Zoning pt. III. Intensity Regulations Meant to dictate the intensity of use Different standards for...

35
Zoning pt. III

Transcript of Zoning pt. III. Intensity Regulations Meant to dictate the intensity of use Different standards for...

Page 1: Zoning pt. III. Intensity Regulations Meant to dictate the intensity of use Different standards for different use districts –Minimum lot size –Minimum.

Zoning pt. III

Page 2: Zoning pt. III. Intensity Regulations Meant to dictate the intensity of use Different standards for different use districts –Minimum lot size –Minimum.
Page 3: Zoning pt. III. Intensity Regulations Meant to dictate the intensity of use Different standards for different use districts –Minimum lot size –Minimum.
Page 4: Zoning pt. III. Intensity Regulations Meant to dictate the intensity of use Different standards for different use districts –Minimum lot size –Minimum.

Intensity Regulations

• Meant to dictate the intensity of use• Different standards for different use districts

– Minimum lot size

– Minimum lot width

– FAR

– Open space ratio

– Livability space

– Recreation space

– Setbacks

Page 5: Zoning pt. III. Intensity Regulations Meant to dictate the intensity of use Different standards for different use districts –Minimum lot size –Minimum.

Intensity Regulations

• Minimum lot size & lot width

– Meant for orderly / consistent development

– Typically enforced through subdivision regs for new development

– Ensures buildable area without need for variance

Page 6: Zoning pt. III. Intensity Regulations Meant to dictate the intensity of use Different standards for different use districts –Minimum lot size –Minimum.

Intensity Regulations

• Floor to Area Ratio (FAR)– The proportion of floor area in relation to lot size

– Typically applied to interior floor space

• Not including garages, patios, etc.

– Applies to all floors, not just the footprint

Page 7: Zoning pt. III. Intensity Regulations Meant to dictate the intensity of use Different standards for different use districts –Minimum lot size –Minimum.

FAR

Page 8: Zoning pt. III. Intensity Regulations Meant to dictate the intensity of use Different standards for different use districts –Minimum lot size –Minimum.

Intensity Regulations

• Open Space Ratio– Gross land area not covered by buildings

• Livability Space Ratio– Improved open space (landscaping, outdoor living)

• Recreation Space Ratio– Applied to PUDs

– Space reserved for common recreational use

Page 9: Zoning pt. III. Intensity Regulations Meant to dictate the intensity of use Different standards for different use districts –Minimum lot size –Minimum.

Intensity Regulations

• Setbacks– A defined area wherein no structure may be located

– To an extent, defines “net” land area

– Street setback

• Distance from the street

• Usually the most restrictive

– Interior setback

• Distance from side and rear property lines

Page 10: Zoning pt. III. Intensity Regulations Meant to dictate the intensity of use Different standards for different use districts –Minimum lot size –Minimum.

Misc. Restrictions

• Parking• Landscaping• Buffering / Screening• Watershed / Floodplain Development• Signage

Page 11: Zoning pt. III. Intensity Regulations Meant to dictate the intensity of use Different standards for different use districts –Minimum lot size –Minimum.

Misc. Restrictions

• Parking– Dimensional Requirements

– Handicapped Spaces

– Typically determined by size of structure being served and/or maximum occupancy

– Typically, off-street parking is required

– Arrangements can be made for off-site parking by contract

Page 12: Zoning pt. III. Intensity Regulations Meant to dictate the intensity of use Different standards for different use districts –Minimum lot size –Minimum.
Page 13: Zoning pt. III. Intensity Regulations Meant to dictate the intensity of use Different standards for different use districts –Minimum lot size –Minimum.
Page 14: Zoning pt. III. Intensity Regulations Meant to dictate the intensity of use Different standards for different use districts –Minimum lot size –Minimum.

Bicycle Parking

Page 15: Zoning pt. III. Intensity Regulations Meant to dictate the intensity of use Different standards for different use districts –Minimum lot size –Minimum.

Misc. Restrictions

• Landscaping– Preservation of existing natural vegetation

– Used in conjunction with livability space ratios and screening/buffering requirements

• Screening and Buffering– Shields incompatible land use types

• The more incompatible, the more screening required

– Can be fencing, can be landscaping

– Screens from sight, noise

Page 16: Zoning pt. III. Intensity Regulations Meant to dictate the intensity of use Different standards for different use districts –Minimum lot size –Minimum.
Page 17: Zoning pt. III. Intensity Regulations Meant to dictate the intensity of use Different standards for different use districts –Minimum lot size –Minimum.
Page 18: Zoning pt. III. Intensity Regulations Meant to dictate the intensity of use Different standards for different use districts –Minimum lot size –Minimum.
Page 19: Zoning pt. III. Intensity Regulations Meant to dictate the intensity of use Different standards for different use districts –Minimum lot size –Minimum.
Page 20: Zoning pt. III. Intensity Regulations Meant to dictate the intensity of use Different standards for different use districts –Minimum lot size –Minimum.

Misc. Restrictions

• Signage– Dimension

• Preventing large signs

– Type• “passive” signs

• Electric signs

– Location• Incorporated with landscaping

• Attached to structure

• Overall, trying to avoid visual clutter

Page 21: Zoning pt. III. Intensity Regulations Meant to dictate the intensity of use Different standards for different use districts –Minimum lot size –Minimum.

Misc. Restrictions

• Floodplain, Watershed– Stormwater management

– Avoiding the impairment of waterways during and after construction

– Location of structure with respect to 100 year floodplain

Page 22: Zoning pt. III. Intensity Regulations Meant to dictate the intensity of use Different standards for different use districts –Minimum lot size –Minimum.

The Permit Process

• Most developments require a permit of some sort– Notification to jurisdiction that development is occurring

– Varying levels of involvement by jurisdiction / boards

– Checking for consistency with ordinances

• Permits also outside of planning realm– Building

– Water / Sewer / Septic

Page 23: Zoning pt. III. Intensity Regulations Meant to dictate the intensity of use Different standards for different use districts –Minimum lot size –Minimum.

The Permit Process

• Development Permits

– Waivers / Exemptions

– Zoning Permits

– Special Use Permits

Page 24: Zoning pt. III. Intensity Regulations Meant to dictate the intensity of use Different standards for different use districts –Minimum lot size –Minimum.

The Permit Process

• Waivers / Exemptions– Assuring that no development permit is necessary

– Threshold is set in ordinance

• Below which, no permit is necessary, but an official waiver is

– What may be exempt?

• Renovations

• Remodeling

• Additions

• Alteration of structure below a certain threshold

Page 25: Zoning pt. III. Intensity Regulations Meant to dictate the intensity of use Different standards for different use districts –Minimum lot size –Minimum.

The Permit Process

• Zoning Permits– “Use by Right”

– Proposed development strictly adheres to use and intensity restrictions of ordinance

– Planning administrator grants permit

– No public meeting required

– No public notification required

Page 26: Zoning pt. III. Intensity Regulations Meant to dictate the intensity of use Different standards for different use districts –Minimum lot size –Minimum.

The Permit Process

• Special Use Permits– Permits may be issued for uses that otherwise may only

require a zoning permit

• Given the context of use and its intensity

– Public notification required

– Public hearing required (BOA or Town Council)

– Conditions may be placed on permit (staff and/or BOA, T.C.)

• Conditions must be met for permit to be valid

– Approval contingent upon a number of questions

• Answers provided by issuing body (BOA, Town Council)

• Decision informed by testimony & evidence at public hearing

Page 27: Zoning pt. III. Intensity Regulations Meant to dictate the intensity of use Different standards for different use districts –Minimum lot size –Minimum.

The Permit Process

• Voting on Board of Adjustment / Town Council (S.U.)

– Does BOA have jurisdiction?

– Is application complete?

– The development will:

• Comply with the requirements of the ordinance

• Not materially endanger public health or safety

• Not substantially injure the value of adjoining or abutting properties

• Be in harmony with the area in which it is to be located

• Be in general conformity with the policy plans adopted by council

• (if required) meet standards of transitional zones

Page 28: Zoning pt. III. Intensity Regulations Meant to dictate the intensity of use Different standards for different use districts –Minimum lot size –Minimum.

The Permit Process

• What determines requirement for permit type?– Ordinance

• Table of Principal Uses

– Discretionary Powers of Administrator

• Granted by governing body

• Outlined in ordinance

– Under what circumstances

– Scope of authority

Page 29: Zoning pt. III. Intensity Regulations Meant to dictate the intensity of use Different standards for different use districts –Minimum lot size –Minimum.

The Permit Process

• The use of discretion

– Creates due process issues

• Many feel that the exercise of discretion by planning administrator is an improper delegation of legislative authority

– Must be outlined

– Ultimate decision must meet a “reasonableness” test

Page 30: Zoning pt. III. Intensity Regulations Meant to dictate the intensity of use Different standards for different use districts –Minimum lot size –Minimum.

Non-Conforming Uses

• Applies to uses, dimensions, lot, projects, signs– Inconsistency with ordinance at time of enactment

– Generally “grandfathered” in

• Uses– Incompatible with zoning district use restrictions

• Dimension– Height, size, FAR

• Lot– Minimum size, width

Page 31: Zoning pt. III. Intensity Regulations Meant to dictate the intensity of use Different standards for different use districts –Minimum lot size –Minimum.

Non-Conforming Uses

• Projects– Project incomplete and inconsistent with any portion of

ordinance (UDO)

• Signs– Blah

Page 32: Zoning pt. III. Intensity Regulations Meant to dictate the intensity of use Different standards for different use districts –Minimum lot size –Minimum.

Non-Conforming Uses

• Provisions in ordinance– Protect existing non-conforming uses

– Ensure these uses do not expand or enlarge

– Provide guidance on reversion of properties to conforming status

• Amortization

• Property changing hands

• Time limit on abandonment of use / situation

Page 33: Zoning pt. III. Intensity Regulations Meant to dictate the intensity of use Different standards for different use districts –Minimum lot size –Minimum.

Variances

• Consider a variance to be a “relief valve”– Protects property interests by allowing the exercise of

development rights

– Protects government from takings actions

Page 34: Zoning pt. III. Intensity Regulations Meant to dictate the intensity of use Different standards for different use districts –Minimum lot size –Minimum.
Page 35: Zoning pt. III. Intensity Regulations Meant to dictate the intensity of use Different standards for different use districts –Minimum lot size –Minimum.

Variances

• Granting a variance– Strict compliance with regs allows no reasonable use of the

applicant’s property

– Hardship is suffered by applicant and not by the neighborhood or general public

– Hardship relates to property, not personal circumstance

– Hardship is peculiar to applicant’s property

– Hardship is not result of applicant’s actions

– Variance won’t interfere with rights of others

– Variance won’t result in the extension of a non-conforming situation nor authorize the initiation of a non-conforming use