![Page 1: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/1.jpg)
Document of
The World Bank
Report No: ICR00004259
IMPLEMENTATION COMPLETION AND RESULTS REPORT
(IBRD-76920, IBRD-79370)
ON A
LOAN
IN THE AMOUNT OF SDR 63 MILLION
(US$ 150 MILLION EQUIVALENT)
TO THE
PEOPLE’S REPUBLIC OF CHINA
FOR A
YUNNAN URBAN ENVIRONMENT PROJECT
April 23, 2018
Global Water Practice
China Country Management Unit
East Asia and Pacific Region
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
![Page 2: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/2.jpg)
The World Bank (P096812)
ii
ABBREVIATIONS AND ACRONYMS
AF Additional Financing
COD Chemical Oxygen Demand
FY Fiscal Year
FYP Five-Year Plan
GEF Global Environment Facility
IBRD International Bank for Reconstruction and Development
IDA International Development Association
ICR Implementation Completion Results Report
ILBM Integrated Lake Basin Management
IO Intermediate Outcome Indicator
ISR Implementation Status and Results Report
M&E Monitoring & Evaluation
MTR Mid-Term Review
MS Moderately Satisfactory
MU Moderately Unsatisfactory
O&M Operation & Maintenance
PAD Project Appraisal Document
PDO Project Development Objective
PIU Project Implementation Unit
PMO Project Management Office
QEA Quality at Entry Assessment
QSA Quality of Supervision Assessment
RF Results Framework
RMB Renminbi
S Satisfactory
SDR Special Drawing Rights
SIL Specified Investment Loan
SWM Solid Waste Management
TA Technical Assistance
UNESCO United Nations Educational, Scientific, and Cultural Organization
USD United States Dollar
WTP Willingness To Pay
WWTP Wastewater Treatment Plant
Senior Global Practice Director: Guang Zhe Chen
Practice Manager: Sudipto Sarkar
Project Team Leader: Joanna Masic
ICR Authors: Scott Moore
Yan Li
![Page 3: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/3.jpg)
The World Bank (P096812)
iii
CHINA
Yunnan Urban Environment Project
CONTENTS
Data Sheet
A. Basic Information
B. Key Dates
C. Ratings Summary
D. Sector and Theme Codes
E. Bank Staff
F. Results Framework Analysis
G. Ratings of Project Performance in ISRs
H. Restructuring
I. Disbursement Graph
1. Project Context, Development Objectives and Design ............................................................ 1
2. Key Factors Affecting Implementation and Outcomes ........................................................... 8
3. Assessment of Outcomes ....................................................................................................... 18
4. Assessment of Risk to Development Outcome ..................................................................... 29
5. Assessment of Bank and Borrower Performance .................................................................. 29
6. Lessons Learned .................................................................................................................... 31
7. Comments on Issues Raised by Borrower/Implementing Agencies/Partners........................ 32
Annex 1. Project Costs and Financing ....................................................................................... 34
Annex 2. Outputs by Component .............................................................................................. 36
Annex 3. Economic and Financial Analysis .............................................................................. 40
Annex 4. Bank Lending and Implementation Support/Supervision Processes.......................... 41
Annex 5. Beneficiary Survey Results ........................................................................................ 42
Annex 6. Stakeholder Workshop Report and Results ............................................................... 43
Annex 7. Summary of Borrower's ICR and/or Comments on Draft ICR .................................. 44
Annex 8. Comments of Cofinanciers and Other Partners/Stakeholders .................................... 57
Annex 9. List of Supporting Documents ................................................................................... 58
MAP…………………………………………………………………………………................59
![Page 4: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/4.jpg)
The World Bank (P096812)
iv
A. BASIC INFORMATION
Country: China Project Name: Yunnan Urban
Environment Project
Project ID: P096812 L/C/TF Number(s): IBRD-76920,IBRD-79370
ICR Date: 04/30/2018 ICR Type: Core ICR
Financing Instrument: SIL Borrower: CHINA
Original Total
Commitment: USD 90.00M Disbursed Amount: USD 130.70M
Revised Amount: USD 130.70M
Environmental Category: A Implementing Agencies:
Yunnan Provincial Environment Protection Bureau - Foreign Financed PMO
Cofinanciers and Other External Partners:
B. KEY DATES
Process Date Process Original Date Revised / Actual Date(s)
Concept Review: 09/26/2006 Effectiveness: 09/30/2009
Appraisal: 12/03/2007
Additional Financing: 05/27/2010
Approval: 05/05/2009 Restructuring(s): 06/15/2015
Mid-term Review: 05/31/2013 12/15/2013
Closing: 06/30/2015 04/30/2017
C. RATINGS SUMMARY
C.1 Performance Rating by ICR
Outcomes: Moderately Satisfactory
Risk to Development Outcome: Substantial
Bank Performance: Moderately Satisfactory
Borrower Performance: Moderately Satisfactory
C.2 Detailed Ratings of Bank and Borrower Performance (by ICR)
Bank Ratings Borrower Ratings
Quality at Entry: Moderately Unsatisfactory Government: Moderately Satisfactory
![Page 5: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/5.jpg)
The World Bank (P096812)
v
Quality of Supervision: Moderately Satisfactory Implementing
Agency/Agencies: Moderately Satisfactory
Overall Bank
Performance: Moderately Satisfactory
Overall Borrower
Performance: Moderately Satisfactory
C.3 Quality at Entry and Implementation Performance Indicators
Implementation
Performance Indicators
QAG Assessments (if
any) Rating
Potential Problem Project at
any time (Yes/No): No Quality at Entry (QEA): None
Problem Project at any time
(Yes/No): Yes
Quality of Supervision
(QSA): None
DO rating before
Closing/Inactive status: Moderately Satisfactory
D. SECTOR AND THEME CODES
Original Actual
Major Sector/Sector
Social Protection
Social Protection 18 18
Water, Sanitation and Waste Management
Other Water Supply, Sanitation and Waste
Management 18 18
Public Administration - Water, Sanitation and Waste
Management 28 28
Waste Management 18 18
Sanitation 18 18
Major Theme/Theme/Sub Theme
Environment and Natural Resource Management
Environmental Health and Pollution Management 45 45
Air quality management 15 15
Soil Pollution 15 15
Water Pollution 15 15
Environmental policies and institutions 5 5
Water Resource Management 5 5
Water Institutions, Policies and Reform 5 5
![Page 6: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/6.jpg)
The World Bank (P096812)
vi
Urban and Rural Development
Cultural Heritage 7 7
Urban Development 38 38
Urban Infrastructure and Service Delivery 38 38
E. BANK STAFF
Positions At ICR At Approval
Regional Vice President: Victoria Kwakwa James W. Adams
Country Director: Bert Hofman David R. Dollar
Practice Manager: Sudipto Sarkar Keshav Varma
Task Team Leader(s): Joanna Masic Takuya Kamata
ICR Team Leader: Joanna Masic
Senior Global Practice Director: Guang Zhe Chen
Co Task Team Leader1: Shunong Hu
Co Task Team Leader2: Scott Michael Moore
ICR Primary Author: Scott Michael Moore
ICR Author: Yan Li
F. RESULTS FRAMEWORK ANALYSIS
Project Development Objectives (from Project Appraisal Document)
To assist Yunnan Province in improving the effectiveness and coverage of critical urban infrastructure services in
selected counties and the effectiveness of lake basin management in Dianchi, through investment in systems for the
management of wastewater, water supply, solid waste, river environment and cultural heritage.
Revised Project Development Objectives (as approved by original approving authority)
PDO was not revised.
(a) PDO Indicator(s)
![Page 7: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/7.jpg)
The World Bank (P096812)
vii
Indicator Baseline
Value
Original
Target Values
(from
approval
documents)
Formally
Revised
Target
Values
Actual Value
Achieved at
Completion or
Target Years Indicator 1 : People in urban areas provided with access to wastewater services (cumulative) Indicator 1 : People in urban areas provided with access to wastewater services (cumulative)
Value
quantitative or
Qualitative)
350,000
n/a
806,000
828,800
Value
quantitative or
Qualitative)
Date achieved 12/31/2009 n/a 04/30/2017 04/07/2017 Date achieved
Comments
(incl. %
achievement)
103% achieved.
Note: Includes Lijiang, Huaping, Qiubei, Guangnan, Yanshan, & Zhaotong.
PO-1 added at restructuring so no original target value available.
Comments
(incl. %
achievement)
Indicator 2 : People in urban areas with access to solid waste management services (cumulative) Indicator 1 : People in urban areas with access to solid waste management services (cumulative)
Value
quantitative or
Qualitative)
182,000
n/a
448,000
455,000
Value
quantitative or
Qualitative)
Date achieved 12/31/2009 n/a 04/30/2017 04/07/2017 Date achieved
Comments
(incl. %
achievement)
102% achieved.
PO-2 added at restructuring so no original target value available.
Comments
(incl. %
achievement)
Indicator 3 : People in urban areas provided with access to water services (cumulative) Indicator 1 : People in urban areas provided with access to water services (cumulative)
Value
quantitative or
Qualitative)
319,000
n/a
404,000
502,000
Value
quantitative or
Qualitative)
Date achieved 12/31/2009 n/a 04/30/2017 04/30/2017 Date achieved
Comments
(incl. %
achievement)
124% achieved.
Note: Includes Zhaotong City and Qiubei County . PO-3 added at restructuring so no original target
value available.
Comments
(incl. %
achievement)
Indicator 4 : Improved capacity for Dianchi Lake Basin management Indicator 1 : Improved capacity for Dianchi Lake Basin management
Value
quantitative or
Qualitative)
Lack of
information to
assess pollution
load into Dianchi
Lake and absence
of planning
towards integrated
lake basin
management
Improved
management and
coordination by
responsible
agencies/bureaus
for Dianchi as
evidenced by
regular sharing of
data among all key
bureaus involved
Lessons included
in sector 13th
FYP, information
system for
Dianchi Lake in
place. Findings
from
integrated plan
incorporated into
sector plans
under the 13th
FYP
Plan completed. Lessons
incorporated into 13th FYP,
information system for
Dianchi Lake in place.
Findings from integrated
plan incorporated into sector plans
under plan for the 13th FYP.
Value
quantitative or
Qualitative)
Date achieved 12/31/2009 06/30/2015 04/30/2017 04/30/2017 Date achieved
Comments
(incl. %
achievement)
100% achieved; lessons included in 13th FYP.
Note that PO-4 originally emphasized data-sharing; this was revised at restructuring to
emphasize completion of an Integrated Lake Basin Management plan (see below).
Comments
(incl. %
achievement)
![Page 8: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/8.jpg)
The World Bank (P096812)
viii
Indicator 5 : Improved management & coordination by responsible agencies/bureaus for
Dianchi as evidenced by regular sharing of data among all key bureaus involved
Value
quantitative or
Qualitative)
n/a (No data entered)
n/a
Dropped
n/a
Date achieved 12/31/2009 06/30/2015 04/30/2017 04/30/2017
Comments
(incl. %
achievement)
This PO dropped at restructuring and incorporated into PO-4. Online monitoring
and data-sharing platform developed and in use as of Project close.
(b) Intermediate Outcome Indicator(s)
Indicator Baseline Value
Original Target
Values (from
approval
documents)
Formally Revised
Target Values
Actual Value Achieved at
Completion or Target Years
Indicator 1 : Total Chemical Oxygen Demand (COD) Pollutant Load Reduction (tons/year)
Value
quantitative or
Qualitative)
1800
n/a
2100
3815
Date achieved 12/31/2007 n/a 04/30/2017 04/30/2017
Comments
(incl. %
achievement)
180% achieved, based on full-year data for 2017. This IO was added at restructuring to
comply with the Core Sector Indicators (2013). The PAD included a related but different
IO, “COD level at main discharge point”, measured in mg/L, for several WWTPs (see
below). Indicator 2 : Volume of Municipal Solid Waste (SW) Disposed in Landfill (tons/year)
Value
quantitative or
Qualitative)
143
n/a
480
535
Date achieved 12/31/2009 n/a 04/30/2017 04/30/2017
Comments
(incl. %
achievement)
141% achieved.
IO-2 was added at restructuring so no original target value available. Original IOs from
PAD were 1) # of new population served by SWM services and 2) amount of SW being
disposed to sanitary landfills. 2nd IO revised to be Core IO (2013). Indicator 3 : Length of river section restored (km)
Value
quantitative or
Qualitative)
0
n/a
49.7
51.97
Date achieved 12/31/2009 n/a 04/30/2017 04/30/2017
Comments
(incl. %
achievement)
103% achieved.
IO-3 was added at restructuring so no original target value available.
Indicator 4 : Increase in visitors to Lion Mountain
Value
quantitative or
Qualitative)
0
n/a
75,000
79,170
Date achieved 12/31/2009 n/a 04/30/2017 04/30/2017
![Page 9: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/9.jpg)
The World Bank (P096812)
ix
Comments
(incl. %
achievement)
106% achieved.
IO-4 was added at restructuring so no original target value available. The PAD included an
IO “Development of rehabilitation plans in compliance with UNESCO protection codes and
other national cultural heritage regulations” (see below). Indicator 5 : Development of Flood Risk Management System for Zhaotong
Value
quantitative or
Qualitative)
n/a
n/a
Flood risk
management
adopted
Flood risk management
adopted
Date achieved 12/31/2007 n/a 04/30/2017 04/30/2017
Comments
(incl. %
achievement)
100% achieved.
IO-5 was added at restructuring so no original target value available. The PAD includes an
IO for “Incidence and severity of floods as compared to historical data in terms of number
of people displaced and extent of material damage” (see below).
Indicator 6 : Number of people in urban areas provided with access to Improved Sanitation under the
project
Value
quantitative or
Qualitative)
190,200 319,300 Dropped
320,600
Date achieved 12/31/2009 06/30/2016 04/30/2017 12/31/2017
Comments
(incl. %
achievement)
100% achieved.
This was a core indicator but was dropped at restructuring. Incorporated in PO-1 following
re-structuring.
Indicator 7 : Number of people in urban areas provided with access to Improved Water Sources under
the project
Value
quantitative or
Qualitative)
270,050 347,600 Dropped
400,000
Date achieved 12/31/2009 06/30/2016 04/30/2017 12/31/2017
Comments
(incl. %
achievement)
115% achieved.
This was a core indicator but was dropped at restructuring. Incorporated in PO-3 following
re-structuring.
Indicator 8 : Number of population served by solid waste management services (104)
Value
quantitative or
Qualitative)
Songming: 5.56
Xundian: 5.73
Luquan: 5.02
Lijiang: 16.66
Funing: 3.52
Songming: 7.36
Xundian: 7.89
Luquan: 7.45
Lijiang: 24.89
Funing: 5.22
Dropped
Songming: 11.42
Xundian: 13.69
Luquan: 8.77
Lijiang: 37.9
Funing: n/a (dropped before
implementation)
Date achieved 12/15/2007 06/30/2015 04/30/2017 10/31/2014
Comments
(incl. %
achievement)
Achievement ranged from 118% to 173%; average of 150%. This indicator was dropped at
restructuring. Incorporated in PO-2 following re-structuring. No data is available after
restructuring. Latest data (herein reported) is from ISR17221 12/06/2014.
![Page 10: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/10.jpg)
The World Bank (P096812)
x
Indicator 9 : Amount of solid waste disposed to sanitary landfills (tons/day)
Value
quantitative or
Qualitative)
Songming: 0
Xundian: 51.61
Luquan: 0
Lijiang: 142.7
Funing: 0
Songming: 79.5
Xundian: 70
Luquan: 80.5
Lijiang: 230.1
Funing: 62.10
Dropped
Songming: 125
Xundian: 62
Luquan: 70
Lijiang: 278
Funing: n/a (dropped before
implementation)
Date achieved 12/31/2009 06/30/2015 04/30/2017 12/31/2017
Comments
(incl. %
achievement)
Achievement ranged from 87% to 157%; average of 114%. Indicator was dropped at
restructuring. Incorporated in PO-2 following re-structuring. At Xundian and Lijiang
original amount was disposed to an old landfill replaced by Project-financed sanitary
landfill.
Indicator 10 : Operating cost covered by solid waste fee revenues (%)
Value
quantitative or
Qualitative)
Songming: 0
Xundian: 0
Luquan: 0
Funing: 0
Songming: 103
Xundian: 55
Luquan: 121
Funing: 100
Dropped
Songming: 91
Xundian: 8.9
Luquan: 11.2
Funing: n/a (dropped before
implementation)
Date achieved 12/15/2007 06/30/2015 04/30/2017 10/31/2014
Comments
(incl. %
achievement)
Achievement ranged from 9% to 88%; average of 38%. Indicator was dropped at
restructuring; at restructuring, the definition of cost recovery was modified to include
governments’ subsidies, thus this indicator became unnecessary.
Indicator 11 : Wastewater Management System – Population Served
Value
quantitative or
Qualitative)
Lijiang Town:
166,600
Huaping: 0
Qiubei: 39,600
Yanshan: 46,500
Guangnan: 0
Ljiang Town:
248,900
Huaping: 56,400
Qiubei: 53,050
Yanshan: 66,200
Guangnan:
68,300
Dropped
Lijiang Town: 192,200
Huaping: 49,000
Qiubei: 72,000
Yanshan: 75,000
Guangnan: 120,000
Date achieved 12/15/2007 06/30/2015 04/30/2017 04/30/2017
Comments
(incl. %
achievement)
77% to 176% achieved; average of 118%. This indicator was dropped at restructuring.
Data provided by PMO as of Project close.
![Page 11: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/11.jpg)
The World Bank (P096812)
xi
Indicator 12 : Lijiang Ancient Town District, Development Masterplan – Compliance with UNESCO and
National Protection Codes (Yes/No)
Value
quantitative or
Qualitative)
Y
Y
Dropped
Y
Date achieved 12/31/2007 06/30/2015 04/30/2017 04/25/2014
Comments
(incl. %
achievement)
100% achieved.
This indicator was dropped at restructuring. No data entered after restructuring; Latest data
(herein reported) from ISR17221 12/06/2014. This indicator was complied with but was
dropped at restructuring.
Indicator 13 : Lijiang Ancient Town District, Maintenance of UNESCO World Cultural Heritage Status
(Yes/No)
Value
quantitative or
Qualitative)
Y
Y Dropped Y
Date achieved 12/31/2007 06/30/2015 04/30/2017 04/25/2014
Comments
(incl. %
achievement)
100% achieved.
This indicator was dropped at restructuring. No data entered after restructuring; Latest data
(herein reported) from ISR17221 12/06/2014. This indictaor was complied with but not
deemed a useful indicator to measure subproject implementation.
Indicator 14 : Rainwater Drainage System – Population served
Value
quantitative or
Qualitative)
Yulong: 30000
60000
Dropped
n/a (no data entered)
Date achieved 12/31/2007 06/30/2015 04/30/2017 04/25/2014
Comments
(incl. %
achievement)
This indicator was dropped in 2010 and incorporated into IO-3. No data in ISRs. No data
on achievement pre-restructuring.
Indicator 15 : Wastewater Management – COD level (mg/L) at discharge point
Value
quantitative or
Qualitative)
Huaping: 250-400
Qiubei: 250-400
Yanshan: 250-400
Guangnan: 250-
400
Huaping: 60
Qiubei: 60
Yanshan: 60
Guangnan: 60
Dropped Huaping: 24
Qiubei: 30
Yanshan: 36
Guangnan: 26
Date achieved 12/15/2007 06/30/2015 04/30/2017 10/31/2014
Comments
(incl. %
achievement)
100% achieved. This indicator was dropped at restructuring. No data is available after
restructuring. Latest data (herein reported) is from ISR17221 12/06/2014.
Indicator 16 : Frequency of water monitoring at Wenshan Prefecture Environment Monitoring Station
(times/year)
Value
quantitative or
Qualitative)
6
12
Dropped 12
![Page 12: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/12.jpg)
The World Bank (P096812)
xii
Date achieved 12/31/2009 06/30/2010 04/30/2017 04/25/2014
Comments
(incl. %
achievement)
100% achieved.
This indicator was dropped at restructuring. No data entered after restructuring; Latest data
(herein reported) from ISR17221 12/06/2014.
Indicator 17 : Wenshan County Environment Monitoring – Percentage of polluters aware of new
regulation standards
Value
quantitative or
Qualitative)
0
100
Dropped 100
Date achieved 12/15/2007 06/30/2015 04/30/2017 04/25/2014
Comments
(incl. %
achievement)
100% achieved.
This indicator was dropped at restructuring. No data entered after restructuring; Latest data
(herein reported) from ISR17221 12/06/2014.
Indicator 18 : Dianchi Lake Basin Management – Number of monitoring on 3 rivers (times per year)
Value
quantitative or
Qualitative)
6
8,760
Dropped 2,190
Date achieved 12/15/2007 06/30/2015 04/30/2017 12/31/2017
Comments
(incl. %
achievement)
25% achieved.
This indicator was dropped at restructuring. Data provided by PMO for full year 2017.
Frequency based on sampling 6x/day, whereas original target assmed 1x/hour.
Indicator 19 : Dianchi Lake Basin Management – Number of monitoring on 14 streams (times/year)
Value
quantitative or
Qualitative)
0
8,760
Dropped 24
Date achieved 12/15/2007 06/30/2015 04/30/2017 12/31/2017
Comments
(incl. %
achievement)
<1% achieved.
This indicator was dropped at restructuring. Data provided by PMO for full year 2017.
Frequency based on sampling 2x/month, whereas original target assmed 1x/hour.
Indicator 20 : Dianchi Lake Basin Management – Online monitoring and information management
carried out (Yes/No)
Value
quantitative or
Qualitative)
N
Y
Dropped Y
Date achieved 12/15/2007 06/30/2015 04/30/2017 04/25/2014
Comments
(incl. %
achievement)
100% achieved.
This indicator was dropped at restructuring. No data entered after restructuring; Latest data
(herein reported) from ISR17221 12/06/2014.
Indicator 21 : Lake Basin Component, System terminal has capacity to receive & process monitoring
data (Yes/No)
Value
quantitative or
Qualitative)
n/a (No data
entered)
Y
Dropped Y
![Page 13: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/13.jpg)
The World Bank (P096812)
xiii
Date achieved 12/31/2009 12/31/2011 04/30/2017 12/31/2011
Comments
(incl. %
achievement)
100% achieved.
This indicator was dropped at restructuring. No data entered after restructuring; Latest data
(herein reported) from ISR17221 12/06/2014.
Indicator 22 : Collection of tariffs covers O&M costs and some debt obligations (wastewater)
Value
quantitative or
Qualitative)
n/a (No data
entered)
n/a (No data
entered)
Dropped Lijiang: Revenue =
1.10RMB/m3 (expenses =
1.76RMB/m3)
Yanshan: Revenue =
0.8RMB/m3 (expenses =
1.26RMB
Qiubei: Revenue = 0.8
RMB/m3 (expenses
unknown)
Guangnan: Revenue =
1RMB/m3 (expenses =
1.1RMB/m3)
Zhaoyang: Revenue =
1.25RMB/m3 (expenses =
1.26RMB/m3)
Date achieved 12/31/2009 06/30/2015 04/30/2017 04/30/2017
Comments
(incl. %
achievement)
0% achieved.
This indicator dropped at restructuring. No data entered pre-restructuring. Wastewater
tariff rate of 0.8RMB defined in Project Agreement (Section 4) and achieved. Lijiang,
Chaoyang & Guangnan on track to achieve full cost recovery w/o subsidies.
Indicator 23 : Increase in collection rate of Solid Waste services
Value
quantitative or
Qualitative)
n/a (No data
entered)
n/a (No data
entered)
Dropped n/a (No data entered)
Date achieved 12/31/2009 12/31/2011 04/30/2017 12/31/2011
Comments
(incl. %
achievement)
This indicator was listed in the PAD but not included in the Project Agreement results
framework (Annex B). No data in ISRs or entered pre-restructuring.
Indicator 24 : Incidence and severity of floods as compared to historical data in terms of number of
people displaced and extent of material damage
Value
quantitative or
Qualitative)
n/a (No data
entered)
n/a (No data
entered)
Dropped n/a (No data entered)
Date achieved 12/31/2009 12/31/2011 04/30/2017 12/31/2011
![Page 14: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/14.jpg)
The World Bank (P096812)
xiv
Comments
(incl. %
achievement)
This indicator was listed in the PAD but not included in the Project Agreement results
framework (Annex B). No data in ISRs or entered pre-restructuring. Indicator incorporated
in IO-5 (see above).
Indicator 25 : Dianchi protection regulations are revised, approved and enforced
Value
quantitative or
Qualitative)
n/a (No data
entered)
n/a (No data
entered)
Dropped Regulations approved in
September 2012 and
enforced since January 1,
2013.
Date achieved 12/31/2009 12/31/2011 04/30/2017 01/01/2013
Comments
(incl. %
achievement)
100% achieved. This indicator was dropped at restructuring. Data provided by PMO as of
Project close.
Indicator 26 : ILBM Master Plan for Dianchi is developed and adopted, particularly conducting water
resource carrying capacity of the lake basin
Value
quantitative or
Qualitative)
n/a (No data
entered)
100%
Dropped 100%
Date achieved 12/31/2009 12/31/2011 04/30/2017 04/30/2017
Comments
(incl. %
achievement)
This indicator was dropped at restructuring and incorporated into PO-4. No data in ISRs or
entered pre-restructuring. However, development and adoption of ILBM Master Plan has
taken place based on data provided by PMO and verified during ICR mission.
G. RATINGS OF PROJECT PERFORMANCE IN ISRs
No. Date ISR
Archived DO IP
Actual Disbursements
(USD millions)
1 12/03/2009 Satisfactory Satisfactory 0.00
2 05/31/2010 Satisfactory Satisfactory 4.00
3 06/27/2011 Satisfactory Satisfactory 21.58
4 04/10/2012 Satisfactory Satisfactory 28.58
5 04/22/2013 Moderately
Satisfactory
Moderately
Satisfactory
37.32
6 11/08/2013 Moderately
Satisfactory
Moderately
Satisfactory
43.32
7 06/24/2014 Moderately
Satisfactory
Moderately
Unsatisfactory
53.49
8 12/06/2014 Moderately
Satisfactory
Moderately
Unsatisfactory
58.60
9 04/21/2015 Moderately
Satisfactory
Moderately
Unsatisfactory
69.80
![Page 15: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/15.jpg)
The World Bank (P096812)
xv
10 06/22/2015 Moderately
Satisfactory
Moderately
Unsatisfactory
71.99
11 12/15/2015 Moderately
Satisfactory
Moderately
Satisfactory
82.30
12 06/24/2016 Moderately
Satisfactory
Moderately
Satisfactory
100.03
13 12/23/2016 Satisfactory Satisfactory 109.33
14 03/14/2017 Moderately
Satisfactory Satisfactory
117.15
15 04/29/2017 Moderately
Satisfactory
Moderately
Satisfactory
117.15
H. RESTRUCTURING (IF ANY)
Restructuring
Date(s)
Board
Approved
PDO
Change
ISR Ratings at
Restructuring Amount Disbursed at
Restructuring in USD
Millions
Reason for Restructuring & Key
Changes Made
DO IP
06/15/2015
MS MU 71.99
The Project underwent an
Additional Financing on
05/27/2010 to fund an additional
Project subcomponent (See Section
1.6). A subsequent Level 2
restructuring took place in 2015. In
addition to the reallocation of loan
proceeds amongst components due
to client decision to finance
subcomponents under Component
1 and to use loan savings from
cultural heritage management to
expand sewer restoration, the 2015
restructuring also included (a) a
revision of the indicators to better
reflect the Project’s scope and
context; (b) an extension of the
Project’s closing date by 22 months
to April 30, 2107 to allow for
completion of delayed and newly
added subcomponents (c) revision
of cost estimates; (d) increase in
disbursement percentages for civil
works; (e) revison of cost recovery
definition in the PA; ; and (f)
![Page 16: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/16.jpg)
The World Bank (P096812)
xvi
change one project implementing
unit and revise another.
I. DISBURSEMENT PROFILE
![Page 17: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/17.jpg)
1
1. Project Context, Development Objectives and Design
1.1 Context at Appraisal
1. At appraisal, China’s Yunnan Province was benefiting from years of strong
economic growth. Gross Domestic Product (GDP) averaged 8.9 percent between
2000 and 2005. Tourism was a key driver of growth. Tourists were attracted to
Yunnan for its scenery and ethnic diversity. Approximately 30 ethnic groups
(representing 40 percent of the population) resided in Yunnan. Economic growth
was accompanied by rapid urbanization in the Province’s largest cities and a
number of county seats, heavily straining existing urban water supply, wastewater
treatment, and solid waste disposal infrastructure. The urbanization rate for
Kunming Municipality, for example, was 57% in 2005, while the province-wide
rate was almost 30%. The strain on sanitation infrastructure was resulting in
considerable environmental degradation, especially water pollution. For example,
at the time of Project appraisal, the Province-wide wastewater treatment rate was
40.5 percent, far below the national level of about 50 percent.1
2. The Provincial Government was focused on sustaining rapid economic
development and reversing environmental degradation. In its 11th Five Year Plan
(2007-2012), the Provincial Government outlined a growth strategy centered on
exploiting its natural resource base, promoting tourism, and providing basic
services to urban residents. The strategy also highlighted the importance of
reducing water pollution in the Province’s smaller cities and county seats. The
strategy targeted one of the most visible signs of water pollution in the Province,
the severe eutrophication of Dianchi Lake. The water quality in Dianchi Lake,
Yunnan’s largest lake and a primary water source, had deteriorated from Grade II
in the 1980s to Grade V2 by the mid-2000s. One reason for the deterioration in
water quality was local authorities’ lack of coordination and capacity to implement
pollution control regulations.
3. Sector Details. Yunnan’s urban sector was under-developed at the time of appraisal,
especially in the semi-urban county seats that were the focus of the Project.
Yunnan’s local governments, which included municipal and county governments,
were primarily responsible for the sector, with financial and technical support from
the provincial government. County-seat towns, and the county-level governments
under whose responsibility they fell, were identified as the focus of the Project
because they played a key role in the province’s development strategy at the time
of appraisal, as they were expected to absorb a substantial share of rural-urban
1 See Project Appraisal Document, Report No. 41199 – CN. 2 Water quality ratings in China correspond to qualitative standards like “Good” and “Very Good.” Grade V represents
water that is not judged as being suitable for human contact or consumption.
![Page 18: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/18.jpg)
2
migration and employment generation from tourism, natural resource-based
manufacturing, trading, and other services. Access to basic urban services,
including WW and water supply services, was very low at appraisal. For example,
Huaping County in Lijiang Municipality did not have any wastewater treatment
plants.3 Meanwhile, as noted above, the province-wide wastewater treatment rate
was well below the national average.
4. Rationale for Bank Involvement. The Yunnan Urban Environment Project (YUEP)
represented a continuation of the Bank’s prior engagement in the Province. YUEP
built upon similar past projects, including the Yunnan Environment Project
(P003599), which financed construction of wastewater treatment systems and other
urban infrastructure in several cities and attempted to address the eutrophication of
Dianchi Lake. In addition, YUEP complemented the Bank’s Global Environment
Facility-funded “Lake Dianchi Freshwater Biodiversity Restoration Project”
(P068239). YUEP also aimed to replicate the cultural heritage management
dimension of the China Yunnan Earthquake Reconstruction Project (P114107).
5. Higher-Level Objectives. The Project’s focus on improving natural resource
management and expanding urban wastewater and solid waste management
(SWM) services directly supported Pillar Three, To manage resource scarcity and
environmental challenges, of the World Bank’s 2006 to 2010 Country Partnership
Strategy (CPS) for China (Report No. 35435).4 The Project also directly supported
China’s 11th Five-Year Development Plan (2006 to 2010), which included targets
for improving water use efficiency and solid waste collection and reducing
pollution discharges.5 Finally, the Project’s emphasis on expanding the coverage of
urban infrastructure services attempted to help Yunnan Province achieve the
Millennium Development Goals pertaining to water supply and sanitation.6
1.2 Original Project Development Objectives (PDO) and Key Indicators
6. The Project Development Objective (PDO) as stated in the Loan Agreement and
Project Appraisal Document (PAD) was “to assist Yunnan Province in improving
the effectiveness and coverage of critical urban infrastructure services in selected
counties and the effectiveness of lake basin management in Dianchi, through
investments in systems for the management of wastewater, water supply, solid
waste, river environment and cultural heritage.”
7. The original PDO outcome indicator was “Improved management and coordination
by responsible agencies/bureaus for Dianchi as evidenced by regular sharing of data
3 See Project Appraisal Document. 4 World Bank. 2006. China - Country partnership strategy . Washington, DC: World Bank.
https://hubs.worldbank.org/docs/imagebank/pages/docprofile.aspx?nodeid=7089669 5 NPC & CPPCC National Committee Annual Sessions. 2006. Facts and figures: China’s main targets for 2006-2010.
http://www.gov.cn/english/2006-03/06/content_219504.htm 6 See United Nations. 2015. Millennium Development Goals. http://www.un.org/millenniumgoals/environ.shtml
![Page 19: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/19.jpg)
3
among all key bureaus involved.” This was the only PDO outcome indicator prior
to restructuring.
1.3 Revised PDO (as approved by original approving authority) and Key Indicators,
and reasons/justification
8. The PDO was not revised during implementation. In 2015, however, the results
framework was substantially modified via a Level 2 Project restructuring. The
original outcome indicator concerning Dianchi Lake management was broadened
to focus on institutional capacity and inter-jurisdictional cooperation instead of
simply data-sharing. In addition, three Project-level outcome indicators (See Table
1 below) were added to measure the Project’s impact on coverage of critical urban
infrastructure. These Project-level outcome indicators incorporated several
intermediate indicators (IOs) from the pre-restructuring results framework (See
Data Sheet).
Table 1. Project Outcome Indicators Before and After Restructuring BEFORE RESTRUCTURING AFTER RESTRUCTURING
IMPROVED MANAGEMENT AND
COORDINATION BY RESPONSIBLE
AGENCIES/BUREAUS FOR DIANCHI AS
EVIDENCED BY REGULAR SHARING OF DATA
AMONG ALL KEY BUREAUS INVOLVED
Improved capacity for Dianchi Lake Basin management
N/A People in urban areas with access to wastewater services
(cumulative)
N/A People in urban areas with access to SWM services
(cumulative)
N/A People in urban areas provided with access to water
services (cumulative)
1.4 Main Beneficiaries
9. The PAD identified Yunnan’s approximately 20.4 million urban residents7 as the
primary beneficiaries of the Project. Yunnan’s urban residents in selected Project
sites were expected to benefit primarily from improved SWM, WW treatment and
access to clean water. The selection of Project sites emphasized Yunnan’s poorer
regions; the poverty rates in Project areas were higher than provincial and national
averages (See Section 2.1). In addition, the Province as a whole was expected to
benefit from the Project’s comprehensive approach to improving urban
infrastructure. For example, the cultural heritage management subcomponent was
expected to benefit both local residents and tourists at Lion Mountain, while the
Integrated Lake Basin Management (ILBM) Plan was expected to substantially
improve the overall natural environment (and thus recreational and tourism
opportunities) in the Kunming area.
7 Per the PAD, page 16, Yunnan’s total population is some 41 million, of whom approximately half are estimated to
live in cities.
![Page 20: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/20.jpg)
4
1.5 Original Components
10. The Loan Agreement referenced three components, which are summarized
below:8
11. Component 1: Urban Environment Infrastructure Development: The objective
of this component was to help key counties develop SWM service systems,
wastewater and water supply systems, cultural heritage management, riverbank
improvement measures, and capacity for environmental monitoring and project
management. This component supported the construction of a wide range of works,
including wastewater treatment plants (WWTPs), landfills, solid waste transfer
stations, and pumping stations (See Annex 2).
12. Component 2: Integrated Lake Basin Management: The objective of this
component was to assist the Kunming municipality in establishing better integrated
lake management systems for Dianchi Lake through technical assistance (TA) to
support policy implementation and the development of monitoring systems. This
component supported the construction of several water quality monitoring and data
management platforms, TA to Dianchi Lake management authorities, and the
development of an ILBM Plan.
13. Component 3: Resettlement: This component was intended to support
resettlement of displaced persons in conjunction with the works completed under
Component 1.9
1.6 Revised Components
14. The Fiscal Year (FY) 2011 Additional Financing (AF, See Section 1.7) and the
2015 Restructuring included the following adjustments to the Project’s components
(See Table 2 and Annex 1).
Table 2. Revised and Additional Subcomponents
Note: The Zhaotong Subcomponent, linked to Component 1, was added as part of the AF SUBCOMPONENT ORIGINAL ADJUSTMENT RATIONALE
I.B.2 (ii) Stormwater drainage in Yulong
County (US$6.3 million)
Dropped in 2015
restructuring.
Borrower financed
this activity
separately. IBRD
financing directed to
other subcomponents.
I.C.1 SWM in Funing County (US$5.2
million)
Dropped in 2015
restructuring.
Borrower financed
this activity
separately. IBRD
8 Component 3 did not appear in the PAD due to human error, but was fully incorporated into the project design. 9 No costs were allocated to this component but was instead included in the cost of each subcomponent. Costs were
financed by domestic funds rather than loan proceeds.
![Page 21: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/21.jpg)
5
financing directed to
other subcomponents.
I.B.3(i) Capacity enhancement for Lion
Mountain (US$44.29 million)
Reduced in 2015 restructuring
to US$10.66 million.
Reduced because of
delays in confirmation
of no objection from
National Government
and UNESCO10 that
led to a reduction in
the sub-component’s
scope and domestic-
financing for several
works. Works
accordingly reduced
and savings
reallocated to a new
subcomponent, Shuhe
Ancient Town sewer
expansion.
I.B.3(ii) Lion Mountain study tours
(US$0.02 million)
Dropped in 2015 restructuring Same rationale as
above—surplus funds
reallocated to new
subcomponent, Shuhe
Ancient Town sewer
expansion.
3.B.2 Support for Resettlement activities Inadvertently left out of PAD,
included in LA and
Restructuring Paper
Resettlement financed
by domestic funds
and not loan proceeds.
SUBCOMPONENT
ZHAOTONG
(LINKED TO
COMPONENT 1)
Water supply, WW treatment, and
riverbank restoration in Zhaotong
Added as part of AF Added in response to
client demand.
1.7 Other significant changes
15. As shown in Table 3, the AF introduced a subcomponent under Component 1 for
Zhaotong Municipality. This subcomponent aimed to substantially expand access
to water supply and wastewater services in Zhaotong given the low quality of
service. This subcomponent supported the (1) construction of (i) two water supply
plants (US$22.73 million) with a total capacity of 60,000 cubic meters per day to
increase the population served by an estimated 194,350 people (from 270,050 in
2010 to 464,400 in 2020); and (ii) a 20,000 meter per day WWTP (US$8.22
million) to expand WW access to an estimated 306,700 people (from 190,200 in
2010 to 496,900 residents in 2020); (2) rehabilitation of 48.2 km of river bank
structures (US$27.69 million); and (3) provision of implementation support,
including TA, equipment, and training in operation and management (O&M) of
water supply and wastewate treatment works (US$1.2 million).11
10 Interventions in this site required approvals from State Administration for Cultural Heritage and UNESCO. 11 See Project Paper, Report No. 53586-CN.
![Page 22: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/22.jpg)
6
Table 3. Other Significant Changes
AF
05/27/2010
The Project received an AF of US$60 million to “a)
include Zhaotong [municipality] to support water supply,
WW treatment and riverbank rehabilitation works and b)
continue to improve the effectiveness and coverage of
critical urban infrastructure services in selected counties
through investment in systems for the management of
wastewater, water supply and river rehabilitation in
Yunnan province.”12 LEVEL II
RESTRUCTURING
06/15/2015
In addition to the changes to the Project-level indicators
and subcomponents reflected in Table 1 and 2
respectively, the restructuring included: (a) a revision of
the IOs to better reflect the Project’s scope and context
as well as to promote alignment with the Bank’s core
indicators. Several indicators originally listed in the RF
were dropped (See Data Sheet); (b) an extension of the
Project’s closing date by 22 months to April 30, 2017 to
allow for completion of delayed works, including the
Lion Mountain Cultural Heritage site, Qiubei water
supply system, Puzhehei Lake environmental
improvements, and Zhaotong civil works, and to provide
time to complete additional work in Lijiang financed
with loan savings re-directed from the Lion Mountain
subcomponent; (c) a revision of cost estimates; (d) the
reallocation of loan proceeds amongst categories and
sub-components (See Table 4); (e) an increase in
disbursement percentages for civil works; and (f) the
amendment of the Project Agrrement to include
Government subsidies in cost recovery calculations.
16. As further indicated in Table 3, the restructuring included an adjustment of cost
estimates as well as a reallocation of loan proceeds. Under the restructuring,
US$16.46 million was reallocated between works, goods, and consulting service
categories (See Table 4). At the request of the client, the restructuring also re-
directed US$500,000 from the Zhaotong sub-component to develop a flood risk
warning system in Zhaotong. The restructuring further redirected funds
(approximately US$7 million) from the two dropped subcomponents to add an
additional 20,000 cubic meters per day of wastewater treatment capacity and an
additional 68 km of sewage pipelines in Lijiang to serve an additional 41,500
residents by 2020 (See Section 1.6). The restructuring also amended the definition
of cost recovery contained in the Project Agreement to, in line with common
practice in China, include the Government’s subsidies in the calculation of
“revenues.”
12 See Loan Agreement, August 23, 2010, Loan Number 7937-CN.
![Page 23: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/23.jpg)
7
Table 4. Subcomponent Cost Changes at Restructuring (from Restructuring Paper) SUBCOMPONENT
NUMBER
SUBCOMPONENT
NAME
PRE-
RESTRUCTURING
BUDGET
ALLOCATION
(US$ MILLION)
POST-
RESTRUCTURING
BUDGET
ALLOCATION
(US$ MILLION)
I.A.1(I) Songming Solid
Waste Management
(SWM)
4.51 4.89
I.A.1(II) Xundian SWM 4.47 9.17
I.A.1(III) Luquan SWM 4.69 5.4
I.B.1 Lijiang Ancient
Town SWM
12.57 20.94
I.B.2(I) Lijiang City
Wastewater
Treatment (WWTP)
25.37 32.66
I.B.2(II) Yulong County
Drainage
6.3 0
I.B.2(III) Huaping Wastewater
Treatment (WWTP)
7.12 9.34
I.B.3(I) Lion Mountain
Cultural Heritage
44.29 10.66
I.B.3(II) Lion Mountain
Study Tours
(Capacity
Enhancement)
0.02 0
I.B.3(III) Shuhe Ancient Town
Wastewater (WW)
0 18.17
I.C.1 Funing County
SWM
5.2 7.0413
I.C.2(I) Qiubei County WW 8.55 12.34
I.C.2(II) Guangnan County
WWTP/WW
4.73 6.04
I.C.2(III) Yanshan County
WW
4.99 4.4
I.C.3(I) Puzhehei Water
Environment (WE)
3.48 5.3
I.C.3(II) Funing WE 6.94 8.7
I.C.4 Wenshan Capacity
Enhancement
0.41 0.47
I.D Technical Assistance
(Design, Review,
Construction, etc)
1.5 0
II.A Dianchi Lake
Integrated Lake
Basin Management
10.98 7.38
CONTINGENCIES 21.98 0
TOTAL COST 178.26 162.89
13 This subcomponent dropped and funds re-allocated to Funing Water Environment subcomponent (I.C.3(II)).
![Page 24: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/24.jpg)
8
2. Key Factors Affecting Implementation and Outcomes
2.1 Project Preparation, Design and Quality at Entry
17. Background Analysis. The Project directly supported the Provincial Government’s
growth strategy, which emphasized enhancing urban environmental services,
especially solid waste and wastewater services. The Province was focused on
facilitating sustainable urbanization to preserve Yunnan’s natural scenery and
environment and to maintain its economic growth rates, especially in the tourism
sector. Accordingly, the Project adopted a comprehensive approach to improving
the Province’s urban environment, including cultural heritage management aspects.
The Project also built on experience from previous World Bank-funded projects
like the Yunnan Environment Project (P003599), which highlighted the need for an
integrated, inter-agency approach to improving water quality and overall
management of Dianchi Lake, a signature part of Yunnan’s natural heritage.14
Finally, the Project integrated lessons from World Bank knowledge products such
as “Stepping Up: Improving the Performance of China’s Urban Water
Utilities,” 15 which recommended raising utility tariffs to support sustainable
operation of urban infrastucture. The Bank Team also conducted a technical
analysis during appraisal that evaluated different wastewater treatment
technologies and identified appropriate solutions, such as a hydro-geological
assessment to ensure proper siting of landfills for solid waste management.
18. Assessment of Project Design and Quality at Entry. The Project’s PDO was well-
aligned with Government and sector priorities. Other elements of the Project design,
such as selection of Project sites, were also well-thought-out. The selection of
Project sites followed a criteria-focused two-step process, first for the selection of
municipalities/prefectures and second for the selection of counties within each
municipality/prefecture,16 to ensure that the Project’s investments targeted areas
where urban infrastructure services were most needed, the environment was most
clearly degraded, and institutional and fiscal capacity was favorable. The Project
14 World Bank. 2006. China - Country partnership strategy . Washington, DC: World Bank.
https://hubs.worldbank.org/docs/imagebank/pages/docprofile.aspx?nodeid=7089669 15 See World Bank, Stepping Up: Improving the Performance of China’s Urban Water Utilities.” Washington, DC:
World Bank, 2008. 16 Criteria for the first-stage selection were: National and provincial strategic priority economic development areas;
high degree of pollution; danger of flood and other issues to be remediated through infrastructure investment;
fiscal/budgetary need; inclusion into a group of five high-priority areas; rapid urbanization rates status; status as rural
areas or small towns; speed of tourism development; willingness for World Bank financing; institutional capacity; and
readiness of Project implementation. Criteria for second-stage selection were: Municipal and provincial/prefectural
strategic economic development priority areas; high degree of pollution; urgency; fiscal/budgetary need; urbanization;
rural and small town status; tourism development; willingness of World Bank financing; institutional capacity; and
readiness of Project implementation. On this basis, the following Project counties and municipalities/prefectures were
selected: Kunming Municipality (Luquan, Songming, and Xundian Counties); Lijiang Municipality (Lijiang Ancient
Towen, Huaping, and Yulong Counties); and Wenshan Prefecture (Funing, Guangnan, Qiubei, and Yanshan Counties).
All four of the Wenshan counties were at appraisal nationally-designated poor counties, while two of the Kunming
counties were at appraisal provincially-designated poor counties.
![Page 25: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/25.jpg)
9
also included an innovative subcomponent on biofiltration plants in Puzhehei to
improve water quality at a low cost.
19. However, the “effectiveness” dimension of the PDO was not clearly defined or
reflected in the outcome indicators. The PAD and legal documents indicate that
“effectiveness” of critical urban infrastructure referred to the financial
sustainability of service providers, including by reference to a minimum tariff
needed for WWTPs to achieve cost recovery.17 In the Project Agreement, cost
recovery is defined in terms of both O&M and debt service payments. 18 This
restrictive definition was codified in covenants in the Project Agreement and
required that Project implementing utilities (PIUs) have total revenues, defined as
the sum of operating and net non-operating revenues, above the sum of O&M costs
and the greater of depreciation and debt service amounts in a given year. This
restrictive definition was inappropriate for the context given that China’s central
and provincial governments regularly and reliably subsidize the provision of urban
infrastructure services.
20. Furthermore, the original results framework lacked a Project-level indicator linked
to Component 1, and the Project-level indicator linked to Component 2, which was
focused on data-sharing, did not fully capture the importance of integrated and
inter-jurisdictional management of Dianchi Lake. Overall, the original results
framework did not have adequate Project-level outcome inidicators to fully
measure achievement of the PDO. Finally, the number of IOs (33 are listed in the
PAD, See Annex 3) was excessive.
21. Implementation Arrangements. In line with other Bank-funded projects in China,
the Project adopted a three-tiered implementation system involving: (i) the
Provincial Government; (ii) municipal and prefectural governments; and (iii)
county governments, utilities and investment companies. The Provincial
Government assumed overall responsibility for Project coordination through its
Project Management Office (PMO), housed in the Yunnan Provincial Environment
Protection Department. Municipal governments were responsible for establishing
PMOs within local Environmental Protection Bureaus to oversee the performance
of three to four implementing agencies at the county level. County-level PIUs were
responsible for engineering design and construction supervision, procurement,
contract management, implementation of safeguard and fiduciary measures, and
monitoring and evaluation (M&E). The PAD noted that the provincial PMO was
17 (i) As per the PAD (refer section 3 on PDO and key indicators - pg 3), ‘for the urban infrastructure component, the
key intermediate outcomes are increased access to and improved financial viability of wastewater services and solid
waste management…’; (ii) Also, the cost recovery aspect was also deemed important in the design of the operation
given there were financial covenants for solid waste and wastewater services, as well as indicators in the results
framework.
18 In contrast to the Project Agreement, the Loan Agreement does not specifically define cost recovery.
![Page 26: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/26.jpg)
10
highly capable and had experience working on previous World Bank-funded
projects, and helped to bolster the ability of the sometimes-less capable PIUs to
implement the Project. These implementation arrangements helped achieve the
Project’s urban infrastructure coverage targets. Senior officials at the county level
frequently chaired inter-agency working groups, helping to facilitate construction
planning and other permissions, for example. For SWM facilities, ownership was
initially vested with specially-created construction entities, but later to be
transferred to county-owned enterprises, which were intended to provide sustained
fiscal capacity (See Section 3.3).
22. Assessment of Risks. Most of the relevant risks, including those related to dam
safety and county and local government fiscal capacity, were identified at design.
The Project also identified relevant mitigation measures. For example, to mitigate
the fiscal capacity risk, utilities with low tariff rates relative to operating expenses
were obliged to comply with a financial covenant in the Project Agreement that
required a minimum level of wastewater tariffs to be attained by 2010 and to
develop financial capacity improvement plans.19 Two PIUs completed these plans
before the start of the Project and all utilities complied with the required minimum
tariff levels as per the Project Agreement by the time of the Project’s close.
23. Safeguards. This Project triggered six safeguards: Environmental Assessment
(Operational Policy (OP) 4.01), Natural Habitats (OP4.04), Physical Cultural
Resources (OP4.11), Involuntary Resettlement (OP4.12), Indigenous Peoples
(OP4.10), and Safety of Dams (OP4.37). The Project adequately complied with all
safeguard preparation requisites. The Project was classified as Category A. The
Environmental Management Plan (EMP) prepared for each Project city/county was
comprehensive. Public consultations were carried out with residents of different
ethnicities, gender, and socioeconomic backgrounds. Information about the Project
and announcements of public meetings were widely disseminated online and in
local newspapers in order to facilitate stakeholder engagement.
2.2 Implementation
24. Project implementation was affected by four principal factors: (i) restructuring and
subcomponent changes, which paved the way toward achievement of Project
objectives in the post-restructuring phase; (ii) implementation delays as a result of
weak contract management of some PIUs and slow approval of the cultural heritage
management component; (iii) supervision by the Bank Team; and (iv) government
commitment and capacity at provincial and local levels. These factors are discussed
briefly below.
25. Restructuring and subcomponent changes: Several adjustments made at Project
restructuring enhanced the impact of the Project. For example, the cultural heritage
subcomponent was substantially delayed due to the need to obtain no objection
19 The required tariff level was 0.8 RMB per cubic meter. See Project Agreement Section IV.
![Page 27: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/27.jpg)
11
from the State Administration for Cultural Heritage (and address comments from
UNESCO). As a result of this delay, some of the proposed investments on Lion
Mountain became prohibitively expensive to proceed with. Therefore the
investments were downscaled to include only those critically important to improve
the environment of the area and the allow safe access of visitors (See Section 1.6).
Savings were subsequently re-directed toward expansion of wastewater access in
Lijiang City, which helped the Project achieve its objective to expand coverage of
critical urban infrastructure services and benefitted the operation of the Project-
financed WWTP in Lijiang (See Section 1.7). In Zhaotong Municipality, in
response to client demand, funds were directed to an innovative flood warning
management system, which was requested by the client and met a critical need for
the City to provide flood warning for its rapidly growing urban area. These changes
helped increase coverage of urban infrastructure services, ensuring that the
coverage aspect of the PDO was met. The AF also helped the Project increase and
meet its coverage goals. Restructuring moreover amended the Project Agreement
to aid implementation, as described below.
26. Implementation delays: The Mid-Term Review (MTR) conducted in December
2013 identified two primary issues that contributed to implementation delays,
namely i) low capacity of some county-level PIUs in contract management; and ii)
unexpectedly long time needed to obtain approval for the Lijiang subcomponent
(Lion Mountain) from cultural heritage management authorities. Although these
issues were eventually resolved, the restructuring extended the Project by 22
months. Overall, though, restructuring substantially aided Project efficacy and the
achievement of Project coverage targets, as detailed below. At restructuring the
Project Agreement was also amended to allow for government subsidies, which
was much more appropriate for the Project context.20
27. Supervision by the Bank Team: The Bank Team ably executed several important
supervision tasks, and the 2015 restructuring addressed several important flaws in
the original Project design (see above). The Fiscal Year (FY) 2016 procurement
post-review documented several instances of non-compliance, including the
rejection of a large number of bids based on deviations that could not constitute
“substantial non-responsiveness” as specified in World Bank guidelines, which the
Bank team helped to correct through intervention by the procurement specialist.
Finally, some minor environmental issues were encountered at one of the Project
sites (See Section 2.4). However, timely intervention by the Team and detailed
coordination with PIUs and the PMO helped ensure that these issues had been
corrected by the time of Project’s close (See Sections 2.4 and 5.2). A participatory
process was also adopted for the selection of village sanitation technology in
20 Covenants concered cost recovery for water utility financial covenants, financial statements, and dam safety. Cost
recovery was defined slightly differently for WW and solid waste, but mandated that operating expenses be met
without subsidies. The PA amended the definition of cost recovery so as to define total operating revenues and total
revenues “including government subsidies.”
![Page 28: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/28.jpg)
12
Puzhehei to ensure local needs were addressed in the implementation of the
Puzhehei subcomponent.21 Perhaps most important, however, as noted above, the
Bank team addressed most of the Project’s initial design flaws at restructuring,
paving the way to achieving Component 1 and 2 objectives post-restructuring in
combination with subcomponent changes also processed at restructuring.
28. Government commitment and capacity at provincial and county levels: Overall, the
Provincial and Local Government Authorities demonstrated commitment to the
Project played a key role in facilitating implementation. Vice-mayors frequently
chaired the PIU inter-agency working group, helping improve inter-agency
coordination and advance smooth implementation. This coordination helped ensure
that an environmental issue concerning a leachate spill was quickly resolved (See
Section 2.4). Moreover, at the Provincial level, the Government diligently allocated
the necessary funds for Project implementation and supported compliance with the
Legal Agreement. 22
29. In general, the PMO evidenced a high level of capacity that greatly enhanced
Project efficacy and efficiency and ensured that the Project met and in many cases
exceeded its coverage targets under Component 1 and lake management objectives
under Component 2. However, some gaps were noticeable in the capacity of some
county-level PIUs that negatively impacted Project implementation, particularly by
causing implementation delays of works, as cited above (See para. 26) and, for
example, the mention in one ISR of: “Weak capacity in contract management and
supervision” at county level.23
2.3 Monitoring and Evaluation (M&E) Design, Implementation and Utilization
30. M&E Design. The original M&E design included several indicators to track
progress toward improving the coverage of urban infrastructure services as well as
improving Yunnan’s urban environment. However, the initial Project design
contained two flaws: (i) an excessive number of IOs, many of which were not well-
aligned with Project components and which hindered M&E implementation; and
(ii) a failure to explicitly define “effectiveness of critical urban infrastructure
services.” In the absence of a clear definition of “effectiveness,” a restrictive and
inappropriate focus was placed on cost recovery for Project implementing utilities.
This definition of cost recovery was not suitable for the context, wherein
government subsidies are regularly allocated to support critical urban infrastructure.
The Project restructuring addressed most of these issues. Additional Project-level
outcome indicators were added to reflect the Project’s focus on increasing the
coverage of critical urban infrastructure services as well as on improving
institutional capacity for ILBM. The IOs were streamlined to focus on the Project’s
21 Initially biofiltration was considered as an alternative to conventional wastewater treatment plants, but was rejected
because it was unclear this technology could meet national water quality standards. However, the biofiltration facility
as piloted in Puzhehei where it serves serves a small rural community in which the discharge standards are lower. 22 See Restructuring Paper, Report No. RES18711. 23 ISR Sequence 4, March 29, 2012.
![Page 29: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/29.jpg)
13
direct scope. The restructuring also adjusted the definition of cost recovery to
reflect the Chinese Government's typical practice of subsidizing public services,
better reflecting the Project’s context.
31. Although the PDO itself was not changed at restructuring, the results framework
was substantially modified in a way that improved M&E implementation and
utilization. Several intermediate indicators were dropped and incorporated into
three new Project-level indicators. These were: Number of people in urban areas
provided with access to improved sanitation, which was incorporated into PO-1
(People in urban areas provided with access to wastewater services); Number of
people in urban areas provided with access to improved water sources, which was
incorporated into PO-3 (People in urban areas provided with access to water
services); and Number of new population served by solid waste management
services, which was incorporated into PO-2 (People in urban areas with access to
solid waste management services). These helped to assess achievement of the
coverage dimension of the PDO. However, the post-restructuring results
framework did not include indicators explicitly linked to “effectiveness,” which
could have included indicators linked to fiscal sustainability when government
subsidies are accounted for. Thus, while the restructuring corrected most M&E
design flaws, the definition of effectiveness remained an outstanding issue. Overall,
however, the post-restructuring results framework was greatly strengthened and
better reflected Project objectives.
32. For example, the Project-level outcome indicator described in the PAD, Improved
management and coordination by responsible agencies/bureaus for Dianchi as
evidenced by regular sharing of data among all key bureaus involved, was
incorporated into PO-4 (Improved capacity for Dianchi Lake management). This
new Project-level outcome indicator more accurately captured the underlying
issues with respect to Dianchi Lake management, which pertained not simply to
data-sharing but also a lack of inter-jurisdictional coordination and capacity more
generally. A total of 11 IOs cited in the PAD were dropped during restructuring,
and a further five IOs related to volume of waste deposited in landfills, cultural
heritage management, water quality, flood protection, drainage, and Dianchi Lake
management were revised (See Table 5).24
33. M&E Implementation. Pre-restructuring, the sheer number of indicators was
unwieldly and hindered M&E implementation. This was rectified post-
restructuring however. County-level PIUs consistently provided data on a timely
basis, which the provincial PMO collected along with other data, such as water
quality data on landfills and rivers and waterways feeding into Dianchi Lake,
relevant to assessing Project outcomes.
24 See Restructuring Paper, Report No. RES18711.
![Page 30: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/30.jpg)
14
Table 5: Comparison of Pre- and Post-Restructuring Results Framework. Note: PO-level
indicators underlined; intermediate indicators in italics.
COMPONENT (FROM
PAD)
PRE-
RESTRUCTURING
INDICATOR (FROM
PAD)
POST-
RESTRUCTURING
INDICATOR
URBAN
INFRASTRUCTURE
DEVELOPMENT
Number of new population
served by expanded
wastewater management
service
People in urban areas
provided with access to
wastewater services
URBAN
INFRASTRUCTURE
DEVELOPMENT
COD level at main
discharge points
Total COD pollutant
load reduction (tons/yr)
URBAN
INFRASTRUCTURE
DEVELOPMENT
Collection of tariffs covers
O&M costs and some debt
obligations
Dropped
URBAN
INFRASTRUCTURE
DEVELOPMENT
Number of new population
served by solid waste
management services
People in urban areas
provided with access to
solid waste management
services
URBAN
INFRASTRUCTURE
DEVELOPMENT
Amount of solid waste
being disposed to sanitary
landfills
Volume of municipal
solid waste disposed in
landfill (tons/yr)
URBAN
INFRASTRUCTURE
DEVELOPMENT
Increase in collection rate
(of SWM tariffs)
Dropped
URBAN
INFRASTRUCTURE
DEVELOPMENT
Incidence and severity of
floods as compared to
historical data in terms of
number of people
displaced and extent of
material damage
Development of Flood
Risk Management System
for Zhaotong
URBAN
INFRASTRUCTURE
DEVELOPMENT
Increased frequency and
regularity of water quality
monitoring
Dropped
URBAN
INFRASTRUCTURE
DEVELOPMENT
% targeted pollutant
producers aware of new
regulatory standards
through surveys
Dropped
URBAN
INFRASTRUCTURE
DEVELOPMENT
n/a Length of river section
restored (km)
URBAN
INFRASTRUCTURE
DEVELOPMENT
n/a People in urban areas
provided with access to
water services
CULTURAL
HERITAGE
MANAGEMENT
Development of
rehabilitation plans in
compliance with UNESCO
protection codes and other
national cultural heritage
regulations
Increase in visitors to
Lion Mountain
DIANCHI LAKE
MANAGEMENT
Improved management
and coordination by
responsible
agencies/bureaus for
Dianchi as evidenced by
regular sharing of data
among all key bureaus
involved
Lessons included in
sector 13th FYP,
information system for
Dianchi Lake in place.
![Page 31: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/31.jpg)
15
34. M&E Utilization. The results framework was used by both the PMO and the Bank
Team to assess implementation progress. In particular, the Bank Team used the
coverage indicators to identify and correct potential delays in construction works.25
The revised results framework also benefitted the Provincial Government by
greatly increasing the knowledge base pertaining to Dianchi Lake management.
The Kunming Municipal Environmental Protection Bureau uses the data generated
from the 12 water quality monitoring stations constructed as part of the Project to
track progress towards pollution reduction goals. These stations are being used to
sample water quality once a month on the basis of 35 separate indicators. The
Project also financed the development of information-sharing systems to facilitate
data-sharing between the various entities involved in Dianchi Lake management.
Information provided by the borrower indicates that this data continues to inform
decision-making by these entities, especially related to targeting enforcement of
pollution regulations based on water quality data from different streams and
waterways feeding into Dianchi Lake (See Section 3.2).
2.4 Safeguard and Fiduciary Compliance
35. Compliance with safeguards was rated Moderately Satisfactory throughout
implementation. The Bank received no complaints regarding social and
environmental issues and safeguards compliance. However, as discussed below, the
Project encountered a minor environmental issue during implementation.
36. Environmental Assessment: Despite the existence of the EMPs, the operation of
landfills was sometimes deficient. For example, operators did not consistently spray
water to reduce dust. In addition, the Bank Team encountered and corrected a
leachate spill at one of the landfills caused by improper O&M procedures. The
Team visited the landfill in question and reported that the environmental issues had
been satisfactorily resolved and that landfill management training procedures had
been conducted. Site visits during the ICR mission to the Luquan County and
Songming landfills demonstrated progress in implementing sound O&M, such as
regular compaction and groundwater and leachate monitoring. No subsequent
environmental issues were reported.
37. Natural Habitats: Several of the Project sites fell within protected areas, notably
the Puzhehei National Wetland. For these areas, mitigation measures were
incorporated into the EMPs. The environmental monitoring required in the EMPs
was conducted for most subcomponents, with the exception of the leachate spill, in
a timely manner in order to control potential impacts. The reporting on the
safeguard was exemplary, and the reports have been shared with other project teams
as a demonstration of good practice. Dedicated staff responsible for implementing
the EMPs were stationed at most sites.
25 See for example Aide-Memoire for Third Supervision Mission, April 4 – 9, 2011.
![Page 32: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/32.jpg)
16
38. Physical Cultural Resources: The potential impact of the Project on physical
cultural resources was identified in the environmental assessments completed for
each subcomponent; mitigation measures were included in the EMPs and were
implemented adequately.
39. Indigenous Peoples: At appraisal it was estimated that approximately 400,000
indigenous people might be affected by the Project. As a result, extensive
consultations were undertaken with these populations. An Indigenous Peoples Plan
was prepared and implemented. A social assessment report prepared at appraisal
concluded that the Project was likely to have a highly beneficial impact on
indigenous communities by improving the urban environment, expanding urban
spaces, and improving tourism and other economic development opportunities. The
assessment also concluded that the risk of tariff increases significantly depressing
indigenous peoples’ income was relatively low.26
40. Involuntary Resettlement: At appraisal, the Project estimated that resettlement
would take place in 17 villages and would impact 376 households (1,570 people),
who were resettled under the client-financed Component 3. Individual
Resettlement Action Plans were completed for each subcomponent. Compliance
with resettlement policy was assessed to be Satisfactory during supervision
missions. The Provincial PMO’s highly competent management was essential to
ensuring compliance with applicable Bank policies related to resettlement. The
engagement of an external entity, Hohai University, to monitor resettlement efforts
also contributed to the Satisfactory rating on compliance with safeguards pertaining
to resettlement. The University prepared a report during implementation identifying
experiences, lessons learned, and beneficiary feedback, which helped ensure
compliance with safeguards. There were no complaints registered from displaced
people affected by the Project.
41. Dam Safety: A dam safety review was conducted by an independent dam safety
specialist from the Nanjing Dam Safety Center. The specialist recommended
remedial and supplementary work at two Project sites. The Provincial PMO ensured
that the recommendations were implemented during Project implementation and
proper measures in place for future management.
42. Financial Management: Except for minor issues concerning delays in
disbursement due to staff changes in the Provincial Finance Bureau, the financial
management system for the Project proved to be adequate. The audits revealed no
major issues during implementation, and there were no outstanding audit issues at
the time of the Project’s closure. The Project closed with a Satisfactory financial
management rating.
26 China Cross-Cultural Consulting Center, Sun Yat-sen University. 2007. Social Assessment (Summary Report).
Report No. IPP252-V2.
![Page 33: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/33.jpg)
17
43. Procurement: The appraisal process concluded that the overall procurement risk
was modest, and that agencies at all levels had allocated sufficient resources to
implement the Project. However, the FY16 post review found a few instances of
non-compliance with respect to a bid evaluation that did not constitute substantial
non-responsiveness. Bidders were not given the opportunity to make necessary
clarifications. As a result, the Bank Team directed the PMO to take remedial actions
to prevent recurrence of these issues. These issues were satisfactorily resolved.
Overall, the procurement performance throughtout Project implementiton was
Satisfactory.
2.5 Post-completion Operation/Next Phase
44. As anticipated in the financial analysis conducted at appraisal, the most significant
risk post-completion is, in the eventual absence of subsidies, the fiscal capacity of
local governments to continue providing financial support to PIUs. At Project
completion, several of the SWM operators remained below cost recovery levels
when subsidies are excluded. In China, however, the tariffs are often set below cost
recovery rates given that the Government, especially in China’s poorest provinces,
subsidizes debt service. In recognition of this reality, the Project team amended the
Project Agreement to include government subsidies as part of utilities’ operating
revenue. The Loan Agreement, which stresses the provision of support for
operation and management of solid waste and wastewater facilities,27 does not
define cost recovery, and was not amended. The strong fiscal position of the
Yunnan Provincial Government and Chinese Central Government mitigates cost
recovery concerns substantially and indicates that subsidies will be maintained. The
urban infrastructure services financed by the Project are central to both
governments’ development plans, and both levels of government have proven more
than willing to subsidize elements of utility operation, especially debt service, for
extended periods. The governments’ active involvement will help ensure that a high
quality of service will be maintained post-Project, and in the case of the solid waste
operators that have not achieved cost recovery, the planned transfer to county-
owned enterprises is likely to assure fiscal sustainability (See Section 3.3). Likewise,
the strong commitment of both levels of government to improving environmental
protection make it highly likely that funding for the continuation of environmental
protection activities under Component 2 post-Project will be secure. The continuing
use of data generated by Project-financed monitoring stations for Dianchi Lake
Management further suggests these are likely to be maintained by the province well
into the future.
27 See Schedule 1, Part 1 e)ii)B).
![Page 34: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/34.jpg)
18
3. Assessment of Outcomes
3.1 Relevance of Objectives, Design and Implementation
Relevance of Objectives: Substantial
45. The PDO continues to be highly relevant to Yunnan’s development needs given the
Province’s continued focus on expanding urban infrastructure provision and
enhancing environmental protection. The PDO is aligned with the Provincial
Government’s 13th Five Year Plan, 2016 to 2020 (developed to complement that of
the Central Government), which emphasizes providing cleaner water and
promoting environmental protection.28 The PDO also remains highly relevant to
Strategic Theme 1, Supporting Green Growth, in the current Country Partnership
Framework.29
Relevance of Design and Implementation Pre-Restructuring: Modest. Post-
Restructuring: Substantial.
46. Overall, the Project design was well aligned with the PDO, and the implementation
arrangements with the PMO overseeing PIUs helped the Project achieve its primary
objectives. The Project’s two primary components targeted two issues, urban
infrastructure service provision and Dianchi Lake management, that are of clear
and substantial importance for Yunnan’s urban environment. The Project design
pre-restructuring, however, had several notable shortcomings related to the results
framework. As mentioned earlier, the original results framework lacked a Project-
level outcome indicator related to Component 1 and did not adequately define
“effectiveness.” Moreover, the initial Project-level outcome indicator for
Component 2 emphasized data sharing but did not include other relevant
institutional aspects critical to effective ILBM, especially coordination among
Dianchi Lake management authorities. Finally, the pre-restructuring definition of
cost recovery was overly ambitious given the Government’s typical practice of
subsidizing service. These design-related shortcomings negatively impacted the
Project’s overall efficacy pre-restructuring. Because of these deficiencies, pre-
restructuring relevance of design and implementation is rated Modest.
47. At restructuring, these shortcomings were largely corrected. The revised Project-
level outcome indicator concerning lake basin management addressed the broader
issue of institutional capacity and inter-agency coordination through preparation of
the ILBM Plan and inclusion of lessons learned in the 13th FYP, which guides all
28 Provincial Five-Year Plans closely reflect those of the country as a whole, but emphasize some region-dependent
issues. 29 World Bank. 2006. China - Country partnership strategy . Washington, DC: World Bank.
https://hubs.worldbank.org/docs/imagebank/pages/docprofile.aspx?nodeid=7089669
See also World Bank. 2012. China – Country partnership strategy. Washington, DC: World Bank.
https://hubs.worldbank.org/docs/imagebank/pages/docprofile.aspx?nodeid=67566
(See previous citation note)
![Page 35: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/35.jpg)
19
local government policy and targets. Indicators related to effectiveness of critical
urban infrastructure services, which was indirectly defined in the pre-restructuring
results framework in terms of full cost recovery, were dropped from the results
framework. Moreover, while the PDO reference to “effectiveness of critical urban
infrastructure services” remained undefined and unmodified post-restructuring,
cost recovery was redefined in the Project Agreement to include the Government
subsidies as part of the utilities’ revenues. Accordingly, post-restructuring
relevance of design and implementation is rated Substantial.
3.2 Achievement of PDO
48. The PDO contains two distinct elements: 1) effectiveness and coverage of critical
urban infrastructure services; and 2) effectiveness of lake basin management in
Dianchi.
Improved effectiveness and coverage of critical urban infrastructure services: Pre-
Restructuring: Modest. Post-Restructuring: Substantial.
49. As noted above, Component 1 consists of two distinct elements, effectiveness and
coverage. As detailed below, the Project substantially achieved the objective of
improving the coverage of critical urban infrastructure services. The Project
delivered a comprehensive set of interventions that substantially improved
Yunnan’s urban environment. The Project’s achievement with respect to improved
effectiveness of critical urban infrastructure services, however, is less clear given
the lack of a direct definition of “effectiveness.” However, as of Project close
wastewater operators had adopted specified tariff increases, and several wastewater
operators were on a predictable path to achieving cost recovery.
50. Although the PAD does not explicitly define “effectiveness of critical urban
infrastructure services,” there is evidence in the PAD and the Loan/Project
Agreements that shows the relevance of the utilities’ financial conditions to the
Project’s objetives. For example, the PAD states that “for the urban infrastructure
component, the key intermediate outcomes are increased access to and improved
financial viability of wastewater services and solid waste management.”30 There
are also IOs on cost recovery in the original results framework. Moreover, the pre-
restructuring Project Agreement included financial covenants that required solid
waste service providers to achieve a certain level of solid waste tariffs at an early
stage of implementation and solid waste and wastewater providers to achieve full
cost recovery31 by the Project’s completion. As such, the effectiveness of the urban
30 As noted in Section 1, the financial performance of the service providers were deemed important enough in the
Project design that financial covenants were included in the original PAD results framework for solid waste and
wastewater services. 31 These covenants specify that each WW implementing utility “Ensure that total operating revenues will be sufficient to
cover total operating expenses including provisions for depreciation and the amount by which debt service requirements
exceed the provision for depreciation” while SWM implementing utilities were required to “cover total operating
![Page 36: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/36.jpg)
20
infrastructure services is interpreted as compliance with the financial performance
criteria outlined in the legal documents.
51. Improved Effectiveness and Coverage Pre-Restructuring: The Project substantially
met the original targets with respect to access to improved water sources, SWM
services, and cultural heritage services. As Table 6 illustrates, the achievement of
these coverage-related targets was in general high, and in several cases the results
exceeded the targets. The Project included a comprehensive set of interventions
with respect to solid waste, wastewater, and water supply that improved coverage
for many Yunnan residents. However, the Project did not meet a few water service
coverage indicators, and fell well short of meeting the three indicators related to
improved effectiveness of critical urban infrastructure services. As a result, the pre-
restructuring efficacy on the effectiveness and coverage dimension of the PDO is
rated as Modest.
52. Improved Effectiveness and Coverage Post-Restructuring: The Project fully
achieved the coverage aspect of its development objective post-restructuring,
accelerating progress towards meeting its coverage targets and substantially
improving urban residents’ access to water, wastewater, and SWM services. The
Project achieved the associated post-restructuring Project-level outcome indicators
(See Data Sheet), which measured access to these services as a result of the Project.
The Project exceeded its target for the “number of people provided with access to
wastewater services” indicator by over 20,000 people, a considerable achievement
given the low rates of access to wastewater treatment in the Province (See Section
1.1). The Project also exceeded its target for the “number of people with access to
SWM services,” providing over 450,000 with SWM services through the
construction of sanitary landfills and waste transfer stations. This level of access
represented a more than two-fold increase over pre-Project levels. The Project also
surpassed the target number of people in urban areas with access to water services
by over 100,000 people.
53. In addition, the Project achieved its objective to improve the coverage of critical
urban infrastructure services with respect to river environment, cultural heritage,
and flood warning. The Project exceeded intermediate objectives for length of river
section restored (IO-3, 103 percent achieved), number of visitors to Lion Mountain
(IO-4, 106 percent achieved), and development and adoption of a flood risk
management system for Zhaotong that provides not only a tool for better
management of flood and water resources, but also a template to guide urban
development to reduce future flood risk32 (IO-5, 100 percent achieved; See Data
Sheet). The selected physical achievements of each subcomponent are also
expenses of garbage collection services, transfer stations, and landfill operations, excluding provision of depreciation for
landfill construction capital cost.” As noted earlier, this definition was later amended to allow for government subsidies
as part of utility operating revenues. The Loan Agreement was not modified.
32 See Borrowers’ ICR.
![Page 37: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/37.jpg)
21
summarized in a table in Annex 2. Overall, the Project produced a comprehensive
set of interventions that improved wastewater and SWM service coverage,
improved lake basin management, reduced flood risk, and improved the quality of
the river environment.
54. By the time of Project close, Project cities and counties had instituted wastewater
tariffs equal to or greater than the level specified in the original Project Agreement,
thereby complying with it (0.8RMB per cubic meter) and, under the revised
definition of cost recovery, two of the five SWM Project implementing utilities
were able to meet O&M expenses with tariff revenues. The remaining three SWM
utilities are expected to be able to meet O&M expenses in the near future when, as
has always been planned, their operation is transferred from the construction
companies that built them to permanent, county-owned enterprises which will
oversee long-term operations (See Section 3.3). Moreover, as noted above, in the
context of China achieving full cost recovery is not necessarily a pre-requisite to
ensuring the provision of reliable urban infrastructure services. Accordingly, post-
restructuring the Project substantially met its effectiveness objectives, and
accordingly is rated as Substantial.
Improving the effectiveness of lake basin management in Dianchi: Pre-Restructuring:
Substantial. Post-Restructuring: Substantial.
55. Improved Effectiveness Pre-Restructuring: The Project contributed to the
establishment of an online data-sharing and information platform as well as a data
processing system to monitor water quality. The Project financed construction of
three fixed automatic monitoring stations for waterways entering Dianchi Lake,
two mobile monitoring vehicles to sample smaller streams and equipment for a
water quality laboratory. In addition, 14 fixed water flow monitoring stations were
procured or constructed. 33 The Project also completed an ILBM Plan (discussed
below) and monitored three major rivers in the Dianchi Lake Basin at a frequency
of over 21,000 times per year. Though this is slightly less than originally envisioned
due to a change in sampling frequency, the combination of these information and
data-collection systems substantially strengthened the capacity of Dianchi lake
basin management authorities to cooperate and share data to facilitate better
decision making. Moreover, new regulations concerning protection of Dianchi
Lake that were related to the ILBM Plan were approved in September 2012 and
have been in effect since January 1, 2013. Thus, the pre-restructuring efficacy on
the lake basin management dimension of the PDO is rated Substantial.
56. Improved Effectiveness Post-Restructuring: During the restructuring, the IOs in the
RF related to lake basin management were dropped and the PO was modified.
However, the Project fully achieved both the original and the revised PO targets. In
compliance with the revised PO, lessons from the ILBM Plan for Dianchi Lake
were incorporated into the Five-Year Plan. Moreover, the completion of the ILBM
33 Data provided by PMO.
![Page 38: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/38.jpg)
22
Plan represented a major step forward for coordination among Dianchi Lake
management authorities as no previous plan existed for the region. Project
investments in water quality data collection and sharing, such as construction of the
water monitoring equipment described above, moreover provided a knowledge
foundation for better lake basin management. Accordingly, post-restructuring
efficacy on the lake basin management dimension of the PDO is rated Substantial.
Table 6: Project Achievement by Indicator, Pre- and Post-Restructuring. Note: PO-level
indicators underlined; intermediate indicators in italics.
PDO DIMENSION PRE-
RESTRUCTURING
INDICATOR
% OF TARGET ACHIEVED POST-RESTRUCTURING
INDICATOR
% OF
TARGET
ACHIEVED
IMPROVED
EFFECTIVENESS
OF CRITICAL
URBAN
INFRASTRUCTURE
SERVICES
Operating cost
covered by SW fee
revenues
0-88%
(Avg. = 26%)
Dropped Not
Applicable
Collection of tariffs
covers O&M costs and some debt
obligations (WW)
0%
Dropped
Increase in collection
rate of SW services
N/A (Dropped before implementation) Dropped
IMPROVED
COVERAGE OF
CRITICAL URBAN
INFRASTRUCTURE
SERVICES
Population served by
WW Management System
77-176%
(Avg. = 118%)
People in urban areas provided
with access to WW services
103%
Number of people in
urban areas provided with access to
Improved Sanitation
62% 100%
Number of population served by
SWM services
118-173% (Avg = 150%)
People in urban areas provided with access to SWM services
102%
Amount of solid waste disposed to
sanitary landfills
87-157% (Avg. = 114%) Volume of municipal solid waste
disposed in landfill
141%
People in urban
areas provided with access to improved
water sources
80% People in urban areas provided
with access to water services
115%
WW management -- COD level
100%
Total COD pollutant load
reduction
180%
% of Wenshan
polluters aware of new regulations
100%
Dropped
Frequency of
Wenshan water
monitoring
100% Dropped
Lijiang Development
Masterplan
100%
Increase in visitors to Lion
Mountain
106%
![Page 39: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/39.jpg)
23
Lijiang UNESCO
Status
100%
Dropped
Incidence and
severity of floods as compared to
historical data in
terms of number of people displaced and
extent of material
damage
Not available
Development of Flood Risk
Management System for Zhaotong
100%
Rainwater drainage
population served
Not Available
Length of river section restored
103%
IMPROVED
EFFECTIVENESS
OF LAKE BASIN
MANAGEMENT
Improved
management &
coordination as evidenced by regular
sharing of data
among all key bureaus involved
Data Sharing platform in place
and in use
Improved capacity for Dianchi
Lake Basin management
100%
Number of
monitoring on 3
rivers (times/yr)
25%
Dropped
Number of
monitoring on 14
streams (times/yr)
<1%
Dropped
Online monitoring and evaluation
system established
(Y/N)
Y
Dropped
Data processing
system established
(Y/N)
Y
Dropped
Dianchi protection
regulations are
revised, approved
and enforced
Y
Dropped
ILBM Master Plan
for Dianchi is developed and
adopted, particularly
conducting water resource carrying
capacity of the lake
basin
Y
Dropped
![Page 40: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/40.jpg)
24
3.3 Efficiency
Rating: Substantial.
57. Efficiency is assessed with respect to three aspects: (i) economic efficiency in terms
of economic internal rate of return (EIRR); (ii) financial viability and sustainability;
and (iii) administrative and operational efficiency. Each aspect is discussed below.
Economic Efficiency
58. At appraisal, a cost-benefit analysis was carried out utilizing a contingent valuation
method based on the responses to a willingness-to-pay (WTP) survey. For each
category of investment, namely wastewater collection and treatment, solid waste
collection and disposal, and river rehabilitation, a Project town was chosen as a
representative site for estimating the EIRR. While wastewater and river
rehabilitation investments showed ample estimated returns of 19.934 percent and
18.2 percent respectively, the solid waste investments only showed an estimated
EIRR of 5.2 percent. This low EIRR was likely the result of the fact that many peri-
urban residents had a surface-level understanding of public sanitation and did not
consider the public health implications of poor solid waste collection and
management.
59. Following the appraisal-stage methodology, the EIRR of each category of
investment was reassessed at completion to reflect: (i) the actual scope of
investments in all Project locations; (ii) the actual scope of Project impact; and (iii)
the actual Project costs. Although the WTP for each category of investment has
almost certainly increased due to rapid growth in income over the Project
implementation period, the analysis maintained the WTP from appraisal to be
conservative.
60. At completion, all categories of investments yielded higher EIRRs than the
estimates at appraisal. (see Table 7 below)
Table 7. EIRR appraisal vs. completion APPRAISAL COMPLETION
WASTEWATER 19.9%
(10.2% cost
adjusted)
24.5%
SOLID WASTE 5.2% 7.6%
RIVER
REHABILITATION
18.2% 28.8%
▪ WW collection and treatment yielded an EIRR of 24.5 percent, higher than the
appraisal-stage estimate of 19.9 percent (not to mention the cost-adjusted
34 At appraisal, the cost of wastewater investments was underestimated due to a longer pipeline resulted from the
expansion of the wastewater subcomponents as described in Section 1.6. Once factored in, the estimated EIRR on the
wastewater at appraisal would decrease from 19.9 percent to 10.2 percent .
![Page 41: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/41.jpg)
25
estimate, based on predicted equipment and materials costs, of 10.2 percent at
appraisal). Two factors contributed to the high EIRR: (i) a higher service ratio
in terms of households served per unit of capacity constructed; and (ii) a better
cost ratio in terms of total system investment (collection and treatment) per unit
of capacity constructed. More people were served at a lower total cost than
initially expected.
▪ SW collection and disposal yielded an EIRR of 7.6 percent, higher than the
appraisal-stage estimate of 5.2 percent and the prevailing economic discount
rate of 6.0 percent. The primary reason for the higher EIRR is a higher service
ratio in terms of households served per capacity constructed.
▪ River rehabilitation yielded an EIRR of 28.8 percent, higher than the appraisal-
stage estimate 18.2 percent. The primary reason for the higher EIRR is a higher
investment-to-service ratio in terms of number of households served per dollar
invested.
61. Thus, from the perspective of economic efficiency, the Project’s performance is
high.
Financial Viability and Sustainability
62. Both the PAD and Project Agreement placed strong emphasis on the financial
viability and sustainability of Project cities/counties and their subordinate
implementing utilities in terms of their cost and debt service coverage ratios.35
However, compliance with these provisions is complicated by the fact that the
implementing utilities are merely operating companies without ownership of fixed
assets registered on their balance sheets. Local governments are responsible for
capital investments along with debt service obligations. In essence, local
governments provide full capital subsidies to all Project implementing utilities.
Under this institutional arrangement – explicitly permitted under the amendment to
the Project Agreement in 2015 — (i) any debt service coverage requirement is
automatically met; and (ii) utilities only need to recover their O&M expenses to
meet the cost recovery requirement.
a. WW: All five Project wastewater utilities comply with the Project
Agreement-mandated tariff rate of 0.8RMB per cubic meter; and they also
fully recover costs when local government capital subsidies are accounted
for (See Table 8).
35 The Project Agreement specifies that a solid waste Project utility’s total revenues, i.e., the sum of its operating and
net non-operating revenues, must the sum of its O&M costs and the greater of depreciation and debt service in a given
year. The Project Agreement was later modified to allow for government subsidies to be counted as part of utility
operating revenue. The Loan Agreement does not define cost recovery, and was not modified.
![Page 42: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/42.jpg)
26
Table 8. Project Wastewater Utility Reported Revenues and Expenses COUNTIES WITH
WW SERVICES
CURRENT LEVEL
OF EXPENSES (AS
PER PA
DEFINITION)
CURRENT LEVEL
OF REVENUES
(W/O SUBSIDIES)
CURRENT LEVEL
OF REVENUES
(WITH CAPITAL
SUBSIDIES)
LIJIANG ANCIENT
TOWN DISTRICT
WWTP
RMB 1.76/ m3 Average: RMB1.10/
m3 (2017)
Average: RMB 1.89/
m3/ (Jan. 1, 2018)
Full cost recovery with
debt service paid by
government
YANSHAN O&M approx. RMB
0.90/ m3
Full: RMB 1.26/ m3
Residential: RMB 0.80/
m3
Non-residential: n/a
Approximately RMB
1.20/ m3 (w/subsidy)
QIUBEI n/a Residential: RMB 0.80/
m3 (to government)
WTTP under
government paid
management &
operating contract)
Full cost recovery with
government paid
management and
operating contract
GUANGNAN RMB 1.10/ m3 Residential: RMB 1.00/
m3
Full cost recovery with
debt service paid by
government
ZHAOYANG RMB 1.26/ m3 Residential: RMB
1.00/ m3
Non-residential: RMB
1.25/ m3
http://shuifei.zhutousan
.net/zhaotong.html
Full cost recovery with
debt service paid by
government
a. SW: the provisions concerning cost recovery for solid waste utilities were
amended at restructuring. In practice, the operator’s revenue is not directly
linked to the market tariff. Instead, local governments pay the operator a
fixed annual lump sum to cover its O&M costs. During the ICR mission,
three operators reported that the subsidies they received from the
government were not sufficient to cover their O&M costs, raising some
concern with respect to fiscal sustainability in the long-term. However, in
all three cases, the operators were construction companies temporarily
managing operation of the sites. Once the sites are, as was always planned,
conferred to county-owned enterprises, the situation is expected to improve
because county-owned enterprises have more direct and reliable access to
government financing and revenues (See Table 9).
63. Thus, from the perspective of financial viability and sustainability, the Project’s
performance is assessed as Substantial.
Administrative and Operational Efficiency
64. Implementation proceeded smoothly after restructuring, and the Provincial PMO
capably addressed several minor issues encountered during implementation
including weak contract management capacity in some county-level PIUs (See
Section 2.1). However, a longer-than-expected period of time to obtain “cultural
heritage” approvals for the Lion Mountain activities did reduce implementation
efficiency.
![Page 43: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/43.jpg)
27
65. Thus, from the perspective of administrative and operational efficiency, the
Project’s performance is rated as Modest.
Table 9. Project SW Utility Reported Expenses and Revenues
COUNTIES
WITH SW
SERVICES
CURRENT LEVEL
OF EXPENSES (AS
PER PA
DEFINITION)
CURRENT LEVEL OF
REVENUES (W/O
SUBSIDIES)
SONGMING
COUNTY SW
Annual O&M: RMB
800,000
+ investment
Residential: RMB
10/HH/month
XUNDIAN SW Annual O&M: RMB
2,070,000 + investment
Residential: RMB
2/HH/month
LIJIANG SW n/a Residential: RMB
8/HH/month
LUQUAN SW Annual O&M: RMB
1,914,000
+ investment
Residential: RMB
6/HH/month
3.4 Justification of Overall Outcome Rating
Rating: Moderately Satisfactory
66. Although the Project’s PDO remained unchanged over the life of the Project,
several PDO and output indicators were amended during the restructuring. As a
result, the Project’s outcome is evaluated against both the pre- and post-
restructuring PDO indicators (See Table 10).
Table 10: Relevance, Achievement of PDO and Efficiency Ratings Pre- and Post-
Restructuring PRE-
RESTRUCTURING
POST-
RESTRUCTURING
RELEVANCE OF
OBJECTIVES
Substantial Substantial
RELEVANCE OF
DESIGN &
IMPLEMENTATION
Modest Substantial
PDO1: IMPROVING
THE
EFFECTIVENESS
AND COVERAGE OF
CRITICAL URBAN
INFRASTRUCTURE
SERVICES
Modest Substantial
PDO 2: IMPROVING
THE
EFFECTIVENESS
OF LAKE BASIN
Substantial Substantial
![Page 44: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/44.jpg)
28
MANAGEMENT IN
DIANCHI
EFFICIENCY
Substantial Substantial
RATING
Moderately
Unsatisfactory
Satisfactory
RATING VALUE 3 5
WEIGHT (%) 55 45
WEIGHTED VALUE 1.65 2.25
Final Rating 3.9 i.e. Moderately Satisfactory
3.5 Overarching Themes, Other Outcomes and Impacts
(a) Poverty Impacts, Gender Aspects, and Social Development
67. Poverty Impacts. Poverty reduction was not an explicit objective of the Project.
However, at appraisal, four Wenshan counties were nationally designated as poor
counties, while two of the Kunming counties were provincially designated poor
counties. These designations suggest that the Project disproportionately benefited
citizens of urban areas who were poorer than the national and provincial averages.
68. Gender Aspects. The Project did not include a gender component, but stakeholder
consultation workshops held as part of the environmental assessment attempted to
secure balance in gender representation. Globally, the burden of poor access to
water and sanitation is moreover felt disproportionately by women, so it may be
expected that Project achievements might disproportionately benefit women,
though this was not explicitly evaluated as part of the results framework.36
69. Social Development. Social development was not an explicit objective of the
Project. However, in Zhaotong, investments in river bank improvements inspired
additional local government investment in walking, jogging, and biking paths along
the river banks, enhancing local residents’ quality of life.
(b) Institutional Change/Strengthening
70. The Project’s support of an ILBM Plan strengthened authorities capacity to manage
Dianchi Lake. To formulate the Plan, a special management agency was established
that brought together several previously disparate and uncoordinated entities. In
addition, as a result of the Project, the Dianchi Management Bureau developed
several subsidiary plans. The Bureau also engaged external experts to ensure that
the Plan reflected international best practice. The Bureau and City’s ownership of
the new management strategy was further highlighted by the fact that the Plan was
listed as one of the City’s achievements for the year 2016.
36 See U.N. HABITAT, “Sanitation: A Women’s Issue,”
http://mirror.unhabitat.org/documents/media_centre/APMC/Sanitation%20-%20A%20womans%20issue.pdf
![Page 45: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/45.jpg)
29
71. The Project also helped strengthen the capacity of local PIUs. In Zhaotong City, for
example, the PIU reported that it had developed and implemented a financial
monitoring system for the local government as a result of the Project.
(c) Other Unintended Outcomes and Impacts (positive or negative)
72. The Project supported the development of the first flood warning and management
system (via a smart phone application) for the rapidly-growing city of Zhaotong.
The application is being used to provide citizens with advance warning of flash
floods in low-lying municipal areas.
3.6 Summary of Findings of Beneficiary Survey and/or Stakeholder Workshops
Not Applicable
4. Assessment of Risk to Development Outcome
Rating: Substantial
73. The failure of some PIUs to achieve full cost recovery by Project close introduces
some degree of risk to the “effectiveness”-related outcomes achieved by the Project.
However, these outcomes represent only part of the Project, and the coverage-
related outcomes of the Project are not at risk. Moreover, overall, the commitment
of the Chinese central and Yunnan provincial governments to maintaining water
supply, wastewater, and SWM services remains strong, mitigating the overall risk
that services will be substantially disrupted as a result of failure to achieve cost
recovery. At the time of Project close all Project cities/counties had adopted the
wastewater tariff levels specified in the Project Agreement and were in compliance
with the modified definition of cost recovery in the amended, post-restructuring
Project Agreement. Furthermore, the fiscal position of SWM operators is expected
to improve considerably pending transfer to county-owned enterprises (See Section
3.3).
5. Assessment of Bank and Borrower Performance
(a) Bank Performance in Ensuring Quality at Entry
Rating: Moderately Unsatisfactory
74. The Bank Team adequately positioned the Project in the existing policy context and
applied thorough technical knowledge to identify the most suitable technologies.
The Project’s design also built upon previous projects and lessons learned. The
Bank properly identified environmental and social safeguard risks and incorporated
adequate mitigation measures in the Project design. Nevertheless, there were
significant gaps in the Project’s results framework as originally designed. The pre-
restructuring results included no Project-level outcome indicators linked to the
![Page 46: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/46.jpg)
30
coverage aspects of the PDO and limited the objective of improved effectiveness
of lake basin management to increased data-sharing. Finally, effectiveness was not
properly defined with respect to critical urban infrastructure services.
(b) Quality of Supervision
Rating: Moderately Satisfactory
75. The Team took appropriate steps to respond to implementation challenges, such as
the leachate spill from a Project-funded landfill (See Section 2.4). After the leachate
spill, the Team directed all landfills financed by the Project to develop O&M
procedures and undergo O&M training. Moroever, the Team processed a
comprehensive restructuring that successfully addressed flaws in the original
Project design, downscaled several subcomponents and redirected funds to higher-
priority activities. During this process, the Project Agreement was amended to
reflect a more appropriate definition of cost recovery, though this was not reflected
in changes to the Loan Agreement. In addition, the Team accommodated client
requests for beneficiary-driven subcomponents, such as the Zhaotong flood
warning management system. However, effectiveness of urban infrastructure
services remained undefined.
(c) Justification of Rating for Overall Bank Performance
Rating: Moderately Satisfactory
76. Based on the Moderately Unsatisfactory Quality at Entry rating and the Moderately
Satisfactory Quality of Supervision rating, overall Bank performance is rated as
Moderately Satisfactory.
5.2 Borrower Performance
(a) Government Performance
Rating: Moderately Satisfactory
77. As noted in Section 2.2 there were some challenges to implementation in the pre-
restructuring phase due to delays in constructing works. Overall, however, the
Yunnan Provincial Government demonstrated commitment to the Project and
offered support to the Project when needed. The commitment of county
governments was evidenced by the participation of high-level officials, usually the
vice-mayor, in site visits and meetings (See Section 2.2).
(b) Implementing Agency or Agencies Performance
Rating: Moderately Satisfactory
78. The Provincial PMO exhibited minor shortcomings in procurement processes,
including an instance in which the bidding process was not conducted in accordance
with Bank procedure (See Section 2.4). However, the Provincial PMO acted
properly and professionally in referring this case to the Bank. Overall, the
Provincial PMO was responsive to Bank supervision missions and took proper
![Page 47: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/47.jpg)
31
steps to address issues encountered in implementation. This competence was
particularly evident in the Provincial PMO’s satisfactory compliance with all
safeguards and promotion of activities that added value to Project investments, such
as the Zhaotong flood warning system. Nevertheless, some PIUs at the county level
demonstrated capacity gaps, particularly in contract management, leading to delays
in the implementation of works.
(c) Justification of Rating for Overall Borrower Performance
Rating: Moderately Satisfactory
79. Based on the Moderately Satisfactory Government Performance and Moderately
Satisfactory Implementing Agency Performance, overall Borrower Performance is
rated as Moderately Satisfactory.
6. Lessons Learned
80. Country Context: One of the most important lessons from this Project is to pay
careful attention to the country context in setting financial targets. While the Project
design emphasized cost recovery that included debt service obligations (which is
usual in World Bank projects), in the Chinese context, it is more important to
consider O&M expenses, since provincial and national governments typically
finance debt payments for urban infrastructure services. The design of this Project
would have been improved, for example, by having realistic indicators tied to the
fiscal sustainability of utilities when government subsidies are accounted for.
Furhtermore, there should be recognition that full costs are often covered through
a combination of tariffs (paid by users) and taxes (through financial support
provided by the government) and they both should be adequate and adjusted to meet
costs. In this Project, the reliance on financial support from the government was not
originally incorporated in the cost recovery plans which led to revisions of the
Project Agreement to reflect the actual situation.
81. Comprehensive Approach to Improving Urban Environmental Service
Provision: This Project’s successfull expansion of key urban environmental
services was notable given its comprehensive approach; the Project included not
only key infrastructure like water supply and WWTPs but also cultural heritage
management and lacustrine water quality. In principle, there are considerable
advantages to attempting to address all of these issues in a comprehensive fashion.
But in practice, this comprehensive approach increased the complexity of the
Project, and introduced delays, especially with respect to the cultural heritage
subcomponent. Future Projects should i) ensure that the implementing agencies
have adequate capacity to undertake all facets of the approach, as was for the most
part the case with this Project; and ii) through frank dialogue with the client identify
highest-priority interventions to ensure all Project subcomponents possess natural
synergies that justify simultaneous implementation. Infrastructure development is
moreover often not sufficient to fully evaluate the success of a Project long-term,
and the results framework should incorporate a range of indicators that reflect
![Page 48: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/48.jpg)
32
indirect impacts of increased service provision, such as for example exposure to
waterborne illnesses which may be expected to be drastically reduced through
improved water infrastructure service coverage.
82. Importance of institutional factors, such as inter-institutional coordination, to
solve complex environmental challenges : Task teams should devote careful
attention to the multiple factors, especially institutional capacity, that underpin
effective coordination and management of inter-jurisdictional resources. The
Project’s successful development of an ILBM Plan was largely the result of
effective coordination between multiple provincial government agencies
responsible for management of Dianchi Lake. Future efforts to address complex
environmental challenges, such as non-point source pollution, should not
underestimate the importance of implementing effective coordination mechanisms.
Accordingly, future Projects focused on addressing such issues should include
inter-jurisdictional coordination capacity, perhaps defined in terms of
representation and frequency of meeting for an inter-jurisdictional commission or
body, as a core element of the desing and indicators.
7. Comments on Issues Raised by Borrower/Implementing Agencies/Partners
(a) Borrower/implementing agencies
Overall comments:
It is highly appreciated that the ICR was deliberated and revised by taking PMO’s
comments into consideration.
It is still considered that the overall project outcome shall be assessed or evaluated
against the post-restructuring result framework and amended LA and PA. As
indicated in the revised ICR, the Project fully achieved the coverage aspect of its
development objective post-restructuring, substantially improving urban residents’
access to water, wastewater, and SWM services. Moreover, in the context of China
achieving full cost recovery is not necessarily a pre-requisite to ensuring the
provision of reliable urban infrastructure services, and accordingly, the Project
substantially met its effectiveness objectives post-restructuring. The post-
restructuring relevance of objectives, relevance of design & implementation,
improving the effectiveness and coverage of critical urban infrastructure services,
improving the effectiveness of lake basin management in Dianchi and efficiency are
all rated as substantial.
Certainly the pre-restructuring indicators could be used for assessment of project
design and quality at entry for the purpose of lessons learned. Also, as indicated in
the revised ICR, those shortcomings of project design and quality at entry were
largely corrected at restructuring.
![Page 49: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/49.jpg)
33
So, from PMO’s point of view, the overall project outcome shall be rated as
Satisfactory, although we don’t fully understand the Bank’s assessment system,
especially the scoring criteria.
(b) Co-financiers
Not Applicable
(c) Other partners and stakeholders
Not Applicable
![Page 50: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/50.jpg)
34
Annex 1. Project Costs and Financing
(a) Project Cost by Component (in USD Million equivalent)
Loan 7692-CN
Component Cost at Project
Completion
Cost Estimated at
Appraisal
Cost at Completion as %
of Estimated
Urban Environment Infrastructure
Development 156.71 166.46 94%
Integrated Lake Basin Management 13.70 11.80 116%
Resettlement included in components
above
included in components
above
Institutional Strengthening & Capacity
Building included in components
above
included in components
above
Interests During Construction 0.88 12.77 7%
Front-end Fee 0.23 0.23 100%
Total Project Costs 171.52 191.26 90%
Loan 7937-CN (AF)
Component Cost at Project
Completion
Cost Estimated at
Appraisal
Cost at Completion as %
of Estimated
Water Supply 54.76 49.58 110%
Wastewater 14.63 17.21 85%
River Rehabilitation 37.69 60.89 62%
Resettlement included in components
above
included in components
above
Institutional Strengthening & Capacity
Building 1.11 1.20 92%
Interests During Construction 0.94 8.44 11%
![Page 51: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/51.jpg)
35
Front-end Fee 0.15 0.15 100%
Total Project Costs 109.28 137.47 79%
(b) Financing
Loan 7692-CN Financing Source At Appraisal
(US$ Million)
Revised
(US$ Million)
Borrower 88.26 72.89
International Bank for Reconstruction and Development 90 90
Total 178.26 162.89
Loan 7937-CN Financing Source At Appraisal
(US$ Million)
Revised
(US$ Million)
Borrower 68.88 64.56
International Bank for Reconstruction and Development 60 60
Total 128.88 124.56
![Page 52: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/52.jpg)
36
Annex 2. Outputs by Component
Component 1. Improving the effectiveness and coverage of critical urban
infrastructure services in selected counties
This component was designed primarily to increase access of urban residents to three
critical services: wastewater, solid waste management, and water supply. These
investments were further expected to help Yunnan meet the challenges of rapid
urbanization while also improving environmental quality and quality of life for urban
residents. This component depended on proper financial management by local Project
implementation units, county governments, and municipally-owned utilities and
enterprises, which operated wastewater treatment plants, water supply infrastructure, and
waste management services. The following seven outcome indicators were identified in
the PAD for measuring the achievement. Three of them are PDO outcome indicators, and
the others are intermediate outcome indicators.
PDO Outcome Indicators:
• Cumulative number of urban residents with access to wastewater treatment
services
• Cumulative number of urban residents with access to solid waste management
services
• Cumulative number of urban residents with access to water supply services
Intermediate Outcome Indicators:
• Total reduction in Chemical Oxygen Demand pollutants loads achieved under the
Project (tons per year)
• Volume of municipal solid waste disposed in landfills (tons per day)
• Length of river section restored (kilometers)
• Increase in number of visitors to Lion Mountain Park (total number of people)
The physical achievements of this component (excluding the AF) are summarized in
Tables 11 and 12 below:
Table 11: Project Physical Achievements by Subcomponent (excludes AF)
SUBCOMPONENT LOCATION SELECTED PHYSICAL
ACHIEVEMENTS
I.A.1.I Kunming 450,000 cubic meter sanitary landfill; 30
ton/day leachate treatment facility; 1 waste
transfer station; 300m access road; associated
equipment for collection and site operation;
closure of existing dumping site.
I.A.1.II Kunming 600,000 cubic meter sanitary landfill; 2 waste
transfer stations; 70 ton/day leachate treatment
station; associated equipment for collection and
site operation; closure of existing dumping site.
![Page 53: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/53.jpg)
37
I.A.1.III Kunming 319,000 cubic meter sanitary landfill; 50
ton/day leachate treatment station; 1 waste
transfer station; associated equipment for
collection and site operation; closure of
existing dumping site.
I.B.1 Lijiang 2.19 million cubic meter sanitary landfill; 9
waste transfer stations, 200 ton/day leachate
treatment station; 3.95 km access road;
associated equipment for collection and site
operation; closure of old landfill site.
I.B.2.I Lijiang 20,000 cubic meter/day wastewater treatment
plant; 311 km of sewers
I.B.2.II Lijiang 129.74 km sewer network
I.B.2.III Lijiang 6,000 cubic meter/day wastewater treatment
plant; 35.74 km sewer network
I.B.3 Lijiang 35 high-powered electric lights, Lion Mountain
access road, trash receptacles, parking lot;
afforestation of 1505m2 and landscape lighting
I.C.2.I.A Wenshan 8km water transfer pipe, 6,000 cubic meter/day
water pumping station, 14 km water supply
pipe
I.C.2.I.B Wenshan 6,000 cubic meters/day wastewater treatment
plant and 850m access road, 14.8 km sewer
network
I.C.2.II Wenshan 8,000 cubic meter wastewater treatment plant,
15.29 km sewer network
I.C.2.III Wenshan 27.25km sewer network, 4.4 km pressure pipe
pipe and channel for discharge of effluent from
WWTP, lifting pump of 10,000 tons/day
I.C.3.I Wenshan 6.17 km drainage ditches and associated
filtration infrastructure
I.C.3.II Wenshan 6.6 km river bank restoration, 1548m
boardwalk construction, and afforestation of
2322 square meter.
I.C.4 Wenshan 1 Environmental monitoring vehicle, 4
emergency protective clothings procured
Component 2. Improving the effectiveness of Dianchi Lake Management
This component was intended to address acute water pollution in Dianchi Lake, which was
largely attributed to coordination challenges between the multiple governments and entities
charged with improving water quality and managing the lake basin. This component
largely took the form of an Integrated Lake Basin Management plan which was formulated
through a consultative process and laid out a master vision for development and
environmental protection of the lake. This component also financed associated water
quality monitoring infrastructure. One PDO outcome indicator was specified to measure
progress toward the objectives of this component.
This component, aside from producing a lake basin master plan, also produced an online
data-sharing platform and associated access system; installed water quality monitoring
equipment; and generated tens of thousands of water quality monitoring records.
![Page 54: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/54.jpg)
38
PDO Outcome Indicators:
• Improved capacity for Dianchi Lake management
Component 3. Resettlement
This component was concerned with managing resettlement related to the Project,
especially compliance with safeguards. No PDO outcome or intermediate indicators were
specified for this component.
Additional Financing
The following subcomponents were added as part of the Additional Financing:
Part 1. Urban Environmental Infrastructure Development
Develop critical urban environmental infrastructure in Zhaoyang District of Zhaotong
Municipality as follows:
(a) Development of wastewater and water supply systems, including expansion of wastewater
treatment plants; construction of sewage collection and drainage networks; construction of
water supply treatment plants and networks and construction of water transmission mains.
(b) Carrying out of investments to improve management of the river environment, including
construction and rehabilitation of river embankments, and dredging of rivers, all to mitigate
against erosion and floods and control and scale down pollution and restore the river eco-
system.
(c) Provision of support for the implementation of Project activities, including:
(i) with respect to Zhaoyang District of Zhaotong Municipality, provision of technical
assistance and equipment for supervision of environmental infrastructure
construction and for environmental monitoring; and
(ii) with respect to other implementing agencies and entities, provision of technical
assistance, training courses and study tours to assist in:
(A) detailed engineering design, design review, procurement management and
contract supervision;
(B) operation and management of water supply, wastewater and river
management facilities; and
(C) building capacity for Project management and operation.
Part 2. Resettlement
![Page 55: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/55.jpg)
39
Carry out resettlement and rehabilitation of Displaced Persons in connection with the
implementation of Part 1 of the Project.
Table 12. Project Physical Achievements by Subcomponent under AF
SUBCOMPONENT LOCATION SELECTED PHYSICAL
ACHIEVEMENTS
(a)(i) Zhaotong 25.79 km water transfer pipe; 2 water
treatment plants of 60,000 m3/day; 1 pumping
station of 20,000 m3/day; 83.46 km water
supply distribution pipes.
(a)(ii) Zhaotong 20,000 cubic meters/day extension of
wastewater treatment plant and 48.92 km
sewer network
(b) Zhaotong 45.35 km river rehabilitation; environmental
monitoring equipment and waste collection
facilities; as well as flood risk management
system
![Page 56: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/56.jpg)
40
Annex 3. Economic and Financial Analysis
Not required.
![Page 57: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/57.jpg)
41
Annex 4. Bank Lending and Implementation Support/Supervision Processes
(a) Task Team members
Name Title Unit
Joanna Mclean Masic Sr Urban Specialist GSU09
Zheng Liu Procurement Specialist GGOPP
Fang Zhang Sr Financial Management Specialist GGOEA
Dan Xie Program Assistant EACCF
Huiying Guo Huiying Guo EACCF
Meixiang Zhou Sr Social Development Specialist GSU02
Scott Michael Moore Young Professional GWA02
Shunong Hu Sr Water Engineer GWA02
Sing Cho
Sr Water Supply and Sanitation
Specialist GWA02
Xin Ren Sr Environmental Specialist GEN2A
Eddie Hum Sr Municipal Engineer Consultant
Mantang Cai
Cultural Heritage and Watershed
Specialist Consultant
Yan Li Economist and Financial Specialist consultant
![Page 58: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/58.jpg)
42
Annex 5. Beneficiary Survey Results
Not Applicable
![Page 59: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/59.jpg)
43
Annex 6. Stakeholder Workshop Report and Results
Not Applicable
![Page 60: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/60.jpg)
44
Annex 7. Summary of Borrower's ICR and/or Comments on Draft ICR
Note: the following is a summary of Borrower’s Implementation Completion Reports for
YUEP and the AF provided by the Borrower.
CHINA
YUNNAN URBAN ENVIRONMENT PROJECT AND ITS ADDITIONAL
FINANCING
SUMMARY OF BORROWER’S IMPLEMENTATION COMPLETION
REPORTS
1. Assessment of Project Objective, Design and Implementation
1.1 Key Project Data
Country People’s Republic of China
Project Name Yunnan Urban Environment Project and its Additional
Financing
Project Number P096812 / P117819
Loan Number 7692 / 7937-CN
Totoal Financing US$ 150 Million (US$ 90 M / US$ 60 M )
Loan Terms
A single currency, variable spread loan, with a maturity of
25 years, incl. an 8-year grace period, and a front-end fee
of 0.25%
Total Estimated Project
Investment
RMB 2,235.33 Million (RMB 1,300.53 M / RMB 934.80
M)
Environmental Category A
Dates of Loan/Project
Agreement July 22, 2009 / August 23, 2010
Effectiveness Dates September 30, 2009 / November 15, 2010
Original Closing Date June 30, 2015 / June 30, 2016
Extended Closing Date April 30, 2017
1.2 Background
1. Yunnan is endowed with rich natural resources in the agriculture, mining and power
sectors as well as in its scenic landscape and cultural heritage. The province’s diverse
cultural heritage includes 25 ethnic minority groups comprising 40 percent of its population
and contributing to a strong tourism industry. Yunnan has experienced robust economic
growth over the past two decades. GDP growth has averaged 8.9 percent. During 2000–
2005, GDP per capita grew from RMB 4,600 to RMB 7,800. Yunnan Province faces urban
development issues on two fronts: (i) the need to develop urban environmental
infrastructure for future growth promotion in secondary urban centers; and (ii) the need to
![Page 61: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/61.jpg)
45
reverse environmental degradation in its largest urban centers caused by the robust
economic growth in the past. The major aim of Yunnan Urban Environment Project
(YUEP) and its Additional Financing (AF) was thus to assist the province in addressing its
lagging basic urban infrastructure.
1.3 Assessment of Project Objective
2. The project development objective (PDO) of YUEP and its AF is to assist Yunnan
Province in improving the effectiveness and coverage of critical urban infrastructure
services in selected counties and effectivenss of lake basin management in Dianchi lake,
through investments in systems for the management of wastewater, water supply, solid
waste, river environment and cultural heritage.
3. The PDO reflects the problems of lagging basic urban infrastructure and the
demands to urgently address them in development of Yunnan Province. The project focus
on the construction of municipal wastewater and solid waste collection and treatment
facilities and integrated management of river/lake environment while is combined with the
improvement of integrated management effectivenss of Dianchi lake basin. It is consistent
with the growth strategy set in Yunnan’s 11th Five-Year Plan, the development policies in
outline of China’s 11th Five-Year Plan and also the key strategic pillars in the Bank’s
Country Partnership Strategy for China.
1.4 Assessment of Project Design
4. The YUEP consists of two pillars: (i) county towns urban environmental
infrastructure development; and (ii) integrated lake basin management infrastructure
investments. The total project investment is estimated at RMB 1,300.53 million, of which
the loan is $90.00 million. Component I: County Towns Urban Environmental
Infrastructure Development would help the selected counties in Kunming, Lijiang and
Wenshan develop critical urban environment service infrastructure by developments of
solid waste management services systems and wastewater and waster supply systems,
cultural heritage management, river improvement measures and capacity building for
environmental monitoring. Component II: Integrated Lake Basin Management would
assist Kunming in establishing more integrated lake management systems in Dianchi Lake
basin through technical assistance in policy actions and development of monitoring
systems. Refer details to the Project Appraisal Document (Report No.: 41199-CN).
5. The AF components for Zhaotong is estimated at RMB 934.80 million, of which
the loan is $60.0 million, including: (a) development of wastewater and water supply
systems, including expansion of wastewater treatment plants, construction of sewage
collection and drainage networks, construction of water supply treatment plants and
networks and construction of water transmission mains; (b) carrying out of investments to
improve management of the river environment, incl. construction and rehabilitation of river
embankments and dredging of rivers; (c) provision of support for the implementation of
project activities. Refer details to the Project Appraisal Document (Report No.: 53586-
CN).
6. Project Restructuring. On the premise that the PDO and total loan amount remained
unchanged, the project restructuring was made and completed in June of 2015 with
approval by the Bank, while the closing dates for both YUEP and its AF were extended to
April 30, 2017 .
![Page 62: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/62.jpg)
46
7. Assessment of project design. In general the project design and preparation are
satisfactory: (i) the project focus on construction of municipal wastewater and solid waste
collection and treatment facilities and integrated management of river/lake environment,
reflecting the issues and demands of Yunnan Province; (ii) the selection of project locations
is consistent with local economic and social development masterplan and special
plannings, fully reflecting the consensus and will of local government and people; (iii) the
alternatives for site selection and process were considered and analyzed in the feasibility
studies and the practical technologies available in market used in the project designs; (iv)
the project procurement plan (PPP) was feasible and the arrangements for implementation,
financial management and disbursement were in accordance with characteristics of the
complex and large-scale project.
8. Major issues in project design: (i) financial covenants designed originally for cost
recovery of wastewater and solid waste management by tariff/fee revenues were actually
difficult to be implemented to meet the requiements and had to be revised in the project
restructuring; (ii) the implementing agency (IA) and the Bank’s team were overly
optimistic about satisfying the general condition for the subcomponent of Lion Mountain
Cultural Heritage Preservation in Lijiang, moreover both sides’ understanding on the
condition was quite different during project implementation, which led to a long delay of
this subcomponent; (iii) most of IAs and local project management offices (PMOs) at levels
of muncipality/prefecture and counties were the first to implement the Bank’s financed
project and lacked of knowledge and experiences on project management, but it was lacked
of enough training for them in project design.
1.5 Assessment of Project implementation
9. Project Management. The project management chain at three levels of governments
was well maintained in general during project implementation. With strong support from
provincial leading committee for the project, provincial PMO and local PMOs strengthened
communication with the Bank’s team and seriously performanced their respective
responsibilties. Overall project management is highly appreciated by the Bank’s team.
10. Procurement Management. The PMOs organized updating of the PPP annually or
as needed, urged and guided the IAs to carry out procurement activities according to the
PPP approved by the Bank. For YUEP, total of 88 contracts (civils 69, goods 15 and
services 4) were awarded with the cumulative prices of about RMB 861.0 million. For AF,
total of 24 contracts (civils 18, goods 4 and services 2) awarded with the cumulative prices
of about RMB 537.58 million.
11. Implementation of Resettlement Action Plan (RAP). The PMOs, IAs and local
related authorities actively coordinated and organized implementation of land acquisition,
demolition and resettlement, and there was no incident of any petition or appeal by affected
persons during project implementation, which created favorable conditions for the project
construction. For YUEP, the permanent land of 959 Mu was acquisited and the
houses/structures of 22,200.6m2 demolished, with about 940 Mu and 41,724m2 less than
the planned respectively, and the temporary land of 1,174.74 Mu borrowed, with increase
of about 506 Mu more than the planned. Total payment of RMB 132.74 million was made
for compensation and resettlement. For AF, the permanent land of 224.38 Mu was
acquisited and the houses/structures of 6,336 m2 demolished, with about 10 Mu and 1,653
m2 less than the planned respectively, and the temporary land of 2,223.37 Mu borrowed,
![Page 63: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/63.jpg)
47
with increase of about 968 Mu more than the planned. Total payment of RMB 58.69 million
was made for compensation and resettlement.
12. Implementation of Environment Management Plan (EMP). The PMOs, IAs and
local related environmental authorities seriously implemented measures proposed in the
EMPs of project and reduced short-term adverse environmental impacts during project
construction to an acceptable level. There was no significant environmental accident or
compliant during project implementation.
13. Financial Management. A relatively stable and complete financial management
system was maintained during project implementation: (i) Yunnan Finance Bureau (YFB)
established the designated accounts for the project and timely made the reibmursement; (ii)
the IAs established the independent account for accounting of the project; (iii) the
provincial PMO periodically consolidated the financial statements of subcomponents, and
reported it to the Bank in time; (iv) an annual audit was regularly made on implementation
of the project, and the aduit reports were submitted to the Bank in time.
14. Performance of Legal Covenants. The PMOs, IAs and related authorities closely
cooperated and actively took measures and actions to performance and satisfy legal
covenants of the project in terms of the Loan Agreement (LA) and Project Agreement (PA).
15. Monitoring and Evaluation (M&E). The PMOs organized carring out the M&E on
project implementation, including: (i) continuous tracking and monitoring implementation
progress; (ii) carring out external independent M&E on implementation of RAPs
periodically; (iii) monitoring of environmental status during construction and operation;
(iv) monitoring and updating of indicators in the Results Framework to reflect the progress
of project implementation.
2. Assessment of Outcome against Agreed Objective
2.1 Outcome/achievement of objective
16. Through implementation of the project, a number of urban environmental
infrastructures had been built, and then the effectiveness and coverage of urban
infrastructure services are further improved in selected counties and the effectivenss of
integrated lake basin management of Dianchi lake further improved. The PDO of YUEP
and its AF is achieved.
17. For YUEP:
(i) 4 new sanitary solid waste landfills and 13 waste collection and transfer stations
were built with total capacity of 515 tons/day, while a number of associated
equipments were procured for clearning, collection and treatment of solid waste.
In project areas, the cumulative number of people in urban areas with access to
solid waste management services is increased from 182,000 in 2009 to 453,800
in 2016.
(ii) 4 new wastewaer treatment plants (WWTPs) were built with total capacity of
40,000 m3/day, and sewage main and branch collectors and home connectors
constructed with total extension of 506.7 km. Additional 27.25 km of sewage
system and drainage pipe was constructed and rehabilitated in Yanshan County.
In project areas, the cumulative numbe of people in urban areas with access to
![Page 64: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/64.jpg)
48
wastewater services is increased from 159,800 in 2009 to 485,200 in 2016.
(iii) With implementation of Lion Mountain Cultural Heritage Preservation
subcomponent in Lijiang, the access road of about 2 km, ecological parking areas
of 4,246.83 m2, greeing areas of 1,505 m2 and landscape lighting facilities were
completed. The mountain’s ecological environment and landscape were
improved and the visitors to the park are increased year by year, reaching about
79,200 person-times in 2016.
(iv) Also in Wehshan, (a) the existed No.1 water treatment plant (WTP) was
renovated and associated raw water transmission of 8 km, a pump station and
distribution network of about 14 km built. The cumulative numbe of people in
urban areas provided with access to water services was increased from 49,000 in
2009 to 96,000 in 2016; (b) with implementation of integrated water environment
(IWE) management of Puzhehei Lake in Qiubei, 6.17 km of villages’ drainage
ditches, 3 soil infiltration treatment systems and 2 surface-flow wetlands with
total treatment capacity of 500 m3/day as well as such facilities as garbage
collection pits and pins, public and household latrines, etc were constructed,
which effectively control major pollution load into the lake and obviously
improve the water quality of lake and ecological landscape of lakeshore; (c) under
the subcomponent of IWE management of Puting River in Funing, the
mainstream and tributaries were rehabilitiated with total lengthe of 6.6 km, which
greatly improved the river environment and ecological landscape along rivers,
and also make county town’s flood control standard increased from five year to
thirty year return; (d) 1 environmental emergency monitoring vehicle including
equipments, 1 automatic chemical analyzer and 4 emergency protective clothings
were procured under the environment management technical assistance for
Wenshan Prefecture, which filled its gap in environmental emergency monitoring
apparatus and response capability.
(v) Under Component II: (a) with implementation of monitoring and management
system for Dianchi Lake basin, 3 water quality automatic monitoring stations and
14 water monitoring stations for rivres into the lake and 1 water quality
monitoring station were built, 2 movable water quality monitoring stations
(vehicles) and 2 sampling vehicles (incl. equipment) procured, and a total
pollutant emission monitoring and management system developed. More than
300,000 of monitoring data have been generating since the stations for Jinjia,
Haihe and Luolong rivers were put into operation, providing the data support to
environmental management sectors. (b) a long-term integrated management
masterplan for Dianchi Lake basin was prepared, in which the idea and tool of
international advanced integrated basin management was introduced, an overall
strategic and forward-looking planning proposed for the resource development,
environmental governance, ecological protection and economic and social
development, based on comprehensive development and protection of water
resources and subject to constraints of comprehensive carrying capacity of
resources and environment in the basin.
18. For AF components:
(i) 2 new WTPs were built with total designed treatmnet capacity of 60,000 m3/day,
![Page 65: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/65.jpg)
49
25.79 km of raw water transmission mains and 83.46 km of water distribution
networks constructed, bringing local water supply capacity to 100,000 m3/day.
The cumulative numbe of people in urban areas provided with access to water
services is increased from 270,000 in 2009 to 400,000 in early 2017.
(ii) Expansion of the existed WWTP was completed with capacity of 20,000 m3/day,
bringing local treatment capacity to 80,000 m3/day, and 97.92 km of sewage
collection networks constructed. The cumulative numbe of people in urban areas
with access to wastewater services is increased from 190,000 in 2009 to 320,000
in 2017.
(iii) The rivers’ courses in total length of 45.32 km were rehabilitiated, including
40.63 km of embankments constructed or reinforced, 5 bridges constructed or
restructured and dredging of rivers at amount of about 520,000m3, which make
rivers’ ecological environment improved, and rivers’ flood discharge capacity
and flood control standard enhanced.
(iv) Also, 78 sets of environmental monitoring equipment and 1 environmental
emergency monitoring vehicle were procured, which filled the gap that local has
no environmental monitoring capacity; 12 garbage transportation vehicles and
collection facilities were procured, which lays a foundation for eliminating urban
black-odor water bodies; a flood risk management system was developed, which
provides not only a tool for better management of flood and water resources, but
also a guidance for urban development to cope with stormwater drainage and
flood risk management in future, and moreover further improve local
comprehensive ability of disaster prevention and reduction.
2.2 Project cost and financing
19. For YUEP, as of the closing date:
• total project investment is completed at RMB 1,154 million, accounting for 88.7%
of total estimated project investment;
• total amount of loan is disbursed at US$ 72.28 million, equivalent to RMB 471.25
million, accounting for 40.8% of total project investment completed and 80% of
the loan amount approved, respectively;
• total amount of counterparts is completed at RMB 682.75 million, accounting for
59.2% of total project investment completed.
20. For AF components, as of the closing date:
• total project investment is completed at RMB 730.32 million, accounting for 78.1%
of total estimated project investment;
• total amount of loan is disbursed at US$ 59.45 million, equivalent to RMB 387.20
million, accounting for 53.0% of total project investment completed and 99% of
the loan amount approved, respectively;
• total amount of counterparts is completed at RMB 343.12 million, accounting for
47.0% of total project investment completed.
2.3 Assessment of project benefits
21. Environmental benefits. Through implementaton of the project:
(i) The system for municipal solid waste collection, transportation and disposal is
![Page 66: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/66.jpg)
50
further improved in project areas. As of the closing date, the cumulative amount
of municipal solid waste disposed at landfill has been 1.114 million tons since 4
built sanitary landfills were put into trial operation or operation, making lcoal
municipal sanitation and appearance improved and pollution by municipal solid
waste reduced.
(ii) The system for municipal wastewater collection and treatment is further
improved in project areas. As of the closing date, the wastewater has been
cumulatively terated at amount of about 55.2 million m3 with removed COD
pollution load of about 10,900 tons since 4 built WWTPs and extension of
Zhaotong WWTP were put into trial operation or operation, which made
contribution to total emission reduction of COD in whole province, and play a
promoting role in improving water qualities of Jinsha River system in upper
reaches of Three Gorges Reservoir and river system in Pearl River basin.
(iii) The situation of sewage discharged directly into rivers was allevated, pollution of
municipal solid waste to rivers reduced, and river environment and ecological
landscape along rivers improved by integrated river rehabilitation in project areas.
(iv) The ecological environment of Lion Mountain was improved, and unique style
and beautiful environment of the Ancient Town expanded and extended by
cultural heritage preservation, which promots the protection of heritage sites in
Lijiang
(v) The point and non-point pollution into Puzhehei Lake in Qiubei County was
effectively reduced, sanitation conditions of villages in vicinity of lake improved,
water quality of the lake improved obviously by integrated environment
management of the lake.
(vi) Capacity building makes local environmental monitoring and emergency
response capabilities improved, and provide scientific data support and
supervision means for local environmental protection.
(vii) The long-term integrated management masterplan for Dianchi Lake basin would
have a positive guiding role in improving fund use efficiency, reducing
governance costs and improving the level of basin management.
(viii) In short, it has regional and basin eco-environmental status be improved, local
urban function improved, and contradiction between urban development and
environmental constraints further alleviated, which create a suitable environment
for sustainable social and economic development in project counties.
22. Social Benefits. Through implementaton of the project:
(i) The system and neworks of local urban environmental infrastructure services are
further improved, local construction of urban infrastructure and urbanization
accelerated, and subsequently urban function promoted and urban development
space expanded.
(ii) Local investment environment is improved, which enhances investor’s
confidence and attracts investment and provides new opportunity for local
economic development, and then enhances local city's competitiveness.
(iii) The flood dischareging capacities of river courses are enhanced, local urban flood
control standards increased and flood disaster risk reduced by rivers
![Page 67: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/67.jpg)
51
rehabititation.
(iv) In project areas, more permanent jobs are created, and a large number of
temporary jobs were added by the construction during project implementation.
(v) The capacity building of environmental protection institutions and technical
progresses of environmental monitoring, scientific research and management
were promoted, the efficiency and effectiveness of government’s environmental
management improved and the environmental awareness of residents be further
increased in project counties.
(vi) A group of project management personnels being familiar with the Bank’s
policies and procedures had been trained and their capcities improved by learning
and practicing the Bank’s criteria and advanced management mode, which creates
favorable conditions for local utilization of foreign capital and international
cooperation in future.
23. Economic benefits. Through implementaton of the project:
(i) It promotes and increases local tourism development and tourism revenue in
project areas. In 2016, Lijiang received a total of about 35.20 million visitors and
total revenue was RMB 60.876 billion, with an increase of 15.18% and 25.91%
over the same period in 2015, respectively. In Qiubei County, it received a total
of about 3 million visitors and total revenue was RMB 1.69 billion in 2015, and
3.11 milliion visitors and revenue of RMB 1.792 billion from January to
November of 2016, with an increase of 13.7% and 16% over the same period,
respectively. In Zhaoyang District, it received a total of about 3.28 million visitors
and total revenue was RMB 1.919 billion in 2016.
(ii) The appreciation of local land is indirectly promoted by improving and expanding
the coverage of urban infrastructure services and improving surrounding
environment of urban areas in project counties.
(iii) Public health is further improved, and moreover the health costs reduced and the
quality of life of residents in project areas improved directly or indirectly, through
improving local urban environmental sanitation and reducing risk of infectious
diseases and health hazards by water pollution and municipal solid waste.
3. Major Factors Affecting implementation and Outcome
3.1 Factors outside the control of government or implementing agency
24. They are summarized as following:
(i) After effectiveness and implementation of the project, the rate of US dollar
against RMB continued to decline, and loan funds in dollar terms was shrunk.
Such changes made greater pressure on raising of counterparts by local
governments and IAs.
(ii) Meanwhile domestic prices were rising, especially labor costs raised rapidly, e.g.
the comprehensive price of labor’s man-days per unit was increased from BMR
34.77 in 2009 to RMB 53.23 in 2011in Yunnan Province. The increases of labor
and material prices caused the project costs increased.
(iii) A new Standard for Pollution Control on the Landfill Sites of Municipal Solid
Waste (GB16889-2008) was issued after project appraisal, in which more strictg
![Page 68: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/68.jpg)
52
requirement is provided for leachate treatment. Subsequently, the works of
leachate treatment stations were added in 4 subcomponents of solid waste
mangement and then their project costs increased accordingly.
(iv) For the Lion Mountain cultural heritage preservation of Lijiang, due to its location
in the world cultural hertiage site, the IA had been applying for its endorsemnet
according to the requirement in the PA, and made all procedures completed and
confirmed by the Bank’s team until the end of 2014, which caused it be delayed
for long time, and had to made changes and reductions to its works.
(v) The consultant firm that undertook techncial assistance of design review,
construction supervision and utility operation support forYUEP was difficult to
mobilize and provide expert resources according to the contract signed, and
termincated the contract in October 2013, which increased difficulties for project
implementation and management, althought remedies were taken by employing
individual consultants to provide services based on approval by the Bank’s team.
(vi) At the early of implementation after effectiveness of the project, it was just the
time when the state was to promote economic growth and respond to the global
financial crisis by expanding investment and stimulating domestic demands.
There existed a certain time difference for some subcomponents that were also
financed by the funds for expanding domestic demands and national debt not only
to meet domestic time requirements for construction, but also to sastify the
Bank’s procurement procedures, which increased difficulties for project
implementation and management.
3.2 Factors generally subject to government control
25. They are summarized as following:
(i) The Bank's methods and requirements for bid evaluation are not exactly the same
as those domestic practices, resulted in great challenge to the procurement
maangement, e.g., the IAs and procurement ageney were used to domestic
procedure and practices, moreover the time for bid evaluation was short and some
robust practices made without clarifications in time, which caused repeated
process of reviewing bid evaluation report by the Bank and affected the progress
of project implementatioin.
(ii) For the subcomponents of river rehabilitation, it has a long range and the
complicated topographic and geological conditions and surroundings along the
route, while more towns were involved and greater coordination required. The
delay of land acquisiton once occurred in process of implementation had a certain
impact on execution of works.
(iii) For the subcomponent of Qiubei County WWTP and sewer network, some
planned sewers were cancelled in process of implementation due to readjustment
to masterplan of county town’s, which had an impact on management of contract
being executed. It was also similar to the implementation of subcomponents under
AF components.
3.3 Factors generally subject to implementing agency control
26. The factors are summarized as following:
(i) Local PMOs and IAs at levels of municipality/prefecuture and counties were
![Page 69: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/69.jpg)
53
unfamiliar with the Bank’s procedure and requirements for procurement, contract
management and reimbursement, and lacked of knowledges and experiences on
the Bank’s financed project, which affected implementation progress of the
project to a certain extent.
(ii) It lasted for longer time for the implementation of the Bank’s finaced project.
During implementation, some IAs’ key personnel such as legal person, finance
person and project manager were changed; and also the employed design institute
and procureent agency changed, which caused it could not give full play to
training provided on project management in early, and had an impact on the
continuity of project management.
(iii) For some subcomponents, after being invitated for bids, there eixsted evident
deviation between actual topographic and geological condition and quantities of
works and those designed, due to inadequate survey, delayed updating of maps,
insufficient design, imperfect bidding documents or without conditions for
execution, resulted in that acutal quantities of works were substantially increased
and variations ocurred in process of execution, which caused more difficulties for
project management.
(iv) Local designers were not understood and used to the specific design concept and
use of computer model for verification, as required by the Bank’s experts, which
caused a long delay of river rehabilitation and water supply networks under AF
components.
(v) Some supervision companies employed were lacked of experiences on contract
management for the Bank’s financed project, moreover understaffed and
performanced inadequately, which had an impact on project implementation and
loan reimbursement.
(vi) Some IAs did not made payment in time for works completed according to terms
of the singed contract, on consideration of possible changes of final price in
domestic audit, or not timely made the completion acceptance and environmental
acceptance of works completed, which caused reimbursement for eligible
expenditures of the project affected to a certain extent.
(vii) For some IAs, the communication was not timely made between their financial
manager and project managers, and their budget management was weak, which
caused an impact on raising of counterparts for the project.
4. Sustainability
27. A series of policies issued by the state and local government provide the sound
policy environment for the sustainability of wastewater and solid waste treatment facilities
constructed as well as river management under the project.
28. The facilities built under the project had been transferred to owners or operating
companies for their O&M. The tariff on municipal wastewater and solid waste had been
implemented in project counties. Although revenues from tariff collection are not sufficient
to cover the costs for landfilling and wastewater treatment expenses, local governments
have been providing subsidies for O&M of the facilities, which ensures the sustainability
of the project.
![Page 70: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/70.jpg)
54
29. The online monitoring system of WWTPs built has been linked with environmental
protection sector, and COD reduction by WWTP is included in assessment of local
government’s target for total emission reduction of major pollutants, which enforced to
ensure operation of WWTPs. Also in Wenshan, it is actively promoting trusteeship of
wastewater treatment services by professional company, which is beneficial to ensure the
O&M of WWTPs.
30. Following to the implemention of AF component in Zhaoyang District, it is
continuing to increase investment for landscape greening along rivers, water replenishing
of rivers and integrated management of surrounding of river courses, and to bring rivers in
urban areas into the scope of long-term governance.
5. Bank and Borrower Performance
5.1 Bank
31. The Bank’s overall performance is satisfactory during identification, desing and
preparation, appraisal and implementation of the project. The diligence and professional of
the Bank’s team was highly appreciated by the local government sectors at all levels, PMOs
and IAs.
32. Identification, preparation and appraisal. Through field investigations and
discussions with local authorities and agencies, the Bank’s team carried out a large number
of project screening and identification based on the development plans of project sites, and
advanced many good suggestions for project design and preparation.
33. Implementation. the Bank’s team carried out the supervison on project
implementation progress every half a year on average, to have discussed issues in the
implementation, provided guidance and support for the PMOs and IAs and jointly
promoted implementation of the proect, by focusing on the PDO. All of which ensured
successful implementation of the project and achievement of the PDO.
5.2 Borrower
34. The Borrower’s overall performance is satisfactory during project preparation,
approval and implementation. The concerned state’s authorities and governemnts and
related authorities at levels of province, project municipalities/prefecture and counties had
paid high attention and strong support to the project.
35. Preparation and appraisal. The coordination leading groups and MPOs were
established at levels of the province, project municipalities/prefecture and counties, and
organized the IAs and consultant institutions to have carried out overall project preparation
in accordance with the domestic procedures for capital construction and requirements for
the Bank’s financed project, through input of a lot of human, physical and financial
resources. All of which effectively ensured that project preparation, appraisal and
negotiation were successfully completed.
36. Implementation. The governments and related authorties at all levels maintained
the strong commitment and support to the project. The PMOs, in particular the provincial
PMO, seriously performed their respective responsibilities for project management and
actively coordinated and guided the IAs to have carried out project design, land acquisiton
& resettlement, procurement, construction, reimbursement, accounting and financial
![Page 71: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/71.jpg)
55
management as well as performance of project leagal documents and subsidiary
loan/agency agreements.
6. Experiences and Lessons Learned
6.1 Experiences
37. The experiences from the project implementation are summarized as following:
(i) The governments and related authorities had paid high attention and strong
support to the project and maintained relative stability of project management
institution, which ensured successful implementation of the project and
achievement of the PDO.
(ii) By practicing the rules and procedures of procurement and contract management
for the Bank’s financed project, local IAs and related sectors and institutions
obtained more management mode, method and experiences, and then their
capacities further enhanced.
(iii) It is useful to make potential adverse environmental impacts during project
construction be well alleviated by including major contents and requirments of
the EMPs in bidding documents and signed contracts to increase the binding on
contractors.
(iv) The IA’s ownership and conscientiousness had a significant impact on ensuring
the successful project implementation and O&M of facilities built. For the
subcomponent in Guangnan County, not only the implemention progress and
project investment were effectively controlled, but also the built facilities were
well operated and maintained, which has a good reference for construction and
O&M of a similar WWTP in county.
(v) The practice by introducing idea and method of ecological sanitation and
community participation in the IWE management of Puzhehei Lake in Qiubei
County provides the experience and reference for planning, design and
implementation of similar project.
(vi) The long-term integrated management masterplan for Dianchi lake basin, by
introducing the ieda of integrated lake basin management, has a positive guiding
role in improving fund use efficiency, reducing governance costs and improving
basin management level.
(vii) The application of computer models for optimizing construction drawing designs
of river rehabilitation and water supply networks, and the practice for
conservation and restoration of such historical structures as ancient hydraulic
drop in rivers as well as a the digital system of flood risk management under AF
components provide the experiences and references for similar project.
6.2 Lessons learned
38. The lessons learned from the project implementation are summarized as following:
(i) It shall be designed to provide more training for PMOs and IAs who are the first
time to implement the Bank’s financed project during prepation and
implemention, including training on project implementation and O&M of
facilities to be built.
![Page 72: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/72.jpg)
56
(ii) The IAs shall pay full attention to preparations of project to be implemented,
including topographic, geological and site surveies, etc., to avoid substantial
variations and more difficultes for project implementation and contract
management.
(iii) The IAs shall strengthen management of supervision companies employed, and
urge them to be staffed with adequate and competent supervisors and in place, so
as to do well quality control, schedule control and cost control of the project.
(iv) The IAs shall attach importance to the O&M of the facilities built under the
proejct, and early consider the arrangements for O&M of the facilities to be
constructed during project implemention, so that ensure transition of built
facilities to regular operations.
(v) The IAs and PMOs shall keep their personnel relatively stable and maintain the
same design institute, procurement agency and/or supervison company under the
same project, as far as possible, to ensure the continuity of project management
and give full play to the role of related training under the project.
(vi) for the Bank’s finaced project in future, it shall strengthen communication with
the Bank’s team to understand well the Bank’s safeguards and its requirements
timely, and desing a more practical and operable convenant or action plan for the
project.
![Page 73: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/73.jpg)
57
Annex 8. Comments of Co-financiers and Other Partners/Stakeholders
Not Applicable
![Page 74: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/74.jpg)
58
Annex 9. List of Supporting Documents
(1) Borrower’s Project Completion Report.
(2) China Cross-Cultural Consulting Center, Sun Yat-sen University. 2007. Social
Assessment (Summary Report). Report No. IPP252-V2.
(3) NPC & CPPCC National Committee Annual Sessions. 2006. Facts and figures:
China’s main targets for 2006-2010. http://www.gov.cn/english/2006-
03/06/content_219504.htm
(4) World Bank. 2010. Project Paper, Report No. 53586-CN.
(5) Project supervision documents, Aides-Memoires, and ISRs.
(6) World Bank. 2015. Restructuring Paper, Report No. RES18711.
(7) World Bank. 2006. China - Country partnership strategy . Washington, DC:
World Bank.
https://hubs.worldbank.org/docs/imagebank/pages/docprofile.aspx?nodeid=70896
69
(8) World Bank. 2012. China – Country partnership strategy. Washington, DC:
World Bank.
https://hubs.worldbank.org/docs/imagebank/pages/docprofile.aspx?nodeid=67566
![Page 75: World Bank Documentdocuments.worldbank.org/curated/en/...management of wastewater, water supply, solid waste, river environment and cultural heritage. Revised Project Development Objectives](https://reader034.fdocuments.net/reader034/viewer/2022042204/5ea5c2bf52acbc3982752049/html5/thumbnails/75.jpg)