QUOTED BY: -M/S Shivam Engineers,818-Laxmideep Building,District centre,Vikas Marg,Delhi-110092 QUOTED FOR :-M/S Kinden India Pvt.Ltd.Gurgaon PROJECT :-M/S YKK INDIA,BAWAL(Haryana) BILL OF MATERIALS 31.05.2013 Unit Price Unit Total Unit Price Unit Total I PHASE - I : REMOVING WORKS. 1 POWER for MACHINE : 1.1 Removal the existing Power distribution panel PCC- 3 at Phase -I area(w:2400,h:2000,d:400) Job 1 - 12,500.00 12,500.00 - - 2 LIGHTING SYSTEM : - - 2.1 Removal the existing Lighting distribution panel LCC-1 at Phase -I area, after removing the Incoming and Outgoing cable terminations and storing the panel in a separate location. - - Incoming cable : 3.5c x 120 sq.mm Alu. Ar Cable - - Outgoing cables / Wires : 3R, 2.5 Sq.mm Copper flexible cable in conduit / Raceways. - 11 Circuits - - Outgoing cables / Wires : 3R, 4.0 Sq.mm Copper flexible cable in condduit / Raceways. - 3 Circuits Job 1 - 20,000.00 20,000.00 - - 2.2 Removal the existing Lighting distribution panels LCC- 2 at Phase - I area, after removing the Incoming and Outgoing cable terminations and storing the panel in a separate location. - - Incoming cable : 3.5c x 120 sq.mm Alu. Ar Cable - - Outgoing cables / Wires : 3R, 2.5 Sq.mm Copper flexible cable in conduit / Raceways. - 13 Circuits - - Outgoing cables / Wires : 3R, 4.0 Sq.mm Copper flexible cable in condduit / Raceways. - 8 Circuits - - Outgoing cables / Wires : 4c x 6.0 Sq.mm Copper cable in conduit / Raceways. - 1 Circuit Job 1 - 25,000.00 25,000.00 - - 2.3 Removal the existing Lighting distribution panels LCC- 3 at Phase - I area, after removing the Incoming and Outgoing cable terminations and storing the panel in a separate location. - - Incoming cable : 3.5c x 120 sq.mm Alu. Ar Cable - - Outgoing cables / Wires : 3R, 2.5 Sq.mm Copper flexible cable in conduit / Raceways. - 10 Circuits - - Outgoing cables / Wires : 3R, 4.0 Sq.mm Copper flexible cable in condduit / Raceways. - 4 Circuits - - Outgoing cables / Wires : 4c x 6.0 Sq.mm Copper cable in conduit / Raceways. - 1 Circuit Job 1 - 20,000.00 20,000.00 - - 2.4 Removing of the 50mm x 50 mm x 2400mm (Length) MS sheet steel Powder coated Race way covers for removing the lighting wirings laid in the raceways and storing them in a safe work place. Mtrs 1355 - 75.00 101,625.00 - - 2.5 Removing of the 3 runs of 2.5 Sq.mm Copper flexible wires in Race ways for lighting circuits, removing the terminations in the fittings and storing. Mtrs 2420 - 15.00 36,300.00 - - 2.6 Removing the Flourscent tube, Reflector and the cover of the light fixtures for disconnecting the circuit wires and storing them in a safe working place. Nos 365 - 125.00 45,625.00 - - 3 POWER SOCKET SYSTEM : - - 3.1 Removing the existing power socket wiring in 25mm dia GI pipe with 3runs of 4.0 Sq.mm copper wires from LCC panels - 1,2 & 3 which is clamped along the wall / RSJ Coloumns etc., Mtrs 665 - 30.00 19,950.00 - - 3.2 Removing the existing power socket wiring in 32mm dia GI pipe with 4c x 6 Sq.mm copper cable from LCC panels - 1,2 & 3 which is clamped along the wall / RSJ Coloumns etc., Mtrs 150 - 35.00 5,250.00 - - 3.3 Removing the existing 1 Gang, Single Phase 6/16A, receptacle mounted in Thermoplastic plate GI Box - Plug and socket outlets mounted over wall surface / RSJ Coloumns etc., Nos 1 - 75.00 75.00 Supply Installation Sr. No. Description Unit Qty 1 - 9

description

jkknk

Transcript of YKK India - BOQ From Shivam

Page 1: YKK India - BOQ From Shivam

QUOTED BY:-M/S Shivam Engineers,818-Laxmideep Building,District centre,Vikas Marg,Delhi-110092QUOTED FOR:-M/S Kinden India Pvt.Ltd.GurgaonPROJECT:-M/S YKK INDIA,BAWAL(Haryana)BILL OF MATERIALS 31.05.2013

Unit Price Unit Total Unit Price Unit TotalI PHASE - I : REMOVING WORKS.

1 POWER for MACHINE :1.1 Removal the existing Power distribution panel PCC-

3 at Phase -I area(w:2400,h:2000,d:400)Job 1 - 12,500.00 12,500.00

- - 2 LIGHTING SYSTEM : - -

2.1 Removal the existing Lighting distribution panelLCC-1 at Phase -I area, after removing the Incomingand Outgoing cable terminations and storing thepanel in a separate location.

- -

Incoming cable : 3.5c x 120 sq.mm Alu. Ar Cable - - Outgoing cables / Wires : 3R, 2.5 Sq.mm Copperflexible cable in conduit / Raceways.- 11 Circuits

- -

Outgoing cables / Wires : 3R, 4.0 Sq.mm Copperflexible cable in condduit / Raceways.- 3 Circuits

Job 1 - 20,000.00 20,000.00

- - 2.2 Removal the existing Lighting distribution panels LCC-

2 at Phase - I area, after removing the Incoming andOutgoing cable terminations and storing the panel ina separate location.

- -

Incoming cable : 3.5c x 120 sq.mm Alu. Ar Cable - - Outgoing cables / Wires : 3R, 2.5 Sq.mm Copperflexible cable in conduit / Raceways.- 13 Circuits

- -

Outgoing cables / Wires : 3R, 4.0 Sq.mm Copperflexible cable in condduit / Raceways.- 8 Circuits

- -

Outgoing cables / Wires : 4c x 6.0 Sq.mm Coppercable in conduit / Raceways.- 1 Circuit

Job 1 - 25,000.00 25,000.00

- - 2.3 Removal the existing Lighting distribution panels LCC-

3 at Phase - I area, after removing the Incoming andOutgoing cable terminations and storing the panel ina separate location.

- -

Incoming cable : 3.5c x 120 sq.mm Alu. Ar Cable - - Outgoing cables / Wires : 3R, 2.5 Sq.mm Copperflexible cable in conduit / Raceways.- 10 Circuits

- -

Outgoing cables / Wires : 3R, 4.0 Sq.mm Copperflexible cable in condduit / Raceways.- 4 Circuits

- -

Outgoing cables / Wires : 4c x 6.0 Sq.mm Coppercable in conduit / Raceways.- 1 Circuit

Job 1 - 20,000.00 20,000.00

- - 2.4 Removing of the 50mm x 50 mm x 2400mm (Length)

MS sheet steel Powder coated Race way covers forremoving the lighting wirings laid in the raceways andstoring them in a safe work place.

Mtrs 1355 - 75.00 101,625.00

- - 2.5 Removing of the 3 runs of 2.5 Sq.mm Copper flexible

wires in Race ways for lighting circuits, removing theterminations in the fittings and storing. Mtrs 2420 - 15.00 36,300.00

- - 2.6 Removing the Flourscent tube, Reflector and the

cover of the light fixtures for disconnecting thecircuit wires and storing them in a safe workingplace.

Nos 365 - 125.00 45,625.00

- - 3 POWER SOCKET SYSTEM : - -

3.1 Removing the existing power socket wiring in 25mmdia GI pipe with 3runs of 4.0 Sq.mm copper wiresfrom LCC panels - 1,2 & 3 which is clamped alongthe wall / RSJ Coloumns etc.,

Mtrs 665 - 30.00 19,950.00

- - 3.2 Removing the existing power socket wiring in 32mm

dia GI pipe with 4c x 6 Sq.mm copper cable fromLCC panels - 1,2 & 3 which is clamped along the wall/ RSJ Coloumns etc.,

Mtrs 150 - 35.00 5,250.00

- - 3.3 Removing the existing 1 Gang, Single Phase 6/16A,

receptacle mounted in Thermoplastic plate GI Box -Plug and socket outlets mounted over wall surface /RSJ Coloumns etc.,

Nos 1 - 75.00 75.00

Supply InstallationSr. No. Description Unit Qty

1 - 9

Page 2: YKK India - BOQ From Shivam

Unit Price Unit Total Unit Price Unit TotalSupply Installation

Sr. No. Description Unit Qty

- - 3.4 Removing the existing 2 Gang, Single Phase 6/16A,

receptacle mounted in Thermoplastic plate with GIBox - Plug and socket outlets mounted over wallsurface / RSJ Coloumns etc.,

Nos 23 - 100.00 2,300.00

- - 3.5 Removing the existing Three Phase 63A, 5 Pin rotary

type Industrial socket with 4P MCB and 20A, SinglePhase rotary type industrial soccket with DP MCB ina powder coated enclosure box.

Nos 4 - 200.00 800.00

- - 3.6 Finishing the surface of the existing Plug & Socket

mounted area and repainting the surface and makingthe surface good. (In Civil Scope ) Nos 28 CIVIL SCOPE -

- - 4 EMERGENCY & EXIT LIGHTING SYSTEM : - -

4.1 Removing the existing Emergency lights mountedover wall surface / Coloumns / From ceiling andstoring in a safe workplace.

Nos 34 - 125.00 4,250.00

- - 4.2 Removing the existing Emergency lighting wiring with

3 Runs of 2.5 Sq.mm copper wires in 25mm dia GIpipe / Raceways / clamped along the wall / RSJColoumns etc.,

Mtrs 500 - 30.00 15,000.00

- - 4.3 Removing the existing Exit lights / Exit Indicators

mounted over wall surface / Coloumns / From ceilingand storing in a safe workplace. Nos 13 - 100.00 1,300.00

- - 4.4 Removing the existing Exit lighting wiring with 3

Runs of 2.5 Sq.mm copper wires laid in 25mm dia GIpipe / Raceways clamped along the wall / ceiling /RSJ Coloumns etc.,

Mtrs 345 - 30.00 10,350.00

- - II PHASE - I : SUPPLY & INSTALLATION WORKS.

- -

- - 1 POWER for MACHINE : - -

1.1 LV Power Panel : PP-1 - - Supply, Installation, Testing and Commissioning of415V, 3Phase, 4 Wire sheet steel fabricated, dust and vermin proof, Cubicle, Indoor type, free standing floormounted expandable type fabricated out of 1.6mmCRCA sheet steel complete with 200A, AluminiumBusbars, Adequate cable alley for terminatingIncoming and Outgoing cables with detachable Glandplates, complete terminal block arrangement withferrule markings, Space Heater, Proper ventillationarrangements complete with powder coated finishand comprising of.,

- -

Incoming : 160A, 4P MCCB with microprocessorbased O/C relay, with On/OFF and Phase Indicationlamps.

- -

Meterings: Digital Multi function meter with 3 Nos200/5A,15VA, Cl:1 CT, Control wirings and controlMCB's (Schneider Power logic series : PM850) - -

Busbars : 200A, 3 Phase Aluminium Busbars withheat shrikable coloured sleeves.

- -

Outgoings :16 Nos, 63A, TP&N MCB with 4R, 16Sq.mm Copper wires wired to the outgoing terminalblocks at cable ally.

Nos 1 227,200.00 227,200.00 12,500.00 12,500.00

- - 1.2 LV Power Panel : PP-2 - -

Supply, Installation, Testing and Commissioning of415V, 3Phase, 4 Wire sheet steel fabricated, dust and vermin proof, Cubicle, Indoor type, free standing floormounted expandable type fabricated out of 1.6mmCRCA sheet steel complete with 250A, AluminiumBusbars, Adequate cable alley for terminatingIncoming and Outgoing cables with detachable Glandplates, complete terminal block arrangement withferrule markings, Space Heater, Proper ventillationarrangements complete with powder coated finishand comprising of.,

- -

Incoming : 250AF/200AT, 4P MCCB withmicroprocessor based O/C relay, with On/OFF andPhase Indication lamps.

- -

2 - 9

Page 3: YKK India - BOQ From Shivam

Unit Price Unit Total Unit Price Unit TotalSupply Installation

Sr. No. Description Unit Qty

Meterings: Digital Multi function meter with 3 Nos250/5A,15VA, Cl:1 CT, Control wirings and controlMCB's (Schneider Power logic series : PM 850) - -

Busbars : 250A, 3 Phase Aluminium Busbars withheat shrikable coloured sleeves.

- -

Outgoings :22 Nos, 63A, TP&N MCB with 4R, 16Sq.mm Copper wires wired to the outgoing terminalblocks at cable ally.

Nos 1 255,000.00 255,000.00 12,500.00 12,500.00

- - 1.3 LV Power Panel : PP-3 - -

Supply, Installation, Testing and Commissioning of415V, 3Phase, 4 Wire sheet steel fabricated, dust and vermin proof, Cubicle, Indoor type, free standing floormounted expandable type fabricated out of 1.6mmCRCA sheet steel complete with 100A, AluminiumBusbars, Adequate cable alley for terminatingIncoming and Outgoing cables with detachable Glandplates, complete terminal block arrangement withferrule markings, Space Heater, Proper ventillationarrangements complete with powder coated finishand comprising of.,

- -

Incoming : 100A, 4P MCCB with microprocessorbased O/C relay, with On/OFF and Phase Indicationlamps.

- -

Meterings: Digital Multi function meter with 3 Nos100/5A,15VA, Cl:1 CT, Control wirings and controlMCB's (Schneider Power logic series : PM 850) - -

Busbars : 100A, 3 Phase Aluminium Busbars withheat shrikable coloured sleeves.

- -

Outgoings :9 Nos, 63A, TP&N MCB with 4R, 16Sq.mm Copper wires wired to the outgoing terminalblocks at cable ally.

Nos 1 203,000.00 203,000.00 11,500.00 11,500.00

- - 1.4 Supply and Installation of Feeder Box for LV Busbar

Trunking system (Make: M/s EAE Catno.KAP0605BB)

Nos 36 3,100.00 111,600.00 650.00 23,400.00

- - 1.5 Supply, Installation, Testing and Commissioning of LV

Busbar Trunking system ( Make: M/s EAE, Catno.KAP0604)

Nos 144 8,715.00 1,254,960.00 600.00 86,400.00

- - 1.6 Supply and Installation of End Box for LV Busbar

trunking system (Make: M/s EAE, Catno.KAP0605BS)

Nos 36 3,100.00 111,600.00 300.00 10,800.00

- - 1.7 Supply, Installation of Tap Off Plug for the LV Busbar

Trunking system (Make: M/s EAE Cat no.KAP16-KL123)

Nos 192 1,500.00 288,000.00 150.00 28,800.00

- - 1.8 Supply and installation of suitable supporting Material

with drop rod arrangement from roofing supports forthe LV Busbar trunking system (The distancebetween supports should be maintained within1500mm)

Lot 1 150,000.00 150,000.00 15,000.00 15,000.00

- - 1.9 Supply and Laying of 10 Sq.mm Copper flexible cable

for earthing from cable tray to the Busbar Trunkingsystem along with the respective power cable. Mtrs 1835 92.00 168,820.00 20.00 36,700.00

1.10 Supply and tagging of cable tie for Wires Lot 1 3,500.00 3,500.00 2,500.00 2,500.00 - -

1.11 Supply, Laying, testing and Commissioning of thefollowing 1.1kV Grade XLPE insulated, PVC sheathed, armoured cable in existing cable trays and clamping. - -

a) 4c x 16 Sq.mm Cu XLPE Ar PVC cable Mtrs 1470 633.00 930,510.00 50.00 73,500.00 b) 3.5c x 50 Sq.mm Al XLPE Ar PVC cable Mtrs 315 226.00 71,190.00 75.00 23,625.00 c) 3.5c x 150 Sq.mm Al XLPE Ar PVC cable Mtrs 730 580.00 423,400.00 110.00 80,300.00 d) Supply and fixing of cable identification tags atboth Panel and at load ends of the cable.

Lot 1 5,000.00 5,000.00 2,500.00 2,500.00

e) Supply and Installation of supporting Material forLT Cables over Cable tray / from the roof levelangular supports.

Lot 1 5,000.00 5,000.00 3,500.00 3,500.00

- - 1.12 Supply and making terminations for the following

1.1kV Grade XLPE Insulated PVC sheathed cablesusing Double Compression cable glands, Copper /Aluminium Lugs, fastening with G.I hardwares withproper colour coded insulating sleeves at cable ends.

- -

a) 4c x 16 Sq.mm Cu XLPE Ar PVC cable Sets 36 350.00 12,600.00 100.00 3,600.00 b) 3.5c x 50 Sq.mm Al XLPE Ar PVC cable Sets 2 570.00 1,140.00 125.00 250.00

3 - 9

Page 4: YKK India - BOQ From Shivam

Unit Price Unit Total Unit Price Unit TotalSupply Installation

Sr. No. Description Unit Qty

c) 3.5c x 150 Sq.mm Al XLPE Ar PVC cable Sets 4 1,095.00 4,380.00 175.00 700.00 - -

1.13 Supply and Installation of the following Hot dipGalvanized Perforated type cable tray includingfittings such as coupling plates, Pre fabricated bends,Tee's , Reducers and Angular offset sections etc.,

- -

a) 150mm x 50mm x 2.0mm (Thick) cable Tray Mtrs 125 538.00 67,250.00 125.00 15,625.00 b) 200mm x 50mm x 2.0mm (Thick) Cable Tray Mtrs 15 645.00 9,675.00 125.00 1,875.00 c) Supporting Material for Cable tray from exisitngroof level angles using G I threaded rods / angleframes, clamping arrangements etc., Lot 1 25,000.00 25,000.00 5,000.00 5,000.00

- - 2 LIGHTING SYSTEM : - -

2.1 LV Lighting Panel : LCC-1 & LCC-2 - - Supply, Installation, Testing and Commissioning of415V, 3Phase, 4 Wire sheet steel fabricated, dust and vermin proof, Cubicle, Indoor type, free standing floormounted expandable type fabricated out of 1.6mmCRCA sheet steel complete with 100A, AluminiumBusbars, Adequate cable alley for terminatingIncoming and Outgoing cables with detachable Glandplates, complete terminal block arrangement withferrule markings, Space Heater, Proper ventillationarrangements complete with powder coated finishand comprising of.,

- -

Incoming : 100A, 4P MCCB with microprocessorbased O/C relay, with On/OFF and Phase Indicationlamps.

- -

Meterings: Digital Multi function meter with 3 Nos100/5A,15VA, Cl:1 CT, Control wirings and controlMCB's

- -

Busbars : 100A, 3 Phase Aluminium Busbars withheat shrikable coloured sleeves.

- -

Outgoings :21 Nos, 20A, DP MCB with 3R, 2.5 Sq.mmCopper wires wired to the outgoing terminal blocks atcable ally. (Each 7 Nos MCB Outgoings has to besegregated in separate chamber for each phase)

- -

Note : A separate chamber for outgoing circuits to beprovided with 16Nos, 2 Way , 16A Modular switchesas per enclosed SLD .

Nos 2 198,200.00 396,400.00 11,500.00 23,000.00

- - 2.2 LV Lighting Panel : LCC-3 - -

Supply, Installation, Testing and Commissioning of415V, 3Phase, 4 Wire sheet steel fabricated, dust and vermin proof, Cubicle, Indoor type, free standing floormounted expandable type fabricated out of 1.6mmCRCA sheet steel complete with 100A, AluminiumBusbars, Adequate cable alley for terminatingIncoming and Outgoing cables with detachable Glandplates, complete terminal block arrangement withferrule markings, Space Heater, Proper ventillationarrangements complete with powder coated finishand comprising of.,

- -

Incoming : 100A, 4P MCCB with microprocessorbased O/C relay, with On/OFF and Phase Indicationlamps.

- -

Meterings: Digital Multi function meter with 3 Nos100/5A,15VA, Cl:1 CT, Control wirings and controlMCB's

- -

Busbars : 100A, 3 Phase Aluminium Busbars withheat shrikable coloured sleeves.

- -

Outgoings :25 Nos, 20A, DP MCB with 3R, 2.5 Sq.mmCopper wires wired to the outgoing terminal blocks atcable ally. (Each 9/8 Nos MCB Outgoings has to besegregated in separate chamber for each phase:Refer SLD)

- -

Note : A separate chamber for outgoing circuits to beprovided with 16 Nos, 2 Way , 16A Modular switchesas per enclosed SLD .

Nos 1 197,000.00 197,000.00 11,500.00 11,500.00

- - 2.3 Supply, Testing , Installation and commissioning of

36W x 2 Industrial type Flourscent lamp withReflector and tubes. Make : Phillips, Cat No:TMC 055(2x36W) EBT

Nos 22 1,895.00 41,690.00 175.00 3,850.00

- - 2.4 Supply and fixing of supporting materials for lighting

fixtures such as clamps and hardwares.Lot 1 4,000.00 4,000.00 2,000.00 2,000.00

- -

4 - 9

Page 5: YKK India - BOQ From Shivam

Unit Price Unit Total Unit Price Unit TotalSupply Installation

Sr. No. Description Unit Qty

2.5 Supply, Fixing and connecting of 2 Way, 16A,Modular type switch with 1 Module Plate and 1Module Zinc Chromate MS Box. Make : MK . Nos 47 325.00 15,275.00 75.00 3,525.00

- - 2.6 Supply and laying of 3Runs, 2.5 Sq.mm FRLS PVC

Insulated copper Wires in raceways for lightingwiring.

Mtrs 5065 77.00 390,005.00 15.00 75,975.00

2.7 Tagging for Wires Lot 1 4,500.00 4,500.00 3,000.00 3,000.00 - -

2.8 Supply & Installation of 50 x 50 x 1.6mm (Thick) MSsheet steel fabricated, Powder coated Raceway forlighting wiring with detachable side cover provision. Mtrs 300 335.00 100,500.00 75.00 22,500.00

2.9 Supply and Installaiton of Fittings such as 'L' Bends ,Tee's, and couplings for Raceway.

Lot 1 15,000.00 15,000.00 5,000.00 5,000.00

2.10 Supply and Fixing of raceway supporting Materialsuch as clamps, Threaded drop rods and Angularsupports etc.,

Lot 1 25,000.00 25,000.00 7,500.00 7,500.00

- - 3 POWER SOCKET SYSTEM : - -

3.1 Supply and Installation of Power Socket outlet of240V 2P+E 6A/16A 1 Gang with 1M oduleSwitch,2Module Socket, 4Module Plate and ZincChromate MS Box.

Nos 27 504.00 13,608.00 75.00 2,025.00

3.2 Supplyand Installation of 3 Phase Power Socketoutlet 63A, 415V 3P+E Plug and socket with 63A, TPMCB in metal clad enclosure.

Nos 2 9,425.00 18,850.00 950.00 1,900.00

- - 3.3 Supply, Laying and Terminating of 3R, 4 Sq.mm

FRLS PVC Insulated Copper flexible cable for Powersocket outlets with suitable copper thimbles. Mtrs 985 111.00 109,335.00 15.00 14,775.00

3.4 Supply and fixing of Tagging materials for Wires Lot 1 2,000.00 2,000.00 2,000.00 2,000.00 - -

3.5 Supply, Laying, testing and Commissioning of thefollowing 1.1kV Grade XLPE insulated, PVC sheathed, armoured cable in existing cable trays and clamping. - -

a) 4c x 16 Sq.mm Cu XLPE Ar PVC cable) Mtrs 115 633.00 72,795.00 50.00 5,750.00 b) Supply and fixing of cable identification tags atboth Panel and at load ends of the cable.

Lot 1 1,580.00 1,580.00 500.00 500.00

c) Supply and Installation of supporting Material forLT Cables over Cable tray / from the roof levelangular supports.

Lot 1 3,500.00 3,500.00 2,000.00 2,000.00

- - 3.6 Supply and making terminations for the following

1.1kV Grade XLPE Insulated PVC sheathed cablesusing Double Compression cable glands, CopperLugs, fastening with G.I hardwares with propercolour coded insulating sleeves at cable ends.

- -

a) 4c x 16 Sq.mm Cu XLPE Ar PVC cable Sets 4 350.00 1,400.00 100.00 400.00 - -

3.7 Supply and Laying of 25mm Dia, 1.6mm Thick G.Iconduit pipe for 240V Power socket wiring withaccessories such as Bends, Junction boxes,Couplings and saddles etc.,

Mtrs 895 195.00 174,525.00 30.00 26,850.00

3.8 Supply and Laying of 40mm Dia, 2.0mm Thick G.Iconduit pipe for 415V Power socket wiring withaccessories such as Bends, Junction boxes,Couplings and saddles etc.,

Mtrs 8 470.00 3,760.00 50.00 400.00

- - III PHASE - III : REMOVING WORKS at N2, S2

AREA:- -

- - 1 POWER DISTRIBUTION FOR MACHINES : - -

1.1 Removing of the existing Bus Trunking system formachines and its supports mounted from roof level. - -

a) 63A, 4P, BT No: 02, Fed from PP-12A Mtrs 48 - 150.00 7,200.00 b) 63A, 4P, BT No: 01, Fed from PP-12 Mtrs 12 - 150.00 1,800.00 c) 63A, 4P, BT No: 56, Fed from PP-12 Mtrs 21 - 150.00 3,150.00 d) 63A, 4P, BT No: 57, Fed from PP-12 Mtrs 12 - 150.00 1,800.00 e) 63A, 4P, BT No: 58, Fed from PP-12 Mtrs 21 - 150.00 3,150.00 f) 63A, 4P, BT No: 60, Fed from PP-12 Mtrs 0.5 - 150.00 75.00 g) 63A, 4P, BT No: 61, Fed from PP-12 Mtrs 21 - 150.00 3,150.00 h) 63A, 4P, BT No: 62, Fed from PP-12 Mtrs 21 - 150.00 3,150.00 i) 63A, 4P, BT No: 63, Fed from PP-12 Mtrs 12 - 150.00 1,800.00 j) 63A, 4P, BT No: 64, Fed from PP-12 Mtrs 21 - 150.00 3,150.00 k) 63A, 4P, BT No: 65, Fed from PP-12 Mtrs 12 - 150.00 1,800.00 l) 63A, 4P, BT No: 31, Fed from PP-11 Mtrs 18 - 150.00 2,700.00 m) 63A, 4P, BT No: 32, Fed from PP-11 Mtrs 15 - 150.00 2,250.00 n) 63A, 4P, BT No: 33, Fed from PP-11 Mtrs 6 - 150.00 900.00 o) 63A, 4P, BT No: 34, Fed from PP-11 Mtrs 18 - 150.00 2,700.00

5 - 9

Page 6: YKK India - BOQ From Shivam

Unit Price Unit Total Unit Price Unit TotalSupply Installation

Sr. No. Description Unit Qty

p) 63A, 4P, BT No: 35, Fed from PP-11 Mtrs 15 - 150.00 2,250.00 q) 63A, 4P, BT No: 36, Fed from PP-11 Mtrs 6 - 150.00 900.00 r) 63A, 4P, BT No: 49, Fed from PP-11A Mtrs 9 - 150.00 1,350.00 s) 63A, 4P, BT No: 50, Fed from PP-11A Mtrs 30 - 150.00 4,500.00 t) 63A, 4P, BT No: 51, Fed from PP-11A Mtrs 9 - 150.00 1,350.00 u) 63A, 4P, BT No: 52, Fed from PP-11A Mtrs 9 - 150.00 1,350.00 v) 63A, 4P, BT No: 53, Fed from PP-11A Mtrs 30 - 150.00 4,500.00 w) 63A, 4P, BT No: 54, Fed from PP-11A Mtrs 30 - 150.00 4,500.00 x) 63A, 4P, BT No: 30&34, Fed from PP-10 Mtrs 30 - 150.00 4,500.00

427 - - 1.2 Removing of the existing 4c x 16 Sq.mm Al Ar cable

feeding the bus trunking from cable tray / supportingfrom roof.

Mtrs 1032 - 50.00 51,600.00

- - 1.3 Removing the terminations of 4c x 16 Sq.mm

Aluminium ar cable at panel and at Bus Trunkingend.

Nos 50 - 100.00 5,000.00

- - 2 LIGHTING SYSTEM : - -

2.1 Removing of the 50mm x 50 mm x 2400mm (Length)MS sheet steel Powder coated Race way covers forremoving the lighting wirings laid in the raceways andstoring them in a safe work place.

Mtrs 952 - 75.00 71,400.00

- - 2.2 Removing of the 3 runs of 2.5 Sq.mm Copper flexible

wires in Race ways for lighting circuits, removing theterminations in the fittings and storing. Mtrs 2176 - 15.00 32,640.00

- - 2.3 Removing the Flourscent tube, Reflector and the

cover of the light fixtures for disconnecting thecircuit wires and storing them in a safe workingplace.

Nos 336 - 125.00 42,000.00

- - IV PHASE - III : SUPPLY & INSTALL WORKS at PF

ASSY AREA.- -

- - 1 POWER for MACHINE : - -

1.1 Supply and Installation of Feeder Box for LV BusbarTrunking system (Make: M/s EAE Catno.KAP0605BB)

Nos 35 3,100.00 108,500.00 650.00 22,750.00

- - 1.2 Supply, Installation, Testing and Commissioning of LV

Busbar Trunking system ( Make: M/s EAE, Catno.KAP0604)

Nos 181 8,715.00 1,577,415.00 600.00 108,600.00

- - 1.3 Supply and Installation of End Box for LV Busbar

trunking system (Make: M/s EAE, Catno.KAP0605BS)

Nos 35 3,100.00 108,500.00 300.00 10,500.00

- - 1.4 Supply, Installation of Tap Off Plug for the LV Busbar

Trunking system (Make: M/s EAE Cat no.KAP16-KL123)

Nos 235 1,500.00 352,500.00 150.00 35,250.00

- - 1.5 Supply and installation of suitable supporting Material

with drop rod arrangement from roofing supports forthe LV Busbar trunking system (The distancebetween supports should be maintained within1500mm)

Lot 1 185,000.00 185,000.00 20,000.00 20,000.00

- - 1.6 Supply and Laying of 10 Sq.mm Copper flexible cable

for earthing from cable tray to the Busbar Trunkingsystem along with the respective power cable. Mtrs 1835 92.00 168,820.00 20.00 36,700.00

1.7 Supply and tagging of cable tie for Wires Lot 1 3,500.00 3,500.00 2,500.00 2,500.00 - -

1.8 Supply, Laying, testing and Commissioning of thefollowing 1.1kV Grade XLPE insulated, PVC sheathed, armoured cable in existing cable trays and clamping. - -

a) 4c x 16 Sq.mm Cu XLPE Ar PVC cable Mtrs 1870 633.00 1,183,710.00 50.00 93,500.00 - -

b) Supply and fixing of cable identification tags atboth Panel and at load ends of the cable.

Lot 1 3,500.00 3,500.00 2,000.00 2,000.00

- - c) Supply and Installation of supporting Material forLT Cables over Cable tray / from the roof levelangular supports.

Lot 1 4,000.00 4,000.00 3,500.00 3,500.00

- -

6 - 9

Page 7: YKK India - BOQ From Shivam

Unit Price Unit Total Unit Price Unit TotalSupply Installation

Sr. No. Description Unit Qty

1.9 Supply and making terminations for the following1.1kV Grade XLPE Insulated PVC sheathed cablesusing Double Compression cable glands, CopperLugs, fastening with G.I hardwares with propercolour coded insulating sleeves at cable ends.

- -

a) 4c x 16 Sq.mm Cu XLPE Ar PVC cable Sets 38 350.00 13,300.00 100.00 3,800.00 - -

1.10 Supply and Installation of the following Hot dipGalvanized Perforated type cable tray includingfittings such as coupling plates, Pre fabricated bends,Tee's , Reducers and Angular offset sections etc.,

- -

a) 150mm x 50mm x 2.0mm (Thick) cable Tray Mtrs 95 538.00 51,110.00 125.00 11,875.00 b) 200mm x 50mm x 2.0mm (Thick) Cable Tray Mtrs 25 645.00 16,125.00 125.00 3,125.00 c) Supporting Material for Cable tray from exisitngroof level angles using G I threaded rods / angleframes, clamping arrangements etc., Lot 1 17,000.00 17,000.00 3,000.00 3,000.00

- - 2 LIGHTING SYSTEM : - -

2.1 Supply, Testing , Installation and commissioning of36W x 2 Industrial type Flourscent lamp withReflector and tubes. Make : Phillips, Cat No:TMC 055(2x36W) EBT

Nos 20 1,895.00 37,900.00 175.00 3,500.00

- - 2.2 Supply and fixing of supporting materials for lighting

fixtures such as clamps and hardwares.Lot 1 3,500.00 3,500.00 2,000.00 2,000.00

- - 2.3 Supply, Fixing and connecting of 2 Way, 16A,

Modular type switch with 1 Module Plate and 1Module Zinc Chromate MS Box. Make : MK . Nos 60 325.00 19,500.00 75.00 4,500.00

- - 2.4 Supply and laying of 3Runs, 2.5 Sq.mm FRLS PVC

Insulated copper Wires in raceways for lightingwiring.

Mtrs 9860 77.00 759,220.00 15.00 147,900.00

2.5 Tagging for Wires Lot 1 5,000.00 5,000.00 3,500.00 3,500.00 - -

2.6 Supply & Installation of 50 x 50 x 1.6mm (Thick) MSsheet steel fabricated, Powder coated Raceway forlighting wiring with detachable side cover provision. Mtrs 115 335.00 38,525.00 75.00 8,625.00

- - 2.7 Supply and Installaiton of Fittings such as 'L' Bends ,

Tee's, and couplings for Raceway.Lot 1 10,000.00 10,000.00 4,000.00 4,000.00

- - 2.8 Supply and Fixing of raceway supporting Material

such as clamps, Threaded drop rods and Angularsupports etc.,

Lot 1 20,000.00 20,000.00 6,500.00 6,500.00

- - V PHASE - III : REMOVING WORKS at N1, S1

AREA:- -

- - 1 POWER DISTRIBUTION FOR MACHINES : - -

1.1 Removing of the existing Bus Trunking system formachines and its supports mounted from roof level. - -

a) 63A, 4P, BT No: 03, Fed from PP-9A Mtrs 15 - 150.00 2,250.00 b) 63A, 4P, BT No: 04, Fed from PP-9A Mtrs 12 - 150.00 1,800.00 c) 63A, 4P, BT No: 5, Fed from PP-9A Mtrs 12 - 150.00 1,800.00 d) 63A, 4P, BT No: 6, Fed from PP-9A Mtrs 15 - 150.00 2,250.00 e) 63A, 4P, BT No: 7, Fed from PP-10 Mtrs 18 - 150.00 2,700.00 f) 63A, 4P, BT No: 17, Fed from PP-10A Mtrs 1 - 150.00 150.00 g) 63A, 4P, BT No: 15, Fed from PP-9A Mtrs 12 - 150.00 1,800.00 h) 63A, 4P, BT No: 16, Fed from PP-9A Mtrs 12 - 150.00 1,800.00 i) 63A, 4P, BT No: 13, Fed from PP-9A Mtrs 15 - 150.00 2,250.00 j) 63A, 4P, BT No: 14, Fed from PP-9A Mtrs 15 - 150.00 2,250.00 k) 63A, 4P, BT No: 12, Fed from PP-9 Mtrs 9 - 150.00 1,350.00 l) 63A, 4P, BT No: 37, Fed from PP-9A Mtrs 9 - 150.00 1,350.00 m) 63A, 4P, BT No: 18, Fed from PP-10A Mtrs 36 - 150.00 5,400.00 n) 63A, 4P, BT No: 38, Fed from PP-9A Mtrs 18 - 150.00 2,700.00 o) 63A, 4P, BT No: 19, Fed from PP-10A Mtrs 30 - 150.00 4,500.00 p) 63A, 4P, BT No: 01, Fed from PP-9 Mtrs 18 - 150.00 2,700.00 q) 63A, 4P, BT No: 02, Fed from PP-9 Mtrs 12 - 150.00 1,800.00 r) 63A, 4P, BT No: 08, Fed from PP-9 Mtrs 15 - 150.00 2,250.00 s) 63A, 4P, BT No: 09, Fed from PP-9 Mtrs 15 - 150.00 2,250.00 t) 63A, 4P, BT No: 10, Fed from PP-9 Mtrs 15 - 150.00 2,250.00 u) 63A, 4P, BT No: 11, Fed from PP-9 Mtrs 9 - 150.00 1,350.00 v) 63A, 4P, BT No: 40, Fed from PP-9 Mtrs 18 - 150.00 2,700.00 w) 63A, 4P, BT No: 16, Fed from PP-10 Mtrs 15 - 150.00 2,250.00 x) 63A, 4P, BT No: 29, Fed from PP-9 Mtrs 15 - 150.00 2,250.00 y) 63A, 4P, BT No: 37, Fed from PP-11 Mtrs 18 - 150.00 2,700.00 z) 63A, 4P, BT No: 25, Fed from PP-10 Mtrs 18 - 150.00 2,700.00 aa) 63A, 4P, BT No: 21, Fed from PP-10 Mtrs 18 - 150.00 2,700.00

7 - 9

Page 8: YKK India - BOQ From Shivam

Unit Price Unit Total Unit Price Unit TotalSupply Installation

Sr. No. Description Unit Qty

ab) 63A, 4P, BT No: 22, Fed from PP-10 Mtrs 12 - 150.00 1,800.00 ac) 63A, 4P, BT No: 23, Fed from PP-10 Mtrs 18 - 150.00 2,700.00 ad) 63A, 4P, BT No: 24, Fed from PP-10 Mtrs 18 - 150.00 2,700.00 ae) 63A, 4P, BT No: 27, Fed from PP-10 Mtrs 6 - 150.00 900.00 af) 63A, 4P, BT No: 28, Fed from PP-10 Mtrs 9 - 150.00 1,350.00

486 - - - -

1.2 Removing of the existing 4c x 16 Sq.mm Al Ar cablefeeding the bus trunking from cable tray / supportingfrom roof.

Mtrs 1675 - 50.00 83,750.00

- - 1.3 Removing the terminations of 4c x 16 Sq.mm

Aluminium ar cable at panel and at Bus Trunkingend.

Nos 64 - 100.00 6,400.00

- - 2 LIGHTING SYSTEM : - -

2.1 Removing of the 50mm x 50 mm x 2400mm (Length)MS sheet steel Powder coated Race way covers forremoving the lighting wirings laid in the raceways andstoring them in a safe work place.

Mtrs 1940 - 75.00 145,500.00

- - 2.2 Removing of the 3 runs of 2.5 Sq.mm Copper flexible

wires in Race ways for lighting circuits, removing theterminations in the fittings and storing. Mtrs 4290 - 15.00 64,350.00

- - 2.3 Removing the Flourscent tube, Reflector and the

cover of the light fixtures for disconnecting thecircuit wires and storing them in a safe workingplace.

Nos 588 - 125.00 73,500.00

- - VI PHASE - III : SUPPLY & INSTALLATION WORKS

at PF CHAIN AREA.- -

- - 1 POWER for MACHINE : - -

1.1 Supply and Installation of Feeder Box for LV BusbarTrunking system (Make: M/s EAE Catno.KAP0605BB)

Nos 24 3,100.00 74,400.00 650.00 15,600.00

- - 1.2 Supply, Installation, Testing and Commissioning of LV

Busbar Trunking system ( Make: M/s EAE, Catno.KAP0604)

Nos 107 8,715.00 932,505.00 600.00 64,200.00

- - 1.3 Supply and Installation of End Box for LV Busbar

trunking system (Make: M/s EAE, Catno.KAP0605BS)

Nos 24 3,100.00 74,400.00 300.00 7,200.00

- - 1.4 Supply, Installation of Tap Off Plug for the LV Busbar

Trunking system (Make: M/s EAE Cat no.KAP16-KL123)

Nos 136 1,500.00 204,000.00 150.00 20,400.00

- - 1.5 Supply and installation of suitable supporting Material

with drop rod arrangement from roofing supports forthe LV Busbar trunking system (The distancebetween supports should be maintained within1500mm)

Lot 1 115,000.00 115,000.00 12,500.00 12,500.00

- - 1.6 Supply and Laying of 10 Sq.mm Copper flexible cable

for earthing from cable tray to the Busbar Trunkingsystem along with the respective power cable. Mtrs 1145 92.00 105,340.00 20.00 22,900.00

1.7 Supply and tagging of cable tie for Wires Lot 1 3,500.00 3,500.00 2,500.00 2,500.00 - -

1.8 Supply, Laying, testing and Commissioning of thefollowing 1.1kV Grade XLPE insulated, PVC sheathed, armoured cable in existing cable trays and clamping. - -

a) 4c x 16 Sq.mm Cu XLPE Ar PVC cable Mtrs 1165 633.00 737,445.00 50.00 58,250.00 b) Supply and fixing of cable identification tags atboth Panel and at load ends of the cable.

Lot 1 3,500.00 3,500.00 2,000.00 2,000.00

c) Supply and Installation of supporting Material forLT Cables over Cable tray / from the roof levelangular supports.

Lot 1 4,000.00 4,000.00 3,500.00 3,500.00

- - 1.9 Supply and making terminations for the following

1.1kV Grade XLPE Insulated PVC sheathed cablesusing Double Compression cable glands, CopperLugs, fastening with G.I hardwares with propercolour coded insulating sleeves at cable ends.

- -

a) 4c x 16 Sq.mm Cu XLPE Ar PVC cable Sets 24 350.00 8,400.00 100.00 2,400.00 - -

8 - 9

Page 9: YKK India - BOQ From Shivam

Unit Price Unit Total Unit Price Unit TotalSupply Installation

Sr. No. Description Unit Qty

1.10 Supply and Installation of the following Hot dipGalvanized Perforated type cable tray includingfittings such as coupling plates, Pre fabricated bends,Tee's , Reducers and Angular offset sections etc.,

- -

a) 150mm x 50mm x 2.0mm (Thick) cable Tray Mtrs 45 538.00 24,210.00 125.00 5,625.00 b) Supporting Material for Cable tray from exisitngroof level angles using G I threaded rods / angleframes, clamping arrangements etc., Lot 1 10,000.00 10,000.00 5,000.00 5,000.00

- - 2 LIGHTING SYSTEM : - -

2.1 Supply, Fixing and connecting of 2 Way, 16A,Modular type switch with 1 Module Plate and 1Module Zinc Chromate MS Box. Make : MK . Nos 60 325.00 19,500.00 75.00 4,500.00

- - 2.2 Supply and laying of 3 Runs, 2.5 Sq.mm FRLS PVC

Insulated copper Wires in raceways for lightingwiring.

Mtrs 9965 77.00 767,305.00 15.00 149,475.00

2.3 Tagging for Wires Lot 1 5,000.00 5,000.00 3,500.00 3,500.00 - -

2.4 Supply & Installation of 50 x 50 x 1.6mm (Thick) MSsheet steel fabricated, Powder coated Raceway forlighting wiring with detachable side cover provision. Mtrs 110 335.00 36,850.00 75.00 8,250.00

- - 2.5 Supply and Installation of Fittings such as 'L' Bends ,

Tee's, and couplings for Raceway.Lot 1 10,000.00 10,000.00 4,000.00 4,000.00

- - 2.6 Supply and Fixing of raceway supporting Material

such as clamps, Threaded drop rods and Angularsupports etc.,

Lot 1 15,000.00 15,000.00 5,000.00 5,000.00

- - 3.0 MISCELLANEOUS : - -

- - 3.1 Charges for providing scaffolding / Ladder for

removing and Installation works.Lot 1 - - 150,000.00 150,000.00

Total: 13,756,528.00 2,781,590.00 (Materials prices must be follow as per terms & conditons)

ADD SERVICE TAX ON [email protected]% 343,804.52

Grand Total 13,756,528.00 3,125,394.52

TOTAL(SUPPLY+INSTALLATION) 16,881,922.52