AN OVERVIEW OF

EXCAVATION AND LATERAL

SUPPORT (ELS) SYSTEMS

December 2012 K.W. LEUNG

Outline of the Talk

� Basic considerations

� Typical lateral support systems

� Permanent support

� Temporary support

� Statutory requirements for ELS Plan

� Experience sharing

Page 2: AN OVERVIEW OF EXCAVATION AND LATERAL SUPPORT ( · PDF fileAN OVERVIEW OF EXCAVATION AND LATERAL SUPPORT (ELS) SYSTEMS December 2012 K.W. LEUNG ... Channel planking Sheet

2012/12/1

2

� Site

characteristics

� Development

proposal

� Construction

� Design

� Performance

Basic

Considerations

CIRIA C580

Typical Section

Struts

Ground surface

Excavation

levelTie-backs (as an

alternative to struts)Seepage

cut-off

Page 3: AN OVERVIEW OF EXCAVATION AND LATERAL SUPPORT ( · PDF fileAN OVERVIEW OF EXCAVATION AND LATERAL SUPPORT (ELS) SYSTEMS December 2012 K.W. LEUNG ... Channel planking Sheet

2012/12/1

3

Braced Excavation

Tie-back Excavation

Page 4: AN OVERVIEW OF EXCAVATION AND LATERAL SUPPORT ( · PDF fileAN OVERVIEW OF EXCAVATION AND LATERAL SUPPORT (ELS) SYSTEMS December 2012 K.W. LEUNG ... Channel planking Sheet

2012/12/1

4

Bottom-up Construction

� � � �

Top-down Construction

� �

� �

Page 5: AN OVERVIEW OF EXCAVATION AND LATERAL SUPPORT ( · PDF fileAN OVERVIEW OF EXCAVATION AND LATERAL SUPPORT (ELS) SYSTEMS December 2012 K.W. LEUNG ... Channel planking Sheet

2012/12/1

5

Permanent Support

� Usually thick and massive

� Suitable for both top-down and

bottom-up construction

� Common types:

� Diaphragm wall

� Bored pile wall

� Caisson wall

Diaphragm Wall

Page 6: AN OVERVIEW OF EXCAVATION AND LATERAL SUPPORT ( · PDF fileAN OVERVIEW OF EXCAVATION AND LATERAL SUPPORT (ELS) SYSTEMS December 2012 K.W. LEUNG ... Channel planking Sheet

2012/12/1

6

Bored Pile Wall

Caisson Wall

Page 7: AN OVERVIEW OF EXCAVATION AND LATERAL SUPPORT ( · PDF fileAN OVERVIEW OF EXCAVATION AND LATERAL SUPPORT (ELS) SYSTEMS December 2012 K.W. LEUNG ... Channel planking Sheet

2012/12/1

7

Temporary Support

� Generally slim and flexible

� Used with bottom-up construction

� Common types:

� Channel planking

� Sheet pile wall

� Pipe pile wall

� Soldier pile and laggings

� Grouted pile wall

� Soil nailing for open cut

Channel Planking

Page 8: AN OVERVIEW OF EXCAVATION AND LATERAL SUPPORT ( · PDF fileAN OVERVIEW OF EXCAVATION AND LATERAL SUPPORT (ELS) SYSTEMS December 2012 K.W. LEUNG ... Channel planking Sheet

2012/12/1

8

Sheet Pile Wall

Pipe Pile Wall

Page 9: AN OVERVIEW OF EXCAVATION AND LATERAL SUPPORT ( · PDF fileAN OVERVIEW OF EXCAVATION AND LATERAL SUPPORT (ELS) SYSTEMS December 2012 K.W. LEUNG ... Channel planking Sheet

2012/12/1

9

Soldier Pile Wall

Grouted Pile Wall

Formed by

� PIP (Pakt-in-Place) piles; or

� Jet grouting; or

� Deep mixing

Page 10: AN OVERVIEW OF EXCAVATION AND LATERAL SUPPORT ( · PDF fileAN OVERVIEW OF EXCAVATION AND LATERAL SUPPORT (ELS) SYSTEMS December 2012 K.W. LEUNG ... Channel planking Sheet

2012/12/1

10

(a) PIP Piling

(b) Jet Grouting

Page 11: AN OVERVIEW OF EXCAVATION AND LATERAL SUPPORT ( · PDF fileAN OVERVIEW OF EXCAVATION AND LATERAL SUPPORT (ELS) SYSTEMS December 2012 K.W. LEUNG ... Channel planking Sheet

2012/12/1

11

(c) Deep Mixing

Soil Nailing for Open Cut

Page 12: AN OVERVIEW OF EXCAVATION AND LATERAL SUPPORT ( · PDF fileAN OVERVIEW OF EXCAVATION AND LATERAL SUPPORT (ELS) SYSTEMS December 2012 K.W. LEUNG ... Channel planking Sheet

2012/12/1

12

Statutory Requirements

� B(A)R 8(1)(bc) requires submission of ELS

plans where consequence of failure is serious

� PN for APs, RSEs & RGEs – APP 57

� Submission is required where the excavation is:

• >4.5m deep and > 5m long

• liable to affect any road, structure, slope (>30o),

or water main (≥75mmø) within the 45o line up

from the base of the excavation to the ground

surface

Contents of ELS Plan

� Lateral support system, e.g. sheet piles

� Strutting (or tie-back) layout

� Construction sequence

� Supporting geotechnical documents

� Realistic estimates of ground movements

� Assessment of effects of excavation & dewatering on adjoining structures

� Monitoring proposal

Page 13: AN OVERVIEW OF EXCAVATION AND LATERAL SUPPORT ( · PDF fileAN OVERVIEW OF EXCAVATION AND LATERAL SUPPORT (ELS) SYSTEMS December 2012 K.W. LEUNG ... Channel planking Sheet

2012/12/1

13

Common Deficiencies

• B(A)R 8(1)(bc) prescribed documentation

• Geological profile

• Groundwater

• Interaction with adjacent features/ structures

• Design calculations

• Inconsistency between plans and calculations

Non-compliance with

Approved Plans

� Support

� Excavation

� Loading situation not covered by design

� Precautionary measures

Page 14: AN OVERVIEW OF EXCAVATION AND LATERAL SUPPORT ( · PDF fileAN OVERVIEW OF EXCAVATION AND LATERAL SUPPORT (ELS) SYSTEMS December 2012 K.W. LEUNG ... Channel planking Sheet

2012/12/1

14

What Happened?

What Happened?

Page 15: AN OVERVIEW OF EXCAVATION AND LATERAL SUPPORT ( · PDF fileAN OVERVIEW OF EXCAVATION AND LATERAL SUPPORT (ELS) SYSTEMS December 2012 K.W. LEUNG ... Channel planking Sheet

2012/12/1

15

Observational Method

�9th Rankine Lecture by

Peck(1969) – “The

Observational Method

in Applied Soil

Mechanics”

�It has the potential for

savings in time or

money, or providing

needed assurance of

construction safety