Www.buttiandpartners.com Environmental disasters and Seveso directives avv. Diana Michelazzo...

55
www.buttiandpartners.com Environmental disasters and Seveso directives avv. Diana Michelazzo diana.michelazzo@buttiandpartners .com

Transcript of Www.buttiandpartners.com Environmental disasters and Seveso directives avv. Diana Michelazzo...

Page 1: Www.buttiandpartners.com Environmental disasters and Seveso directives avv. Diana Michelazzo diana.michelazzo@buttiandpartners.com.

www.buttiandpartners.com

Environmental disasters and Seveso directives

avv. Diana Michelazzo [email protected]

Page 2: Www.buttiandpartners.com Environmental disasters and Seveso directives avv. Diana Michelazzo diana.michelazzo@buttiandpartners.com.

www.buttiandpartners.com

Index

1. Seveso disaster (Italy), 1976;

2. Bhopal (India), 1984;

3. Deepwater Horizon oil spill (gulf of Mexico),

2010;

4. Other major environmental disasters in History;

5. Seveso Directives.

Page 3: Www.buttiandpartners.com Environmental disasters and Seveso directives avv. Diana Michelazzo diana.michelazzo@buttiandpartners.com.

www.buttiandpartners.com

1. Seveso dioxin pollution (Italy) 1976

Page 4: Www.buttiandpartners.com Environmental disasters and Seveso directives avv. Diana Michelazzo diana.michelazzo@buttiandpartners.com.

www.buttiandpartners.com

An extremely serious accident occurred in 1976 in a small chemical plant located not far from Milan. It is known as “Seveso disaster”, because Seveso was the most affected community.

The industrial plant was owned by the company ICMESA (Industrie Chimiche Meda Società Azionaria), a subsidiary of Givaudan which in turn was a subsidiary of Hoffmann-La Roche. The plant was built many years before the accident, and was manufacturing dioxins.

The accident (1)

Page 5: Www.buttiandpartners.com Environmental disasters and Seveso directives avv. Diana Michelazzo diana.michelazzo@buttiandpartners.com.

www.buttiandpartners.com

Due to a mechanical failure the temperature rose to around

300°C, and the relief valve eventually opened: 6 tons of

material, including 1 kg of TCDD* (tetrachlorodibenzodioxin),

were released over an 18 km2 area.

Dioxin first came to widespread public notice during the

Vietnam War, when it was identified as a component of the

defoliant Agent Orange. Previously, the substance had been

banned from agricultural use, because of its alleged toxic

effects on humans.

The accident (2)

Page 6: Www.buttiandpartners.com Environmental disasters and Seveso directives avv. Diana Michelazzo diana.michelazzo@buttiandpartners.com.

www.buttiandpartners.com

The safety measures taken by the Company and the

Authorities were badly coordinated. At least a week

passed before it was publicly stated that a dioxin pollution

occurred, and another week passed before the evacuation

began.

Within days a total of 3,300 animals were found dead,

mostly poultry and rabbits. Emergency slaughtering

started, to prevent TCDD from entering the food chain, and

by 1978 over 80,000 animals had been slaughtered.

Safety measures, cleanup and restoration (1)

Page 7: Www.buttiandpartners.com Environmental disasters and Seveso directives avv. Diana Michelazzo diana.michelazzo@buttiandpartners.com.

www.buttiandpartners.com

Safety measures, cleanup and restoration (2)

The contaminated area was divided into different zones: A, B and R, in decreasing order of surface soil concentrations of TCDD. Zone A (the closest to the plant) was completely evacuated and fenced, and 1.600 people of all ages had been examined. The local population was advised not to touch or eat locally grown fruits or vegetables. Many people were found to suffer from skin lesions. Zone A had a TCDD soil concentration of >50 microgram/m2, and about 700 residents.

Page 8: Www.buttiandpartners.com Environmental disasters and Seveso directives avv. Diana Michelazzo diana.michelazzo@buttiandpartners.com.

www.buttiandpartners.com

Zone B had a TCDD soil concentration between 5 and 50 micrograms/m2, and about 4700 residents. Zone R (“Respect zone”) had a TDCC soil concentration of < 5 micrograms/m2, and about 31.800 residents.

2 months after the disaster, the Italian government granted a loan of 40 billion lire to the region, to finance necessary measures. In 1978, the government raised its special loan from 40 to 115 billion lire.

6 months after the accident, the decontamination works began, to enable resumption of productive activities.

Safety measures, cleanup and restoration (3)

Page 9: Www.buttiandpartners.com Environmental disasters and Seveso directives avv. Diana Michelazzo diana.michelazzo@buttiandpartners.com.

www.buttiandpartners.com

More than 1 year after the accident, the decontamination works of zone A was completed. The government decided to demolish most heavily contaminated houses and rebuild.

Waste from the cleanup activities, containing chemical residues and a protecting clothing, were stored in containment tanks, designed for the storage of nuclear waste. In 1982 several barrels of toxic waste left the ICMESA plant. After a series of unclear events, nine years after the disaster, Roche - which stated that the Company wanted to take the responsibility for the safe destruction of the waste - declared that the toxic waste had all been incinerated in Switzerland.

Decontamination and restoration (2)

Page 10: Www.buttiandpartners.com Environmental disasters and Seveso directives avv. Diana Michelazzo diana.michelazzo@buttiandpartners.com.

www.buttiandpartners.com

In 1980 the Director of Production at ICMESA was shot by a member of a terrorist organization.

A few months later a compensation agreement was signed by representatives of the Region, President of the Italian Republic and Givaudan/ICMESA. The total amount of the agreement was about 20 billion lire.

The technical director of ICMESA was sentenced to five years imprisonment in the first degree trial, then had his sentence reduced to two years and was paroled on appeal.

The judiciary case (1)

Page 11: Www.buttiandpartners.com Environmental disasters and Seveso directives avv. Diana Michelazzo diana.michelazzo@buttiandpartners.com.

www.buttiandpartners.com

• 1981: settlement with the municipalities of Desio and Cesano Maderno: ICMESA pays respectively 1.45 and 2.85 billion lire;

• 1982: settlement with Meda: ICMESA pays 1.3 billion lire;

• 1983: settlement with Seveso: ICMESA pays 15 billion lire.

The judiciary case (2)

Most individual compensation claims had been settled out of Court:

Page 12: Www.buttiandpartners.com Environmental disasters and Seveso directives avv. Diana Michelazzo diana.michelazzo@buttiandpartners.com.

www.buttiandpartners.com

In 1991 the Civil Court of Milan required the Company to pay 2 millions lire (around € 1,000) to each inhabitant of the contaminated zones B and R. The Court's pronounce stated: "The exposure to an unknown quantity of dioxin, the restrictions on liberty of actions and of life, the oppressive public-health measures, all constitute causes for disturbance and moral damage.”

In 2009 the Supreme Court sentenced ICMESA to pay € 5,000 to each resident of the zone A.

The judiciary case (3)

Page 13: Www.buttiandpartners.com Environmental disasters and Seveso directives avv. Diana Michelazzo diana.michelazzo@buttiandpartners.com.

www.buttiandpartners.com

The European Union Industrial Safety Regulations

are known as:

- Seveso I Directive (82/501/EEC);

- Seveso II Directive (96/82/EEC);

- Seveso III Directive (2012/18/UE).

The judiciary case (4)

Page 14: Www.buttiandpartners.com Environmental disasters and Seveso directives avv. Diana Michelazzo diana.michelazzo@buttiandpartners.com.

www.buttiandpartners.com

2. Bhopal gas leak (India), 1984

Page 15: Www.buttiandpartners.com Environmental disasters and Seveso directives avv. Diana Michelazzo diana.michelazzo@buttiandpartners.com.

www.buttiandpartners.com

The accident (1)

The Bhopal disaster is considered the worst disaster of the modern history.

On the night of December 2, 1984, at the Union Carbide pesticide plant in Bhopal, water entered a tank containing 42 tons of methyl isocyanate (MIC) causing a leak of gas and other chemicals.

MIC is an hazardous chemical element, highly reactive, in particular with water.

A gas cloud was formed, and since it was denser than the surrounding air, it stayed close to the ground, causing the intoxication of hundreds of thousands of people.

Page 16: Www.buttiandpartners.com Environmental disasters and Seveso directives avv. Diana Michelazzo diana.michelazzo@buttiandpartners.com.

www.buttiandpartners.com

According to a report, causes of the accident were:

- insufficient training of workers;- poor maintenance of the plant;- failure of several safety system (some of them were

switched off to save money);

The gravity of the leak was increased by the absence of a cathastrophy plan.

The accident (2)

Page 17: Www.buttiandpartners.com Environmental disasters and Seveso directives avv. Diana Michelazzo diana.michelazzo@buttiandpartners.com.

www.buttiandpartners.com

Injury to or loss of life

People were awaken by symptoms such as cough, eye irritation, vomiting, and were already dead in the morning hours.

3.787 deaths were officially related to the gas exposure, but up to 25.000 deaths have been attributed to this tragedy in more recent estimates. More than 500.000 people were injured. More than 120.000 people still suffer of serious disability and diseases.

Environmental damage

Thousands of animals were slaughtered, and the gas caused visible damage to vegetation. Fishing was prohibited.

The accident (3)

Page 18: Www.buttiandpartners.com Environmental disasters and Seveso directives avv. Diana Michelazzo diana.michelazzo@buttiandpartners.com.

www.buttiandpartners.com

The Union Carbide is an American chemical company.

United Carbide India Limited (UCIL), a 49% public participation company, was the Indian subsidiary of the Union Carbide Corporation (UCC).

In 2001 Dow Chemical Company purchased UCC.

The Company

Page 19: Www.buttiandpartners.com Environmental disasters and Seveso directives avv. Diana Michelazzo diana.michelazzo@buttiandpartners.com.

www.buttiandpartners.com

Two years after the disaster the plant was closed. Pipes, drums and tanks were sold.

The plant was not dismantled and is still there, as are storages of different residues.

In December 2008, the High Court decided that the toxic waste should be incinerated.

Chemicals abandoned at the plant continue to leak and pollute the groundwater.

The (unperformed) cleanup

Page 20: Www.buttiandpartners.com Environmental disasters and Seveso directives avv. Diana Michelazzo diana.michelazzo@buttiandpartners.com.

www.buttiandpartners.com

December 7, 1984 Anderson, Chairman and CEO of UCC was arrested by the Indian Police at the airport (in order to ensure his safety). He was released after 6 hours, on a $2.100 bail, and flew back to US.

Later he was charged by the Bhopal Authorities for manslaughter (culpable homicide), a crime punished with a maximum of 10 years imprisonment. He did not appear at the hearing and was declared fugitive.

UCC tried to hide the poor safety of the plant and the lack of prevention measures, and claimed publicly that the disaster was caused by a sabotage.

The judiciary case (1)

Page 21: Www.buttiandpartners.com Environmental disasters and Seveso directives avv. Diana Michelazzo diana.michelazzo@buttiandpartners.com.

www.buttiandpartners.com

In 1985 the Bhopal Gas Leak Disaster Act made the Government the sole representative of the victims, meaning that victims could not personally ask for compensation.

In 1986 the Indian Government filed a civil law suit against UCC in Bhopal.

In 1989 the Company offered $350 million, the amount of the insurance policy. The Government of India claimed $3.3 billion from UCC.

In 1989, UCC agreed to pay $470 million (the insurance sum plus interest) in a full and final settlement of its civil and criminal liability. As a consequence, victims of the accident obtained only $300 each!

The judiciary case (2)

Page 22: Www.buttiandpartners.com Environmental disasters and Seveso directives avv. Diana Michelazzo diana.michelazzo@buttiandpartners.com.

www.buttiandpartners.com

Indian Supreme Court required UCC to finance a 500 bed hospital for survivors. Bhopal Memorial Hospital was inaugurated in 1998. It was obliged to give free care to survivors for eight years.

In 1991 the Indian Tribunal decided to continue the penal prosecution, but only for negligence*.

In 2003 India pressed for the extradition of the Chairman and CEO (fugitive). The next year US denied the extradition.

The judiciary case (3)

Page 23: Www.buttiandpartners.com Environmental disasters and Seveso directives avv. Diana Michelazzo diana.michelazzo@buttiandpartners.com.

www.buttiandpartners.com

]

Several civil and criminal proceeding are still pending, in

Indian and US Courts, concerning UCIL, UCC, employees,

victims, and Anderson (the CEO).

In June 2010 a Bhopal Court delivered a guilty verdict on 7

Indian former members of the UCIL government board,

and the chairman. Being the charge a gross negligence

manslaughter, the punishment is 2 years imprisonment and

100.000 rupie (about $2.000 fine). The appeal is pending.

The judiciary case (4)

Page 24: Www.buttiandpartners.com Environmental disasters and Seveso directives avv. Diana Michelazzo diana.michelazzo@buttiandpartners.com.

www.buttiandpartners.com

3. BP oil spill (Mexico), 2010

Page 25: Www.buttiandpartners.com Environmental disasters and Seveso directives avv. Diana Michelazzo diana.michelazzo@buttiandpartners.com.

www.buttiandpartners.com

On April 20, 2010 due to an explosion, followed by an inextinguishable fire, the

British Petroleum platform, located on the Gulf of Mexico, not far from the

coast of Louisiana, sank. As a consequence, an oil spill occurred.

The platform, named “Deepwater Horizon”, was a 9 year old offshore drilling

unit, capable to operate in waters up to 2,400 m deep, and drill down to about

9,000 m. From March 2008 it was under lease to BP Company.

The explosion killed 11 men working on the platform and injured 17 others.

The BP platform explosion caused the "worst environmental disaster the US

has faced” according to the US government.

The accident

Page 26: Www.buttiandpartners.com Environmental disasters and Seveso directives avv. Diana Michelazzo diana.michelazzo@buttiandpartners.com.

www.buttiandpartners.com

About 5 million barrels (790,000 m3) of

crude oil flood into the see, from the

accident to july 2010, when the leak was

stopped by a giant cap.

The spill caused an extremely serious

damage to marine habitats, and to the

Gulf's fishing and tourism industries.

One year after the accident, august 2011,

oil was covering several square miles

of water not far from the platform.

Scientists reported immense underwater

“bubbles” of oil, not visible at the

surface.

Environmental damage

Page 27: Www.buttiandpartners.com Environmental disasters and Seveso directives avv. Diana Michelazzo diana.michelazzo@buttiandpartners.com.

www.buttiandpartners.com

Ships, underwater vehicles, airplanes, recovery vessels were active in cleanup activities, in the attempt to protect the environment from the spreading oil. Nearly 7,500 personnel were participating, with an additional 2,000 volunteers assisting.

Three fundamental strategies were developed:

to contain the oil on the surface, away from the most sensitive areas;

to dilute and disperse it into less sensitive areas;

to remove it from the water.

Cleaup activities (1)

different techniques: anchored

barriers, sand-filled

barricades,disperdants, etc.

Page 28: Www.buttiandpartners.com Environmental disasters and Seveso directives avv. Diana Michelazzo diana.michelazzo@buttiandpartners.com.

www.buttiandpartners.com

Cleaup activities (2)

By October, the State of Louisiana had spent $240

million of the proposed $360 million from BP.

The barrier had captured an estimated 1,000 barrels

(160 m3) of oil, but critics and experts said the barrier

was purely symbolic and call it "an exercise in futility"

given the estimated 5,000,000 barrels (790,000 m3).

Many scientists say the remaining oil in the Gulf is too

dispersed to be blocked or captured.

Page 29: Www.buttiandpartners.com Environmental disasters and Seveso directives avv. Diana Michelazzo diana.michelazzo@buttiandpartners.com.

www.buttiandpartners.com

Causes of the disaster: - a series of cost-cutting decisions;- lack of a security system of the platform;- defects in the cement structure.

BP attitude: BP admitted that it made mistakes which led to the accident and the oil spill. In June 2010 BP set up a $20 billion fund as a compensation to the victims.To July 2011, the fund has paid $4.7 billion to about 200.000 claimants. The fund has nearly 1 million claims and continues to receive thousands of claims each week.

Causes and Responsabilities

Page 30: Www.buttiandpartners.com Environmental disasters and Seveso directives avv. Diana Michelazzo diana.michelazzo@buttiandpartners.com.

www.buttiandpartners.com

Several lawsuits were filed against BP and other related companies. Then BP took legal action against the company (Halliburtun) which cemented the drilling unit. Thousands of claims, coming from out-of-work fishers and tourist resorts receiving cancellations were filed and many of them have so far been settled with the Company.

In September 2011, the US government published its final investigative report on the accident. In essence, that report states that the main cause was the defective cement job, and Halliburtun, BP and Transocean (the owner of the drilling unit) were, in different ways, responsible for the accident.The trials are still pending.

The judicial case

Page 31: Www.buttiandpartners.com Environmental disasters and Seveso directives avv. Diana Michelazzo diana.michelazzo@buttiandpartners.com.

www.buttiandpartners.com

4. Other major environmental disasters (1)

a) Chernobyl nuclear plant explosion (Russia), 1986: a mix of human errors and mechanical failures caused the plant reactor’s explosion. An atmospheric cloud containing approximately 200 million curies of radioactive material was formed. More than 8.000 people died during the first cleanup operation, and hundreds thousands have been suffering from birth defects, cancer, heart diseases in the following years. The most hazardous substances dispersed were plutonium and cesius. The reactor was wrapped in a concrete sarcophagus. This is a very expensive solution, since the sarcophagus has to be replaced with a new one periodically. The reactor was closed in 2000.

Page 32: Www.buttiandpartners.com Environmental disasters and Seveso directives avv. Diana Michelazzo diana.michelazzo@buttiandpartners.com.

www.buttiandpartners.com

b) Basel chemical disaster (Switzerland), 1986: a fire at chemical company Sandoz exposed the entire region to a poisonous veil of thick smoke, carrying 1,351 tons of pesticides and agrochemicals. The contamination affected the surrounding soil and also groundwater. The pollutants destroyed the river’s flora and fauna. Despite Swiss authorities stated that it is not necessary to decontaminate the site again, a leading expert on the disaster says the area remains polluted. No one at Sandoz management was ever held responsible for the disaster, the cause of which has never been firmly established.

4. Other major environmental disasters (2)

Page 33: Www.buttiandpartners.com Environmental disasters and Seveso directives avv. Diana Michelazzo diana.michelazzo@buttiandpartners.com.

www.buttiandpartners.com

Directive 82/501/EEC(Seveso I)

Directive 96/82/EC(Seveso II)

Seveso (I)Luglio 1976

Beek (NL)Novembre 1975

Bhopal (India)Dicembre 1984

Mexico City (MEX)Novembre 1984

Basel (CH)Novembre 1986

Seveso (I)July 1976

Beek (NL)November 1975

Mexico City (MEX)November 1984

Chernobyl (UA)April 1986

Flixborough (UK)June 1974

Bhopal (India)December 1984

Page 34: Www.buttiandpartners.com Environmental disasters and Seveso directives avv. Diana Michelazzo diana.michelazzo@buttiandpartners.com.

www.buttiandpartners.com

“Seveso II” Amendment(2003/105/EC)

Enschede (NL)May 2000

Toulouse (F)September 2001

Buncefield (UK) December 2005

Baia Mare (RO)January 2000

Basel (CH)November 1986

BP oil spill (Mexico) April 2010

“Seveso III”(2012/18/EU)

Page 35: Www.buttiandpartners.com Environmental disasters and Seveso directives avv. Diana Michelazzo diana.michelazzo@buttiandpartners.com.

www.buttiandpartners.com

5. 5. Seveso Directives

- SEVESO I: 82/501/EEC (replaced by the following);

- SEVESO II: 1996/82/EC, modified by Directive 2003/105/EC (transposed in the Italian legislation with the D.lgs. 238/2005, which has replaced the previous D.lgs. 334/1999).

- SEVESO III: Directive n. 2012/18/EU (still to be transposed in Italy)

Page 36: Www.buttiandpartners.com Environmental disasters and Seveso directives avv. Diana Michelazzo diana.michelazzo@buttiandpartners.com.

www.buttiandpartners.com

5. SEVESO Directive5. SEVESO Directive

5.1. General principles

5.2. Scope of the directive and exclusions

5.3. Relevant definitions

5.4. Obligations of the operator

5.5. Emergency plans

5.6. Domino effect

5.7. Information to be supplied after a major accident

5.8. Inspections

Page 37: Www.buttiandpartners.com Environmental disasters and Seveso directives avv. Diana Michelazzo diana.michelazzo@buttiandpartners.com.

www.buttiandpartners.com

5. SEVESO Directive: General principles

1) It aims to control major-accidents hazards involving dangerous substances

2) It covers substances considered dangerous for the environment, in particular aquatoxics

3) It introduced new requirements concerning safety management systems, emergency plans and land-use planning, competent authorities’ inspections and public information

Page 38: Www.buttiandpartners.com Environmental disasters and Seveso directives avv. Diana Michelazzo diana.michelazzo@buttiandpartners.com.

www.buttiandpartners.com

The Directive's scope:

The Directive applies to any establishment where dangerous substances are present, or likely to be produced as a result of an accident or a loss of control of the process, in quantities equal to or in excess of the quantities listed in Annex I.

5. SEVESO Directive: Scope of the Directive and exclusions

Page 39: Www.buttiandpartners.com Environmental disasters and Seveso directives avv. Diana Michelazzo diana.michelazzo@buttiandpartners.com.

www.buttiandpartners.com

Annex I Part 1: Categories of dangerous substances

Four sections are identified on the basis of the specific hazard for human health and environment:

1) Section “H”: health hazards2) Section “P”: Physical hazards3) Section “E”: Environmental hazards4) Section “O”: Other hazards

Each section contains specific hazard categories (e.g. Section “P”:explosives, flammable, self-reactive…)

5. SEVESO Directive: Scope of the Directive and exclusions

Page 40: Www.buttiandpartners.com Environmental disasters and Seveso directives avv. Diana Michelazzo diana.michelazzo@buttiandpartners.com.

www.buttiandpartners.com

Annex I Part 2: Named dangerous substances

In Annex I, Part 2, 41 dangerous substances are listed and classified in accordance with Regulation EC n. 1272/2008 (the European Regulation on classification, labeling and packaging of substances and mixtures).

Where a dangerous substance is covered by Part 1 and is also listed in Part 2, the qualifying quantities set out in Part 2 apply.

5. SEVESO Directive: Scope of the Directive and exclusions

Page 41: Www.buttiandpartners.com Environmental disasters and Seveso directives avv. Diana Michelazzo diana.michelazzo@buttiandpartners.com.

www.buttiandpartners.com

The following establishments are not covered by the Directive:

• military establishments;

• hazards created by ionising radiation;

• transport of dangerous substances by road, rail, air and inland waterways, sea or air;

• transport of dangerous substances in pipelines;

• offshore exploration and exploitation of minerals;

• waste landfill sites.

5. SEVESO Directive: Scope of the Directive and exclusions

Page 42: Www.buttiandpartners.com Environmental disasters and Seveso directives avv. Diana Michelazzo diana.michelazzo@buttiandpartners.com.

www.buttiandpartners.com

Establishments: the whole location under the control of an operator where dangerous substances are present. Establishments are classified in lower-tier establishments or upper-tier establishments.

Lower-tier establishments: an establishment where dangerous substances are present in quantities equal to or in excess of the quantities listed in Column 2 of Part 1 or 2 of Annex I (but less than the quantities listed in Column 3 of Part 1 or 2 of Annex I).

Upper-tier establishments: an establishment where dangerous substances are present in quantities equal to or in excess of the quantities listed in Column 3 of Part 1 or 2 of Annex I.

5. SEVESO Directive: Relevant definitions

Page 43: Www.buttiandpartners.com Environmental disasters and Seveso directives avv. Diana Michelazzo diana.michelazzo@buttiandpartners.com.

www.buttiandpartners.com

Operator: any natural or legal person who operates or controls an establishment or installation or, where provided for by natural legislation, to whom the decisive economic or decision-making power over the technical functioning of the establishment or installation has been delegated.

Dangerous substances: a substance or mixture covered by Part 1 or listed in Part 2 of Annex I (in the form of raw material, product, by-product, residue or intermediate).

Presence of dangerous substances: the actual or anticipated presence of dangerous substances in the establishment, or of dangerous substances which can be generated during loss of control of the process (…).

5. SEVESO Directive: Relevant definitions

Page 44: Www.buttiandpartners.com Environmental disasters and Seveso directives avv. Diana Michelazzo diana.michelazzo@buttiandpartners.com.

www.buttiandpartners.com

1) General obligation

Member States must ensure that the operator:

• takes all measures necessary to prevent major

accidents and to limit their consequences for human

health and the environment;

• is required to prove to the competent authority that

all the necessary measures have been taken.

5. SEVESO Directive: Obligations of the operator

Page 45: Www.buttiandpartners.com Environmental disasters and Seveso directives avv. Diana Michelazzo diana.michelazzo@buttiandpartners.com.

www.buttiandpartners.com

2) Obligation to notify

The operator has to send a notification to the competent authority containing the following details:

• the name of the operator and the address of the establishment;

• the registered place of business of the operator; • the name or position of the person in charge of the

establishment; • information sufficient to identify the dangerous substances

or category of substances involved; • the quantity and physical form of the dangerous substance

or substances involved; • the immediate environment of the establishment.

5. SEVESO Directive: Obligations of the operator

Page 46: Www.buttiandpartners.com Environmental disasters and Seveso directives avv. Diana Michelazzo diana.michelazzo@buttiandpartners.com.

www.buttiandpartners.com

3) Safety Report (only for upper-tier establishments)The Safety Report shall demonstrate that:

• a prevention policy and a safety management system have been put into effect;

• major-accident hazards have been identified and that the necessary measures have been taken to prevent such accidents and to limit their consequences;

• adequate safety and reliability have been incorporated into the design, construction, operation and maintenance of any installation, storage facility, equipment and infrastructure connected with its operation, which are linked to major-accident hazards inside the establishment;

• internal emergency plans have been drawn up.

.

5. SEVESO Directive: Obligations of the operator

Page 47: Www.buttiandpartners.com Environmental disasters and Seveso directives avv. Diana Michelazzo diana.michelazzo@buttiandpartners.com.

www.buttiandpartners.com

Internal emergency plans:

- are drawn up by the operator (safety report)- concern measures to be taken inside the establishment

External emergency plans:

- are drawn up by the competent authority basing on information sent by operators

- concern measures to be taken outside the establishment

5. SEVESO 5. SEVESO DirectiveDirective: : Emergency plansEmergency plans

Page 48: Www.buttiandpartners.com Environmental disasters and Seveso directives avv. Diana Michelazzo diana.michelazzo@buttiandpartners.com.

www.buttiandpartners.com

The competent Authority must:

• identify establishments or groups of establishments where the risk or consequences of a major accident could be increased due to the location and the proximity of the establishments and their holdings of dangerous substances;

• ensure an exchange of information and cooperation between the establishments.

5. SEVESO Directive: Domino effect

Page 49: Www.buttiandpartners.com Environmental disasters and Seveso directives avv. Diana Michelazzo diana.michelazzo@buttiandpartners.com.

www.buttiandpartners.com

5. SEVESO Directive: Information to be supplied after a major accident

After a major accident, the operator must:

• provide the competent authority with information on the circumstances of the accident, the dangerous substances involved, the data available for assessing the effects of the accident on people and the environment and the emergency measures taken;

• inform the authority of the treatments/remedial measures defined to minimize the effects of the accident and to prevent any recurrence of such an accident;

• update the information provided.

Page 50: Www.buttiandpartners.com Environmental disasters and Seveso directives avv. Diana Michelazzo diana.michelazzo@buttiandpartners.com.

www.buttiandpartners.com

5. SEVESO Directive: Information to be supplied after a major accident

After a major accident, the Authority must:

ensure that emergency measures have been taken;

collect the all the information for a full analysis of the accident, if necessary by inspection;

ensure that the operator takes any necessary remedial measures;

make recommendations on future preventive measures.

Page 51: Www.buttiandpartners.com Environmental disasters and Seveso directives avv. Diana Michelazzo diana.michelazzo@buttiandpartners.com.

www.buttiandpartners.com

Member States must inform the Commission of major accidents which have occurred within their territory.

The information must include:

• the name and address of the authority responsible for the report;

• the date, time and place of the major accident;

• the name of the operator and the address of the establishment;

• a description of the circumstances of the accident;

• a description of the emergency measures and precautions taken.

5. SEVESO Directive: Information to be supplied after a major accident

Page 52: Www.buttiandpartners.com Environmental disasters and Seveso directives avv. Diana Michelazzo diana.michelazzo@buttiandpartners.com.

www.buttiandpartners.com

DATA BASEDATA BASE

In order to fulfil its obligations with respect to

informing Member States, the the CommissionCommission must

establish a file and an information system to

collect all the data on major accidents occurring

within the territory of Member States.

5. SEVESO Directive: Information to be supplied after a major accident

Page 53: Www.buttiandpartners.com Environmental disasters and Seveso directives avv. Diana Michelazzo diana.michelazzo@buttiandpartners.com.

www.buttiandpartners.com

5. SEVESO Directive: Inspections

The competent authority must organize a system of inspections so as to ensure:

• that the operator can demonstrate that he has provided appropriate measures for preventing major accidents and limiting their consequences;

• that the safety report is accurate and complete;

• that information has been supplied to the public.

Page 54: Www.buttiandpartners.com Environmental disasters and Seveso directives avv. Diana Michelazzo diana.michelazzo@buttiandpartners.com.

www.buttiandpartners.com

5. SEVESO Directive: Prohibition of operations

Member States must:

- prohibit the operating of any establishment, installation or storage facility where the measures taken by the operator for the prevention of accidents are inadequate;

- prohibit the operations if the operator has not submitted:– the notification; – the reports; – any other information required by the Directive.

Page 55: Www.buttiandpartners.com Environmental disasters and Seveso directives avv. Diana Michelazzo diana.michelazzo@buttiandpartners.com.

www.buttiandpartners.com

5. SEVESO Directive: 5. SEVESO Directive: Collateral legislation to be consideredCollateral legislation to be considered

• Convention on the Transboundary Effects of Industrial Accidents (Decision 98/685/EC of March 23, 1998);

• Protocol on civil liability for damage and compensation of damage caused by transboundary effects of industrial accidents on transboundary waters (Kiev, May 21, 2003).