Youth Café Capital Programme Pre-contract Support Event F 2 Community Centre 16 January 2014.

4
Youth Café Capital Programme Pre-contract Support Event F 2 Community Centre 16 January 2014

Transcript of Youth Café Capital Programme Pre-contract Support Event F 2 Community Centre 16 January 2014.

Page 1: Youth Café Capital Programme Pre-contract Support Event F 2 Community Centre 16 January 2014.

Youth Café Capital Programme

Pre-contract Support Event

F 2 Community Centre

16 January 2014

Page 2: Youth Café Capital Programme Pre-contract Support Event F 2 Community Centre 16 January 2014.

2

Pobal’s Role

Pobal is assisting DCYA to manage the implementation of the Youth Cafés programme with overall responsibility for:

Programme Design and Application Processing; Application Appraisal & Decision-Making; Pre-Development Supports; Contract Administration; Grant Administration; Performance Monitoring; Financial Controls; Verification;Audit and Reporting to the Department.

Page 3: Youth Café Capital Programme Pre-contract Support Event F 2 Community Centre 16 January 2014.

3

Phase 2 - Pre contract

Phase 2 is essentially a pre-development stage and involves further project development and a robust pre-contracting process.

Templates are provided to complete approval process Applicants are assigned a Pobal staff member to assist them. This phase involves procurement, project design, seeking planning

permission, agreeing premises/lease arrangements and the development of relevant policies/procedures.

Those applicants who successfully meet the Phase 2 requirements must then be approved for funding by DCYA (subject to the availability of resources) following which a Grant Agreement will be issued.

Phase 2 is an intensive and critical process; projects who do not meet the requirements by mid-March 2014 will not be recommended for funding to DCYA.

Progression to Phase 2 is not a guarantee of funding.

Page 4: Youth Café Capital Programme Pre-contract Support Event F 2 Community Centre 16 January 2014.

4

Criteria

• Evidence that the project be completed within budget, sufficient funds are available/committed.

• Compliance with tendering/ procurement requirements,

• Ownership or sufficient lease on building/ approval by landlord

• Planning requirements and permissions secured (where necessary)

• Plan of activities to engage youth participation, targeted numbers.

• Opening Hours.

• Evidence of high standards regarding governance,