Your Facilities Master Plan: Building a Better Business Case Your Facilities Master Plan: Building a...
-
Upload
nathan-baldwin -
Category
Documents
-
view
218 -
download
0
Transcript of Your Facilities Master Plan: Building a Better Business Case Your Facilities Master Plan: Building a...
Your Facilities Master Plan:
Building a Better Business CaseJim TurnerDirector, Workplace Solutions
Slide 2
Program
• Learning Objectives• Consider this project…• A simplified five-step process
– Develop Objectives– Prepare Criteria– Consider Alternatives– Analyze and Evaluate Alternatives– Rank and Recommend
• Other approaches• Q & A
Slide 3
…but first…
The presentation used to focus on the facilities master plan – learning objectives:
1. Collecting and analyzing facilities data2. Financial/resource objectives3. Construct a business case model4. Implementation road map
Now it’s about developing a business case for facilities projects!
Slide 4
Building a Better Business Case Learning Objectives:
• Business cases analyze the costs, benefits, and risks of a facilities project to support good decisions
• The current and planned future use of the building is a major driver for facilities investment decisions
• It is a good practice to consider as many alternatives that meet your requirements as possible
• Business case evaluation metrics often include net present value and payback period
Slide 5
Consider this Project
Strategy: Retrofit for energy efficiency• Renew and retrofit to reduce capital program• Reduce current costs: O&M, utilities• Add new tenant offerings including chilled water and
reliable emergency power• Increase occupancy, improve rents, gain other tenant
income based on updated services
Eight major program elements:
Program cost estimate: $500 million
•Radiative barrier•Tenant ventilation control•Tenant day lighting•Lighting and plugs
•Direct digital controls•Chiller plant retrofit•VAV air handling•Tenant energy management
New York City (not Las Vegas, and not Legos)
Sources: A Landmark Sustainability Program for the Empire State Building, Jones Lang LaSalle; Serious Materials on-line case study. Photos: Wikipedia
ESB Project Drill Down
Slide 6
• Windows update became a key project element
• Originally estimated at $20 million, came in at under $5 million
• On-site process to upgrade rather than replace windows
Detail of the 6,500 operable, double-pane
ESB windows
Learning Objective 1: Business Cases should analyze a project’s costs, benefits, and risks.
Constructing the Business Case
Slide 7
Context and Objectives
Ranking and Recommendatio
n
Evaluation of Alternatives
Alternative Coursesof Action
Evaluation Criteria
Assessment ofCurrent State
Assessment ofFuture State
Gap Analysis Specification of Alternatives
Evaluation of Alternatives
Cost Analysis
Benefits Analysis
Risk Analysis
Present Findings, Including ROI and
Cost/Benefit
Sensitivity Analysis
A simplified five-step process
Step 1 Step 2 Step 3 Step 4 Step 5
Step 1: Context and Objectives and Step 2: Gap Analysis
Slide 8
Major drivers might include:
•Current and future use of the facility•Forecast of utilization and other performance metrics•Legal, regulatory, or policy criteria of high importance
CRITERIA INSIGHTS
Personnel Impacts Changes in attrition that would result from the relocation; the ability to recruit civilian personnel as measured by cycle-time to fill a position and number of unfilled positions; assessed by job category
Facilities Impacts Quality of destination space as measured by commonly used space quality standards (e.g., class A space)
Environmental Impacts The anticipated level of migration efforts required to satisfy national Environmental Protection Act requirements
Facility longevity Timeframe that facility will be available compared to period of interest
Ease of travel to/from Average commute times; transportation infrastructure
Political implications Expected implications from moving from one political district to another
Learning Objective 2: Current and planned future use of the facility is a major driver of investment decisions.
Step 3: Brainstorm Solutions to Meet Future Requirements
• Soccer Field Project: (1) status quo, (2) improved natural turf field, and (3) artificial turf field
• Wet Basement Project: (1) slight external grading and downspout relocation, (2) improve seals in isolation slabs and add optional redundant sump, (3) excavate foundation and reseal walls
Slide 9
Learning Objective 3: It’s a good practice to consider a wide range of alternatives that will meet your requirements.
Solutions Brainstorming
Slide 10
StrategyCOA
NumberCOA Description
Status Quo 1 Status Quo: Limited recap, retire in placeExisting Site 2a Existing Site: Data Center Equipment Recap OnlyExisting Site 2b Existing Site: Data Center Densification Only
Existing Site 2cExisting Site: Phased Renovation including New Building, Data Center Centralization and Office Space Realignment
Partial Relocation 3aPartial Move: Non-essential Administrative Functions Move (Lease or Other Owned Facilities)
Partial Relocation 3bPartial Move: Non-essential Data Center Equipment and Related Support People Move Off-site (Co-location)
Partial Relocation 3cPartial Move: HQ, Data Center and Core Functions Remain On-site, Other Functions and Support Move Off to Leased or Owned Facilities
Partial Relocation 3dPartial Move: All Functions Remain Except Data Centers and Tenant Data Center Equipment and Support
Partial Relocation 3ePartial Move: Partial Move, Tenant and Equipment Relocates, All Existing Functions Remain and are Realigned
Full Move 4 Full Move: New Site, New Building
Note: Since this project had so many alternatives, we did a “down-select” to focus on the two most likely to be selected.
Fleshing out the Alternatives
• For each of the alternatives (COA stands for courses of action), a simple but thorough description might include:– A summary or overview of the COA– A list of assumptions about the COA– A list of requirements that may have to be put in place
(these aid in the development of the cost evaluation)– A list of benefits that will be achieved– A list of risks– A cost analysis – focus on relevant cost, with enough
detail to make a valid comparison
Slide 11
Fleshing out the Alternatives
Slide 12
Sp
ecif
icat
ion
sB
enef
its
Fleshing out the Alternatives
Slide 13
Ris
ks
ESB Windows Project - Alternatives
Slide 14
1. Retrofit with new windows - demo and replace old ones
2. Traditional de-install and repair job – done by NJ specialist
3. Complete the repairs on-site, in an empty suite
Step 4: Evaluating Risks, Costs, and Benefits
Slide 15
Develop a thorough framework to evaluate the relevant costs and benefits of each alternative
Examples of Costs to Consider
Slide 16
Type Short Definition
Initial Purchase Cost or Capital Investment
Costs associated with initial planning, design, and construction; including acquisition, transportation, and installation
Financing Costs Includes one time financing costs, or interest on interim construction financing
O&M CostsAssociated with maintaining or restoring to original condition, including routine maintenance, utilities, taxes, and contracted servicing
Repair and Replacement CostsAssociated with maintaining or restoring to original performance, including major renovation and repair, and non-annual services
Alterations and Improvements Costs of planned additions, alterations, major reconfigurations, and other improvements
Functional Costs Costs associated with performing intended use of the facility
Salvage or Disposal Costs Values of land, building, or building elements at the time they are removed from service
Examples of Benefits to Consider
Slide 17
• Other potential benefits:– Additional rent revenues
• Mid-town rentals average $71/SF• ESB has over 2.85-million SF
• Tax incentives for sustainability• Access to capital for financing
Benefits
• $414K annual utilities savings from windows alone• Green benefits from reuse of windows
Detail of the 6,500 operable, double-pane ESB windows
Examples of Risks to Consider
Slide 18
Scale Very Low Low Moderate High Very High
Cost Impacts Insignificant < 5% 5-10% 10-20% > 20%
Schedule Impacts Insignificant < 5% 5-10% 10-20% > 20%
Scope Impacts
Barely Noticeable
Minor Areas Affected
Major Areas Affected
Scope Reduction/
Client Won’t Accept
End Item Unusable
Quality Impacts
Degradation Barely
Noticeable
Affects Only Demanding
Apps
Quality Reduced,
Client Approval Needed
Quality Reduced,
Client Won’t Accept
End Item Unusable
The Project Management Institute has useful tools for risk analysis, essentially evaluating likelihood of the event and estimated impact.
Combining Costs and Benefits
Slide 19Sources: A Landmark Sustainability Program for the Empire State Building, Jones Lang LaSalle; Serious Materials on-line case study. Photos: Wikipedia
* These are illustrative calculations!
Item Cost*
Design $0.5M
Rental Space $0.2M
Materials and Labor
$4.0M
Life-cycle repair and maintenance
$0.5M
Total $5.2M
Item Benefit*
Utilities (Ann/ 20-years)
$0.4M/$8.0M
Raised Rent (Ann./20-Years)
$3.0M$60.0M
Tax Savings $? M
Easier Capital Access
$? M
Total $68+M
Examples of Payback Measures
Slide 20
Learning Objective 4: Business case decision metrics include net present value and payback period.
NPV compares investment life-cycle costs with its returns by taking a sum of their discounted value. Essentially, it measures the excess or shortfall of cash flows.
ROR is stated as a percentage, and is calculated as the ratio of the return from theinvestment relative to investment cost. Thereturns can be interest, profit, or netincome, and the investment may be referred to as capital or principal.
Payback period is the period of time required for the investment’s returns to “repay” the original cost. It measures how long it takes for the investment to “pay for itself.”
Other customized measures may be used.Cost per customer describes the cost of acquiring a customer by dividing the totalinvestment cost by the expected number of new customers gained.
Scoring the Alternatives
Slide 21
StrategyCOA No.
COA Description Benefits Costs Risks
Status Quo 1 Status Quo: Limited recap, retire in place
Existing Site 2a Existing Site: Data Center Equipment Only
Existing Site 2b Existing Site: Data Center Densification Only
Existing Site 2d Existing Site: Phased Renovation including New Building, Data Center Centralization and Office Space Realignment
Partial Relocation
3a Partial Move: Non-essential Administrative Functions Move (Lease or Owned Facilities)
Partial Relocation
3b Partial Move: Non-essential Data Center Equipment and Related Support People Move Off-site (Co-location)
Partial Relocation
3c Partial Move: HQ, Data Center and Core Functions On-site, Other Functions and Support Move to Leased or Owned Facilities
Partial Relocation
3d Partial Move: All Functions Remain Except Data Centers and Tenant Data Center Equipment and Support
Partial Relocation
3e Partial Move: Partial Move, Tenant and Equipment Relocates, All Existing Functions Remain and are Realigned
Full Move 4 Full Move: New Site, New Building
Grade the alternatives on an appropriate scale, (e.g., 1 to 10; high, medium, low; if a full cost and benefits estimate was developed, use those dollar values)The key is quantifiable metrics!
Putting it All Together
Slide 22
Executive SummaryIntroduction/Overview
– Subject, Purpose, Scope, Objectives– Background– Organization
Methodology– Major Assumptions and Constraints– Criteria and Financial Metrics– Description of Cost Analysis Methodology
Analysis of Alternatives– Description of Status Quo and Alternatives– Cost Analysis– Comparison of Alternatives
Sensitivity and Risk AnalysisConclusions and Recommendations
– Results Discussion– Recommendation– Scenarios for Implementation (Sources of Funding, Timeframes, etc.)
Bonus Tips!
Slide 23
• Imagine you’re telling a story – Start with the problem – the business need you’re solving
• Identify your characters– Stakeholders who will approve or reject your business case– Beneficiaries who stand to gain from your proposal– Subject-matter experts to clarify how to solve the problem
• Identify the alternatives for meeting the business need—the different ways your story might play out
• Choose the best one, and create a project plan – the plot• After you estimate and analyze the costs, benefits and risks, and calculate the
return on investment (ROI), you’ve reached the story’s satisfying end
• Remember this isn’t a mystery novel—your story needs to be clear and easy to understand.
Recap of Learning Objectives
• Business cases analyze the costs, benefits, and risks of a facilities project to support good decisions– Slide 6
• The current and planned future use of the building is a major driver for facilities investment decisions– Slide 8
• It is a good practice to consider as many alternatives that meet your requirements as possible– Slide 9
• Business case evaluation metrics often include net present value and payback period– Slide 20
Slide 24
Wrap up
Slide 25
Questions?…Thank you!
Las Vegas (not New York City)
Legos (not New York City)
• The presentation is in your Conference packet, but you can also request a copy electronically from me at [email protected]
• Connect on LinkedIn: http://www.linkedin.com/in/jimturner