theinitial limit will be subjected to consideration of the Change Review Team.
4. If the budget goes beyond the 10% buffer soon, expenditures have to be rationalizedbefore the client.
5. Class 1 budget estimate has been used in this project with the consideration of theproject nature. It is a deterministic approach. Further details are added in the appendix A.
7/30/2019 Automated Student Management System for South East Gippsland University - SPMP
31/67
6) Quality Management Plan
6.1 Quality Standards
Project Processes/Reports Quality Standards
Project Initiation IEEE 1058-1998IEEE[1] 1074-1997Project Initiation Check List[2]
Project Monitoring & Control IEEE 1058-1998
IEEE 1074-1997IEEE 828-1998IEEE 730-2002IEEE 1012-1998 + IEEE 1012a-1998IEEE 830-1998IEEE 829-1998IEEE 1016-1998Project Monitoring & Control CheckList
Configuration Management IEEE 828-1998Configuration Management Check List
Software QualityManagement
IEEE 730-2002Quality Management Check List
System Allocation N/A[3]
Requirement Analysis IEEE 830-1998Requirement Analysis Check List
Design IEEE 1016-1998
Verification & Validation IEEE 1012-1998 + IEEE 1012a-1998IEEE 829-1998V&V check list
Documentation development IEEE 1063-2001
Training Training Check List
Implementation Implementation Check List
Installation N/A
Operation & Support N/A
Maintenance N/A
7/30/2019 Automated Student Management System for South East Gippsland University - SPMP
32/67
Table 11 Quality Metrics
6.2 Quality Metrics
Notes:[1] Kilo Lines Of Code
Project Deliverables Quality metrics
Software Product Functional Point AnalysisLines of CodeCustomer Satisfaction (Usability)Response TimeBugs per KLOC[1] (Correctness)FunctionalityComments per KLOC
Software DesignSpecification (SDS)
CorrectnessIntegrity
Software ProjectManagement Plan(SPMP)
CorrectnessIntegrityCustomer Satisfaction / Acceptance
Software ConfigurationManagement Plan(SCMP)
CorrectnessIntegrity
Software QualityAssurance Plan(SQAP)
CorrectnessIntegrity
Software Verificationand Validation Plan(SVVP)
CorrectnessIntegrity
Software RequirementsSpecification(SRS)
CorrectnessIntegrity
Software Test Plan(STP)
CorrectnessIntegrity
Software RiskManagement Plan(SRMP)
CorrectnessIntegrity
Software User Manual CorrectnessIntegrity
Customer Satisfaction / AcceptanceEnd User Training Customer Satisfaction
7/30/2019 Automated Student Management System for South East Gippsland University - SPMP
33/67
6.3 Quality Management Approach
The quality management approach of this Automated Student Management System (ASMS)project will establish and ensure the required quality of the project deliverables and itsprocesses. Considering in the higher level quality management perspective, this project willfollow the traditional quality management phases to establish required quality of the project.According to traditional quality management approach quality planning, assuring andcontrolling are the three main phases which taken place in quality management.
At the initial phase of the quality management approach will focus into define or deriverequired quality standards, quality metrics and tools to gain the expected quality of theproject and its deliverables. The next phase is Quality Assurance (QA) which ensures thatproject processes are used effectively to produce quality project deliverables.
The approaches for quality assurance phase will describe in detail under Quality Assurancetopic of this document. Final step of the quality management approach is Quality Controlling(QC) phase that monitors the project deliverables to verify that the deliverables haveacceptable quality and the customer is satisfied. In detail description about QC process willprovide under Quality Control topic of this document.
Following tools will be used to support the quality management process throughout the QAand QC phases of the project.
Phase Tool Tool Description
Qual
ityAssurance
Quality Audits Quality audit is an essential quality assurance toolused in assessing process successfulness of the
projects. Quality audit is a systematic approach toidentify the problems in project processes and reportinefficiencies for improvements. Quality analysts areresponsible for performing the quality audits atpredefined intervals to ensure the quality of theproject processes
Process Analysis Process analysis is a set of logically related
instructions which aimed for continuous improvementof project processes.
Benchmarking Comparing project processes with another comparableproject
Flow Charting Flow charts are various kinds of diagrams used to
7/30/2019 Automated Student Management System for South East Gippsland University - SPMP
34/67
Table 12 Quality Management Approach
processesStatistical Sampling Statistical process control is a quality control method
which uses statistical methods to monitor and control a
process. That ensures the process operates with its fullpotential.
Control Charts Control charts are statistical process controlling methodused for quality control.
Standards and matrices for quality can be identified by any stake holder of the project. Projectmanager responsible for review the standards, matrices to determine cost versus benefit and
how processes or deliverables affected by that standard or metric. If a standard or metricimplemented, project manager should update all related project documentation for qualitymanagement.
6.4 Quality Assurance
Quality assurance ensures that project processes are used effectively to produce quality
project deliverables In order to ensure quality; an iterative quality process will be usedthroughout the project life cycle. This iterative process includes measuring process metrics,analyzing process data, and continuously improving the processes.
Quality manager and the quality team will perform assessments at planned intervalsthroughout the project to ensure all processes are being correctly implemented and executed.Process improvement is another aspect of quality assurance. Quality assurance reviews,findings, and assessments should always result in some form of process improvement and, as
a result, product improvement. All process improvement efforts must be documented,implemented, and communicated to all stakeholders as changes are made.
Following table describes the quality assurance plan for the project processes.
Project Process QualityStandardsStakeholderExpectations
QualityAssurance
Activity
Frequency/Interval
ResponsiblePerson(s)
ProjectInitiation
SPMPSPMP CheckList
Planning theupcoming sub
tasks with
After every subtask have beencompleted
ProjectManager
7/30/2019 Automated Student Management System for South East Gippsland University - SPMP
35/67
process analysis.Implement anyimprovements
identifiedProjectMonitoring &Control
SPMP, SRS,SDS, SQAP,SVVP, STP,SCMP, SRMP,ProjectMonitoring &Control Check
List
Normal qualityaudits and
process analysis.If any exceptionalsituation occurs,additional QA
activities such as
Benchmarkingand fishbonediagrams will use
to identify theproblems.
Weekly ProjectManager
ConfigurationManagement
SCMPSCMP CheckList
Analyze theprocess andimplementidentified
improvements
After eachiteration of thesoftware in theprojectexecution
ProjectManager,ConfigurationManager
SoftwareQualityManagement
SQMPSQMP CheckList
Audit the qualitysystem. Identifyquality problems
and needs.Improve the
quality system
Weekly,throughout theproject.
ProjectManager,Quality Analyst
System
Allocation
N/A[*]
Requirement SRSSRS Check List
Audit and analyzethe requirement
identifying,validation anddocumentation
process.Eliminate the
problemsidentified andimprove the
process.
Weekly, in therequirementphase.
ProjectManager,RequirementAnalyst
Design SDSSDS Check List
Review theprogress of
Weekly, in thedesign phase
ProjectManager
7/30/2019 Automated Student Management System for South East Gippsland University - SPMP
36/67
Table 13 Quality Assurance
Verification &Validation
SVVPSVVP CheckList
Review the V&Vprocess progress.
Identify the
inconsistencieswith the V&V
standards.Eliminate the
issues.
Weekly, in theV&V phase
Verification,ValidationEngineer and
Consultant
DocumentationDevelopment
IEEE 1063-2001
Review thedocumentationcontents and
progress. Identifytheinconsistencies
and issues.Improve the
documentationquality
Weekly TechnicalWriter
Training Training CheckList
Peer review thetraining progress.
Improve thetraining process.
Weekly, Whentraininghappens.
TrainingSpecialist
Implementation ImplementationCheck List
Review theimplemented
source codes withdesign andidentify the
inconsistencies.
Audit the sourcecode relevant
matrices to ensurethe quality.Execute a
resolution plan.
Weekly, in theimplementationphase.
Programmer
Installation N/A[*]
Operation &Support N/A
[*]
Maintenance N/A[*]
Note:[*] D t ti t d th t i t lit ill t b f d f th
7/30/2019 Automated Student Management System for South East Gippsland University - SPMP
37/67
6.5 Quality Control
Quality control ensures that project deliverables complies with quality standards and
customer satisfied with the deliverable.
ProjectDeliverable
Quality Standards/Customer
Satisfaction
QualityControlActivity
Frequency/Interval
ResponsiblePerson(s)
SoftwareProject
ManagementPlan (SPMP)
Document mustcomplies with
following StandardsIEEE 1058-1998IEEE 1074-1997
Review byProject
Sponsor
After plan hasdelivered
ProjectManager
SoftwareConfigurationManagementPlan (SCMP)
Document mustcomplies with
following StandardsIEEE 828-1998
Review byProject
Manager
After plan hasdelivered
ConfigurationManager
SoftwareQualityAssurance Plan(SQAP)
Document mustcomplies with
following StandardsIEEE 730-2002
Review byProject
Manager
After plan hasdelivered
QualityAnalyst
SoftwareVerificationand ValidationPlan (SVVP)
Document mustcomplies with
following StandardsIEEE 1012-1998 +IEEE 1012a-1998
Review byProject
Manager
After plan hasdelivered
VerificationEngineer ,Consultant ,ValidationEngineer
Software
RequirementsSpecification(SRS)
Document must
complies withfollowing Standards
IEEE 830-1998
Review by
RequirementsAnalyst and
ProjectManager
After
document hasdelivered
Requirements
Analyst
Software TestPlan (STP)
Document mustcomplies with
following StandardsIEEE 829-1998
Review byProject
Manager
After plan hasdelivered
VerificationEngineer
SoftwareDesignSpecification(SDS)
Document mustcomplies with
following StandardsIEEE 1016-1998
Review byProject
Manager
After plan hasdelivered
System Designer
Software RiskManagement
Document mustcomplies with
Review byProject
After plan hasdelivered
Project Manager
7/30/2019 Automated Student Management System for South East Gippsland University - SPMP
38/67
Table 14 Quality Control
Average customersatisfaction rating
should be above 7.0
Review andrated the
satisfaction by
the usersusing 0 to 10satisfaction
scale.SoftwareSource Code
Bugs per KLOC < 5 Codewalkthroughs
and AlphaTesting
After sourcecode for eachiteration havedelivered
Programmer
Response Time 100
Codewalkthroughs
User Training
Average usersatisfaction rating
should be above 8.0
Review andrated the
satisfaction bythe users
using 0 to 10satisfaction
scale.
After usertraining
finished
TrainingSpecialist
Review
Reviewing a deliverable documentation or work products, particularly for consistency with
the higher-level plans on which the document is based (i.e. design consistency with
requirements, source code consistent with design). Inconsistencies will be noted and an
action plan for resolution produced. Inspection of a document for compliance with the
standard or template on which mentioned in the table should be carried out within the project
7/30/2019 Automated Student Management System for South East Gippsland University - SPMP
39/67
7) Risk Management
7.1 Risk Management Strategies
Risk management is aimed to identification measurement of risks and prioritizing them. Inrisk management we are more focused on risks that are more probable and effect more for theproject
ProcessName
Process Description
1.0 Establishingthe context
1.1 Factors thatmay effect
Physical An electrical failure
Long working hours and bad siting positionsFinancial
Over expenditureLegal
Client may sue against company
Employee may sue against company
Environmental Bad environmental conditions.
1.2 Stakeholderswho need to beinvolved
University maintain staff
Employees of the project
Project manager
University administrative staff
Lectures of the university
Local government
1.3 risk criteriaidentified
Likelihood of death or serious injury
Likelihood of decreasing profitability
Likelihood of litigation
Likelihood of inclement weather
2.0 Identify theRisks 2.1 To identify therisk
Looked at the records of previous accidents of theuniversity
Inspect the area provide and get advice fromengineers
Interview the stakeholders
Check financial stability of the university
7/30/2019 Automated Student Management System for South East Gippsland University - SPMP
40/67
Legal that caused due to breech of agreement withthe client
2.3 Major risksidentified
Employee problems due to bad seating positions Fluctuations in labor rates
If there is heavy rains its hard to continue theproject
If the implementation process was crashed withstudent management system client may sue for thefinancial damages
3.0 Analyze the
Risk
3.1 Evaluate the
effect againstprobability
Likelihood Low Likelihood High
ConsequencesLow
If theimplementationprocess wascrashed withstudentmanagementsystem client maysue for the financial
damages
Employee problemsdue to bad seatingpositions
ConsequencesHigh
If there is heavyrains its hard tocontinue theproject
Fluctuations inlabor rates
4.0 Evaluate
the Risk
4.1 whether a risk isacceptable
High probable high Consequences risks need to be gettingmore concern. Employee problems due to bad seatingpositions is a risk need our concern. Flood problem is aconcern that needs our attention.
5.0 Manage theRisks
5.1 Avoid the risk,Control the risk,Transfer therisk orRetain the risk
1. Fluctuations in labor rates - Avoid the riskMaking arrangement with client to calculateprofit on the proposed budget +/- 10% ofinitial figure and beyond that limit willconcern as the new base for profit
calculation2. Employee problems due to bad seating
positions - Control the riskConducting training sessions on properpositions and insuring
7/30/2019 Automated Student Management System for South East Gippsland University - SPMP
41/67
Table 16 Risk Management Tools
Table 15 Risk Management Strategies
7.2 Risk Management Tools
Risk management tools are mainly used to measure the magnitude of a risk and probability
and they help to calculate and rank the risks
Tool Name Tool Description
1.0 Risk Register Acts as a central repository for all risks recognized by the project or businessand, for each risk, consist of information such as risk likelihood, impact,counter-measures, risk holder
2.0 SAPHIRE Probabilistic risk and reliability assessment software tool. SAPHIRE standsfor Systems Analysis Programs for Hands-on Integrated Reliability
Evaluations.
7.3 Data Sources
riskLet the university staff to decide what timewe are going to conduct integration to the
main system
6.0 Review 6.1 monitor andevaluate
Need to constantly monitor and evaluate the strategies thatare using to manage risks, as risks do not remain the same.There may find that over time new risks are created,existing risks are increased or decreased, some risks nolonger exist and risk management strategies are no longereffective.
Category Data Source Name Data Source Description
1.0 Weather1.1 Local environment agency
area officesThere does not appear to be a singledatabase of historical flood events(maps) or arecord of their outcomes
l il i ll l l il
7/30/2019 Automated Student Management System for South East Gippsland University - SPMP
42/67
Table 17 Data Sources
7.4 Risk Categories
These are the areas that may likely to contain risks (Refer risk strategies factors that mayaffect).
Physical
Financial
Legal
Environmental
7.5 Risk Probability and Impact
2.0 Health
2.1 Health and safety - Australia Provide detail guide to employee healthand free consultation services
3.0 Financial3.1 Banks Provide detail of financial history of
university and its credibility
3.2 Other contractors to theuniversity
Not a very official way of gatheringinformation but valuable source ofinformation
4.0 Legal
4.1 Company legal officer Provide initial bases for the legal risk
identification4.2 Consultants Provide in deep assessment of legal
environment
Item Probability(P)
Impact (I) Total RiskScore
1.0 Employee problems due to bad seating positions 0.8 3 2.4
2.0 Fluctuations in labor rates 0.6 8 4.8
3.0 If there is heavy rains its hard to continue theproject
0.3 9 2.7
4.0 If the implementation process was crashed with 0.2 5 1
7/30/2019 Automated Student Management System for South East Gippsland University - SPMP
43/67
Table 19 Project Team
8) HR management plan
8.1 Project Organization
8.1.1 Project Team
This list would include the information of project manager and all the team members whowill be involved with the planning and execution of the project.
Name Role PhoneNumber
Email Address
Beth Storry Project Manager 0778442010 [email protected]
Emily Maguire Software Architect 0711993060 [email protected]
LauraUnsworth
Programmer 0717625535 [email protected]
Crista Cullen Requirements Analyst 0719251470 [email protected]
Anne Panter Configuration Manager 0724526264 [email protected]
HannahMacleod
Quality Analyst 0712730729 [email protected]
Mark Knowles Database Engineer 0723424233 [email protected]
Jamie Dwyer Software Designer 0772323097 [email protected]
Liam de Young Validation Engineer 0782382327 [email protected]
Simon Orchard Verification Engineer 0712468075 [email protected]
Glenn Turner Consultant 0771245769 [email protected]
Chris Ciriello Installation Specialist 0729434740 [email protected]
MatthewButturini
Technical Writer 0783232394 [email protected]
Russell Ford Training Specialist 0773292928 [email protected]
Eddie
Ockenden
Help Desk Level 1 0718373427 [email protected]
Peter Samuels Human ResourceManager
0715879564 [email protected]
7/30/2019 Automated Student Management System for South East Gippsland University - SPMP
44/67
8.1.1.1 Hierarchy of the project team
Sponsor
InformationTechnologyServices
Consultant
Project Manager
Configuration Manager Software Architect
Design & Development
Software Designer
Programmer
Analysis
Requirements Analyst
Quality Analyst
Database Handling Database Engineer
Testing & Installation
Validation Engineer
Verification Engineer
Installation Specialist
Operation & Support
Help Desk Level 1
Technical Writer
Training Specialist
7/30/2019 Automated Student Management System for South East Gippsland University - SPMP
45/67
UCSC ICT 2009 IT Project Management Assignment 2012 | Page 45 of60
8.1.2 Key Stakeholders
Information
Technology
Services
Gilbert Roks Beth Storry Emily Maguire,
Crista Cullen,
Anne Panter,
Hannah Macleod,
Mark Knowles,
Jamie Dwyer,
Liam de Young,
Simon Orchard,Glenn Turner,
Chris Ciriello,
Matthew Butturini,
Russell Ford,
Eddie Ockenden
Role on Project ProjectSponsor
ChiefInformation
Officer (CIO)
Project Manager Project Team Students Lecturers AdministrativeStaff
Organization South East
Gippsland
University
SouthEast
Gippsland
University
MIT Company MIT Company South East
Gippsland
University
South East
Gippsland
University
South East
Gippsland
University
Contact
Information
southeastgip
om
gilbertroks@gm
ail.com
bethstorry@gmail
.com
itpm-group-
7/30/2019 Automated Student Management System for South East Gippsland University - SPMP
46/67
UCSC ICT 2009 IT Project Management Assignment 2012 | Page 46 of60
Table 20 Key Stakeholders
Unique Facts Prefers use
of email forproject
documents
Responsible for
Develop,maintain, and
facilitate
implementation
of a sound and
integrated IT
architecture as
such they
require more
detailedcommunications
Manages day to
day resources,provides project
guidance and
monitors and
reports on the
projects metrics
Need to have a clear
understanding of thework to be completed
and the framework in
which the project is to
be executed.
Level of
Interest
High High High High Medium Medium Medium
Level of
Influence
High High High High Low Low Low
Suggestions for
managing
relationships
Keep
informed of
all projectprogress
Keep all
information
about theproject progress
He is the primary
communicator for
the projectdistributing
information
according to this
Communications
Management Plan
Require a detailed
level of
communicationswhich is achieved
through day to day
interactions with the
Project Manager and
other team members
along with weekly
team meetings
Keep
informed
aboutcurrent
changes and
can get
feedback to
assist the
progress
Keep
informed
about currentchanges and
can get
feedback to
assist the
progress
Keep informed
about current
changes and canget feedback to
assist the
progress
7/30/2019 Automated Student Management System for South East Gippsland University - SPMP
47/67
8.2 Resource Requirements
Following chart depicts you how the resources will be used within each month. This graph
helps you to analyse the resource usage of the project. The team members of the project have
to engage with different type of tasks & activities. They should be responsible for each task
& activities that they have been assigned.
8.3 Resource Assignment
.
Note: Here we have assigned resources according to the Level 2 WBS. Further informationcan be perceived in the Gantt chart at the appendices.
8.3 Resource Assignment
WBS
Tasks anager
Architect
mer en
tsAnalyst
tionManager
nalyst
Engineer
Designer
nEngineer
onEngineer
t nSpecialist
Writer
Specialist
kLevel1
ger
Figure 2
0
200400
600
800
1000
1200
1400
1600
1800
June
August
October
December
February
April
June
August
October
December
February
April
June
August
October
December
February
2012 2013 2014 2015
Resources Allocation - Hours Per MonthHR Manager
Help Desk Level 1
Training Specialist
Technical Writer
Installation Specialist
Consultant
Verification Engineer
Validation Engineer
Software Designer
Database Engineer
Quality Analyst
Configuration Manager
Requirements Analyst
Programmer
Software Architect
Project Manager
Hours
7/30/2019 Automated Student Management System for South East Gippsland University - SPMP
48/67
1.3 Establish project environment X X
1.4 Plan project management X X X X X
2 Project Monitoring & Control X X
2.1 Start the project X
2.2 Analyze risks X
2.3 Create contingency plan X
2.4 Manage the project X X
2.5All project deliverables have beendelivered
X
2.6 project closeout X3 Configuration Management X
3.1 Plan configuration management plan X
3.2 Configuration Items Identification X
3.3 Configuration plan finalization X
3.4 SCMP completed X
3.5 Configuration ControlX
3.6 Configuration Auditing/Reporting X
4 Software Quality Management X
4.1 Plan software quality management X
4.2Create Software Quality AssurancePlan (SQAP)
X
4.3 SQAP completed X
4.4 Define indicators X
4.5 Manage software quality X
4.6 Identify quality improvement needs X
5 System Allocation X
5.1 Analyzing system functions X
5.2 Develop System Architecture X
5.3 Decompose system requirements X5.4 System allocation completed X
6 Defining Requirements X
6 1Define and develop softwarerequirements
X
7/30/2019 Automated Student Management System for South East Gippsland University - SPMP
49/67
7.1Perform the architectural design ofthe system
X
7.2 Design the database X
7.3 Design interfaces X
7.4 Select Algorithms X
7.5 Detail Design X
8 Verification & Validation X X X
8.1 Plan verification and validation X X X
8.2
Execute verification and validation
tasks
X
8.3Requirements & Design V&Vcompleted
X
8.4 Plan testing X
8.5 Develop test requirements X
8.6 Execute the tests X
8.7 V&V completed X
9 Documentation development X X X X X
9.1 Plan documentation X
9.2 Implement documentation X X X
9.3Produce and distributedocumentation
X
9.4 Documentation completed X
10 Training X
10.1 Plan training program X
10.2 Develop training materials X
10.3 Validate training program X
10.4 Implement the training program X
10.5 Training completed X
11 Implementation X X
11.1 Create test data X
11.2 Create source code X
11.3 Generate object code X
11.4 Plan integration X
12 4 H d i ll i X
7/30/2019 Automated Student Management System for South East Gippsland University - SPMP
50/67
Table 21 Resource Assignment
*Assumption: Resources for the project will stably remain during the project execution
time.
9) Communication plan
9.1 Stakeholder Analysis
*Refer 8.1.2
9.2 Project Reports
Data Needed FrequencyofCollection
ResponsibleParty forDataCollection& Analysis
Report Media& Format
ResponsibleParty forDistributingReport
Project Status
Dashboard/report
Tracking
Gantt Chart
Weekly Beth Storry Status Form Eddie Ockenden
Trend Analysis Past projectdata,PreviousStatus reports
Monthly CristaCullen
Printeddocument withcalculations
Crista Cullen
Variance Analysis Proposed Bi weekly Mark Through e Mark Knowles
12.4 Hardware installation X
12.5Accept software in operationalenvironment
X
12.6 Installation Completed X X
13Operation & Support X
13.1Operate the system X
13.2Provide technical assistance andconsulting X
13.3Maintain support request log X
14 Maintenance X
14.1Re-apply Software DevelopmentLife Cycle
X
proposed
7/30/2019 Automated Student Management System for South East Gippsland University - SPMP
51/67
Table 22 Project Reports
proposedbugdet
9.3 Project Meetings
Purpose Frequency Attendees Reporting Requirements
Status ReviewMeeting
Update onprojectstatus,Informand identifyproblems andidentyfy
posssibleaction items
Weekly(Monthly withthe ITSreperesentativeand GilbertRoks)
All of theprojectteam,GilbertRoks,ITSrepresentative(ifneeded)
Meeting Minutes,varianceand trend analysis, Statusreport
Problem SolvingMeeting
Specially tosolve problemsarised
Bi-Weekly(if aproblem arisesinstantly)
ProjectManager, GlennTurner and theproject teammembersresponsible
Requirement specification,Problem document
Tecnical DesignReview Meeting
To review thesystem design
After everydesignoutput(mainlypreliminaryand final)
Projectmanager,GilbertRoks,MITrepresentative,Emily Maguire,Crista Cullen,Jamie Dwyer
Design specificationdocuments,Requirementspecification documents
Project Wikisthrough CentralDesktp
Communicatewith all theteam membersregarding anysituation
Instantly(anytime) All the teammembers andGlenn Turner
Electronic File sharing
Customer ProjectReview meeting
Show anddiscuss theprogress of theproject with thecustomer
Monthly BethStorry,GlennTurner, ITSrepresentaiveand UniversityadministrationincludingGilbert Roks
Status report, Requirementspecification document
are given access to the server information through their individual logins. But the project
7/30/2019 Automated Student Management System for South East Gippsland University - SPMP
52/67
are given access to the server information through their individual logins. But the projectmanager and the consultant have higher authority along with the project sponsor (Universityauthority) to view and access all the information. Other team members and stakeholders aregiven necessary access grants to carry out their work effectively.
And the communication will be done mainly through e-mails as it is easy and moreconvenient. And it is also the professional way of work and is easy to keep track of thedocuments passed. Use of Central Desktop is very helpful as the project team members andthe stakeholders can communicate instantly when they want with anyone in the network. Allthe documents will be shared through the system to all the necessary users and they have theability to reply or call a meeting regarding an issue through the system whenever they want.And all the documents will be archived in this system too, making it a backup storage of the
project information.
9.5 Communications Summary
Stakeholder Type Communication
Medium
Frequency Responsible
PartyBeth Storry
Status Report E-mail and printedcopy handed
Every Tuesdayand after everymilestone
EddieOckenden
EmilyMaguire
Trend analysis Email Monthly Crita Cullen
CristaCullen
Status report,Requirementspecification,Varianceanalysis,Trendanalysis
Email and printedcopy andcollaborativesoftware
Weekly EddieOckenden
AnnePanter Status report,Trendanalysis E-mail,collaborativesoftware Bi-weekly HannahMacleod
HannahMacleod
Status report E-mail Weekly EddieOckenden
Si St t E il C l b ti Bi kl H h
7/30/2019 Automated Student Management System for South East Gippsland University - SPMP
53/67
Table 24 Communication Summary
SimonOrchard
Statusreport.TechnicalDesign Review
report
E-mail,Colaborativesoftware
Bi-weekly HannahMacleod
GlennTurner
Status review,Trendanalysis,Varianceanalysis
E-mail,Collaborativesoftware
Weekly (instantlyif needed )
EddieOckenden
MatthewButturini
All the reports E-mail As those reportsare made
EddieOckenden,
HannahMacleod
EddieOckenden
All the reports E-mail and hecreates
As these reportsare created
HannahMacleod andhe createthem
PeterSamuels
Status report,Variance analysis,Trend Analysis
E-mail andcollaborativesoftware
Weekly andMonthly(analysis)
EddieOckenden,HannahMacleod
Reference List
7/30/2019 Automated Student Management System for South East Gippsland University - SPMP
54/67
Unknown, 2012. PROJECT QUALITY MANAGEMENT PLAN TEMPLATE, [E book],Available: http://www.projectmanagementdocs.com/templates/Quality_Management_Plan_Template.pdf, [Accessed date: 10th Aug 2012]
Unknown, 2012,IT Project Quality Management Plan,[Document],Available: http://www.itplanning.org.vt.edu/pm/ITPMQualityMgmtPlan.doc, [Accessed Date10th Aug 2012]
Wikipedia, 2012, SRS- Wikipedia, the free encyclopedia, [online],Available:http://en.wikipedia.org/wiki/Software_Requirements_Specification,[Accessed date:4th June 2012]
Pcubed, 2012, Write a scope statement - Project - Office.com, [online], Available:http://office.microsoft.com/en-us/project-help/write-a-scope-statement-HA001142472.aspx,[Accessed date: 5th June 2012]
Preferred Customer, 2012, [Document], Available:http://wweb.uta.edu/insyopma/prater/OPMA%205364%20Scope%20statement.doc,[Accessed date: 10th June 2012]
IT Department, Scope Statement, 2012, [Document], Available:http://www.augsburg.edu/ppages/~schwalbe/scope_statement.doc, [Accessed date: 12th June2012]
Prof. B. Meyer, Prof. P. Kolb, 2012, [E book], Available:http://se.inf.ethz.ch/old/teaching/ws2005/0273/slides/Template%20Project%20Plan.pdf,[Accessed date: 16th June 2012]
Unknown, 2008, [E book], Available:http://www.collegiateproject.com/articles/Preliminary%20Change%20Management%20Plan.pdf, [Accessed date: 16th June 2012]
Francine Richards,2012,How to Change a Project Management Plan | eHow.com, [Online],Available: http://www.ehow.com/how_7798951_change-project-management-plan.html,[Accessed date: 5th June 2012]
Unknown, 2012, Legal Consultant Salary in California - Legal Consultant Salary, [online],
Appendices
7/30/2019 Automated Student Management System for South East Gippsland University - SPMP
55/67
pp
Appendix A: Generic Cost Estimate Classification Matrix
Note:
[a] If the range index value of 1 represents %10/.5%, then an index value of 10 represents
%100/.50%.
[b] If the cost index value of 1 represents 0.005% of project costs, then an index value
of 100 represents 0.5%.
PrimaryCharacteristics
Secondary Characteristics
EstimateClass
LEVEL OFPROJECTDEFINITION[
Expressedas % ofcompletedefinition]
ENDUSAGE[Typical Purpose
of Estimate]
METHODOLOGY[Typicalestimating
methodology]
EXPECTEDACCURACYCHANGE[Ty
pical +/- rangerelative tobest index of 1(a)* ]
PREPARATIONEFFORT[Typic
al degree ofeffort relative toleast cost indexof 1 (b)*]
Class 5 0% to 2%Screening orFeasibility
Stochastic orJudgment
4 to 20 1
Class 4 1% to 15%
Concept
Study orFeasibility
PrimarilyStochastic 3 to 12 2 to 4
Class 3 10% to 40%Budget,Authorization,or Control
Mixed, butPrimarilyStochastic
2 to 6 3 to 10
Class 2 30% to 70%Control orBid/ Tender
PrimarilyDeterministic
1 to 3 5 to 10
Class 1 50% to 100% Bid/Tender Deterministic 1 10 to 100
Appendix B: Project Budget
7/30/2019 Automated Student Management System for South East Gippsland University - SPMP
56/67
Budget Report - ASMS Project South East Gippsland University (2012-2015)ID Project Expenditures Rate(USD) Cost(USD)
* Stated under assumptions
Estimated Total Working Hours = 175441 Employee Cost
1.1 Labor Cost $2,074,144.001.1.1 Project Manager $978,920.00
1.1.2 Software Architect $83,200.001.1.3 Programmer $118.080.001.1.4 Requirement Analyst $50,160.00
1.1.5 Configuration Manager $56,000.00
1.1.6 Quality Analyst $100,480.00
1.1.7 Database Engineer $18,720.00
1.1.8 Software Designer $92,400.00
1.1.9 Validation Engineer $72,000.00
1.1.10 Verification Engineer $246,720.001.1.11 Consultant $101,760.00
1.1.12 Installation Specialist $20,640.00
1.1.13 Technical Writer $36,000.00
1.1.14 Training Specialist $61,440.00
1.1.15 Help Desk Level 1 $3,840.00
1.1.16 Human Resource Manager $33,984.00
1.2 Food & Beverage 12$/hour $210,528.00
2 Rent Fee* $800/Week $76,800.00
3 Insurance Cost
3.1 Employee*$150 for $50000Labor cost $6,222.43
3.2 Equipment* $0.00
4 Software Cost4.1 Student Management System(TCO) $900,000.00
4.2 Software Development Kit(SDK) $25,000.00
4.3Microsoft Office 2010
$495/Year $2,970.00
4 4 Testing Tools $1000/machine $3 000 00
6.1 IT Service Desk $20,000.00
6 2 Ad i i t ti b d t $5 000 00
7/30/2019 Automated Student Management System for South East Gippsland University - SPMP
57/67
Table 9 Summarized Budget
Appendix C: Risk Categorization Table
6.2 Administrative budget $5,000.00
Total Implementation Cost $3,413,664.43
7 Legal Consultation $60000/annum $120,000.00
Total Budget for the Project $3,533,664.43
7/30/2019 Automated Student Management System for South East Gippsland University - SPMP
58/67
UCSC ICT 2009 IT Project Management Assignment 2012 | Page 58 of60
Risk Factors and
Categories
Low Risk Evidence (L) Medium Risk Evidence (M) High Risk Evidence (H) Risk
Rating
(H,M,L)
Comments
Project Fit Project fits within
SixSigmas area of
expertise and interest
Project limits SixSigmas
ability to take on other
attractive projects
Mid-project, the project
conflicts with a change in
SixSigmas direction.
L Unlikely to be an issue, since
the project involves most of
SixSigmas resources and
therefore sustains it
Organization management factors
Project team
Stability
Project staff are expected
to stay with SixSigma forthe duration of the project
One or more key project staff
are expected to leaveSixSigma before their
accountabilities are met
More than three key
project staff are expectedto leav