Www.fdiplan.com Simulation Modeling and Design David Ferrin Principal Tanner Flynn Associate...
-
Upload
bertram-ferguson -
Category
Documents
-
view
222 -
download
4
Transcript of Www.fdiplan.com Simulation Modeling and Design David Ferrin Principal Tanner Flynn Associate...
www.fdiplan.com
Simulation Modeling and DesignSimulation Modeling and Design
David FerrinPrincipal
Tanner FlynnAssociate Principal
Brian HolleyHealthcare Market Director-
California Region
Designing how facilities will be used before designing the facilities.
Confidential and Proprietary © 2008 FDI
Agenda
Lean PhilosophyWhat is Simulation – Who uses it?Comparing Simulation To “Spreadsheet” PlanningSimulation In Action - MethodologyCase Study Outcomes and Conclusions
Confidential and Proprietary © 2008 FDI
Lean Philosophy
Lean means eliminating waste from any process or product.
The first step is to identify the true Value Stream of a business process. A clearly defined and agreed upon Value Stream throughout the organization is the basis for any improvement action to achieve high process performance at a significantly reduced cost base.
Confidential and Proprietary © 2008 FDI
Lean Philosophy
Conceptually, the business processes in Lean are viewed from the customer’s perspective.
The value of an activity is solely defined by the customer.
Activities that add value to the customer are those that make the product or service resemble more of what the customer actually wants and for which he is willing to pay.
Non value-added activities, however, do not create any value for the customer, and therefore all nonessential, non-value-added activities are considered as waste.
Waste is any activity in the workflow that adds time, effort or cost but does not create value.
Confidential and Proprietary © 2008 FDI
Six Sigma and Lean
Eliminate defects as defined by the customer
Recognizes that variations hinder our ability to reliably deliver high quality products
Requires data-driven decisions
Set tools for effective problem solving
Focus on maximizing process velocity
Tools for analyzing process flows and delays
Centers on value added vs non-value added
Means for quantifying and eliminating complexity
Six Sigma Lean
Confidential and Proprietary © 2008 FDI
Lean and Six Sigma
Lean = Improved process flow
Six Sigma = Reduced process variation
Confidential and Proprietary © 2008 FDI
Agenda
Lean Philosophy
What is Simulation – Who uses it?
Comparing Simulation To “Spreadsheet” Planning
Simulation In Action - Methodology
Case Study Outcomes and Conclusions
Confidential and Proprietary © 2008 FDI
How industry analysts regard simulation
"Virtually all of the Fortune 50, a majority of the Fortune 1000 and military planning units of all technologically advanced countries, use simulation rather than subjective notions to make decisions about key manufacturing and logistics process decisions. There are no good reasons why simulation should not be used to aid decisions about key business processes. On the contrary, there are numerous good reasons why simulation should be used for BPR."
Robert Crosslin
"Simulation, The Key to Designing and Justifying Business Reengineering Projects"The Electronic College of Process Innovation
.
Simulation and animation technology offers ... organizations the potential to more rigorously test, analyze, validate and communicate their business processes and systems before they invest in implementation.”
- The Gartner Group
Confidential and Proprietary © 2008 FDI
Rush-Presbyterian-St. Luke’s Medical Center
Organizations our team members have helped realize the benefits of Simulation Modeling
Confidential and Proprietary © 2008 FDI
“When should we use simulation?”
Simulation is the only tool that can provide the right answer when:
You can’t afford to miss the design the first time.
You need to evaluate complex system interactions - when operations have lots of steps with wide time variations and require multiple individuals and physical resources.
You need to understand the combined financial, operational, and human
experience of the design
Confidential and Proprietary © 2008 FDI
Agenda
Lean PhilosophyWhat is Simulation – Who uses it?Comparing Simulation To “Spreadsheet” PlanningSimulation In Action - MethodologyCase Study Outcomes and Conclusions
Confidential and Proprietary © 2008 FDI
Most Planning Is Done Using Static Models Based on Averages
Example: Let us attempt to model ED flow
using averages (e.g. the spreadsheet model) Patients arrive every 10 minutes Each activity lasts 10 minutes
Can you predict what the mean patient LOS will be?
What will be the 95%-ile range?
Spreadsheet Model
Simulation Model
Mean
Lower Bound
Upper Bound
Run spreadsheet model:
Patients Arrive
10 minutes between arrivals
Triage Patient
Physician 1
1.1
10 m
Assess Patient
Physician 2
1.2
10 m
Diagnose Patient
Physician 3
1.3
10 m
Discharged /AdmittedPatients
Confidential and Proprietary © 2008 FDI
The Results Are Predictable… And Do Not Mirror Real Processes!
Results of the spreadsheet model are at the right:
Notice the process behavior of the model: Physicians finish their activity just as the
next patient arrives Patients never wait in queue The LOS never varies Patients move with drum-beat
synchronicity through the ED Physician utilization is effectively 100%
Spreadsheet Model
Simulation Model
Mean 30mins
Lower Bound 30mins
Upper Bound 30mins
Do real processes behave like this?
Confidential and Proprietary © 2008 FDI
Simulation Accounts for Process Variability
Triage is normally distributed with a mean of 10mins, and a standard deviation of 2mins
Diagnosis is uniformly distributed, so that all times between 8 and 12 minutes are equally likely, mean is 10mins
Note-average times for these activities are still 10mins give or take a couple!
Let us introduce variability into this example (ED flow) and analyze the process:
Can you predict the new patient LOS? What will be the 95%-ile range?
Run simulation model:
Patient arrival is exponential with a mean of 10mins
Assessment is triangularly distributed, so that it always takes 8mins, usually takes 10mins, but never more than 12mins
Confidential and Proprietary © 2008 FDI
Simulation Model Produces Drastically Different Outcomes From Spreadsheet Model
Results of the simulation model are at the right (50 iterations of 1 week are run):
Notice the process behavior of this model: Patient LOS is 3 – 5 hours Long queue waiting for Physician 1 Physician utilization still 100%
Notice how small variations in the process increased patient LOS dramatically
Triage Patient
Physician 1
1.1
Normal (10,2)
Patients Arrive
Time between arrivals: Exponential (10) minutes
Assess Patient
Physician 2
1.2
8 m 10 m 12 m
Diagnose Patient
Physician 3
1.3
Uniform (8,12)
Discharged /AdmittedPatients
Spreadsheet Model
Simulation Model
Mean 30mins 4.3 hrs
Lower Bound 30mins 3.5 hrs
Upper Bound 30mins 5.1 hrs
Only about 10% of the total LOS is value-added time; the rest is time spent in queue – how would you account for this on a spreadsheet?
Confidential and Proprietary © 2008 FDI
Agenda
Lean PhilosophyWhat is Simulation – Who uses it?Comparing Simulation To “Spreadsheet” PlanningSimulation In Action - MethodologyCase Study Outcomes and Conclusions
Confidential and Proprietary © 2008 FDI
Confidential and Proprietary © 2008 FDI
Confidential and Proprietary © 2008 FDI
Confidential and Proprietary © 2008 FDI
Confidential and Proprietary © 2008 FDI
A Process Map of an Emergency Department
Confidential and Proprietary © 2008 FDI
Number of ED Arrivals By Time of Day
Confidential and Proprietary © 2008 FDI
Impact of Inpatient Discharge Time of Day on ED Length of Stay
6
7
8
9
10
11
12
13
14
Baseline 3pm 2pm 1pm noon 11am
ED A
vg L
OS
(Hours
) 13h 11m 11h
28m 10h 28m
10h 15m 10h
6m 9h 17m
Area of Opportunity
Inpatient Discharge Time of Day
Confidential and Proprietary © 2008 FDI
Identifying a Facility “Break Point”
0
1
2
3
4
5
6
Current 40,000 41,000 42,000
ED LOS(hrs)
How many visits to the Emergency Department can our facility handle as designed with 32 ED Beds and 370 IP Beds?
Confidential and Proprietary © 2008 FDI
AnimationsAnimations
ED 2
ED 1 Operating RoomPatient Care Throughput
Patient Care Throughput 2
Operating Room 2
Clinics (3) Loading Dock
Construction
ED 3
Radiology
Confidential and Proprietary © 2008 FDI
Agenda Lean PhilosophyWhat is Simulation – Who uses it?Comparing Simulation To “Spreadsheet” PlanningSimulation In Action - MethodologyCase Study Outcomes and Conclusions LAC+USC Medical Center UCSF Pharmacy Medical Center Operating Room California Department of Corrections and Rehabilitation
www.fdiplan.com
Case Study - LAC+USC Medical Center
Confidential and Proprietary © 2008 FDI
Simulations:
Emergency Department
Operating Suites
House-wide Patient Throughput
Outpatient Clinic Operations/Space Allocation
Loading Dock
Case Study – LAC+USC Medical Center
Confidential and Proprietary © 2008 FDI
Project History
Flagship Hospital of Los Angeles County Dept. of Health Services
Originally 4 hospitals with 2,104 licensed beds
2 hospitals were destroyed in 1994 earthquake
Complete replacement hospital approved designed for 946 beds - approved for construction of 600 beds
Case Study – LAC+USC Medical Center
Confidential and Proprietary © 2008 FDI
Facility Configuration
Current Facility New Facility
Inpatient Beds 671 600
Outpatient Visits 520,000 350,000
Admissions 38,000 -
ED Visits 172,000 -
Clinic Exam Rooms 340 217
Inpatient Length of Stay 6.1 days 5.5 days
Case Study – LAC+USC Medical Center
Confidential and Proprietary © 2008 FDI
The Effects of a Volume Increase on the Emergency Department Design
0
0.5
1
1.5
2
Time to ED Bed
97% 143%
7h30m
126%
ED LOS ED LOS95%
13h 11m
30h 27m
56%
81%73%
29%36%34%
3 Scenarios: Volumes increase by 5%, 10%, and 15% (95% IP Occupancy):
+5%10%15%
Confidential and Proprietary © 2008 FDI
Adding Observation Beds Allows Faster Discharge Patient Flow
0
0.5
1
1.5
2
Time to ED Bed
7h30m
20%18h
Time to ED Bed
95%
ED LOS
21h 57m
13h 11m
15%11h
13m
38%55%
% Time EDGeneral Bed
Are Full
88%
39% 4.5h
Wait Time For An IP Bed
125% 7h
3h 6m
Process Times Associated With Addition of 22 Observation Beds:
Confidential and Proprietary © 2008 FDI
“Building a Duplicate ED” To Test ED Capacity
2X%12h 44m
0
0.5
1
1.5
2
Time to ED Bed
81%1h
24m
7h30m
43%9h
29m
Time to ED Bed
95%
ED LOS
21h 57m
13h 11m 28%
9h 28m
69%27%
% Time EDGeneral Bed
Are Full
88%
Wait Time For An IP Bed
3h6m
Simulation Results if ED Had Twice the Number of Beds and Staff:
Confidential and Proprietary © 2008 FDI
Inpatient Bed Availability Is The Major Bottleneck In ED Operations
0
0.5
1
1.5
2
Baseline +10 Beds +20 Beds +30 Beds
Time to ED Bed
16%6h 20m
83%1h 16m
7h30m
46%4h
Time to ED Bed 95% ED LOS
21h 57m
13h 11m7%
20h 25m
76%5h 16m
30%15h 22m
10%11h 52m
52%
28%9h 30m
6h 20m
+10 +20 +30
Confidential and Proprietary © 2008 FDI
Emergency Department
Sized for 946 Inpatient Beds v. 600 – OPERATIONAL/DESIGN MISMATCH causing a dramatic impact on the ED
More than 85% of inpatient admissions enter via the ED
3X the square footage with the same number of ED Beds
6 free-standing EDs moving into one location
+172,000 visits - 3rd busiest ED in the US
Case Study – LAC+USC Medical Center
Confidential and Proprietary © 2008 FDI
Emergency Department - What did we learn?
Current demand v. new demand
Waiting Room Capacity Impact
Geographic Staffing
Impact of changes to Inpatient Occupancy Rate, LOS and DTOD
Effect of various changes to internal ED processes: radiology TAT Discharge process, etc.
Case Study – LAC+USC Medical Center
Confidential and Proprietary © 2008 FDI
Case Study – LAC+USC Medical Center
Outpatient Clinic – Design Challenges
Excluded Primary Care (Internal Medicine Clinic) - Primary Care is on Campus today, with highest volume of all Clinic Groups
Designed to accommodate up to 350,000 Annual Visits - Must maintain current visits of over 500,000 annual visits. (42% increase)
Designed to accommodate Infusion Therapy Services for 22 patients in one location (Adult and Peds combined) - Current Infusion Therapy Services accommodates over 54 Infusion patients in one location (trending upwards)
Exam Rooms - 50% reduction Existing Buildings: 340 New Building: 171
Confidential and Proprietary © 2008 FDI
Outpatient Clinic - Project Goals
Accommodate current service volumes
Minimize the move of services to the Community Health Centers
No addition of evening/off-hours sessions due to staffing limitations
Minimize session/schedule change to the extent possible
Minimize session over-time
Optimize space utilization of the new facility
Case Study – LAC+USC Medical Center
Confidential and Proprietary © 2008 FDI
Simulation gave us a way to…
Accommodate 500 individual Clinics in 104 Service Groups
Minimize clinic schedule changes to just 23 Services
Identify the 64 Services that needed to adjust their time per patient to sustain
current volumes (benchmarked for feasibility)
Address numerous factors in the clinic operations to assess impact of clinic
designation such as patient arrival patterns, appointment slots, physician ratios,
etc.
Redesign, refine and standardized clinic processes
Experiment with over 120 scenarios to determine best fit for each clinic service
Case Study – LAC+USC Medical Center
Confidential and Proprietary © 2008 FDI
Without Simulation…
We would have had to try multiple scenarios using post-it notes and averages!
Move or eliminate services that we would have otherwise assumed would fit and function
Alternatives would have been tried in the facility at the expense of the patients
Case Study – LAC+USC Medical Center
www.fdiplan.com
Case Study - Pharmacy Operations and Construction Phase Model Final Report
Confidential and Proprietary © 2008 FDI
Situation Challenge
Pharmacy is transforming from centralized manual pick operation to a decentralized automated operation
Must stay operational with very limited space available for temporary setup.
Typical healthcare renovation challenges exist (ILS, ICRA, OSHPD, etc)
Confidential and Proprietary © 2008 FDI
CurrentNarc
BS
IJS
IV
MP
UD
TI
Visual Representation of the pharmacy as it exists today.
The departure point for the 4 phased construction project.
Confidential and Proprietary © 2008 FDI
New
MP
NARC
BS
UD
IVIJS
SL
All work stations are now in place
Swiss Log & Carousals are installed for operation
Confidential and Proprietary © 2008 FDI
Objectives
Establish realistic expectations for the operational impacts and necessary planning during the design phase.
Communicate the phasing plan to the department users.
Define metrics for evaluating/ managing the plan.
Simulate results and define monitoring points
Confidential and Proprietary © 2008 FDI
Approach
Phasing Overview Design Team: BFHL Architects- San Francisco, C Current versus New Phases 1 – 4
Metrics Simulation Result- example of findings from data evaluation.
Confidential and Proprietary © 2008 FDI
Phase IUD
Narc
BS
IJS
IV
MP
Unit Dose is moved to location in front of Narc.
Manual Pick is moved to previous order entry location
Transplant/Investigational & Order Entry is displaced elsewhere in the facility
Confidential and Proprietary © 2008 FDI
Phase 2
IV
UD
NARC
BS
MP
IJS
IVAS is moved to new home
Inject able storage is moved to the previous transplant/Investigational
Confidential and Proprietary © 2008 FDI
Phase 3
MP
BS
NARC
IV
UD
IJS
Bulk Storage is moved to new home
Inject able storage is moved to new home
Unit Dose is moved to new home
Confidential and Proprietary © 2008 FDI
Phase 4
MP
BS
UD
NARC
IV
IJS
Narc is moved to new home
Manual Pick is moved to new home
Confidential and Proprietary © 2008 FDI
Metrics
The project analysis was focused on two components:
Workload - defined by the number of “Orders” processed
Orders may contain several sub-orders (referred to as labels)85.8% of all orders had 1 label and were processed the same day
Confidential and Proprietary © 2008 FDI
Metrics
The project analysis was focused on two components:
“Storage Capacity” - defined by the physical storage space necessary to accomplish the workload
Confidential and Proprietary © 2008 FDI
Reducing IVAS Techs/Space
0
0.5
1
1.5
2
2.5
3
0%
82%
22m 0% 66m22m
0%
IVAS Unit Dose
4.6% 69m
2hr 28m
39m
124%
- 1 - 2 - 1 - 2 Baseline Baseline
Approach:
This graph represents the effect of reducing an IVAS tech/space vs. the time it takes to have an order ready for delivery once the order has been electronically forwarded to the IVAS pharmacist.
Key Points:
Reducing 1 tech/space will have no effect for the IVAS area. A slight increase, however, was noted in the time it takes to have an order ready for delivery in the Unit dose area. This is due to the fact that some Unit dose orders require use of an IVAS work area.Reducing 2 tech/space results in significant increases in both IVAS and Unit dose times.
Confidential and Proprietary © 2008 FDI
Summary
In addition to confirming the operational impact of a design…..
Simulation can be an invaluable design / construction planning tool for implementing complex hospital projects. Communicate phase planning in operational terms. Test the results before the OSHPD permit / construction barricades Define key monitoring points for managing the plan
www.fdiplan.com
Case Study – Operating Room
Confidential and Proprietary © 2008 FDI
Project History
The hospital needed to redesign their work processes, Identify capacity constraints and operational bottlenecks, and determine mitigation approaches for their new Operating Room. The facility is planning for the same number of operating rooms, but needs to handle more volume.
Case Study
Confidential and Proprietary © 2008 FDI
Simulations:
Operating Suite with Demographic Changes for 2010, 2015 & 2018
Case Study
Confidential and Proprietary © 2008 FDI
Average Minutes PACU Full in an Hour
Key Points: Yr – 2010 Number of OR’s – 6 PACU = 3 beds
0
5
10
15
20
25
30
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Hour of Day
Min
utes
Ful
l
Confidential and Proprietary © 2008 FDI
Average Minutes PACU Full in an Hour
Key Points: Yr – 2010 Number of OR’s – 6 PACU = 3 beds
0
5
10
15
20
25
30
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Hour of Day
Min
utes
Ful
l
Confidential and Proprietary © 2008 FDI
Average Minutes PACU Full in an Hour
Key Points: Yr – 2010 Number of OR’s – 6 PACU = 4 beds
0
5
10
15
20
25
30
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Hour of Day
Min
utes
Ful
l Recommendation: PACU = 4 beds 2010
Confidential and Proprietary © 2008 FDI
Average Minutes PACU Full in an Hour
Key Points: Yr – 2010 Number of OR’s – 6 PACU = 5 beds
0
5
10
15
20
25
30
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Hour of Day
Min
utes
Ful
l
Confidential and Proprietary © 2008 FDI
Average Minutes PACU Full in an Hour
Key Points: Yr – 2010 Number of OR’s – 6 PACU = 6 beds
0
5
10
15
20
25
30
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Hour of Day
Min
utes
Ful
l
Confidential and Proprietary © 2008 FDI
Average Minutes PACU Full in an Hour
Key Points: Yr – 2015 Number of OR’s – 6 PACU = 3 beds
0
5
10
15
20
25
30
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Hour of Day
Minu
tes F
ull
Confidential and Proprietary © 2008 FDI
Average Minutes PACU Full in an Hour
Key Points: Yr – 2015 Number of OR’s – 6 PACU = 4 beds
0
5
10
15
20
25
30
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Hour of Day
Minu
tes F
ull Recommendation:
PACU = 4 beds 2015
Confidential and Proprietary © 2008 FDI
Average Minutes PACU Full in an Hour
Key Points: Yr – 2015 Number of OR’s – 6 PACU = 5 beds
0
5
10
15
20
25
30
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Hour of Day
Minu
tes F
ull
Confidential and Proprietary © 2008 FDI
Average Minutes PACU Full in an Hour
Key Points: Yr – 2015 Number of OR’s – 6 PACU = 6 beds
0
5
10
15
20
25
30
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Hour of Day
Minu
tes F
ull
Confidential and Proprietary © 2008 FDI
Average Minutes PACU Full in an Hour
Key Points: Yr – 2018 Number of OR’s – 6 PACU = 3 beds
0
5
10
15
20
25
30
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Hour of Day
Minu
tes F
ull
Confidential and Proprietary © 2008 FDI
Average Minutes PACU Full in an Hour
Key Points: Yr – 2018 Number of OR’s – 6 PACU = 4 beds
0
5
10
15
20
25
30
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Hour of Day
Min
utes
Ful
l
Confidential and Proprietary © 2008 FDI
Average Minutes PACU Full in an Hour
Key Points: Yr – 2018 Number of OR’s – 6 PACU = 5 beds
Recommendation: PACU = 5 beds
0
5
10
15
20
25
30
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Hour of Day
Min
utes
Ful
l
Confidential and Proprietary © 2008 FDI
Average Minutes PACU Full in an Hour
Key Points: Yr – 2018 Number of OR’s – 6 PACU = 6 beds
0
5
10
15
20
25
30
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Hour of Day
Min
utes
Ful
l
Confidential and Proprietary © 2008 FDI
Average Minutes Pre Op Full in an Hour
Key Points: Yr – 2010 Number of OR’s – 6 Pre Op = 7 beds
0
10
20
30
40
50
60
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Hour of Day
Min
utes
Ful
l
Confidential and Proprietary © 2008 FDI
Key Points: Yr – 2010 Number of OR’s – 6 Pre Op = 8 beds
0
10
20
30
40
50
60
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Hour of Day
Min
utes
Ful
l
Average Minutes Pre Op Full in an Hour
Confidential and Proprietary © 2008 FDI
Average Minutes Pre Op Full in an Hour
Key Points: Yr – 2010 Number of OR’s – 6 Pre Op = 9 beds
0
10
20
30
40
50
60
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Hour of Day
Min
utes
Ful
l
Confidential and Proprietary © 2008 FDI
Average Minutes Pre Op Full in an Hour
Key Points: Yr – 2010 Number of OR’s – 6 Pre Op = 10 beds
0
10
20
30
40
50
60
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Hour of Day
Min
utes
Ful
l
Confidential and Proprietary © 2008 FDI
Average Minutes Pre Op Full in an Hour
Key Points: Yr – 2010 Number of OR’s – 6 Pre Op = 11 beds
0
10
20
30
40
50
60
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Hour of Day
Min
utes
Ful
l Recommendation: Pre Op = 11 beds 2010
Confidential and Proprietary © 2008 FDI
Average Minutes Pre Op Full in an Hour
Key Points: Yr – 2010 Number of OR’s – 6 Pre Op = 12 beds
0
10
20
30
40
50
60
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Hour of Day
Min
utes
Ful
l
Confidential and Proprietary © 2008 FDI
Key Points: Yr – 2015 Number of OR’s – 6 Pre Op = 7 beds
0
10
20
30
40
50
60
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Hour of Day
Min
utes
Ful
l
Average Minutes Pre Op Full in an Hour
Confidential and Proprietary © 2008 FDI
Key Points: Yr – 2015 Number of OR’s – 6 Pre Op = 8 beds
0
10
20
30
40
50
60
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Hour of Day
Min
utes
Ful
l
Average Minutes Pre Op Full in an Hour
Confidential and Proprietary © 2008 FDI
Average Minutes Pre Op Full in an Hour
Key Points: Yr – 2015 Number of OR’s – 6 Pre Op = 9 beds
0
10
20
30
40
50
60
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Hour of Day
Min
utes
Ful
l
Confidential and Proprietary © 2008 FDI
Key Points: Yr – 2015 Number of OR’s – 6 Pre Op = 10 beds
0
10
20
30
40
50
60
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Hour of Day
Min
utes
Ful
l
Average Minutes Pre Op Full in an Hour
Confidential and Proprietary © 2008 FDI
Key Points: Yr – 2015 Number of OR’s – 6 Pre Op = 11 beds
0
10
20
30
40
50
60
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Hour of Day
Min
utes
Ful
l
Average Minutes Pre Op Full in an Hour
Confidential and Proprietary © 2008 FDI
Average Minutes Pre Op Full in an Hour
Key Points: Yr – 2015 Number of OR’s – 6 Pre Op = 12 beds
0
10
20
30
40
50
60
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Hour of Day
Min
utes
Ful
l Recommendation: Pre Op = 12 beds 2015
Confidential and Proprietary © 2008 FDI
Average Minutes Pre Op Full in an Hour
Key Points: Yr – 2015 Number of OR’s – 6 Pre Op = 13 beds
0
10
20
30
40
50
60
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Hour of Day
Min
utes
Ful
l
Confidential and Proprietary © 2008 FDI
Key Points: Yr – 2018 Number of OR’s – 6 Pre Op = 7 beds
0
10
20
30
40
50
60
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Hour of Day
Min
utes
Ful
l
Average Minutes Pre Op Full in an Hour
Confidential and Proprietary © 2008 FDI
Average Minutes Pre Op Full in an Hour
Key Points: Yr – 2018 Number of OR’s – 6 Pre Op = 8 beds
0
10
20
30
40
50
60
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Hour of Day
Min
utes
Ful
l
Confidential and Proprietary © 2008 FDI
Key Points: Yr – 2018 Number of OR’s – 6 Pre Op = 9 beds
0
10
20
30
40
50
60
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Hour of Day
Min
utes
Ful
l
Average Minutes Pre Op Full in an Hour
Confidential and Proprietary © 2008 FDI
Average Minutes Pre Op Full in an Hour
Key Points: Yr – 2018 Number of OR’s – 6 Pre Op = 10 beds
0
10
20
30
40
50
60
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Hour of Day
Min
utes
Ful
l
Confidential and Proprietary © 2008 FDI
Average Minutes Pre Op Full in an Hour
Key Points: Yr – 2018 Number of OR’s – 6 Pre Op = 11 beds
0
10
20
30
40
50
60
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Hour of Day
Min
utes
Ful
l
Confidential and Proprietary © 2008 FDI
Average Minutes Pre Op Full in an Hour
Key Points: Yr – 2018 Number of OR’s – 6 Pre Op = 12 beds
0
10
20
30
40
50
60
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Hour of Day
Min
utes
Ful
l Recommendation: Pre Op = 12 beds 2018
Confidential and Proprietary © 2008 FDI
Average Minutes Pre Op Full in an Hour
Key Points: Yr – 2018 Number of OR’s – 6 Pre Op = 13 beds
0
10
20
30
40
50
60
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Hour of Day
Min
utes
Ful
l
Confidential and Proprietary © 2008 FDI
Capacity Summary/Recommendations
Operating Rooms=62010 OR=5
2015 OR=6
2018 OR=6
PACU Beds=5 Pre/Post Op Beds= 112010 PACU=4 Pre Op=11
2015 PACU=4 Pre Op=12
2018 PACU=5 Pre Op=12
Confidential and Proprietary © 2008 FDI
Proposed OR LayoutAnimation
QVMC OR animationV3.exe
www.fdiplan.com
CDCR Receiving and Release Simulation CDCR Receiving and Release Simulation Model Model
David FerrinPrincipal
Tanner FlynnAssociate Principal
Steve FallerSr. Project Engineer
September 24, 2008
Confidential and Proprietary © 2008 FDI
Simulations:
The Process of Receiving and Releasing Inmates
Case Study – CDCR Receive and Release
Confidential and Proprietary © 2008 FDI
Case Study – CDCR Receive and Release
The reception centers process all inmates coming in to the system. The reception center assesses each inmate’s health and routes them to the correct prison. The inmates then wait at the reception center until the selected prison has an available bed for them. The challenge for the reception center was to reduce the typical three-day period assessment to six hours per inmate on the day of arrival.
Confidential and Proprietary © 2008 FDI
CDCR Reception & Release Process
Standardizing the inmate property received to the lowest acceptable level from the counties This was supposed to improve the value stream (processed inmates) by
removing a bottle neck and increasing the percent of inmates completed in six hours and decreasing the inmates time to be seen
Although this did not have the desired effect it was found that the staffing hours per week could be dramatically reduced using this standard
The following two slides show how the numbers played out
Confidential and Proprietary © 2008 FDI
Scenario:Reduce Inventory Property Times (To-Be)
Key Points: Does not have a major impact on the % complete in 6 hours
The other 8 activities in the parallel process dilute the time that is saved in this one activity
NK SQ Wasco
5%38%
37%
% Complete in 6 hours
Time Waiting to Begin Process
Time in Parallel Process
NK SQ Wasco NK SQ Wasco
85% 36%7 h
27 m 57 m7 h
59 m2 h
24 m2 h
28 m2 h
18 m
6%38%
8%6 h
53 m
2%56 m
5%7 h
36 m1%
86%
3%2 h
19 m
3%2 h
24 m
6%2 h
11 m
Methodology:
Green % is GOODRed % is BAD
Confidential and Proprietary © 2008 FDI
Scenario:Hours Per Week Required for Inventory Property Screening (To-Be)
Key Points: Hours saved per week by reducing the inventory property:
NK – 24 hoursSQ – 20 hoursW – 48 hours
NK Wasco
47 h
Hours per Week
36 h
56%16 h
Methodology:
Green % is GOODRed % is BAD
51%23 h
75 h
64%27 h
SQ
Confidential and Proprietary © 2008 FDI
CDCR Reception and Release Process
Doubling the quantity of resources revealed that the only additional space necessary would be for additional RN offices. Doubling the RN offices increased the velocity of inmates on the reception
end of the process
Confidential and Proprietary © 2008 FDI
Analysis to increase the quantity of resources by Double
Methodology:
Green % is GOODRed % is BAD
Key Points: Resource analysis
Each bar is a different scenario with that sole resource being doubled
The bottleneck resource will give the highest % improvement
% Complete in 6 hours
37%1%
36%4%
38%
17%30%
5%39%
42%52%
9%40%
4%38%
3%38%
Baseline Counter Live Scan
Photo Room
Psych Room
PanorexLab Table
Nurse Office
LVN Station
Resources Doubled to: Counter – 30 Live Scan – 10 Photo Room – 2 LVN Station – 4 Nurse Office – 4 Lab Table – 4 Panorex – 4 Psych Room - 10
Confidential and Proprietary © 2008 FDI
FDI Simulation is the largest Healthcare Simulation Modeling firm in the country with more than 20 years experience, providing custom models incorporating best-practices and
hospital’s own data routinely yielding multi-million dollar financial impacts. FDI’s models simulate and analyze hundreds of scenarios projecting multi-annual impacts in minutes.
FDI uniquely provides prioritized implementation strategies for patient throughput and capacity issues. Our prioritization is based on the greatest and quickest financial and
patient experience benefits with the least amount of change required.
www.fdiplan.com
David Ferrin 602-212-3565 (office)630-258-0141 (cell)[email protected]
Tanner [email protected]