X-Stream Gas Transport Concept Rev

download X-Stream Gas Transport Concept Rev

of 28

Transcript of X-Stream Gas Transport Concept Rev

  • Asle Venas, Director Pipelines

    20 Jan 2012

    X-Stream Gas transport concept

    Press conference, London

  • Det Norske Veritas AS. All rights reserved.

    X-Stream Gas transport concept

    20 Jan 2012

    The challenge

    2

    An increasing challenge:

    Long distance gas transport-ation in deep waters

    More and more harsh environment

    The time of easy oil is over

  • Det Norske Veritas AS. All rights reserved.

    X-Stream Gas transport concept

    20 Jan 2012

    Deepwater and ultra-deepwater gas pipelines

    3

    Large diameter Thick wall:

    Difficult to produce Limited number of pipe mills Heavy pipes difficult

    handling and logistics

    Difficult to weld

    Extremely thick and costly buckle arrestors

    Limited number of pipe-lay vessels

  • Det Norske Veritas AS. All rights reserved.

    X-Stream Gas transport concept

    20 Jan 2012

    X-Stream

    4

    Idea:

    Reduced wall thickness of long distance deepwater gas pipelines by controlling the differential pressure

    The objective:

    Reduce the cost of deepwater gas pipelines within current safety regime

    About X-Stream:

    A DNV innovation project

  • Det Norske Veritas AS. All rights reserved.

    X-Stream Gas transport concept

    20 Jan 2012

    X-Stream

    5

    Codes and standards:

    The new concept fulfills common pipeline

    codes like ISO and DNV-OS-F101

    Basis:

    The concept is based on a combination of already established and field proven technology in an innovative way

  • Det Norske Veritas AS. All rights reserved.

    X-Stream Gas transport concept

    20 Jan 2012

    X-Stream

    6

    Inspired by the HIPPS concept There are already more than 20 HIPPS systems in use worldwide today

  • Det Norske Veritas AS. All rights reserved.

    X-Stream Gas transport concept

    20 Jan 2012

    Video 1

    7

  • Det Norske Veritas AS. All rights reserved.

    X-Stream Gas transport concept

    20 Jan 2012

    X-Stream

    In order to control the differential pressure

    DNV introduces

    i-HIPPS (Inverted-HIPPS)

    8

  • Det Norske Veritas AS. All rights reserved.

    X-Stream Gas transport concept

    20 Jan 2012

    Video 2

    9

  • Det Norske Veritas AS. All rights reserved.

    X-Stream Gas transport concept

    20 Jan 2012

    X-Stream main principle in a lifecycle perspective

    1. Install pipeline water filled fully or partly

    2. Carry out normal flooding, cleaning and gauging of the pipeline

    3. Dewater and dry the pipeline

    4. Maintain a certain minimum internal pressure in the pipeline during the entire life of

    the pipeline by use of i-HIPPS

    10

  • Det Norske Veritas AS. All rights reserved.

    X-Stream Gas transport concept

    20 Jan 2012

    Example

    Product: treated associated gas (pipeline export)

    Distance to shore: 400 km

    - 300 km in deep waters

    - 100 km in shallow waters

    Water depth: 3,000 meters (ultra-deep waters)

    Pipeline export:

    - Diameters analysed: 4 off (18, 24, 28 and 32)

    - Installation method: J-lay

    - Installation: Partially water-filled

    - Safety Class: Medium

    - Operational pressure: 250 bar

    - Minimum internal pressure: 200 bar (in i-HIPPS area)

    - With and without concrete coating (specific gravity

    1.1)

    11

  • Det Norske Veritas AS. All rights reserved.

    X-Stream Gas transport concept

    20 Jan 2012

    Installation

    12

    Collapse Depth

    Flood Level

    Factor of Safety

    Seabed

    Level

    Empty Pipe

    Flooded Pipe

  • Det Norske Veritas AS. All rights reserved.

    X-Stream Gas transport concept

    20 Jan 2012

    Required wall thickness

    13

  • Det Norske Veritas AS. All rights reserved.

    X-Stream Gas transport concept

    20 Jan 2012

    Top tension vs. flooding level

    14

  • Det Norske Veritas AS. All rights reserved.

    X-Stream Gas transport concept

    20 Jan 2012

    15

    Reduced wall thickness Example for 18 diameter

    Pipeline data Traditional

    pipeline

    X-Stream

    without

    concrete

    X-Stream

    with concrete

    OD (m) 0,457

    0,457 0,457

    Wall thickness (mm) 25

    17 16

    Concrete thickness (mm)

    minimum 12

    Wall thickness saving 32% 36%

  • Det Norske Veritas AS. All rights reserved.

    X-Stream Gas transport concept

    20 Jan 2012

    Reduced costs four diameters

    Reduced cost due to less steel required

    Reduced installation costs due to reduced welding times

    16

    -40 %

    -35 %

    -30 %

    -25 %

    -20 %

    -15 %

    -10 %

    -5 %

    0 %

    18" 24" 28" 32"

    -32 %-30 % -29 %

    -28 %

    -36 % -36 % -37 % -37 %

    X-Stream without Concrete

    X-Stream with Concrete

  • Det Norske Veritas AS. All rights reserved.

    X-Stream Gas transport concept

    20 Jan 2012

    How can the X-stream concept work safe and reliable?

    17

  • Det Norske Veritas AS. All rights reserved.

    X-Stream Gas transport concept

    20 Jan 2012

    How can the X-stream concept work safe and reliable?

    18

  • Det Norske Veritas AS. All rights reserved.

    X-Stream Gas transport concept

    20 Jan 2012

    How can the X-stream concept work safe and reliable?

    19

  • Det Norske Veritas AS. All rights reserved.

    X-Stream Gas transport concept

    20 Jan 2012

    How can the X-stream concept work safe and reliable?

    20

  • Det Norske Veritas AS. All rights reserved.

    X-Stream Gas transport concept

    20 Jan 2012

    How can the X-stream concept work safe and reliable?

    21

  • Det Norske Veritas AS. All rights reserved.

    X-Stream Gas transport concept

    20 Jan 2012

    How can the X-stream concept work safe and reliable?

    22

  • Det Norske Veritas AS. All rights reserved.

    X-Stream Gas transport concept

    20 Jan 2012

    i-DBB concept

    DNV has run a concept risk analysis and one major issue came up:

    There will at least be required to have a 100% leak tight secondary valve as a leak or rupture may take time to repair.

    - We have therefore also developed a very simple and reliable system that will give a 100%

    internal leak tight valve.

    - The system is an inverted double-block-and-bleed system we call i-DBB

    23

  • Det Norske Veritas AS. All rights reserved.

    X-Stream Gas transport concept

    20 Jan 2012

    Video 3

    24

  • Det Norske Veritas AS. All rights reserved.

    X-Stream Gas transport concept

    20 Jan 2012

    Main benefits

    Reduced steel quantity

    More pipe mills can deliver linepipe

    Easier to manufacture higher grades

    Reduced weight of linepipe

    Reduced welding times

    Increased lay rates

    May not need buckle arrestors

    Equal safety level

    25

  • Det Norske Veritas AS. All rights reserved.

    X-Stream Gas transport concept

    20 Jan 2012

    Some of the planned deepwater pipelines

    26

  • Det Norske Veritas AS. All rights reserved.

    X-Stream Gas transport concept

    20 Jan 2012

    Conclusion

    27

    Fulfils common pipeline codes and standards, i.e. ISO and DNV-OS-F101

    Based on established and field proven technology combined in an innovative way

    A safe and reliable system that ensures significant savings in terms of wall thickness, handling and installation time