WP 6: New s cales and ices · economically feasible. It seems that vessels that fall within the...
Transcript of WP 6: New s cales and ices · economically feasible. It seems that vessels that fall within the...
WWP 6:
D6
C R Pr W R
New s
.4: Synt
reation Daevision Daroject:
WP: esponsible
0/57
scales
thesis an
ate: 2013–1ate: 2014-0
MoveIT6
e: Ecorys
W
s and
nd impa
12-20 04-14 T! -
s - Johan G
WP 6: New
serv
act asses
Gille, Linett
w scales an
ices
ssment
te de Swar
nd services
rt
s
WP 6: New scales and services
1/57
ABSTRACT Inland waterway vessels are considered the cleanest land based transport mode in terms of its CO2 emissions on a per ton-km basis. However other modes are quickly catching up and speeding up is needed to maintain the IWT green character. For some emission categories (NOx, PM), road transport is already outperforming IWT. One reason for IWT to lag behind other modes is the long technical and economic lifetime of ships, which can easily extend 50 years. The replacement rate of the fleet is therefore rather low. This means, by modernising just through replacing older vessels by newer ones, the sector may become bypassed by other transport sectors soon. Therefore, action is needed targeting the existing IW fleet. To improve the performance of the inland waterway sector especially the existing fleet should be modernized. Currently there is insufficient knowledge about how to modernize the inland waterway fleet efficiently. The MoVe IT! project aims to develop concrete applications that can be installed on existing ships. WP 6 focuses on the most common old vessels in the fleet. WP6 can be split in two clusters. The first cluster analyses the options to improve the competitive position of relatively small vessels in the fleet (CEMT II and III) by lengthening them (with a goal to reach CEMT IV). The second cluster assesses new market opportunities for single hull tankers. This report is the last step of the first cluster where the economic and environmental feasibility of the lengthening steps are assessed. Lengthening of small inland vessels (by contemporary standards) is found to be economically feasible. It seems that vessels that fall within the CEMT II and III class can benefit of this retrofit option, as is shown from the business cases for the MV Hendrik and the MV Rheinland conducted in this task. Based on the analysis done and also in line with the results of the lengthening done in WP 7.2, inland vessels already need to have a critical mass to ensure that the lengthening will be economically feasible. If a vessel is too small, as is the case for e.g. the MV Rheinland, lengthening will be less feasible, especially when the vessel is only lengthened with 6 metres. To make lengthening a feasible option the benefits need to outweigh the investment costs. From an economic and environmental perspective it seems feasible to install a propeller in nozzle instead of a naked propeller. The propeller in nozzle is able to reduce the fuel consumption and therefore the impact of CO2 emissions. To have full economical and environmental effects, the speed should be reduced, but speed reduction has a cost too and is not as easy as it sounds.
WP 6: New scales and services
2/57
Document Properties Document Name: WP 6: New scales and services Document Author(s) Johan Gille, Linette de Swart. Document Editor(s) Date of delivery 2014 04-14 Nature of Deliverable Report Prototype Demonstrator Other Circulation Security Status Document Status Draft
X Final Approved by SG Steering (or SP meeting type-D) Approved by reviewer Acknowledged by MOVEIT! Steering Issued to EC
Keywords economic feasibility, environmental assessment, IWT, synthesis Related MoVeIT! Reports D6.1, D6.2 and D6.3.
Partners involved No. Organisation Name Name Email 12 UNIVERSITATEA DUNAREA DE
JOS DIN GALATI Ionel Chirica
14 University of Belgrade Dejan Radojcic
Document history Version Date of delivery Changes Author(s)
Editor(s) Reviewed by
0.1 2013 – 12 - 20 First draft Johan Gille Linette de Swart
Dejan Radojcic
0.2 2014 – 04 - 17 Second draft Johan Gille Linette de Swart
Robert Hekkenberg
0.3 2014 – 04 - 24 Final report Johan Gille Linette de Swart
Table
ABSTR
1 EX
1.1
1.2
1.3
2 INT
2.1
2.2
2.3
3 ME
3.1 3.1
3.2
PART A
4 DE
4.1
5 CO
5.1
5.2
5.3
6 EC
6.1
6.2 6.2
6.3
6.4
e of Con
ACT ...........
XECUTIVE S
PROBLEM
TECHNIC
RESULTS
TRODUCT
BACKGR
AIM OF T
STRUCT
ETHODOL
METHOD1.1 Asse
METHOD
A: HENDRI
ESCRIPTIO
OPERAT
ONSIDERED
SHIP STR
MANOEU
POWERIN
CONOMIC
COMMER
INPUT D2.1 Spec
RESULTS
SENSITIV
ntents
.....................
SUMMARY
M DEFINITI
CAL APPRO
S AND ACH
TION ............
ROUND .....
TASK 6.4 .
URE OF TH
OGY ...........
DOLOGY Oessing diffe
DOLOGY FO
IK .................
ON OF THE
IONAL PRO
D SHIP MO
RUCTURE ..
UVRABILITY
NG ...........
FEASIBILIT
RCIAL / EC
DATA AND cific assum
S OF ECON
VITY ANAL
.....................
Y ...................
ION ..........
OACH .......
HIEVEMENT
.....................
...............
...............
HE REPORT
.....................
OF ECONOMerent econo
OR ASSESS
.....................
E SHIP .........
OFILE .......
ODIFICATI
...............
Y .............
...............
TY ...............
CONOMIC I
ASSUMPTImptions .....
OMIC ASSE
YSES ........
3/57
.....................
.....................
................
................
TS .............
.....................
................
................
...............
.....................
MIC ASSESSomic scena
SING ENVIR
.....................
.....................
................
ONS ..........
................
................
................
.....................
MPACTS ...
ONS .........................
ESSMENT ..
................
W
.....................
.....................
...............
...............
...............
.....................
...............
...............
...............
.....................
SMENT .....arios ........
RONMENTA
.....................
.....................
...............
.....................
...............
...............
...............
.....................
...............
...............................
...............
...............
WP 6: New
.....................
.....................
................
................
................
.....................
................
................
................
.....................
................
................
AL IMPACTS
.....................
.....................
................
.....................
................
................
................
.....................
................
................
................
................
................
w scales an
.....................
.....................
................
................
................
.....................
................
................
................
.....................
................................
S ..............
.....................
.....................
................
.....................
................
................
................
.....................
................
................................
................
................
nd services
.................. 1
.................. 7
.............. 7
.............. 7
.............. 8
.................. 9
.............. 9
............ 10
............ 11
................ 13
............ 13
............ 15
............ 16
................ 19
................ 21
............ 21
................ 23
............ 23
............ 24
............ 25
................ 27
............ 27
............ 28
............ 28
............ 29
............ 30
s
7
7
7
8
9
9
0
3
3 5
6
9
3
3
4
5
7
7
8 8
9
0
WP 6: New scales and services
4/57
7 ENVIRONMENTAL FEASIBILITY ................................................................................................... 33
7.1 INPUT DATA AND ASSUMPTIONS ................................................................... 33
7.2 RESULTS ....................................................................................................... 33
7.3 SENSITIVITY ANALYSIS .................................................................................. 35
PART B: RHEINLAND ................................................................................................................................. 37
8 DESCRIPTION OF THE SHIP .......................................................................................................... 39
8.1 OPERATIONAL PROFILE ................................................................................. 39
9 CONSIDERED SHIP MODIFICATIONS ....................................................................................... 41
9.1 SHIP STRUCTURE ........................................................................................... 41
9.2 MANOEUVRABILITY ....................................................................................... 41
9.3 POWERING .................................................................................................... 42
10 ECONOMIC FEASIBILITY ............................................................................................................ 43
10.1 COMMERCIAL / ECONOMIC IMPACTS ............................................................. 43
10.2 INPUT DATA AND ASSUMPTIONS ................................................................... 43 10.2.1 Specific assumptions .............................................................................. 44
10.3 RESULTS OF ECONOMIC ASSESSMENT ............................................................ 44
10.4 SENSITIVITY ANALYSIS .................................................................................. 45
11 ENVIRONMENTAL FEASIBILITY .............................................................................................. 47
11.1 INPUT DATA AND ASSUMPTIONS ................................................................... 47
11.2 RESULTS ....................................................................................................... 47
11.3 SENSITIVITY ANALYSIS .................................................................................. 49
12 CONCLUSIONS ............................................................................................................................... 51
12.1 THE MAIN CONCLUSIONS FOR HENDRIK: ....................................................... 51
12.2 MAIN CONCLUSIONS FOR RHEINLAND: .......................................................... 51
12.3 OVERALL CONCLUSIONS ............................................................................... 51
13 BIBLIOGRAPHY AND REFERENCES ....................................................................................... 53
13.1 BOOKS AND ARTICLES ................................................................................... 53
WP 6: New scales and services
5/57
13.2 WEBSITES ...................................................................................................... 53
14 INDEXES ............................................................................................................................................ 55
14.1 INDEX OF FIGURES ........................................................................................ 55
14.2 INDEX OF TABLES .......................................................................................... 55
14.3 LIST OF ABBREVIATIONS ................................................................................ 56
1 Ex
1.1 PInland CO2 emterms osector PM), roother mextend by modbypassis needwaterwinsuffic The Moexistingsplit in positionThe sereport feasibil The aimbenefitsenvironvesselsthe firson man Each lethe ecologisticcurrentprofile investm Also thenvironcurrent
1.2 TThe aimproposcompashippinassump
xecutive
Problem Dshipping imissions oof energy is neededoad transpmodes is
50 years.dernising jused by otheded target
way sector cient knowl
oVe IT! prg ships. W
two clusten of relativecond clusis the lasity of the le
m of this ts once the
nmental ims were chot part of Wnoeuvrabili
engtheningonomic pral operatiot operationonce a ce
ment is con
e environmnmental imt performan
Technicalm of task 6ed lengthered with th
ng compaptions are
e Summ
Definitios consider
on a per toefficient a to mainta
port is alrethe long t The replaust througer transpoting the exespeciallyedge abou
roject aimsWP 6 focuse
ers. The fvely small ster assesst step of engthening
task is twoe vessel is
mpact of theosen, the H
WP 6. For eity and the
g step will rofile of thon of the nal profile ertain retronsidered.
mental impmpact the nce of the
l approa6.4 is to aening stepshe referencany conce
made whic
mary
on red the cle
on-km basisnd clean t
ain its leadeady outpetechnical aacement rah replacingrt sectors, xisting IW y the existiut how to m
s to develes on the mfirst clustervessels inses new
f the first g steps are
ofold: on tmodernize
e modernizHendrik aneach of the powering
impact thehe vessel vessel. Tof the ve
ofit option
pact will chchange invessels.
ch nalyse thes on the oce situatioerned. Toch are veri
7/57
eanest lans. Howevetechnologie
ding positioerforming Iand econoate of the fg older veesp. the rfleet. To
ing fleet smodernize
op concremost commr analysesn the fleet market opcluster w
e assessed
he one haed need tozing needsnd Rheinlae two vesserequireme
e businesschange; t
o analyseessel is co
is implem
ange oncen environm
e operationoperator’s bn which eq
o establishified with s
W
nd based ter other moes take-upon. For somIWT. One omic lifetimfleet is thessels by nroad sectoimprove thould be mthe inland
ete applicamon old ves the optio
(CEMT IIpportunitieswhere the d.
and the coo be estimas to be assand, these els severa
ents were a
s case of tthere migh the impaompared w
mented. Al
e the vessemental per
nal, logisticbusiness. quals the ch current
ship owners
WP 6: New
transport modes are qp and speeme emissireason fo
me of shiperefore rathnewer onesor, very soothe performmodernizewaterway
ations that essels in thns to imprand III) b
s for singleconomic
onsequenceated and oessed. In tvessels a
l lengtheniassessed.
the ship oht also be
acts of thewith the eso the pa
el is lengthrformance
cs and ecoThe effectcurrent op
operatins participat
w scales an
mode in tequickly catceding up oon catego
or IWT to lps, which her low. Ths, the secton. Therefomance of
ed. Currentfleet efficie
can be inhe fleet. Wrove the c
by lengthene hull tan
c and env
es on the on the othetask 6.0 tware used toing steps,
wner. Not e an impae retrofit oexpected oayback per
hened. To ais compa
onomic effets of each perating prog profilesting in the
nd services
erms of itsching up inof the IWT
ories (NOxlag behindcan easilyhis meanstor may beore, actionthe inlandtly there isently.
nstalled onWP6 can becompetitivening them
nkers. Thisironmenta
costs ander hand thewo possibleo carry outthe impact
only doesact on theoptions theoperationariod of the
assess thered to the
ects of theoption areofile of thes, generaproject.
s
s n T ,
d y ,
e n d s
n e e . s l
d e e t t
s e e l
e
e e
e e e l
WP 6: New scales and services
8/57
For each of the five lengthening options, the main economic advantages and drawbacks were identified by the Move-IT WP6 partners jointly with the ship operators and checked with the technical partners to ensure consistency and reliability. From tasks 6.1, 6.2 and 6.3 cost estimates for the lengthening, impacts on maintenance costs and effects on fuel consumption were provided. These estimates are the basis of the analyses made to assess the feasibility of each lengthening option. For each vessel several options are calculated, and the results are compared to the reference situation. The payback time of the investment is calculated as well as other indicators, i.e. the internal rate of return (IRR) and the net present value (NPV).
1.3 Results and Achievements Lengthening of small inland vessels (by contemporary standards) is found to be economically feasible. It seems that vessels that fall within the CEMT II and III class can benefit from this retrofit option, as is shown from the business cases for the MV Hendrik and the MV Rheinland conducted in this task. Based on the analysis done and also in line with the results of the lengthening done in WP 7.2, inland vessels already need to have a critical mass to ensure that the lengthening will be economically feasible. If a vessel is too small, as is the case for e.g. the MV Rheinland, lengthening will be less feasible, especially when the vessel is only lengthened by only 6 metres. To make lengthening a feasible option the benefits need to outweigh the investment costs. From an environmental perspective it seems desirable to install a propeller in nozzle instead of a naked propeller, which is commonly found on old inland ships. The propeller in nozzle is able to reduce the fuel consumption and therefore the amount of CO2 emissions. To have more effect of the propeller in nozzle the vessel should also reduce its speed. In this case the implementation of the nozzle is most effective.
2 Int
2.1 BDue to transpomodes or carg On topuse foshigher from 20on the losing transpo In ordeknown efficienhave astrategefficienimportashows Europe Table 2Tonnagvessel 0 – 650650 – 11500 – 3000 – Over 40Average Currenfleet efObjecti
• • • •
v•
WP6 ccompet
troduct
Backgrouthe liberal
ort sector h(road, rail
go markets
p of that, thssil fuels (fuel bills.
009, freighmarket, trmore and
ort.
er to copeas the cle
nt than it aa very lony of phasin
nt ones is nant to modthe avera
ean fleet is
2.1 Averagege of the
tons 500t tons 3000 tons 4000 tons
000 tons e age of pus
tly there isfficiently. Tives of the Improve thImproving Improve thImprove tvessels to Finding nereconstruc
an be splititive posit
tion
und ization of thas increa and IWT)).
he fuel prie.g. dieselDue to th
ht rates anransport cod more gr
with the eanest andalready is, g life spang out of enot easily ernize andge age peof similar
e age of WeBuild
Ca. 1Ca. 1Ca. 1Ca. 2Ca. 2
shing units
s insufficieThe goal o
project arehe hydrodythe operat
he performthe constrmeet new
ew trades fction of par
t in two clion of the
the Europesed consid) and within
ces have l, gasolinee sharpend transporompanies round to t
increased d most fueas to imprn and rem
existing inedone, take
d improve ter vessel cage, thoug
estern Euroding year
1950 1960-19701995 (110 m2000 (135m2005 (barge and
ent knowleof the MoVe:
ynamic behtional perfoance of enruction (al
w requiremefor existingrts of the v
usters. Thsmaller ve
9/57
ean continederably. Thn the same
increased e and gasoned comperted volumhave to b
the other
competitioel-efficient rove businmain in thefficient veses too longthe existingclass in Wgh in some
opean vessCla
CECE
m ship) CEm) CE
>Cd pushers) is
dge aboutVe IT! proje
haviour of tormance (Wngines (WPso when ents) (WP5g vessel aessel (WP
he first clusessels in th
W
ental transhis appliese mode (e
during theoil) and theetition as a
mes have decome momodes lik
on and cotransport m
ness operae market ssels and rg, and is mg vessel fle
Western Eue places ma
sels assificatio
EMT I and IEMT III and EMT V EMT VI CEMT VI s 20 years
t how to mect is to o
the ships inWP3); P4);
integratin5); nd/or impr6).
ster analyshe fleet (C
WP 6: New
sport markes both the c.g. betwee
e last yeare rising fuea result of decreased.ore efficienke rail and
ost increasmode, nee
ations. Howfor a con
replace themuch too ceet as welrope. On aaintenance
n
I IV
modernize obtain the
nvolved (W
g new st
roving their
ses the opCEMT II an
w scales an
et competicompetitio
en vessel t
rs. All model prices hthe econo
To stay cnt. Especiad in partic
ses, inlandeds to becwever inlannsiderable em by newcostly. Thel. The folloaverage the levels are
Average a
60 years 45 years 25 years 15 years 5 years
the inlandrequired k
WP2);
tructures i
r competiti
ptions to imnd III) by le
nd services
tion on then betweenypes and /
des mainlyhave led toomic crisiscompetitiveally IWT iscular road
d shipping,come morend vesselstime. The
w and moreerefore it isowing tablehe Easterne low.
ge
waterwayknowledge
n existing
iveness by
mprove theengthening
s
e n /
y o s e s d
, e s e e s e n
y .
g
y
e g
WP 6: New scales and services
10/57
them. The second cluster assesses new market opportunities. WP6 consists of seven tasks and an 8th task (task 0) that was added after the start of the project:
New scales 0. Added Task – concentrates on identification of vessels that should be lengthened
(6.0); 1. Focus on ship structure, especially lengthening (6.1); 2. Impact of ship lengthening on manoeuvring (6.2); 3. Impact of ship lengthening and repowering on powering requirements (6.3); 4. Synthesizing the outcomes of the previous tasks and assessing the economic
and environmental impacts (6.4).
New services 5. Evaluating technical solutions to adjust to climate change (6.5); 6. Evaluating possibilities for the transport of CO2 (6.6); 7. Evaluating new markets for single hull tankers (6.7).
2.2 Aim of task 6.4 The aim of this task is twofold: on the one hand the consequences on the costs and benefits once the vessel is modernized need to be estimated and on the other hand the environmental impact of the modernizing needs to be assessed. In task 6.1 two example vessels were selected, the Hendrik and Rheinland, which may be considered examples of the types of vessels that should be lengthened. These vessels are used to carry out the first part of WP 6 (tasks 6.2 to 6.4). For each of the two vessels several lengthening steps, their impact on manoeuvrability and the associated powering requirements were assessed. Each lengthening step will impact the business case of the ship owner. Not only does the economic profile of the vessel change; there might also be an impact on the logistical operations of the vessel. To analyse the impacts of the retrofit options the current operational profile of the vessel is compared with the expected operational profile once a certain retrofit option is implemented. Also the payback period of the investment is considered. Also the environmental impact will change once the vessel is lengthened. To assess the environmental impact the change in environmental performance is compared to the current performance of the vessels. As no details on the operating profile and current environmental performance were known to the Consortium some expert judgements were made in order to carry out both the economic and environmental assessment. The result of task 6.4 is an overview of the impacts of the different lengthening steps considered. The approach chosen within WP6 is considered classical and while two typical class II and III vessels were chosen, it is assumed that the conclusions derived apply to other similar vessels as well. It is noted that apart from the technical characteristics also the operational profile has a large influence on the economic viability.
WP 6: New scales and services
11/57
2.3 Structure of the report Chapter 3 describes the methodology used to assess the economic feasibility of the proposed retrofit options. The main assumptions are presented as well as the evaluation criteria. The chapter also describes the methodology used to assess the environmental performance of the vessels considered. The remaining of the report is divided into two parts that each have the same structure. Part A focuses on the larger inland vessel, Hendrik, and part B describes the smaller inland vessel assessed, the Rheinland. For both vessels a general description is provided (chapters 4 and 8), the proposed retrofit options are described (chapters 5 and 9), the economic assessment is described (chapters 6 and 10) and the environmental assessment is carried out (chapters 7 and 11). Chapter 12 provides the main research findings and in chapter 13 the literature used is presented.
3 Me
3.1 MThe aimproposcompashippinassumpThe as For eacadvantathe shiconsist From tacosts athe anasevera Table 3
NPV IRR Paybac For easituatiocompathe shimoneyback hi Anothecompainvestmflows) flows) retrofit A last policy discountoday taccounretrofit
11 Two lengt
ethodol
Methodolm of task 6ed lengthered with th
ng compaptions are sumptions
ch of the fages and ip operatotency and r
asks 6.1, 6and effectsalyses madl options a
3.1 Present
k period
ach of theon is calcunies the paip owner h. The loweis investme
er indicatorres the p
ment is theof the invof the inveoption.
indicator urelated dented: cashto the pre
nt. The higoption.
thening steps for f
logy
logy of e6.4 is to aening stepshe referencany conce
made whs made for
five lengthdrawbacksrs, and chreliability.
6.2 and 6.3s on fuel code to assere calculat
tation of ouReferencesituation
options tulated, as ayback pehas earneer the payent.
r used is thprofitability e discount vestment eestment. T
used is thecisions anh inflows aesent valuegher the va
fhe Rheinland and
economicnalyse thes on the oce situatioerned. Toich are vethe two sp
hening optis were idehecked wit
3 cost estimonsumptio
ess the feated, so the
utcomes fee R
the changwell as th
riod is the ed back hiyback perio
he internalof differe
rate at whequals the The higher
e Net prend indicate
and cash oe of monealue of this
d three lengthenin
13/57
c assesse operationoperator’s bn which eq
o establiserified with pecific ship
ons considentified by th the part
mates for tn were prosibility of e results loo
asibility asRetrofit opt
e in operhe paybacmost relev
is initial inod is the s
l rate of reent optionhich the ne
net preser the IRR i
esent valuees the ‘difoutflows. Itey in the s indicator
g steps for the He
W
sment nal, logisticbusiness. quals the ch currentship owne
ps are discu
dered in ththe MoVe
tners with
the lengtheovided. Theach lengthok similar t
ssessmention 1 Ret
ating costck time of vant indicanvestment sooner the
eturn (IRR)s or moreet present ent value is the mor
e (NPV). Tfference at comparefuture, tak
r the more
endrik were consid
WP 6: New
cs and ecoThe effectcurrent opt operatiners participussed in ch
he project1e IT! WP6
technical
ening, impaese estimahening optto:
trofit option
ts comparethe inves
ator. This inand when
e ship own
). This indie specificvalue of cof the be
re profitabl
This indicaamount’ bes the presking inflatiattractive
dered.
w scales an
onomic effets of each perating prong profilespating in thhapters 6 a
1 the mainpartners jexpertise
acts on maates are thtion. For ea
n 2 Retrof
ed to the stment. Fondicator shn he startsner will ha
icator meaally the Icosts (negnefits (posle it is to i
ator is ofteetween thesent value ion and reit is to inv
nd services
ects of theoption areofile of thes generahe projectand 11.
economicjointly withto ensure
aintenancehe basis ofach vesse
fit option 3
referenceor shippinghows whens to make
ave earned
asures andRR of an
gative cashsitive cashinvest in a
en used ine sums ofof money
eturns intovest in the
s
e e e l .
c h e
e f l
3
e g n e d
d n h h a
n f y o e
WP 6: New scales and services
14/57
General assumptions Several general assumptions are made, which apply to all shipping companies and all retrofit options. The first assumption relates to the time horizon used to calculate the effects. Apart from the investments costs, which occur only once, all other costs components are recurring. Some of them recur every year, e.g. the casco insurance premium and wages of employees, while other cost components only occur every two or three years, e.g. large maintenance costs. The time horizon chosen is set at 25 years. The second assumption relates to the discount rate. All future costs or benefits are expressed in their present value, so all effects will be discounted to the year of investment. The year of investment is assumed to be 20162. By discounting the costs and effects, costs and effects later in time count less heavily than costs and effects made earlier in time. The discount rate used in the analysis is 5.5%. The third assumption relates to the prices used. All effects will be expressed in Euros, and data obtained in other currencies are converted to Euros. The effects will all be expressed in real prices and the price level used is price level 2013.
Main effects – direct effects: • Investment costs: One of the most important aspects in the economic
evaluation is the investment costs needed to obtain the new retrofit option. For each of the options the partners with technical expertise have estimated the investment costs. It is assumed that the investment costs will all fall in one year and can be qualified as one-of costs;
• Maintenance costs: Closely related to the investment costs are the additional costs for maintenance. Installing a new engine or place a new rudder arrangement might cause an increase of the maintenance costs. It is assumed that maintenance related to the retrofit installation is needed every couple of years, and assumptions on this are made for each option. This means associated costs are included in the analysis using the assumed frequency (e.g. every 2 years, 3 years, etc.).
Main effects – operational profile • Fuel consumption: Depending on the retrofit option chosen, fuel consumption of
the vessel may increase or decrease. Most of the technical improvements suggested in the previous Work packages will result in a decrease of the fuel consumption of the vessel, resulting in a lower fuel bill, assuming that fuel prices remain constant. However some options, e.g. lengthening of the vessel, will increase the fuel consumption and therefore increase the fuel bill. For estimating the fuel prices the CBRB Gas oil circulars for inland shipping are used;
2 The MoVe-IT project ends in November 2014. It is assumed that companies need 2015 to ensure financing,
make arrangements, e.g. reserve yard space and decide on the retrofit options. The first possible year of investment is 2016.
WP 6: New scales and services
15/57
• Insurance costs: In inland shipping there two important types of insurances; the casco insurance or the hull and machinery insurance (H&M) and the protection and indemnity insurance (P&I). For the economic evaluation the casco insurance is the most important one, because the modernisation of the vessel will influence the height of the casco insurance. Insurance costs may increase if a technology is implemented that is much more expensive then the systems in place in the reference situation. On the other hand as it may concern a replacement by a newer and more reliable system, in some cases perhaps premiums can be reduced, because the chance of failure had reduced;
• Capital costs: The financial picture of the company can change due to the retrofitting of the vessel. To finance a retrofit option it is assumed that the shipping company has to obtain an additional loan from a bank or from another investor. The interest costs will probably increase and the company faces higher financing costs than before.
Additional effects • Cargo volumes: Cargo carrying capacity can change due to the retrofit
modernization of the ship. For most proposed retrofit options this effects will be limited, as cargo capacity or sailing speeds will not change. However in case the vessel is lengthened the ship’s capacity will increase allowing larger volumes to be transported, resulting in a revenue increase (assuming sufficient demand). On the other hand some other retrofit options may cause a (slight) reduction of the cargo capacity of the vessel;
• Labour costs: labour costs could be affected by the modernisation of the vessel. This could concern the need for hiring additional personnel to comply with current legislation, or the need for additional training, which brings (temporary) additional costs. The first impact may occur when a vessel is lengthened, and if a threshold in manning regulations is passed, additional crew is required. On the other hand the retrofit option can require additional skills of the employees for which and additional training is required.
3.1.1 Assessing different economic scenarios As assumptions are made which are uncertain, while the base case development may also be uncertain (e.g. how will the IW market develop, what will the level of fuel prices be in future years, etc.), for each ship/retrofit option combination, multiple scenarios will be tested. Generally we assess a baseline scenario (e.g. applying the middle assumptions on costs and impacts), a high, and a low scenario (using the range ends of costs and impacts estimated. These will be presented as sensitivity tests on the baseline scenario. As the uncertainties on assumptions vary between the ships and retrofit options, no standard scenarios for all ships are developed, but the baseline and alternative scenarios are made for each ship/retrofit option specifically. However general inputs such as interest rates, residual values or fuel prices are applied similar for all ships.
WP 6: New scales and services
16/57
3.2 Methodology for assessing environmental impacts The second aim of task 6.4 is to assess the environmental impact of the retrofit options proposed in tasks 6.1 – 6.3. The emissions considered in the assessment are:
• Carbon dioxide (CO2); • Nitrogen oxide (NOx); • Particular matter (PM); • Hydrocarbon (HC); • Carbon monoxide (CO); • Sulphur dioxide (SO2).
The emissions are related to the change in fuel consumption and are compared to the situation without any retrofit option. The emissions are presented as yearly values and values related to the transport performance in ton kilometres (tkm). Fuel consumption is estimated for all lengthening options considered. Also a distinction is made between the fuel consumption in case the vessel uses a naked propeller and the fuel consumption in case the vessel has a propeller with nozzle. The fuel consumption and therefore the emissions will increase due to lengthening of the vessel as the vessel requires more power to achieve the same performance. Taking only this aspect into account lengthening might not be a desirable option from an environmental point of view. However not only the fuel consumption of the vessel changes, but also the cargo carrying capacity will increase significantly. Due to this increase in cargo carrying capacity the relative values (kg emission / tkm) can be lower than without lengthening of the vessel. This can make lengthening, also from an environmental perspective, a more favourable option than doing nothing. The total emissions per year are determined using the following equation: where FC is the total fuel consumption per year in kg and EF is the respective emission factor given in kg/fuel for CO2 and g/fuel for all other emission factors. The factors used are based on the factors used in other studies. The factors are the same factors that are used in the environmental assessment in WP7. The following table shows the factors used in this study. Table 3.2 Emission factors for inland waterway vessels CO2 NOx PM HC CO SO2 Source kg / kg fuel g / kg/fuel g / kg/fuel g / kg/fuel g / kg/fuel g / kg/fuel 3,175 57 0,83 3,4 6,5 0,02 VBD, 2001 3,173 46 2,116 5,1 19 0,02 TNO, 2010 Source: VBD (2001) and TNO (2010). It is noted that the differences between TNO and VBD (now DST) data is large. Reasons for deviations are the uncertainty associated with PM measurements as well as the fact that the emission factors are average values over different power classes of engines. In this study the TNO figures will be the leading factors as the study is more
WP 6: New scales and services
17/57
recent. For more information on the methodology used, please see Deliverable 7.3 ‘Environmental impact’.
Par
19/57
rt A: He
W
endrik
WP 6: Neww scales annd servicess
4 DeThe HDuijventhe vesholds a BetweeConsorlengtheassignmqualifiemeasu Table 4 Length Beam DraughtDisplaceMain enSource: h Figure
Source: w
4.1 OAs the severaenvironbetwee100 km It is alsnot saioperateAs the client o48 sing
escriptiendrik (cundijk, locatssel had tware covered
en 1975 anrtium whenening is noment is theed as a Crements of
4.1 Main ch
t ement
ngine http://www.deb
4.1 Impres
www.debinnen
Operationactual op
l assumpnmental asen Duisburm and so a
so assumel the wholees 48 weevessel is
only and is gle trips an
on of thurrently naed in Krim
wo separatd with slidi
nd 1990 thn this lengtot considere original
CEMT III of the vesse
haracteristi
binnenvaart.nl
ssion of the
nvaart.nl (left)
nal profilperating protions havssessment
rg and Coloround trip
d that the e year rounks per yeasailing on carrying cd the othe
he shipamed Alk) pen a/d IJte cargo hong hatch c
e vessel wthening prered in the length of tor CEMT el.
cs of the H
/schip_detail/
e Hendrik
& www.binne
le ofile of the
ve been t. It is asogne, Germhas a leng
vessel pernd. In the
ar and so ta short d
cargo only r remaining
21/57
was builtssel. The lolds with acovers to p
was lengtheecisely tooanalysis a
the vessel,IV vesse
Hendrik (19 698.62.913SK
1649/.
nvaart.eu (righ
e vessel ismade whssumed thmany. A ongth of 200
rforms maxcalculationhe maximuistance it ione way ag 48 trips t
W
t in 1975 length of tha length of protect the
ened to 80ok place. Fand the st, hence 70l. Followin
75)
9.98 m 60 m 95 m
360 ton KL 660 PK 6
ht).
s unknownhich are hat the vene way tripkm.
ximum onens it is therum numbeis assume
and therefothe vessel
WP 6: New
at the Dhe vessel wf 20.0 metrcargo.
0.0 metres.For researcarting poin0.0 metresng table p
6 NVD 48 –
n to the Mused in
essel operp has a len
e round triprefore assuer of trips ped that the ore the ves
does not c
w scales an
Dutch yardwas 70.0 mres each. B
. It is unknch purposent of the les. The vessprovides th
– 2U
oVe IT! Cthe econrates on
ngth of app
p per weekumed that performed
vessel sassel is only carry cargo
nd services
Joh. vanmetres andBoth cargo
own to thees this pastengtheningsel can behe origina
onsortiumnomic andthe Rhine
proximately
k and doesthe vesseequals 48
ails for oneloaded on
o.
s
n d o
e t
g e l
, d e y
s l . e n
5 CoThis chsevera6.2 ascarryingonce th
5.1 SIn taskanalysi(80.0 mrules. Elength o The folengthe Table 5 Max. drTotal caholds Additionin holdsRelativeSource: M For eacthe ove
onsiderhapter prel lengthen
ssessed thg out sevehe vessel is
Ship struck 6.1 the s is the or
metres). ThEach lengof one TEU
ollowing taening optio
5.1 Max. dra
raught argo in
nal cargo s e change Move-it WP 6,
ch of the oerall costs
red shipesents the ing steps
he manoeeral manoes lengthen
cture lengtheninriginal lenghe structurthening stU) and in to
able showon. For eac
aught and Loa(m) (t)
(t)
(%) task 6.1 final
options a dper lengthe
p modifioutcomes
were consuvrability euvrability ed taking i
ng option ogth of the re of the vitep is 6.0 otal 5 leng
ws the mach new opt
additional 70 m Loa2.960 1.114
-
- report.
detailed coening step
23/57
icationss of tasks sidered anof the vetests. Tas
into accou
of the Hevessel (70rtually lengmetres (w
gthening ste
aximum drion also th
cargo for da 76m Lo
2.9521.241
128
11.5
ost estimatp and the c
W
s 6.1 to 6.3
d for eachessel undesk 6.3 assent different
ndrik is a0.0 metresgthened ve
which correeps were c
raft and toe additiona
different leoa 82m L
2.9451.373
259
23.3
te was maosts per m
WP 6: New
3 for the h of the ster differenessed the t water dep
nalysed. Ss) instead oessel compesponds wconsidered
otal cargoal cargo ca
engtheningLoa 88m
2.940 1.502
388
34.9
ade. The fometre.
w scales an
Hendrik. Iteps considnt circums
power reqpths and c
Starting poof the currplies with c
with the apd.
o capacityapacity is p
steps Loa 90m
2.938 1.545
432
38.8
ollowing ta
nd services
n task 6.1dered task
stances byquirementsurrents.
oint of therent lengthcurrent GLpproximate
y for eachpresented.
Loa 95m2.9341.653
539
48.4
able shows
s
1 k y s
e h L e
h
43
9
4
s
WP 6: New scales and services
24/57
Table 5.2 Summary of costs per lengthening step for MV ’Hendrik’ Loa
76mLoa 82m
Loa 88m
Loa 90m
Loa 95m
Lengthening step ΔL (m) 6.0 12.0 18.0 20.0 25.0New hull section (€) 35.000 88.000 126.000 142.000 178.000Upgrade existing parts (€) 18.000 18.000 18.000 18.000 18.000Hatch cover (€) 10.000 20.000 30.000 33.300 41.700Total (€) 64.000 126.000 175.000 193.300 237.700
Costs per meter of the new section (steel)
(€/m) 10.500 10.500 9.700 9.700 9.500
Costs for additional modification (structure)
(€/m) 1,000 1,900
Costs per meter of the new section (dry dock per week)
(€/m) 1,200 600 400 400 300
Total cost per m (€/m) 11,700 11,100 10,100 11,100 11,700Source: Move-it WP 6, task 6.1 final report. In task 6.1 it was concluded that, although the lengthening steps Loa 90m and Loa 95m are technically feasible, they are too comprehensive as a retrofit option, because various additional changes in the structure of the forward and aft part of the vessel would be needed to meet GL requirements. Therefore these options are rather complex ones and are no longer considered in the remaining part of the analysis; see the task 6.1 report for further details.
5.2 Manoeuvrability Manoeuvrability and the impact of lengthening of the vessel on the manoeuvrability is the main focus of task 6.2. To establish the effect of lengthening on a vessel’s manoeuvrability four different tests were conducted:
1. Combined turning circle / pull-out manoeuvres; 2. Standard zigzag manoeuvres; 3. Evasive manoeuvres; and 4. Crash stop manoeuvres.
The analysis was carried out for three different lengths of the vessel. The first length is the original length of 70.0 metres and the tests were also done for lengths of 82 metres and 95 metres. All tests are carried out for different water levels, to establish the effects in deep water as well as shallow water. The depths considered were 3.5 m, 5 m, and 20 m. On top of that different speed levels were taken into account and each test was carried out for a speed of 10 km/h and 13 km/h. The lengthening of the vessel was found to have no significant impact on the turning ability and directional stability of the vessel (the combined turning circle and pull-out manoeuvres). In shallow water the turning ability of the vessel is worse, but to improve the turning ability the vessel could decrease it approach speed. Further no improvements are needed. The same conclusions are drawn for the yaw checking ability and the initial turning ability (zigzag manoeuvres).
WP 6: New scales and services
25/57
Lengthening of Hendrik has a small influence on the evasive manoeuvring ability. In shallow water the capabilities of the vessel are reduced and to solve the problem the rudder dimensions and characteristics could be improved. The lengthening does not affect the stopping ability (crash stop manoeuvres) of the vessel and no action is needed with regard to the stopping ability of the vessel.
5.3 Powering In task 6.3 the influence of lengthening the vessel on the powering arrangement is analysed. The Hendrik is a single-propelled vessel, with a SKL 660 PK 6 NVD 48 – 2U engine. The vessel has one naked propeller with diameter of 1.5 metres. It is estimated that the maximum speed of the vessel with its initially installed engine is 19.5 km/h, however the vessel hardly sails at maximum speed. In the analysis not only the effect of the lengthening on the required power is analysed, but also the water depth is considered. The lengthening itself does not significantly influence the power needed to achieve a certain speed. Therefore the same power train (engine, gearbox and propeller) was considered for all lengthening steps. It should be noted that the power train is renewed in the analysis, but the technical specifications remain more or less the same. Speed reductions of 1 to 2 km/h as result of the lengthening might occur in case the water depth changes. In shallow water (from deep to h= 5m and then from 5m to 3.5 m) the speed reduction of Hendrik is around 4 km/h. In very shallow water the maximum speed is even further reduced due to squat. The maximum allowed speed for the vessel is 13 km/h for h=5 m and 8 km/h for h=3.5 m. The installation of a propeller in nozzle will improve the propulsive efficiency compared to the naked propeller. The expected improvement is around 10% which can increase the speed for 1 km/h.
6 Ec
6.1 CThe opaim is tthe comoperatesail witthe othrevenu Lengthcompalengthethe samconsumof the consumtable sh Table 6 Ship’s (m) 69.98 76 82 88 Besidelengthecarryingthe car18 met In the tshows more cfuel con Table 6 Ship’s (m) 69.98 76 82 88
conomic
Commercptions propto increasempany to tes on the h a lower d
her hand te per trip.
ening of thny. First a
ening it is eme operatimption will increased
mption of thows the a
6.1 Total fue
length
s an increening of thg capacity rgo carryintres the ad
table belowthe fuel c
cargo, this nsumption
6.2 Fuel con
length
c feasib
cial / ecoosed mighe the cargotransport tRhine, a rdraught, ththe compa
he vessel wnd foremoexpected ting speed.increase, ship capathe Hendrabsolute in
el consumRelatiNaked
propell30323539
ase in fuee cargo hoincreases
g capacityditional ca
w the fuel consumptiois irrespec per ton is
nsumptionRelatNaked
propell
bility
onomic imht influenceo capacity the same ariver with flhe companany can tra
will have sst the fuel that the ve. Accordingeven in caacity. The rik under dcrease in f
ption of Heive speed 1d er
P
0,049 2,962 5,936 9,095
el consumpold. In cas
s with 127 ty increasesrgo carryin
consumpton per tonctive the sp
even furth
n of Hendrikive speed 1d er
P
0.75 0.74 0.73 0.72
27/57
mpacts e the logistof the vesamount of luctuating
ny is able tansport m
some impaconsumpt
essel will cg to the fin
ase a propefollowing
different refuel consu
endrik in lit10.0 km/hPropeller in
nozzle 24,526,628,830,9
ption the vese the vestons, in cass with 258 ng capacity
tion per tran decreasepeed that iher reduced
k in litre pe10.0 km/hPropeller in
nozzle 0000
W
tical operassel. On the
cargo witwater leveo operate
more cargo
acts on thetion of the
consume mndings in teller in noztable pro
elative spemption.
tre per yea
n Nake
530676823969
essel is absel is lengse the vestons and iny is 388 ton
ansported es, once ts sailed. Ind.
er ton trans
n Nake
0.610.600.580.57
WP 6: New
ation of thee one handh a lower
els, and if longer tha than befo
business vessel wil
more fuel iftask 6.3 it zzle is instavides an oeeds and
ar on RhineRelative s
ed propelle
59,7265,8972,0778,24
ble to carrygthened byssel is lengn case of ans.
ton is prehe vessel n case a n
sported Relative s
ed propelle
1.481.471.451.44
w scales an
company.d this optiodraught. Tthe vessel
an it is nowore and in
case of thl change. f it wants tis likely thalled. Thisoverview oretrofit op
e speed 14.4 er Pro
n26 98 70 43
y more cay 6 metresthened by a lengthen
sented. Asis able to
nozzle is in
speed 14.4 er Pro
n89 75 59 47
nd services
. The mainon enablesThe vessel is able to
wadays. Onncrease its
he shippingDue to theo maintain
hat the fues is a resultof the fue
ptions. The
km/h peller in
nozzle 47,56352,82758,27463,538
rgo due tos the cargo
12 metresing step of
s the tableo transportnstalled the
km/h peller in
nozzle 1.1861.1821.1801.175
s
n s l
o n s
g e n l t l
e
3748
o o s f
e t
e
6205
6.2 InAs deinvestmabout €task 6.order towill be is renewstep thoperateThe invas wellfrom ainvestm For all will notand ontime the It is asand wil Table 6 Investm(lengtheengine)InvestmrenewaInvestmpropelleTime atMaintenAddition(tons) Δ insura
6.2.1 1.
o
2. a
3 Base4 The c
addit5 Base
nput datascribed b
ment costs€ 70,400.- 2 it was ao improve renewed awed in all
he main ee the vessevestments l as the ins
a naked pment for the
three optiot change d
nce the vese vessel n
sumed thal increase
6.3 Overvie
ment costs ening and n
ment costs rul
ment costs er and nozzt yard nance costsnal ship cap
ance costs
Specific It is assumof these co
In case oavailable f
ed on expert jucosts for a newional to the inv
ed on expert ju
a and asbefore, thrs of lengthfor Loa 76
advised to the manoe
and that thoptions congine neeel in the sacosts for t
stallation cropeller toe new prop
ons it is codue to lengssel is in deeds to be
at the additthe initial i
w of data i
new
udder
le
s pacity
assumpmed that thommodities
of lengthenfor the fuel
udgement. Thew propeller arevestment cost
udgement.
sumptioree lengthhening only6m, € 133,
improve oeuvrability e investme
onsidered. eds to be ame way. Tthe new encosts. In tao a propepeller and
onsidered tgthening adry dock the at the yar
tional insuinsurance
nput
€
€
ptions he vessel ts a transpo
ning the fl consump
e price chosene only considets mentioned i
28/57
ons hening stey (so no i400.- for Lor renew tof the vesent costs aIn task 6.3changed
Total costsngine consask 6.3 it weller in noznozzle is €
hat the timas the lenghe total lerd.
rance costcosts by 1
Loa 76m€ 303,200
€ 100,000
€ 57,500
4 weeks€ 0
127
+ 10%
ransports ort price pe
fuel consution of the
n allows for reered in the optin table 6.2.
W
eps are cnstallation
Loa 82m athe ruddersel. It is as
are € 100,03 it was advas well, to
s for the nesist of bothwas also azzle. It is
€ 57,500.4
me at yard igthened pangth of the
ts are the 0%.
bulk, e.g. er ton of €
umption w main and
enewal of the etion where the
WP 6: New
consideredn of a propnd € 182,0r arrangemssumed th000 euros3
vised that o ensure eew engine h the sellindvised to c
assumed
is four weeart is pre-pe new part
same for a
Loa 82m € 366,200
€ 100,000
€ 57,500
4 weeks € 0
259
+ 10%
agricultura24, - is co
will rise. A auxiliary e
entire rudder se propeller is r
w scales an
d for Henpeller in n000.- for Lo
ment of theat the rudd3. The ruddfor each leenough poadd up to €
ng price of change the
d that the
eks. The timproduced at is irrelev
all lengthe
al productsnsidered.5
As no infoengine it is
system. replaced and t
nd services
ndrik. Thenozzle) areoa 88m. Ine vessel inder systemder systemengtheningowering to€ 232.800an engine
e propelleradditiona
me at yardat the yardant for the
ening steps
Loa 88m€ 414,800
€ 100,000
€ 57,500
4 weeks€ 0
388
+ 10%
s. For each
rmation iss assumed
the costs are
s
e e n n m m g o .
e r l
d d e
s
m0
0
0
s08
%
h
s d
WP 6: New scales and services
29/57
that the fuel consumption used only compromises the main engine. The consumption of the auxiliary engines will not change as a result of the lengthening. Therefore, to calculate the fuel increase only the fuel consumption of the main engine is considered.
3. To lengthen the vessel, the vessel needs to go in dry-dock for 4 weeks. It is
assumed that the vessel performs one round trip per week, for instance between Nurnberg and Regensburg in Germany. Therefore the vessel will miss 4 round trips and its related revenues.
4. Inland vessels are often not fully loaded. The Hendrik was compared with other
vessels sailing on the Rhine and it is assumed that the load factor of the vessel is 75%. This is more or less equal to the load factors of similar vessels. It is assumed, that also when the vessel is lengthened, the vessel will not be fully loaded. According the task 6.1 the additional cargo capacity for Loa 76 m is 127 tons, for Loa 82 m is 259 tons and for Loa 88 m is 388 tons. For the additional capacity it is assumed that 75% will be used, equalling 95, 192 and respectively 289 tons (assuming there is sufficient demand).
6.3 Results of economic assessment The economic assessment is carried out for two different relative speeds. The first table presents the results when a relative speed of 10.0 km/h is used, which is the lowest speed considered in the analysis. The upstream speed equals 5.0 km/h and the downstream speed 15.0 km/h. A distinction is made between the option of only lengthening the vessel with 6, 12 or 18 metres and the option of also changing the propeller from a naked propeller to a propeller in nozzle. Table 6.4 Outcome of economic assessment for relative speed of 10.0 km/h Loa 76m Loa 82m Loa 88m Naked
propeller Propeller in nozzle
Naked propeller
Propeller in nozzle
Naked propeller
Propeller in nozzle
NPV (x 1000) € 791 € 801 € 2,073 € 2,091 € 3,355 € 3,383IRR 23% 21% 53% 48% 93% 83%Payback time 6 years 6 years 3 years 3 years 2 years 2 years As the table shows most retrofit options are economically feasible with a maximum payback period of 5 years. Lengthening the vessel with only 6 metres has a payback period of six years. These options will not be feasible from a ship owner’s perspective and these options will probably not be chosen. According to interviews held with different ship owners their desirable payback period is between 3-4 years as a maximum. If this criterion is followed only the lengthening option of 76 m with a propeller in nozzle is not a feasible option for them. However it should be noted that one the economic climate is improving this might be a viable option as well. The same analysis was carried out for the higher relative speed of 14.4 km/h. The upstream speed in this situation is 9.4 km/h and the downstream speed equals 19.4 km/h. The results are shown in the following table.
WP 6: New scales and services
30/57
Table 6.5 Outcome of economic assessment for relative speed of 14.4 km/h Loa 76m Loa 82m Loa 88m Naked
propeller Propeller in nozzle
Naked propeller
Propeller in nozzle
Naked propeller
Propeller in nozzle
NPV (x 1000) € 760 € 835 € 2,011 € 2,093 € 3,264 € 3,356IRR 22% 22% 51% 48% 89% 82%Payback time 6 years 6 years 3 years 3 years 2 years 2 years The results of this analysis are more or less similar to the results of the analysis with a relative speed of 10.0 km/h. Also in this analysis all options are economically feasible. However ship owners will probably not use for the lengthening options of 76 metres as the payback period is beyond their desired pay back periods.
6.4 Sensitivity analyses The following tables show the outcome of the sensitivity analyses carried out for the lengthening options. All analyses are carried out for a relative speed of 10.0 km/h which is probably the speed most often used. The first analysis carried out focuses on lengthening the vessel by 6 metres and the installation of a propeller in nozzle. This option is chosen as it is the option with the longest payback period. Changes in fuel price, investment costs or transport prices might make this option a less desirable one. Each of these effects is considered separately and a worst case and best case scenario are presented. Table 6.6 Outcome of sensitivity analysis Loa 76 m and propeller in nozzle (relative speed 10.0 km/h) Investment costs Fuel price Transport price Base
case -20% +20% -10% +10% -25% +25%
NPV (x 1000)
€ 801 € 880 € 723 € 798 € 805 € 505 € 1,098
IRR 21% 26% 18% 21% 21% 16% 26%Payback time
6 years 5 years 7 years 6 years 6 years 8 years 5 years
The sensitive analysis shows that this retrofit option is most sensitive to changes in the investment costs and transport price. The option becomes less attractive once the investment costs increase by 20% or the transport prices drop by 25%. In these cases the payback period will be seven respectively eight years and ship owners indicated that the desirable payback period is 3 to 4 years. However if the investment costs decrease or the transport prices increase it become more attractive to invest in this option as the payback period is shortened to five years in both scenarios. It seems that this retrofit option is not very sensitive for changes in the fuel price as the pay back remains the same in both situations. The same sensitive analysis was done for lengthening the vessel with 6 metres, but without changing the propeller arrangement.
WP 6: New scales and services
31/57
Table 6.7 Outcome of sensitivity analysis Loa 76 m and naked propeller (relative speed 10.0 km/h) Investment costs Fuel price Transport price Base
case -20% +20% -10% +10% -25% +25%
NPV (x 1000)
€ 791 € 859 € 722 € 793 € 788 € 494 € 1,087
IRR 23% 28% 19% 23% 23% 17% 28%Payback time
6 years 5 years 7 years 6 years 6 years 8 years 5 years
According to the sensitivity analysis carried out this option is also sensitive to increases in investments costs and decrease in transport prices. The conclusions are more or less the same as for the option reviewed above. The pay back periods are the same as the ones found in the above mentioned sensitivity analysis. It seems that also this option is insensitive to changes in the fuel price.
7 En
7.1 InThe asdescribof 10.0averagdifferenupstreathe usa Table 7
Propellenaked
Propellenozzle
In the afollowin
• 6• • 8• 8
7.2 RIn the elengtheenvironon the propellethe inckilomet
nvironm
nput datasessment
bed in chap0 km/h pere speed nt fuel coam and doage of a no
7.1 Total fue Ship’slength(m)
er: 69.98 76 82 88
er: 69.98 76 82 88
analysis thng data are69.98 m: 76 m: 82 m: 88 m:
Results environme
ening + repnmental asrelative sper. As the
creased catre are pre
mental fe
a and asof the env
pter 2. In tr journey aa differennsumptionwnstream
ozzle.
el consumRe
s h
Upstrea5.0 km
34453334
he tonne ke used:
10,69411,91313,17114,419
ental assesplacementssessment peed of 10. figure sho
apacity andsented and
easibilit
sumptiovironmentahe analysiand an av
nt speed un levels. T
per relativ
ption of Heelative speam
m/h Down
15.0
392 430 469 510 320 348 376 404
ilometres p
4,000 tkm;3,600 tkm;,200 tkm;
9,200 tkm.
ssment, a t of the profor the len0 km/h. In ows all emd volumes d this table
33/57
ty
ons al performa
s a distincverage speupstream The followve speed a
endrik in kged 10.0 kmnstream 0 km/h
131143156170107116125135
per lengthe
distinctionopeller. Thngthening these cas
missions wtransporte
e shows a
W
ance is carrction is maeed of 14.and down
wing table and per len
g for operam
Total Up9.
523573625680427464501539
ening step
n is made he figure bonly option
ses the veswill increaseed. In tabledecrease i
WP 6: New
ried out fode betwee4 km/h penstream isshows th
ngthening s
ation of 100Relative
pstream 4 km/h
700772845917558619683745
p per year
between lebelow showns in casessel still use in absolue 7.2 the in emission
w scales an
llowing theen an averer journey.s used, rehe fuel costep with a
0 km on Rhe speed 14Downstrea
19.4 km/h
33442333
are consid
engtheningws the res
e the vessees its curreute numbeemissions ns.
nd services
e approachage speed. For eachesulting in
onsumptionand without
hine .4 km
am h
Total
339 1,039374 1,146409 1,254444 1,361270 827300 919331 1,014361 1,105
dered. The
g only andsults of theel operatesent ‘nakeders, due to
per tonne
s
h d h n n t
96417945
e
d e s ’
o e
Figure propell
In the nozzle.current69.98+ Figure nozzle)
As the propelleand theof the vlower ttkm. Fothe micmade b
7.1 Annualer)
second st. The figurt environm indicates
7.2 Annual)
figure shoer in nozzerefore thevessel alsothan withoor CO2 thecrograms between th
l emissions
tep of the re shows th
mental perfothe installa
l emissions
ows the enle is instal
e absolute o increaseut the retre grams peper tonne
he lengthen
s of the He
analysis the resultsormance oation of the
s of the He
nvironmenlled. The tincrease is and ther
rofitting. Foer tonne kkilometres
ning option
34/57
endrik for a
the nakedof this ana
of the vesse propeller
endrik for a
tal performtwo figuresin emissiorefore the ollowing tailometre as are calcns with and
W
an average
propeller alysis. Forsel is presin nozzle.
an average
mance of ts only showns. Howevrelative va
able showsre presentulated. Als
d without a
WP 6: New
speed of 1
is replacer a good cosented (i.e
speed of 1
the vessel w the totaver the caralues (kg es the chanted, for all so in this t propeller
w scales an
10,0 km (na
ed for a pomparabili
e. 69.98). T
10,0 km (pr
will improl emissionrgo carryinemission/tknge in emi
the other table a disrearrangem
nd services
aked
propeller inty also theThe option
ropeller in
ove once as per year
ng capacitykm) can bessions peremissions
stinction isment.
s
n e n
a r y e r s s
Table 7
Propellenaked
Propellenozzle
Althougpositiveonce mthe emcargo itimes atranspo
7.3 SIn the sthe firsin the f Figure propell
The enlevels ipropelleperformlength
7.2 EmissioShlen
er: 69768288
er: 69768288
gh the eme environm
more cargomissions wis transporas the enviorted.
Sensitivitsensitivity at step onlyigure below
7.3 Annualer)
nvironmentincrease oer in noz
mance of thand the fir
ons in g/tkmhip’s ngth (m)
9.98 6 2 8 9.98 6 2 8
mission levmental impo is transpowill decreas
rted. Thereironmental
ty analysanalysis th
y the lengthw.
l emissions
al performonce the vzzle is cohe vessel rst lengthen
m and mg/tCO2 (g/tkm)
7.47.37.27.26.15.95.85.7
els are incpact as theorted. The se consideefore it wo performan
sis he relative hening of t
s of the He
ance of thessel is lensidered. improves oning steps
35/57
tkm for relaNOx (mg/tkm
4 107.923 106.272 104.792 104.141 88.109 86.008 84.057 82.49
creasing ine emission
installatioerably andould be wnce will inc
speed is inthe vessel
endrik for a
e vessel hengthened.
As the fionce the nthe absolu
W
ative speed
m) PM (mg/tk
25 4.972 4.898 4.841 4.702 4.006 3.953 3.896 3.7
n absolutes per tonnn of a propd can be ise to instcrease, eve
ncreased fis conside
an average
has decrea. In the seigure belonew propeute emissio
WP 6: New
d of 10.0 km
km) HC (mg/t
965 11888 11821 11790 11053 9956 9866 9795 9
e numbersne kilometrpeller in nofurther de
tall a propen when n
from 10.0 kered. The r
speed of 1
sed and thecond stepow shows,ller is instaon levels a
w scales an
m/h
km) CO (mg/
.966 44
.782 4
.619 4
.546 4
.768 3
.535 3
.319 34
.146 34
s, lengthenre are all dozzle is beecreased oeller in no
no addition
km/h to 14results are
14,4 km (na
he absolutep the instal, the envalled. For tare below t
nd services
/tkm) SO(mg
4.578 03.895 03.286 03.015 06.390 05.524 04.178 04.074 0
ning has adecreasingeneficial asonce moreozzle at alal cargo is
.4 km/h. Inpresented
aked
e emissionllation of a
vironmentathe currentthe current
s
2 g/tkm) 0.04690.04620.04560.04530.03830.03740.03650.0359
a g s e l
s
n d
n a l t t
emissiowill incr Figure nozzle)
The thiThe res Table 7
Propellenaked
Propellenozzle
When tto the eCO2 arthe veseffect okilometinstalla
on levels. rease, how
7.4 Annual)
ird step in sults are p
7.3 EmissioShipleng
er: 69.976 82 88
er: 69.976 82 88
the relativeemission lere almost tssel transpon the envitre will be
ation of a p
If the vesswever the le
l emissions
the sensitresented in
ons in g/tkmp’s gth (m)
CO(g
98
98
e speed inevels whentwo times
ports more ironmentalreduced eropeller in
sel is lengtevels are b
s of the He
tivity analyn the table
m and mg/tO2
g/tkm) (14.814.714.514.411.811.711.711.7
ncreases, tn sailing was high. Tcargo. Th
l performanven more.nozzle is b
36/57
thened by below the l
endrik for a
ysis is to ce below.
tkm for relaNOx (mg/tkm)
214.512212.459210.173208.424170.827170.318169.938169.254
the level owith a relativThe enviroe installatince of the Also whebeneficial f
W
18 metreslevels of th
an average
calculate th
ative speedPM (mg/tkm)
9.869.779.669.587.857.837.817.78
of emissionve speed onmental pon of a provessel andn sailing wfrom an en
WP 6: New
s the absohe lengthen
speed of 1
he emissio
d of 14.4 km
) HC (mg/tkm
8 23.73 23.58 23.37 23.18 18.95 18.87 18.86 18.7
n increasesof 10.0 kmerformancopeller in nd the emiswith a highenvironment
w scales an
olute emissning only o
14,4 km (pr
on per ton
m/h
m) CO (mg/tk
783 88555 87302 86108 86939 70883 70841 70765 69
s as well. m/h emissioce is increanozzle hassion levelser relative tal point of
nd services
sion levelsoptions.
ropeller in
kilometre
km) SO2
(mg8.603 07.755 06.810 06.088 00.559 00.349 00.192 09.909 0
Comparedon levels ofasing onces a positives per tonne
speed theview.
s
s
.
2 g/tkm) 0.09330.09240.09140.09060.07430.07410.07390.0736
d f e e e e
Part
37/57
t B: Rhe
W
einland
WP 6: Neww scales annd servicess
8 DeThe RLankewthe ves It seemConsormetresthe stahence provide Table 8 Length Beam DraughtDisplaceMain enSource: w Figure
Source: w
8.1 OAs the assumpassessConstaround t It is asupstreaaccounapprox
escriptiheinland (werft, locatssel has on
ms that thrtium when. For rese
arting poin57.50 met
es the origi
8.1 Main ch
t ement
ngine www.binnenva
8.1 Impres
www.binnenva
Operation actual opptions hav
sment. It isanta, Romatrip has a le
ssumed tham, will tant in theseximately 24
on of th(currently ted in Berlne cargo ho
e vessel in this leng
earch purpot of the letres. The inal measu
haracteristi
aart.eu.
ssion of the
aart.eu.
nal profilperating prve been ms assumedania. A onength of 2,
at the tripake 14 daye figures a4 days and
he shipnamed Nain-Splandaold, which
is already gthening toses the lengtheningvessel can
urements o
cs of the R
e Rheinland
le rofile of thmade whicd that the e way trip ,000 km.
downstreys. The d
as well. Thd on avera
39/57
apoleon) wau. The lenis covered
lengthenetook placeengthening
g assignmen be qualifof the vess
Rheinland ( 576.32.453De
d
he vessel ch are usevessel opehas a len
eam takes ays in poherefore itage 15 rou
W
was built ngth of thed with a ha
ed once; h. Current g is not coent is the fied as a el.
1959)
7.50 m 35 m 43 m
37 ton eutz 375 hp
is unknowed in the erates betgth of app
10 days ort and wat is assumund trips p
WP 6: New
in 1959 ae vessel waatch cover.
however itlength of
onsidered original le
CEMT II s
TAMD 163
wn to the economic
tween Budproximately
on averagaiting for cmed that a
er year ar
w scales an
at the Geras 57.50 m
t is unknothe vessein the ana
ength of tship. Follo
3 C
Consortiumc and envdapest, Huy 1,000 km
e, while thcargo are round trip
re performe
nd services
rman yardmetres and
own to theel is 63.44alyses andhe vesselwing table
m, severaironmenta
ungary andm and so a
he journeytaken intop will takeed. As the
s
d d
e 4 d ,
e
l l
d a
y o e e
WP 6: New scales and services
40/57
vessel is sailing on long distances it is assumed that the vessel will wait for cargo instead of sailing empty. Therefore it is assumed that the vessel will carry cargo on all its 30 single trips. However the vessel will not be fully loaded.
9 CoThis chsevera6.2 ascarryingonce th
9.1 SIn task analysi(63.44 lengthe The folFor eac Table 9 Max draTotal caAdditionRelativeSource: M For eacoverall Table 9 LengtheCosts pCosts pTotal coSource: M
9.2 MManoethe mamanoe
1. 2. S3. 4.
The anthe origmetres
onsiderhapter presl lengtheni
ssessed thg out sevehe vessel is
Ship struc6.1 the le
s is the ormetres). T
ening steps
llowing tabch new opt
9.1 Max. dra
aught argo in holdnal cargo ine change caMove-it WP 6,
ch of the ocosts per
9.2 Summa
ening step Δper meter ofper meter ofost per m Move-it WP 6,
Manoeuvruvrability aain focus uvrability fCombinedStandard zEvasive mCrash stop
nalysis wasginal length and 69.50
red shipsents the ing steps whe manoeeral manoes lengthen
cture engtheningriginal lengThe lengths is 6.0 me
ble shows tion also th
aught and
s holds
argo holds task 6.1 final
options a dlengthenin
ry of costs
ΔL f the new sef the new se
task 6.1 final
rability and the imof task 6
four differe turning cirzigzag man
manoeuvresp manoeuv
s carried oh of 57.50 0 metres. A
p modifioutcomes were consuvrability euvrability ed taking i
g option of gth of the vhening steetres and in
the maximhe addition
additional (m) (t) (t) (%)
report.
detailed cong step and
s per length
ection (steeection (dry d
report.
mpact of le6.2. To esent tests arrcle / pull-onoeuvres;s; and vres.
out for thremetres. ThAll tests ar
41/57
icationsof tasks 6
sidered andof the vetests. Tas
into accou
the Rheinvessel (57
eps proposn total 2 le
mum draft nal cargo c
cargo for dLoa 57
st estimated the costs
hening met
l) dock per we
engtheningstablish the conducteout manoe
e differenthe tests were carried o
W
s 6.1 to 6.3 d for each essel undesk 6.3 assent different
nland was .50 metres
sed complyngthening
and the toapacity is
different le7.50m2.429537,8
--
e is made.s per metre
ter for MV ’ (m)(€/m
eek) (€/m(€/m
of the vehe effect oed: uvres;
t lengths oere also doout for diff
WP 6: New
for the Rhof the ste
er differenessed the t water dep
analysed. s) instead y with cursteps were
otal cargo presented
engtheningLoa 63.50
2.461
71
The followe.
’RheinlandLoa 63
) ) )
ssel on thof lengthe
f the vesseone for a sferent wate
w scales an
heinland. Ieps considnt circums
power reqpths and c
Starting pof the curr
rrent BV rue consider
capacity p.
steps 0 m L429 5.6
77.8 4.5
wing table
d’ 3.50 m L
6.0 5.000
800 5.800
he manoeuening on a
el. The firsship’s lengter levels, to
nd services
n task 6.1ered tasks
stances byquirementsurrents.
point of therent lengthules. Eachred.
per option
oa 69.50 m2.420
694156.2
29.0
shows the
oa 69.50 m12.0
5.000400
5.400
uvrability isa vessel’s
st length isth of 63.50o establish
s
1 s y s
e h h
.
m0420
e
m0000
s s
s 0 h
WP 6: New scales and services
42/57
the effects in deep water as well as shallow water. The depths considered were 3.5 m, 5 m, and 20 m. Also different speed levels were considered and each test was carried out for a speed of 10 km/h and 13 km/h. The lengthening of the vessel has no significant impact on the turning ability and directional stability of the vessel (the combined turning circle and pull-out manoeuvres). In shallow water the turning ability of the vessel is impaired, but to improve the turning ability the vessel could decrease it approach speed. No further improvements are needed. The same conclusions are drawn for the yaw checking ability and the initial turning ability (zigzag manoeuvres). Also the lengthening of Rheinland has no influence on the evasive manoeuvring ability (evasive manoeuvres) and the stopping ability (crash stop manoeuvres) of the vessel and no action is needed.
9.3 Powering In task 6.3 the influence of lengthening the vessel on the powering arrangement is analysed. The Rheinland is a single-propelled vessel, with a Deutz 375 hp TAMD 163 C engine. The vessel also has one propeller with a propeller diameter of 1.0 metres. The propeller has no nozzle. It is estimated that the maximum speed of the vessel is 17.8 km/h, however the vessel hardly ever sails at maximum speed. In the analysis not only the effect of the lengthening on the required power is analysed, but also the water depth is considered. The lengthening itself does not significantly influence the power needed to achieve a certain speed. Therefore the same power train (engine, gearbox and propeller) was considered for all lengthening steps. It should be noted that the power train is renewed in the analysis, but the technical specifications remain more or less the same. Speed reductions of 1 to 2 km/h as result of the lengthening might occur in case the water depth changes. In shallow water (from deep to h= 5 m and then from 5 m to 3.5 m) the speed reduction of Rheinland is around 2 km/h. In very shallow water the maximum speed is even further reduced. The maximum allowed speed 10 km/h for h=3.5 m. The installation of a propeller with nozzle will improve the propulsive efficiency compared to the usage of a naked propeller. The expected improvement is 10% which increases the max. speed up to 1 km/h.
10 Ec
10.1 CLengthcompalengthethe samabsolutThe foldifferen Table 1year) Ship’s (m) 57 63 69 Besidethe lencapacitcargo c These increascompaoperatesail witthe othrevenu
10.2 InFor Rlengthetask 6.changeTotal cengine tasks 6propelleare € 5
6 The c
addit
conomic
Commercening of thny. First a
ening it is eme operatte fuel conlowing tab
nt relative s
0.1 Total fu
length
s an increngthening. ty increasecarrying ca
options mse the carny to tranes on the Dh a lower d
her hand te.
nput dataheinland ening only 3 it was a
ed as well,osts for thconsist of
6.3 it waser in nozz
57,500.6
costs for a newional to the inv
c feasib
cial / ecohe vessel wnd foremoexpected ttional levensumption ble providesspeeds an
uel consum
RelatNaked
propell414448
ase in fueIn case
es with 77.apacity incr
might influego capacit
nsport the Danube, a draught, ththe compa
a and astwo lengtare about
advised th, to ensuree new engf both the s also advle. It is as
w propeller arevestment cost
bility
onomic imwill have sst the fuel that the ve
el. Accordinwill increas an overvd retrofit o
mption of R
ive speed d ler
P
1,943 4,651 8,125
el consumpthe vesse8 tons andreases with
ence the loty of the vsame amriver with
he companany can tra
sumptiothening stt € 34,800at for eace enough gine add uselling pric
vised to chssumed tha
e only considets mentioned i
43/57
mpacts some impa
consumptessel will cng to the
ase, even iview of the ptions.
Rheinland i
10.8 km/hPropeller in
nozzle 36,39,441,
ption the veel is lengthd in case thh 156.2 ton
ogistical opvessel. On
mount of cfluctuating
ny is able tansport m
ons teps are for Loa 6
ch lengthenpowering p to € 232ce of an enhange theat the add
ered in the optin table 10.2.
W
acts on thetion of the
consume mfindings in
in case a fuel consu
in litre per
n Nake
397481937
essel is abhened by he vessel ins.
peration ofn the one cargo with g water levo operate
more cargo
considere63.5 m, anning step to operate
2.800. The ngine as w propeller itional inve
tion where the
WP 6: New
business vessel wil
more fuel ifn task 6.3propeller i
umption of
year on Da
Relative sed propelle
95,12108,11120,69
ble to carry6 metres
is lengthen
f the comphand thisa lower d
vels, and if longer tha than befo
d. The ind € 64,800the main
e the vessinvestmen
well as the from a n
estments f
e propeller is r
w scales an
case of thl change. f it wants t3 it is likeln nozzle isthe Rhein
anube (litre
speed 14.8 er Pro
n28 19 91
y more ca the carg
ned by 12
pany. Mains option endraught. Tthe vesse
an it is nowore and in
nvestment 0 for Loa engine ne
sel in the snts costs foinstallatio
naked propfor the new
replaced and t
nd services
he shippingDue to theo maintainly that thes installedland under
es per
km/h peller in
nozzle 81,70992,184
101,403
rgo due too carryingmetres the
n aim is tonables theThe vesseel is able towadays. Onncrease its
costs of69.5 m. In
eeds to besame wayor the newn costs. Inpeller to aw propeller
the costs are
s
g e n e . r
943
o g e
o e l
o n s
f n e .
w n a r
WP 6: New scales and services
44/57
For both options it is considered that the time at yard is four weeks. The time at yard will not change due to lengthening as the lengthened part is pre-produced at the yard and once the vessel is in dry dock the total length of the new part is irrelevant for the time the vessel needs to be at the yard. It is assumed that the additional insurance costs are the same for all lengthening steps and will increase the initial insurance costs by 10%. Table 10.2 Overview of input data Loa 63.5 m Loa 69.5 m Investment costs € 267,600 € 297,600 Time at yard 4 weeks 4 weeks Maintenance costs € 0 € 0 Additional ship capacity (ton) 78 156 Δ insurance costs + 10% +10%
10.2.1 Specific assumptions 1. It is assumed that the vessel transports bulk, e.g. agricultural products. For each
of these commodities a transport price per ton of € 17 is considered7.
2. In case of lengthening the fuel consumption will rise. As no information is available for the fuel consumption of the main and auxiliary engine it is assumed that the fuel consumption used only compromises the main engine. The consumption of the auxiliary engines will not change as a result of the lengthening. Therefore, to calculate the fuel increase only the fuel consumption of the main engine is considered.
3. To lengthen the vessel, the vessel needs to go in dry-dock for 4 weeks. It is
assumed that the vessel sails between Budapest and Constanta. If the vessel needs to go in dry dock the vessel will miss one round.
4. Inland vessels are often not fully loaded. The Rheinland is compared other
vessels sailing on the Danube and it is assumed that the load factor of the vessel is 75%. This is more or less equal to the load factors of similar vessels. It is assumed, that also when the vessel is lengthened, the vessel will not be fully loaded. According the task 6.1 the additional cargo capacity for Loa 63.5 m is 78 tons and for Loa 69.5 m is 156 tons. For the additional capacity it is assumed that 75% will be used, equalling 59 respectively 118 tons (assuming there is sufficient demand).
10.3 Results of economic assessment The economic assessment is carried out for two different relative speeds. The first table presents the results when a relative speed of 10.8 km/h is used. The upstream speed equals 6.8 km/h and the downstream speed 14.8 km/h. A distinction is made between
7 Based on expert judgement.
WP 6: New scales and services
45/57
the option of only lengthening the vessel with 6 or 12 metres and the option of also changing the propeller from a naked propeller to a propeller in nozzle. Table 10.3 Outcome of economic assessment for relative speed of 10.8 km/h Loa 63.5 m Loa 69.5 m Naked
propeller Propeller in nozzle
Naked propeller
Propeller in nozzle
NPV (x 1000) € 70 € 71 € 298 € 385 IRR 9% 8% 20% 18% Payback time 15 years 16 years 6 years 7 years As the table shows especially the lengthening of the vessel with 12 metres is a feasible option. It should be noted that according to ship owners interviewed even a payback period of 6 or 7 years is too long, however if the economic situation improves it might become an attractive option. To lengthen the vessel by only six metres is not economically feasible as the payback period is 15 respectively 16 years. The calculations show that the options with a naked propeller are earned back earlier then the options with a propeller in nozzle. These options have higher investment costs, as the nozzle needs to be installed, and the maintenance and insurance costs are higher as well. The amount of additional cargo does not compensate for this increase in costs and therefore it takes longer to earn back the initial investment. The same analysis was also carried for a relative speed of 14.8 km/h. The upstream speed considered is 10.8 km/h and the downstream speed is 18.8 km/h. Also for this analysis both the lengthening only option and the option lengthening + propeller in nozzle are considered. Table 10.4 Outcome of economic assessment for relative speed of 14.8 km/h
Loa 63.5 m Loa 69.5 m Naked
propeller Propeller in nozzle
Naked propeller
Propeller in nozzle
NPV (x 1000) € -27 € 75 € 190 € 325 IRR 4% 9% 13% 16% Payback time > 26 years 16 years 10 years 8 years When the vessel sails with a relative speed of 14.8 km/h some options are feasible. Lengthening the vessel with 12 metres and installation of a propeller in nozzle is the most feasible option. The options where the vessel is lengthened with only 6 metres the payback period is not feasible. This is due to the increased fuel consumption. Sailing at a higher speed increases the fuel consumption of the vessel considerably and the additional cargo capacity does not compensate for the fuel increase. However the installation of a propeller in nozzle is beneficial as the payback period has decreased to 16 years.
10.4 Sensitivity analysis The following tables show the outcome of the sensitivity analyses carried out for the lengthening options. All analyses are carried out for a relative speed of 10.8 km/h which is probably the speed most often used. The first analysis carried out focuses on
WP 6: New scales and services
46/57
lengthened the vessel with 6 metres and the current propeller arrangement. This option is chosen as it is the option with a longer payback period than desired by the ship owner, however with the potential to become an attractive option. Changes in fuel price, investment costs or transport prices might make this option a less desirable one. Each of these effects is considered separately and a worst case and best case scenario are presented. Table 10.5 Outcome of sensitivity analysis Loa 63.5 m and naked propeller (relative speed 10.8 km/h) Investment costs Fuel price Transport price Base
case -20% +20% -10% +10% -25% +25%
NPV (x 1000)
€ 70 € 116 € 25 € 73 € 69 € -17 € 158
IRR 9% 12% 6% 9% 9% 5% 12%Payback time
15 years 11 years 21 years 15 years 15 years >26 years 11 years
As the analysis shows this lengthening option is most sensitive to changes in the investment costs and in changes in transport prices. In case the investment costs decrease or the transport prices increases the payback period is shortened from 15 to 11 years. However if the investment costs increase or the transport prices decrease the payback period becomes longer. In case the transport prices drop the ship owner is no longer able to earn back his initial investment. In the second sensitivity analysis the lengthening option of 6 metres and installation of a propeller on nozzle is considered. Also in this analysis a change in investment costs, fuel prices and transport prices were taken into account. Table 10.6 Outcome of sensitivity analysis Loa 63.5 m and propeller in nozzle (relative speed 10.8 km/h)
Investment costs Fuel price Transport price Base
case -20% +20% -10% +10% -25% +25%
NPV (x 1000)
€ 71 € 126 € 15 € 68 € 73 € -16 € 158
IRR 8% 11% 6% 8% 8% 5% 11%Payback time
16 years 12 years 22 years 16 years 16 years >26 years 12 years
In this sensitivity analysis the conclusions are the same as for the previous analysis. It can be concluded that the effect of installation of a propeller in nozzle is not much influenced by changes in fuel prices at the shortest lengthening step.
11 En
11.1 InThe asdescribof 10.8averagdifferendownsta nozzconsum Table 1
Propellenaked
Propellenozzle
In the adata ar
• 5• 6• 6
11.2 RIn the lengtheenvironon the ‘naked’
nvironm
nput datasessment
bed in chap8 km/h pere speed ant fuel contream per zle. It shomption.
1.1 Total fu
Ship’slength(m)
er: 57 63 69
er: 57 63 69
analysis thre used: 57 m: 63 m: 69 m:
Results environme
ening + repnmental as
relative s’ propeller.
mental fe
a and asof the env
pter 2. In tr journey aa differentnsumption.average s
ould be no
uel consumRe
s h
Upstrea6.8 km/
2,02,12,21,71,82,0
e tonne kil
16,13418,46820,820
ental assesplacementssessment speed of 1. As the fig
easibilit
sumptiovironmentahe analysiand an avt speed up Followingpeed and oted that t
mption of Relative speam h
Down14.8 k
000 147 294 735 882 000
lometres p
4,000 tkm;8,000 tkm;0,000 tkm.
ssment a t of the profor only th
10.8 km/h ure shows
47/57
ty
ons al performa
s a distincverage spepstream a
g table shoper lengththe table
Rheinland ied 10.8 km
nstream km/h
919960
1,055797865919
per lengthe
distinction opeller. Thhe lengtheand in th
s all emissi
W
ance is carrction is maeed of 14.and downsows the fuening steppresents
in kg for opm
Total Up10.
2,9193,1073,3492,5322,7472,919
ening steps
is made he figure bning optionis case thons will inc
WP 6: New
ried out fode betwee8 km/h pe
stream is uel consump with and the absolu
peration ofRelative
pstream .8 km/h
D1
4,2044,7785,3333,6114,0744,481
s are consi
between lebelow showns in casehe vessel crease.
w scales an
llowing theen an averer journey.used, resu
mption upswithout theute increa
f 1000 km oe speed 14Downstrea18.8 km/h
2,42,73,02,02,32,5
idered. The
engtheningws the res the vessestill uses
nd services
e approachage speed. For eachulting in atream ande usage of
ase in fue
on Danube.8 km m Total
415 6,619745 7,523064 8,397074 5,685340 6,414574 7,055
e following
g only andsults of theel operatesits current
s
h d h a d f l
937545
g
d e s t
Figure propell
In Figuconsidebetweenozzle in casebelow cto the cvessel Figure in nozz
It shouthe absalso incretrofitt
11.1 Annuaer)
ure 11.2 tered. Alsoen sailing w
to the proe the vesscurrent levcurrent levis lengthen
11.2 Annuazle)
ld be notesolute incrcreases anting. Follow
al emission
the lengtho the currwith and wopeller withel is lengt
vel. If the vevels, howened but no
al emission
d that the rease in emnd the relawing table
ns of the R
hening optrent situatwithout a phout lengthhened to 6essel is len
ever they wo rearrange
ns of the R
figures onmissions. Hative value
show the
48/57
Rheinland f
tions incluion is add
propeller inhening the 63 m and ngthened twill be loweement in th
Rheinland f
nly show thHowever t
es (kg emischange in
W
or an avera
ding a neded to th
n nozzle. Tvessel wia nozzle i
to 69 m theer than the
he propelle
or an avera
he total emhe cargo cssion/tkm) n emission
WP 6: New
age speed
ew propelle figure,
The figure ll decreaseis added te emissione emission
er system is
age speed
missions pecarrying cacan be low
ns per tkm
w scales an
of 10,8 km
er arrangethis for cshows thae all emisshe emissio
ns level willns levels ins made.
of 10,8 km
er year andapacity of wer than w. Also in th
nd services
m (naked
ement arecomparisonat adding asions. Alsoons will bel be similarn case the
m (propeller
d thereforethe vesse
without thehis table a
s
e n a o e r e
r
e l
e a
distinctrearran Table 1
Propellenaked
Propellenozzle
In all caThe em
11.3 SIn the scarriedThe firlengtheemissio Figure propell
Figure Also in a goodincreasmaximuincreas
tion is mangement.
1.2 EmissiShilen
er: 57 63 69
er: 57 63 69
ases the emissions ar
Sensitivitsensitivity out as warst figure ened and on levels w
11.3 Annuaer)
11.4 showthis figure
d comparisses once tum 63 m. se, howeve
ade betwe
ions in g/tkip’s
ngth (m)
emissions lre even fur
ty analysanalysis th
as for the eshows ththe same
will increase
al emission
ws the lene the curreson. As thethe propeIn case th
er the incre
een the le
km and mgCO2 (g/tkm)
8.68.07.77.57.16.7
evels in g/rther reduc
sis he higher renvironmee outcom
e propellere once the
ns of the R
ngthened oent situatione figure shller in noze vessel is
ease is sm
49/57
engthening
g/tkm for reNOx (mg/tkm)
124.818116.083110.979108.311102.641
96.710
/tkm or mgced once a
relative spental assese for the r arrangeme vessel is
Rheinland f
options incn (length o
hows the ezzle is inss lengthenealler than l
W
g options
elative speePM (mg/tkm
8 5.743 5.349 5.101 4.981 4.720 4.44
g/tkm reducpropeller
eed is conssment for
situation ment is uslengthened
or an avera
cluding theof 57m andenvironmenstalled anded to 69 mlengthenin
WP 6: New
with and
ed of 10.8 k
m) HC (mg/tk
42 13.40 12.05 12.82 12.21 11.49 10.
ce as the vin nozzle is
nsidered. Ta relative in which
sed. As thd.
age speed
e new prod naked prntal perford the vessm the envirg without a
w scales an
without a
km/h
km) CO (mg/t
838 51870 47304 45008 44380 42722 39
vessel is les installed.
The same speed of the vess
he figure s
of 14,4 km
opeller arrropeller) is mance of sel is lengronmental a propeller
nd services
a propeller
tkm) SO2
(mg1.555 07.947 05.839 04.737 02.395 09.945 0
engthened.
analysis is14.4 km/h
sel is onlyshows the
m (naked
angementshown forthe vesse
gthened toimpact wil
r in nozzle.
s
r
2 g/tkm) 0.05430.05050.04830.04710.04460.0420
.
s . y e
. r l
o l
Figure in nozz
Also focalcula Table 1
Propellenaked
Propellenozzle
At this all casepropellethe instthat sa
11.4 Annuazle)
or sailing ated. Follow
1.3 EmissiShlen
er: 57 63 69
er: 57 63 69
higher spees the emier in nozztallation ofiling on a h
al emission
on this hiwing table
ions in g/tkip’s
ngth (m)
eed the emissions per
zle is instaf a nozzle higher spee
ns of the R
igher relatshows the
km and mgCO2
(g/tkm)19.519.419.216.816.516.1
missions ter g/tkm or lled the peis beneficied increas
50/57
Rheinland f
tive speed outcomes
g/tkm for reNOx
(mg/tkm283.087281.084278.323243.154239.658233.843
end to redumg/tkm de
erformanceal for the e
ses the env
W
or an avera
d the perfos of this an
elative speex)
P(mg/tkm
7 13.024 12.933 12.804 11.188 11.023 10.75
uce less thaecrease one of the veenvironmevironmenta
WP 6: New
age speed
ormance palysis.
ed of 14.8 kPMm) (mg/tk22 31.30 31.03 30.85 26.24 26.57 25.
an sailing nce the veessel furthnt. Overall
al impact of
w scales an
of 14,8 km
per ton ki
km/h HC
km) (mg/386 116164 116857 114958 100571 98926 96
on a lowerssel length
her increasl it can be f shipping.
nd services
m (propeller
lometre is
CO/tkm) (m6.927 06.100 04.959 00.433 08.989 06.587 0
r speed. Inhened. If ases and soconcluded
s
r
s
SO2
g/tkm)0.12310.12220.12100.10570.10420.1017
n a o d
12 Co
12.1 T•
e
a•
v• A
•
• a
• Tw
12.2 M• •
va
• Aa
• tc
• ete
12.3 OLengthvesselsof this line witalreadyfeasiblenot be
onclusio
The main Lengtheninevaluated retrofit opadjustmenLengtheninvessel. SpAlthough tis advised Lengtheninpropeller inLengtheninas the admain beneThe lengthwell as its performanperforman
Main concLengtheninLengtheninvessel. In approach sAlthough tadvised toin nozzle; Lengtheninthe vesselconditions It should aenough incthe Rhine earn back.
Overall coening of ss in the fleeretrofit optth the resy need to he. If a vess
e an optio
ons
conclusng of the vlengths w
ption, becnts becomeng will not
peed reduche currentto change
ng of this n nozzle, ang becomeditional ca
efit for the shening of t
cargo carce of the ce can be
clusionsng of the vng of the
some casspeed; the curren
o change th
ng of the l with onlythe invest
also be nocome to eaare consi
.
onclusiosmaller inlet. It appeaion, while
sults of thehave a critsel is too s
on to mak
sions forvessel is t
within the cause at e technicalt have a c
ctions will st power trae the engin
vessel isand under des more eargo carryiship ownerhe vessel rrying capavessel in improved
s for Rhevessel is tevessel wilses the m
t power trhe current
vessel is y 6 metrestment will noted that farn back thidered for
ons land vessears that vesmaller she lengthenical mass small, as iske the ves
51/57
r Hendrikechnically boundarieslarger le
ly very comconsiderabsolve manoin is suitabe and prop
s economidifferent re
economicaing capacir; will increa
acity and toa positivefurther.
einland:chnically fel have no
manoeuvra
rain is suffengine fo
often econs will have not be earnfreight ratehe investmthe Rhein
els is ecoessels that hips do notning optionto ensure s the casessel more
W
k: possible,
s of the Cengtheningmplicated, ble effect oeuvrabilityble for all lepeller to encally feas
elative spelly feasibleity (revenu
se the fueogether th
e way. In c
easible; influence
bility can
ficient to pr a newer
nomicallylong payb
ned back aes paid onment. Evennland, the
onomically fall within . Based onns analysethat the le for the Rh competiti
WP 6: New
although nCEMT clasg options hence expon the may issues; engtheningnsure betteible, both eds; e for largeue genera
l consumpis will affecase a no
on the mabe improv
perform in one and t
feasible, hback perioat all. n the Danu when the investmen
feasible mthe CEMT
n the analyed in WP ngthening heinland, leive. The
w scales an
not all conss are suit
the hull pensive tooanoeuvrab
g steps coner efficienc
with and
er lengthenting capac
ption of thect the envzzle is ins
anoeuvrabved by red
the samehe install a
however leod and und
ube do nofreight rat
nts will be
mainly for T III class cysis done a
7.2, inlanwill be eco
engtheninginvestmen
nd services
nsidered ortable as a
structureo; bility of the
nsidered, ity; without a
ning stepscity) is the
e vessel asironmenta
stalled, the
bility of theducing the
e way, it isa propeller
engtheningder certain
t generatetes paid on
difficult to
mid-sizedcan benefitand also innd vesselsonomicallyg will oftent costs of
s
r a e
e
t
a
, e
s l
e
e e
s r
g n
e n o
d t n s y n f
WP 6: New scales and services
52/57
lengthening cannot be compensated. It can also be concluded that a small vessel like Rhineland is wrongly utilized on large/long river as is the Danube. From an environmental perspective it is desirable to install a propeller in nozzle instead of a naked propeller. The propeller in nozzle is able to reduce the fuel consumption and therefore the amount of all emissions. To have more benefit from the propeller in nozzle the vessel should also reduce its speed. In these cases the implementation of the nozzle works best.
13 Bi
13.1 B•
•
• S2
• S2
•
2•
•
•
T•
o•
2•
V
• S• V
s
13.2 W• • • •
bliogra
Books anEcofys, EPerceel 3 Ecofys, 31Ecorys, CEindrappoMoveIT!, MSystem In2013-10-2MoVe-IT, System In2013; MoveIT!, MNew scale2013; MoveIT!, MNew scaleMoveIT!, MNew scaleMoVe IT!, Literature Transport MoVe IT!, of the art, NEA, PlanPerspectiv2011; PLANCO, VerkehrstrConsultingSeitz M., MVan Beelesector, 201
Websiteshttp://wwwhttp://wwwhttp://wwwhttp://www
aphy and
nd articlecorys, Ma(cluster 4 juli 2013; E Delft, Ert perceel
Modernisatntegration 2; Modernisantegration
Modernisates and ser
Modernisates and servModernisates and serv
Modernisaon retrofitSystems; Modernisa
Deliverablenco, via donves of IWT
VerkerägerStraßg GmbH anManual on en, Structu11.
w.binnenvaw.binnenvaw.cbrb.nl/; w.interrijn.n
d refere
es arin, TU D), Deelrap
ICB, TU D3 (cluster 4tion of Ves& Assessm
ation of Ve& Assess
tion of Vesrvices, D 6
tion of Vesvices, D 6.2tion of Vesvices, D 6.3ation of Vetting, DST
ation of Vee 1.1, 14 Dnau, CE D
T in the Eur
ehrswirtschße, Schiennd BundesDanube N
uring and M
art.nl; art.eu;
l/.
53/57
ences
Delft, EICBport 2: Inv
Delft, Marin4), juli 201ssels for Inment, D 7
ssels for Isment, D
ssels for In6.1: Ship s
ssels for In2: Manoeussels for In3: Powerin
essels for In - Develo
essels for December elft and Mropean Un
aftlicher ne und WanstaltfürG
Navigation, Modelling d
W
B and CEventarisatie
n and Eco3; nland wate.1: System
nland wate7.3: Envir
nland watestructure,
nland wateuvrability, Mnland wateng, Universnland watepment Ce
Inland wat2012; DS Transm
nion, Final
und WasserstraßGewässerkvia donau
decision m
WP 6: New
E Delft, Se en categ
ofys, IDVV
erway freigm Integrati
erway freigronmental
erway freigCMT and
erway freigMarin, 2013erway freigsity of Belgerway freigntre for S
terway fre
modal, Medreport, Zoe
ökologiscße, Schlukunde, Nov, Vienna, J
making in t
w scales an
Schone Bigoriseringte
– Schone
ght Transpon, TU De
ght Transpimpact, v
ght TranspUniversity
ght Transp3; ght Transpgrade, 2013ght Transpohip Techn
ight Trans
dium and Letermeer,
cherVergleissbericht,
vember 20January 20the inland
nd services
nnenvaartechnieken,
e schepen
port, WP 7elft (DUT)
port, WP 7via Donau,
port, WP 6y of Galati
port, WP 6
port, WP 63; ort, WP 1 -
nology and
port, State
Long TermDecember
ich derPLANCO
07; 007; navigation
s
, ,
,
: ,
: ,
: ,
:
:
- d
e
m r
r O
n
14 Ind
14.1 InFigure Figure (nakedFigure (propelFigure (nakedFigure (propelFigure Figure (nakedFigure (propelFigure (nakedFigure (propel
14.2 InTable 2Table 3Table 3Table 4Table 5Table 5Table 6Table 6Table 6Table 6Table 6Table 6speed Table 610.0 kmTable 7Table 7Table 7Table 8Table 9Table 9Table 1year) ..Table 1Table 1
dexes
ndex of f4.1 Impres7.1 Annu propeller)7.2 Annuler in nozz7.3 Annu propeller)7.4 Annuler in nozz8.1 Impres11.1 Annu propeller)11.2 Annuler in nozz11.3 Annu propeller)11.4 Annuler in nozz
ndex of t2.1 Averag3.1 Presen3.2 Emissio4.1 Main ch5.1 Max. dr5.2 Summa6.1 Total fu6.2 Fuel co6.3 Overvie6.4 Outcom6.5 Outcom6.6 Outco10.0 km/h)6.7 Outcomm/h) ..........7.1 Total fu7.2 Emissio7.3 Emissio8.1 Main ch9.1 Max. dr9.2 Summa10.1 Total ................10.2 Overv10.3 Outco
figures ssion of theal emissio al emissio
zle)al emissio al emissio
zle)ssion of theual emissio ual emissiozle)ual emissio ual emissiozle)
tables ge age of Wntation of oon factors haracteristraught andary of costsuel consumonsumptionew of data me of econme of econme of sen) ...............me of sens................
uel consumons in g/tkons in g/tkharacteristraught andary of costsfuel cons
................view of inpuome of eco
e Hendrikons of the
ons of the
ons of the
ons of the
e Rheinlanons of the
ons of the
ons of the
ons of the
Western Euutcomes fefor inland w
tics of the Hd additionas per lengt
mption of Hn of Hendrinput .......omic asseomic asse
nsitivity an................
sitivity anal................
mption of Hm and mg/m and mg/tics of the Rd additionas per lengtumption of................ut data .....
onomic ass
55/57
Hendrik i
Hendrik i
Hendrik i
Hendrik i
ndRheinland
Rheinland
Rheinland
Rheinland
uropean veeasibility awaterway Hendrik (1
al cargo forthening ste
Hendrik in liik in litre p................
essment foressment foralysis Loa................lysis Loa 7................
Hendrik in k/tkm for rel/tkm for relRheinland
al cargo forthening mef Rheinlan................................
sessment fo
W
n kg for a
n kg for a
n kg for a
n kg for a
d in kg for
d in kg for
d in kg for
d in kg for
essels .......assessmenvessel .....975) ........r different leep for MV ’itre per yeaer ton tran................r relative sr relative s
a 76 m an................
76 m and n................
kg for operlative speelative spee(1959) .....
r different leeter for MVnd in litre p................................or relative
WP 6: New
an average
an average
an average
an average
an averag
an averag
an averag
an averag
................t ..............................................engtheningHendrik’ ..ar on Rhinsported ...................
speed of 10speed of 14nd propelle................naked prop................
ration of 10ed of 10.0 ked of 14.4 k................engthening
V ’Rheinlanper year o................................speed of 1
w scales an
e speed o
e speed o
e speed o
e speed o
ge speed o
ge speed o
ge speed o
ge speed o
................
................
................
................g steps ....................e .............................................0.0 km/h ...4.4 km/h ...er in nozzl................peller (rela................
00 km on Rkm/h ........km/h ........................g steps ....nd’ ............n Danube................................10.8 km/h .
nd services
21of 10,0 km
34of 10,0 km
34of 14,4 km
35of 14,4 km
3639
of 10,8 km48
of 10,8 km48
of 14,4 km49
of 14,8 km50
.............. 9
............ 13
............ 16
............ 21
............ 23
............ 24
............ 27
............ 27
............ 28
............ 29
............ 30le (relative............ 30
ative speed............ 31
Rhine .... 33............ 35............ 36............ 39............ 41............ 41 (litres per............ 43............ 44............ 45
s
m 4 m 4 m 5 m 6 9 m 8 m 8 m 9 m 0
9 3 6
3 4 7 7 8 9 0 e 0 d
3 5 6 9
r 3 4 5
WP 6: New scales and services
56/57
Table 10.4 Outcome of economic assessment for relative speed of 14.8 km/h ............. 45 Table 11.1 Total fuel consumption of Rheinland in kg for operation of 1000 km on Danube .......................................................................................................................... 47 Table 11.2 Emissions in g/tkm and mg/tkm for relative speed of 10.8 km/h .................. 49 Table 11.3 Emissions in g/tkm and mg/tkm for relative speed of 14.8 km/h .................. 50
14.3 List of abbreviations BV Bureau Veritas; CBRB Centraal Bureau voor de Rijn- en Binnenvaart CCR Central Commission for Navigation on the Rhine; CO Carbon monoxide; CO2 Carbon dioxide; GL Germanischer Lloyd; HC Hydrocarbon; H&M Hull and machinery; IRR Internal rate of return; IW Inland waterway; IWT Inland waterway transport; kW Kilo watt; NOx Nitrogen oxide; NPV Net present value; P&I Protection and indemnity; PM Particular matter; SO2 Sulphur dioxide; TEU Twenty feet equivalent unit; WP Work Package.