WP1 Progress report Vienna, 13 March 2011

Transcript of WP1 Progress report Vienna, 13 March 2011. Achievements General -4 Staff members (1 Image Analyst, 1...

Page 1: WP1 Progress report Vienna, 13 March 2011. Achievements General -4 Staff members (1 Image Analyst, 1 part-time Radiologist, 2 Research Assistants) in.

WP1 Progress report

Vienna, 13 March 2011

Page 2: WP1 Progress report Vienna, 13 March 2011. Achievements General -4 Staff members (1 Image Analyst, 1 part-time Radiologist, 2 Research Assistants) in.

AchievementsGeneral

- 4 Staff members (1 Image Analyst, 1 part-time Radiologist, 2 Research Assistants) in place

- Obtained approval from Medicines and Healthcare products Regulatory Agency

- Local Ethical Approval obtained provisionally, pending clarifications

Page 3: WP1 Progress report Vienna, 13 March 2011. Achievements General -4 Staff members (1 Image Analyst, 1 part-time Radiologist, 2 Research Assistants) in.

AchievementsStructural Imaging

1 Site survey ✔2 Site selection ✔3 Radiological and structural protocols (ADNI-GO) for 3T

scanners finalised and Manual sent to sites ✔4 Image Management System (TrialTracker) and electronic

data transfer tool (TrialWire) ✔

1 Sites to upload protocol and return protocol form in progress2 Sites to scan phantom and send details to IXICO in progress3 Sites to scan 1 healthy volunteer and send details to IXICO

not startedQualification and start scanning

Page 4: WP1 Progress report Vienna, 13 March 2011. Achievements General -4 Staff members (1 Image Analyst, 1 part-time Radiologist, 2 Research Assistants) in.

AchievementsStructural Imaging

3T SITESurvey

SentSurvey

ReceivedProtocol

SentProtocol Received

ACR Phantom at Site

ACR Phantom Scan Requested

ACR Phantom Scan Received

London Y Y Y Y Y Y YPrague Y Y Y Y Y Y YLeuven Y Y Y Y Y Y YUtrecht Y Y Y Y Y Y NMelbourne Y Y Y Y Y Y NCopenhagen Y Y Y Y Y Y NTel Aviv Y Y Y Y Y Y NMadrid Y Y Y Y N N NNaples Y Y Y N N N NBucharest Y Y Y N N N N

Innsbruck considering to join WP1

Page 5: WP1 Progress report Vienna, 13 March 2011. Achievements General -4 Staff members (1 Image Analyst, 1 part-time Radiologist, 2 Research Assistants) in.

AchievementsMagnetic Resonance Spectroscopy1 London, Copenhagen, Utrecht have met and agreed

protocol2 Spectra (anterior cingulate and thalamus) from

Copenhagen and Utrecht can be read and give reasonable values

3 The data can provide metabolite ratios4 Currently exploring whether we can do correction for

CSF in the MRS voxel which is a superior approach to the ratio method

Page 6: WP1 Progress report Vienna, 13 March 2011. Achievements General -4 Staff members (1 Image Analyst, 1 part-time Radiologist, 2 Research Assistants) in.

Milestones 1 Completion of preparation work for MRI sites

2 Start scanning

Deliverables1 Qualification of sites, test of electronic data transfer tool

2 Estimate of numbers (200 in total: if 10 sites, 20 patients per site)

Page 7: WP1 Progress report Vienna, 13 March 2011. Achievements General -4 Staff members (1 Image Analyst, 1 part-time Radiologist, 2 Research Assistants) in.

Possible concerns

Combination of MRS data:

- Existing power calculation did not take into account the greater variability of multicentre design

- Increase number of subjects with MRS at each site (~30-40 each: existing plan is for 20 subjects scanned twice in London and Copenhagen, so it would be slightly more than double)

- If datasets cannot be combined, we could explore whether findings are reproduced across sites

Page 8: WP1 Progress report Vienna, 13 March 2011. Achievements General -4 Staff members (1 Image Analyst, 1 part-time Radiologist, 2 Research Assistants) in.

Planned progress- Obtain final approval from local ethics- Qualify sites- Start recruitment and scanning- All sites to continue to scan phantom regularly plus 2

healthy volunteers (from the site) yearly, preferably every 6 months and before and after upgrades